The U.S. state of Massachusetts has vast wind energy resources offshore, as well as significant resources onshore. The 2016 update to the states's Clean Energy and Climate Plan had a goal of reducing 1990 baseline greenhouse gas emissions levels by 25% by 2020. [1] Current goals include installing 3,500 megawatts (MW) of offshore wind power in the state by 2035. [2] However, as of Q4 2021 the state had only 120 MW of wind powered electricity generating capacity, responsible for generating 0.9% of in-state electricity production. The state has awarded contracts to two offshore projects, the 800 MW Vineyard Wind project and 804 MW Mayflower Wind project. [3] Construction began on the Vineyard Wind 1 project on November 18, 2021, after a long fight for approval. [4] Commonwealth Wind was selected for development in 2021, but the developer has attempted to cancel the project due to increased costs. There are eight projects planned for off the southern coast of Massachusetts, though some will deliver power to Rhode Island, Connecticut, and New York. [5]
Installed in 2005, the International Brotherhood of Electrical Workers (IBEW) 100 kW wind turbine along I-93 south of Boston drew attention to wind power to tens of thousands of commuters. [6] In 2009, a similar wind turbine was installed along I93 north of Boston, in Medford, expected to generate 170,000 kWh/year. [7] [8]
A GE Wind Energy 1.5 MW turbine was the first wind turbine to be installed at a ski resort in the United States of America at Jiminy Peak in Hancock, MA. The turbine, installed in 2007, is visible from many of the slopes on the mountain and it produces 4,600 MWh annually, about one third of the facilities electricity demands. [9]
At the Joint Base Cape Cod three turbines generate power for the base and construction is underway for two additional 1.68 MW turbines to power the radar unit. The three, soon to be five, turbines are highly visible from both the Bourne Bridge and the Sagamore Bridge looking to the East. The turbines have resulted in significant savings for the base, the turbines also do not generate any controversy because they are located well within the base boundaries far from civilian homes. [10]
In June 2017, the Massachusetts courts shut down two town-owned 1.65-megawatt wind turbines in Falmouth, Massachusetts. Each turbine generates up to 110 decibels of noise requiring almost 3000-foot setback. The decibel level for two wind turbines operating at the same time is unknown. Massachusetts has twenty-one communities with noise and alleged shadow flicker health issues. The neighbors describe the noise as torture. The Town of Falmouth in November 2019 approved 2.5 million to disassemble and store the wind turbines. The turbines were designed in the late 1990s and have the original gearboxes and blades. [11]
Cape Wind was an offshore wind farm that would have produced 450 MW, enough electricity to power nearly 420,000 homes using 130 wind turbines, [12] The project made its first federal filings in 2001, and faced a lengthy federal, state, and municipal permitting processes and considerable local controversy because of its location (in federal waters) between Cape Cod, Nantucket, and Martha's Vineyard, within sight of the mainland. It was cancelled in 2017 after losing utility support.
On August 8, 2016 the Massachusetts governor signed Bill H.4568 which mandates that Massachusetts utilities obtain 1.6 GW of offshore wind power by 2027. [13] [14] Policy also mandated that utilities acquire 1.2 GW of power from other renewable sources, including onshore wind. [15]
On December 14, 2018, the U.S. Bureau of Ocean Energy Management (BOEM) opened bids for leases on three parcels, each 13,000 acres, located in federal waters south of Martha's Vineyard and Nantucket. The three tentative winners, subject to final negotiations, were:
The auction raised a total of $405 million. The three areas could support 4.1 gigawatts of wind nameplate power, according to BOEM estimates. [17]
In April 2019, Vineyard Wind was awarded a contract to supply 800 MW of power to Massachusetts utilities at a price of 8.9 cents/kWh and will also spend $15 million on battery systems for energy storage. [18] They plan to install 84 turbines, with their power line running between the Vineyard and Nantucket to Covell Beach in Centerville, and from there via land to the grid. [19] The vessels used must comply with the Jones Act. [20] Final major federal approval was granted on May 11, 2021. [21] Power from the first turbine started flowing into the ISO New England grid on January 2, 2024. [22] Construction is expected to be complete by the end of 2024. [22]
Commonwealth Wind (lease area OCS-A 0534) [23] was selected for development in 2021, and signed agreements with all three major Massachusetts electric utilities - Eversource, National Grid, and Unitil. [24] In 2022, developer Avangrid asked that its project be canceled and rebid due to higher supply costs. The Massachusetts Department of Public Utilities rejected this request and approved the Commonwealth Wind and Mayflower Wind agreements instead. [25] A Mayflower Wind cable is expected to come ashore at the site of the former coal-powered Brayton Point Power Station, [26] which already has transmission infrastructure.
