Snowy 2.0 Pumped Storage Power Station | |
---|---|
Country | Australia |
Location | Snowy Mountains |
Coordinates | 35°47′11″S148°26′40″E / 35.78639°S 148.44444°E |
Status | Under construction |
Construction began | 2019 |
Construction cost | AUD 12 billion [1] |
Owner | Snowy Hydro |
External links | |
Website | https://www.snowyhydro.com.au/ |
Snowy 2.0 Pumped Storage Power Station or Snowy Hydro 2.0 or simply Snowy 2.0 is a pumped-hydro battery megaproject in New South Wales, Australia. The dispatchable generation project expands upon the original Snowy Mountains Scheme (ex post facto Snowy 1.0) connecting two existing dams through a 27-kilometre (17 mi) underground tunnel and a new, underground pumped-hydro power station. [2] It is expected to supply 2.2 gigawatts of capacity and about 350,000 megawatt hours of large-scale storage to the national electricity market. [3] [4] It is the largest renewable energy project under construction in Australia. [5] It includes one of the largest and deepest cavern excavations ever undertaken. [6] It also includes the longest tunnels at 27 kilometres in length, of any pumped-hydro station ever built.
It is designed for grid stabilization; to be a backup at times of peak demand and for when solar and wind energy are not providing sufficient power. [7] It provides valuable firming capability. Snowy Hydro acts like a giant battery by absorbing, storing, and dispatching energy. [3] Snowy 2.0 can be "switched on" very quickly. [8] The battery is designed to operate for up to 175 hours of temporary supply. [9] It is Australia's largest energy project, [10] estimated to cost 12 billion Australian dollars and projected to generate 10% of the nation's energy. [11]
Construction began in 2019. [2] By 2023, AU$4.3 billion had been spent. [1] Snowy 2.0 has been described as a white elephant. [12] The project is led by public company Snowy Hydro Limited. [10] Snowy 2.0 will last for at least 100 years. [13] When complete it is expected to have a large impact on the price and reliability of electric power. [14]
Initial plans for a power station at the location were discussed in 1966. [15] Further studies were undertaken in 1980 and 1990. [15] The current project originated as the centrepiece of Malcolm Turnbull's climate change policy in 2017. [16] The original cost of the project was around $2 billion. [17] A feasibility study carried out in 2017 finding the project was both technically and financially feasible. [15] The study was released on 21 December 2017 and found the project cost would be between $3.8 and 4.5 billion. [18]
The first tunnel that was completed by October 2022, was a 2.85 kilometre section that provided main access at Lobs Hole. [19] It was 10 metres in diameter and provides pedestrian and vehicle access into the power station. [19] By May 2023 the emergency, cable and ventilation tunnel was excavated. [20] It is 2.93 kilometre long, 10 metres in diameter and will be used for power station ventilation and high-voltage cables. [20] Excavation of the transformer and machines halls began in June 2023. [6] By February 2024, half of the construction required was complete. [21]
It was originally expected to be completed by 2024. [22] [23] Snowy Hydro 2.0 has been beset by delays and cost blowouts. [16] [7] [4] Delays have been caused by the COVID-19 pandemic, global supply chain disruptions, complex design elements and variable site and geological conditions. [9] The delays have raised concerns that Snowy Hydro will not be ready in time for new solar and wind projects coming online as five coal-fired power stations close. [7] AEMO warns that supply gaps will emerge from 2025. [4] The project is currently expected to be fully operational by the end of 2028 and generating power as early as late 2027. [5]
The project is using three tunnel boring machines to dig tunnels. [16] One of the machines, called Florence was stuck for 19 months after encountering soft rock near Tantangara. [23] Florence is excavating the 16 km headrace tunnel, which will connect the underground power station to the upper Tantangara reservoir. [24] Florence launched in March 2022 and was named in honour of Australia's first female electrical engineer, Florence Violet McKenzie. [17] Eight weeks later the machine was bogged in wet soft ground. The machine is capable of digging 30 to 50 metres a day. In December 2022, a sinkhole opened up above the tunnel. [23] Florence was moving at a pace of six metres a day by early December 2023. [21] In May 2024 the tunnel boring machine was stuck in hard rock. [25] By 11 July Florence was clear of the hard rock after using ultra-high pressure water jetting. [26] A fourth boring machine was required due to the delays caused by Florence. [27]
Drilling and blasting was used to dig caverns. The company managing underground blasting operations was Orica. [28] Rock bolts and shotcrete support the exposed solid rock face. [28] The main cavern was excavated between June 2023 and January 2024. [29]