The Park City Wind project [27] would supply power to Connecticut but land cables in Barnstable on Cape Cod. Avangrid attempted to renegotiate its agreement with Connecticut due to cost increases. [26]
The proposed offshore Bay State Wind project failed to arrange purchasing agreements in Massachusetts. The joint venture between Eversource and Ørsted proposed a new design called Revolution Wind 2, to supply clean electricity to Rhode Island Energy. [28]
The state has implemented policy and infrastructure to support efforts to reduce greenhouse gas emissions. These policies and infrastructure are partially focused on promoting on- and off-shore wind power.
Green Communities Act (2008): created a commission to provide technical and financial support to reduce energy costs, strengthen local economies, and support renewable energy efforts. [2]
Green Jobs Act (2008): created the Massachusetts Clean Energy Center (MassCEC), which is a state authority designated for “job development and economic development in the clean energy sector.” The Act created the Alternative and Clean Energy Investment Trust Fund to further this economic development. [29]
Global Warming Solutions Act (2008): requires reduction in 1990 greenhouse gas emission levels to 25% by 2020, and at least an 80% reduction by 2050. Policy information and figures depicting state progress can be viewed on the Mass.gov website. [30]
The New Bedford Marine Commerce Terminal is the first hub in the country designed for the deployment of offshore wind farms. [31] The terminal is managed by the Massachusetts Clean Energy Center which supports the fabrication and implementation of offshore wind projects and the transportation of large scale marine cargo. The Terminal contains 26 acres of storage space that can be used by businesses and to aid shipping and transportation. Besides the auxiliary I-195 interstate running directly through New Bedford's downtown, it also has access roads to two highways, I-495 and I-95, and is accessible from other ports. [32]
The Massachusetts Wind Technology Testing Center in Charlestown is managed by the Massachusetts Clean Energy Center. The center offers testing for blades up to 90 meters long and different prototyping methods in order to support the production and installation of land and offshore wind turbines. The blade testing is required for turbines to meet international qualifications and to be certified for use. [33]
In July 2015, the administration of Massachusetts Governor Charlie Baker announced that Baker filed legislation to require the state to procure 1,600 megawatts of offshore wind power, as well as 1,200 megawatts of hydropower. [34] In March 2016, the legislation received the endorsement of all three of the Energy and Environmental Affairs Secretaries of the Deval Patrick administration, [35] and the following August, Baker signed the legislation into law. [36] In September 2016, Baker's administration announced that the offshore wind companies Deepwater Wind, DONG Energy, and OffshoreMW agreed to use the New Bedford Marine Commerce Terminal built during the Patrick administration as a staging area for their projects. [37] In June 2017, Massachusetts utilities issued the first RFP under the energy diversification law signed by Baker in August 2016, [38] and the following month, five major bids were submitted. [39]
In May 2018, Baker's administration selected Vineyard Wind to construct an 800-megawatt offshore wind farm off the southern coast of Martha's Vineyard, [40] and the following October, Vineyard Wind announced that it had signed an 18-month lease to also conduct their staging operations at the New Bedford Marine Commerce Terminal. [41] In December 2018, the Bureau of Ocean Energy Management announced the sale of three wind lease plots of 390,000 acres of ocean south of Nantucket and Martha's Vineyard to Equinor Wind, Mayflower Wind, and Vineyard Wind for a national record of $405 million that the agency estimated could generate as much as 4,100 megawatts of wind power. [42] In May 2021, the U.S. Department of the Interior announced that a record of decision had been issued giving final federal approval for the Vineyard Wind project. [43]
An Offshore Wind Study published in mid-2020 analyzed procuring an additional 1.6 GW of off-shore capacity in addition to the 1.6 GW already in progress. [44]
In late 2020, the Baker Administration released a Decarbonization Roadmap that aims for net zero greenhouse gas emissions by 2050. The plan calls for major investments in offshore wind and solar energy. [45] [46]
Parts of this article (those related to the table which needs to show the growth in wind power installed nameplate capacity in MW for Massachusetts since 1999 (last update was only for 2020) need to be updated.(September 2023) |
The following table shows the growth in wind power installed nameplate capacity in MW for Massachusetts since 1999. [47] [48] [49] [50] [51]
Year | Amount (MW) | Change (MW) | % Change |
---|---|---|---|
1999 | 0.3 | 0 | |
2000 | 0.3 | 0 | 0% |
2001 | 1 | 0.7 | 233% |
2002 | 1 | 0 | 0% |
2003 | 1 | 0 | 0% |
2004 | 1 | 0 | 0% |
2005 | 1.1 | 0.1 | 10% |
2006 | 3.5 | 2.4 | 218% |
2007 | 5 | 1.5 | 43% |
2008 | 5.7 | 0.7 | 14% |
2009 | 15 | 9 | 163% |
2010 | 17.7 | 2.7 | 18% |
2011 | 47 | 29.3 | 166% |
2012 | 103 | 56 | 119% |
2013 | 106 | 3 | 3% |
2014 | 107 | 1 | 1% |
2015 | 107 | 0 | 0% |
2016 | 115 | 8 | 7% |
2017 | 115 | 0 | 0% |
2018 | 113 | -2 | -2% |
2019 | 120 | 7 | 6% |
2020 | 120 | 0 | 0% |
In early 2010, the National Renewable Energy Laboratory released the first comprehensive update of wind energy potential by state since 1993, showing that Massachusetts had potential to install 1,028 MW of onshore wind power, using 80 meter high wind turbines, [52] and 1,913 MW of 100 MW wind turbines could achieve 30% or better capacity factor - and of those, almost 500 MW could reach a capacity factor of 40%. [53]
In 2009, the Massachusetts Department of Energy Resources (DOER) contracted Navigant Consulting to determine new locations of potential wind turbine sites throughout the state. The study identified 44 locations with 947 MW of potential power. The locations are centrally focused in the Berkshire and Barnstable counties. [54] The Massachusetts Executive Office of Energy and Environmental Affairs has this information publicly available with a Wind Energy Site Screening Tool. [55]
To meet renewable power minimums and with state approval, Massachusetts utilities agreed to pay for 40% of the output of the proposed King Pine wind farm in Aroostook County, Maine developed by Longroad Energy. As of January 2023 was approved by the Maine Public Utilities Commission but required further design and approval of the transmission line developed by LS Power of New York. [56]
The Cape Wind Project was a proposed offshore wind energy project on Horseshoe Shoal in Nantucket Sound off Cape Cod, Massachusetts. It was projected to generate 1,500 gigawatt hours of electricity a year at a first-dollar cost of $2.6 billion.
Wind power is a branch of the energy industry that has expanded quickly in the United States over the last several years. From January through December 2023, 425.2 terawatt-hours were generated by wind power, or 10.18% of electricity in the United States. The average wind turbine generates enough electricity in 46 minutes to power the average American home for one month. In 2019, wind power surpassed hydroelectric power as the largest renewable energy source in the U.S.
Wind power in Texas, a portion of total energy in Texas, consists of over 150 wind farms, which together have a total nameplate capacity of over 30,000 MW. If Texas were a country, it would rank fifth in the world: The installed wind capacity in Texas exceeds installed wind capacity in all countries but China, the United States, Germany and India. Texas produces the most wind power of any U.S. state. According to the Electric Reliability Council of Texas (ERCOT), wind power accounted for at least 15.7% of the electricity generated in Texas during 2017, as wind was 17.4% of electricity generated in ERCOT, which manages 90% of Texas's power. ERCOT set a new wind output record of nearly 19.7 GW at 7:19 pm Central Standard Time on Monday, January 21, 2019.
Wind power in California had initiative and early development during Governor Jerry Brown's first two terms in the late 1970s and early 1980s. The state's wind power capacity has grown by nearly 350% since 2001, when it was less than 1,700 MW. In 2016, wind energy supplied about 6.9% of California's total electricity needs, or enough to power more than 1.3 million households. Most of California's wind generation is found in the Tehachapi area of Kern County, California, with some large projects in Solano, Contra Costa and Riverside counties as well. California is among the states with the largest amount of installed wind power capacity. In recent years, California has lagged behind other states when it comes to the installation of wind power. It was ranked 4th overall for wind power electrical generation at the end of 2016 behind Texas, Iowa, and Oklahoma. As of 2019, California had 5,973 megawatts (MW) of wind power generating capacity installed.
Wind power in Ohio has a long history, and as of 2016, Ohio has 545 megawatts (MW) of utility-scale wind power installations installed, responsible for 1.1% of in-state electricity generated. Over 1000 MW more were under construction or pending approval. Some installations have become tourist attractions. There has been a sudden increase in generating capacity, as the total wind power capacity in the state was just 9.7 MW in 2010. By 2019, there were 738 MW of capacity, which generated 1.71% of Ohio's electricity.