It is located remotely within the Kosciuszko National Park in the Snowy Mountains. [3] Snowy Hydro 2.0 will use water from the Talbingo Reservoir (bottom storage) and Tantangara Reservoir (top storage). [14] The dams have a height differential of 700 metres. [15] [11] The new power station is being built by the Italian firm Webuild. [30] It will be located in a cavern 800 metres underground. [14] The underground location allows for reduced environmental impacts within the national park. [11] The operational footprint of the facility is less than 0.01% of the total size of the park. [31]
The Inclined Pressure Shaft (IPS) through which the water will pass is the largest of its kind in the world and facilitates the water's return to the upper reservoir when the pump-turbines operate in reverse. [32] The IPS is 10 metres in diameter, 1.6 kilometres long and at a 25-degree incline. Pre-cast concrete segments for the shaft are produced at a factory in the town of Cooma. [32] Fatigue resistance is a key design element in the IPS. [32]
The power station will measure 22 metres wide, 50 m high and 250 m long. [10] The station will house six reversible Francis pump-turbine and motor-generator units. [22] Three units will be of variable speed with the remaining of synchronous speed. Each turbine will have a rated output of 333 megawatts. [33] Power generating equipment is being supplied by Voith. [33]
It will be connected to the grid via the HumeLink transmission line. [16] [34] The construction of overhead power lines by TransGrid has been opposed by community advocacy groups. [35] Landholders desire to see the transmission line built underground have been opposed due to prohibitive costs. [35]
The Kosciuszko National Park is a 6,900-square-kilometre (2,700 sq mi) national park and contains mainland Australia's highest peak, Mount Kosciuszko, for which it is named, and Cabramurra, the highest town in Australia. Its borders contain a mix of rugged mountains and wilderness, characterised by an alpine climate, which makes it popular with recreational skiers and bushwalkers.
The Snowy Mountains Scheme, also known as the Snowy Hydro or the Snowy scheme, is a hydroelectricity and irrigation complex in south-east Australia. Near the border of New South Wales and Victoria, the scheme consists of sixteen major dams; nine power stations; two pumping stations; and 225 kilometres (140 mi) of tunnels, pipelines and aqueducts that were constructed between 1949 and 1974. The Scheme was completed under the supervision of Chief Engineer, Sir William Hudson. It is the largest engineering project undertaken in Australia.
Pumped-storage hydroelectricity (PSH), or pumped hydroelectric energy storage (PHES), is a type of hydroelectric energy storage used by electric power systems for load balancing. A PSH system stores energy in the form of gravitational potential energy of water, pumped from a lower elevation reservoir to a higher elevation. Low-cost surplus off-peak electric power is typically used to run the pumps. During periods of high electrical demand, the stored water is released through turbines to produce electric power.
Mica Dam is a hydroelectric embankment dam spanning the Columbia River 135 kilometres north of Revelstoke, British Columbia, Canada. It was built as one of three Canadian projects under the terms of the 1964 Columbia River Treaty and is operated by BC Hydro. Completed in 1973, the Mica powerhouse had an original generating capacity of 1,805 megawatts (MW). Mica Dam, named after the nearby settlement of Mica Creek and its associated stream, in turn named after the abundance of mica minerals in the area, is one of the largest earthfill dams in the world. The reservoir created by the dam is Kinbasket Lake. Water from the dam flows south directly into Revelstoke Lake, the reservoir for the Revelstoke Dam. Mica Dam is the tallest dam in Canada and second tallest in North America after the Chicoasén Dam in Mexico and it is the farthest upstream dam on the Columbia River. The dam's underground powerhouse was the second largest in the world at the time of its construction, and was the first 500 kV installation of sulphur hexafluoride (SF6) insulated switchgear in the world.
An underground power station is a type of hydroelectric power station constructed by excavating the major components from rock, rather than the more common surface-based construction methods.
Snowy Hydro Limited is an electricity generation and retailing company in Australia that owns, manages, and maintains the Snowy Mountains Hydro-electric Scheme that consists of nine hydro-electric power stations and sixteen large dams connected by 145 kilometres (90 mi) of tunnels and 80 kilometres (50 mi) of aqueducts located mainly in the Kosciuszko National Park. Snowy Hydro also owns and operates two gas-fired power stations in Victoria and one in New South Wales, three diesel power stations in South Australia and owns two electricity retailing businesses, Red Energy and Lumo Energy.