There are a number of wind power projects in the state of Maine, totaling more than 900 megawatts (MW) in capacity. In 2020 they were responsible for 24% of in-state electricity production. In 2019, Maine had more wind capacity than the other five New England states combined, at 923 MW.
New York has 2,192 MW of installed wind power capacity as of 2022. Most of New York's wind power is located in upstate New York as onshore wind farms. New York has set a goal of developing 9,000 MW of offshore installed wind power capacity by 2035 that will power an estimated 6 million homes. As of October 2022, New York has five offshore wind farms in development with approximately 4,300 MW installed capacity.
Wind power in Indiana was limited to a few small water-pumping windmills on farms until 2008 with construction of Indiana's first utility-scale wind power facility, Goodland with a nameplate capacity of 130 MW. As of March of 2024, Indiana had a total of 2,743 MW of wind power capacity installed, ranking it 12th among U.S. states. Wind power was responsible for 4.8% of in-state electricity production in 2016.
GE Wind Energy is a branch of GE Renewable Energy, a subsidiary of General Electric. The company manufactures and sells wind turbines to the international market. In 2018, GE was the fourth largest wind turbine manufacturer in the world.
In 2016, Arizona had 268 megawatts (MW) of wind powered electricity generating capacity, producing 0.5% of in-state generated electricity.
Wind power in New Jersey is in the early stages of development. New Jersey has just six wind turbines, but the state has plans to develop several major offshore wind projects on the continental shelf of the Atlantic Ocean off the southern Jersey Shore. Legislation has been enacted to support the industry through economic incentives and to permit wind turbines on existing piers.
Solar power in Massachusetts has been increasing rapidly, due to Section 1603 grants for installations that began before December 31, 2011, and the sale of SRECs for $0.30/kWh, which allows payback for the system within 5 or 6 years, and generates income for the life of the system. For systems installed after December 31, 2011, and before December 31, 2016, the 30% tax grant becomes a 30% tax credit. There has been an appeal to the Congress to extend the 1603 program, the grant program, for an additional year.
The U.S. state of Connecticut has vast wind energy resources offshore as well as onshore although Connecticut was the last state in the United States to block the construction of utility scale wind turbines. Connecticut maintains a renewable portfolio standard that requires 21% of the state's electricity to come from renewable sources by 2020.
Wind power in Rhode Island is in the early stages of development. There are several small scale wind turbine projects in the state. As of December 2013 there were 11 turbines at 10 sites in the state. In 2014, Rhode Island had 9 MW of installed wind power capacity, which quickly rose to 75 MW in 2019.
Wind power in Virginia is in the early stages of development. In March 2015, Virginia became the first state in the United States to receive a wind energy research lease to build and operate offshore wind turbines in federal waters. Virginia has no utility scale wind farms.
South Fork Wind Farm is a utility-scale offshore wind farm on the Outer Continental Shelf Offshore Rhode Island, providing energy to New York state.
Vineyard Wind 1 is an offshore wind farm under construction in U.S. federal waters in the Atlantic Ocean in Bureau of Ocean Energy Management-designated Lease Area OCS-A 0520, about 13 nautical miles south of Martha's Vineyard and Nantucket, Massachusetts. The array is designed to include 62 wind turbines manufactured by GE Offshore Wind with a nameplate capacity of 804 MW combined, equivalent to the annual power use of 400,000 homes. The Massachusetts Department of Public Utilities approved the project in 2019. Construction began on November 18, 2021. In October 2023, the first turbine was installed. Power from the first turbine started flowing into the ISO New England grid on January 2, 2024. Construction is expected to be complete by the end of 2024.
Offshore wind power is in the early stages of development in the United States. In 2016, the United States Department of Energy estimated that the country has a gross resource potential of 10,800GW of offshore wind capacity, with a "technical" resource potential of 2,058GW. Offshore wind projects are under development in wind-rich areas of the East Coast, Great Lakes, and Pacific coast. The first commercial offshore wind farm, Block Island Wind Farm, began operation in 2016. As of 2017, about 30 projects totaling 24 gigawatts (GW) of potential installed capacity were being planned.
{{cite web}}
: CS1 maint: archived copy as title (link){{cite web}}
: CS1 maint: multiple names: authors list (link) CS1 maint: numeric names: authors list (link)