The Shoalhaven Scheme is a dual-purpose water supply and Pumped-storage Hydroelectricity scheme located on the South Coast region of New South Wales, Australia.
Jindabyne Dam is a major ungated rockfill embankment dam across the Snowy River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is to redirect water from the Snowy River to the Murray, for the generation of hydro-power and irrigation. It is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
Eucumbene Dam is a major gated earthfill embankment dam with an overflow ski-jump and bucket spillway with two vertical lift gates across the Eucumbene River in the Snowy Mountains of New South Wales, Australia. The dam's main purpose is for the generation of hydro-power and is one of the sixteen major dams that comprise the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro.
The Robert-Bourassa generating station, formerly known as La Grande-2 (LG-2), is a hydroelectric power station on the La Grande River that is part of Hydro-Québec's James Bay Project in Canada. The station can generate 5,616 MW and its 16 units were gradually commissioned between 1979 and 1981. Annual generation is in the vicinity of 26500 GWh.
The Tumut Hydroelectric Power Stations is a series of three hydroelectric power stations on the Tumut River in New South Wales, Australia, that are part of the Snowy Mountains Scheme.
The Kiewa Hydroelectric Scheme is the largest hydro-electric scheme in the Australian state of Victoria and the second-largest in mainland Australia after the Snowy Mountains Scheme. The scheme is situated in the Australian Alps in north-eastern Victoria about 350 kilometres from Melbourne and is wholly owned by AGL Energy. In 2024, AGL studied the options of expanding the scheme with pumped-storage hydroelectricity.
Renewable energy in Australia is mainly based on biomass, solar, wind, and hydro generation. Over a third of electricity is generated from renewables, and is increasing, with a target to phase out coal power before 2040. Wind energy and rooftop solar have particularly grown since 2010. The growth has been stimulated by government energy policy in order to limit the rate of climate change in Australia that has been brought about by the use of fossil fuels. Pros and cons of various types of renewable energy are being investigated, and more recently there have been trials of green hydrogen and wave power.
Tantangara Dam is a major ungated concrete gravity dam with concrete chute spillway across the Murrumbidgee River in Tantangara, upstream of Adaminaby in the Snowy Mountains region of New South Wales, Australia. The dam is part of the Snowy Mountains Scheme, a vast hydroelectricity and irrigation complex constructed in south-east Australia between 1949 and 1974 and now run by Snowy Hydro. The purpose of the dam includes water management and conservation, with much of the impounded headwaters diverted to Lake Eucumbene. The impounded reservoir is called Tantangara Reservoir.
Talbingo Dam is a major ungated rock fill with clay core embankment dam with concrete chute spillway across the Tumut River upstream of Talbingo in the Snowy Mountains region of New South Wales, Australia. The impounded reservoir is called Talbingo Reservoir.
Webuild SpA is an Italian industrial group specialising in construction and civil engineering. The company was formally founded in 2014 as the result of the merger by incorporation of Salini into Impregilo. Webuild is the largest Italian engineering and general contractor group and a global player in the construction sector.
The Cruachan Power Station is a pumped-storage hydroelectric power station in Argyll and Bute, Scotland, UK. The scheme can provide 440 MW of power and produced 705 GWh in 2009.
The Australian Renewable Energy Agency (ARENA) is an independent agency of the Australian federal government, established in 2012 to manage Australia's renewable energy programs, with the objective of increasing supply and competitiveness of Australian renewable energy sources.
The Nant de Drance Hydropower Plant is a pumped-storage power station in the canton of Valais in Switzerland. It is within the municipality of Finhaut, district of Saint-Maurice and about 14 km (8.7 mi) southwest of Martigny. Construction on the power plant began in 2008 and it began operations in 2022. It is owned by Nant de Drance SA, a consortium of Alpiq (39%), SBB (36%), Industrielle Werke Basel (15%) and Forces Motrices Valaisannes (FMV) (10%). The US$1.9 billion plant has an installed capacity of 900 MW and an energy storage capacity of 20 GWh.
The Borumba Dam Pumped Hydro Power Station is a proposed 2,000 MW pumped hydro energy storage system at Lake Borumba, located in Imbil, south-west of Gympie in Queensland, Australia. First power is expected in 2030. A state-owned entity called Queensland Hydro is coordinating the project.