Euston tunnel

Last updated

Euston tunnel
HS2 Euston tunnel.png
HS2 route out of Euston via Old Oak Common
Overview
Coordinates 51°32′13″N0°11′31″W / 51.537°N 0.192°W / 51.537; -0.192
StatusUnder construction
System High Speed 2
CrossesWest London
Start Euston railway station
End Old Oak Common railway station
Operation
TrafficRail
Technical
Length4.5 miles (7.2 km)
No. of tracks 2
Track gauge 1,435 mm (4 ft 8+12 in)
Electrified 25 kV 50 Hz AC
Operating speed120 km/h (75 mph)
Width7.5 metres (25 ft)

Euston tunnel is a tunnel currently planned in London that will carry the High Speed 2 (HS2) railway between Euston railway station and Old Oak Common railway station.

Contents

Work to prepare the site for construction was undertaken in the late 2010s, such as the clearance of the old carriage sheds near Euston station in 2018. A legal challenge to the tunnel's design was defeated in mid-2020. During October 2020, HS2 Ltd ordered the two tunnel boring machines (TBMs) from Herrenknecht that will excavate the tunnel. Excavation is scheduled to take place between 2022 and 2024.

History

To bring the HS2 high speed line into London, it was decided that a series of twin-bore tunnels underneath the city would be the most practical approach. [1] These will have a combined total of 26 miles (42 km), roughly equivalent in length to those built for the Crossrail programme. Responsibility for the construction of the section between central London and the M25 has been assigned to HS2's main works contractor, Skanska Costain STRABAG JV. In total, it has been envisaged that ten tunnel boring machines (TBMs) will be used to bore the 64 miles (103 km) of tunnelling along the HS2 route between the West Midlands and London. [1] [2]

During 2018, the disused Euston Downside Carriage Maintenance Depot, close to Euston railway station, was demolished in order to clear space for the future construction work; the tunnel portal of the future Euston tunnel is to be present at this location. [3]

During 2019, a legal challenge to the design of Euston tunnel was launched by a local resident, alleging failures to address safety concerns; [4] in June 2020, the High Court dismissed the challenge as "impossible to accept". [5]

During October 2020, HS2 Ltd signed a contract with the manufacturing group Herrenknecht to build and supply the two TBMs for Euston tunnel. [1] These are to be custom-designed to suit the local geology, which ground surveys indicated to consist largely of clay and chalk, with which the tunnels are to be bored through. Each TBM is 140 m (460 ft) in length, headed by a 9.84 m (32.3 ft) diameter cutter head, weighing approximately 2,050 tonnes. [1] Delivery of the two TBMs has been scheduled to take place sometime in late 2021. [1]

In summer 2022, initial boring is expected to take place; this phase of the work is expected to take roughly two years to complete. Boring is set to proceed on a non-stop working pattern, only shutting down temporarily on Christmas and for bank holidays. During the excavation phase, it has been projected that 1,200,000 cubic metres (42,000,000 cu ft) of spoil (excavated material), weighing 2.46 million tonnes, will be removed by the TBMs. [6] [1] Between August 2021 and December 2033, a portion of London Zoo's car park is to be temporarily borrowed for use by construction vehicles while Euston Tunnel is being built. [7]

Construction

Euston tunnel will be bored using tunnel boring machines launched from the western entrance, near Old Oak Common railway station. [1] The tunnel will be 4.5 miles (7.2 km) long, with an outer diameter of 9.5 m (31 ft). At its deepest point, the tunnel will run 50 m (160 ft) below ground. [1]

The pre-cast concrete sections lining the tunnel will be manufactured by Pacadar UK at their factory on the Isle of Grain, Kent. [6] These sections, each weighing seven tonnes, will be transported to site by rail. In excess of 160,000 cubic metres (5,700,000 cu ft) of concrete has been anticipated to be used to produce these sections. [6] The use of 3D printing technology will reportedly reduce the amount of concrete used in Euston tunnel in comparison to traditional methods. [8]

One of the few above-surface elements of the tunnel will be a three-storey building near Euston railway station, adjacent to the existing West Coast Main Line, which will accommodate a 12 m (39 ft) diameter ventilation shaft from the surface to the twin tunnels below; this structure will also facilitate emergency access to the tunnel along with supporting electrical plant rooms. The top of this building will be covered by a green roof, stone-paved courtyard and have an entrance from Park Village East. [9] [7]

In advance of the tunnel's boring, a smaller 853m long logistics tunnel is being bored using a separate smaller TBM that will facilitate access between the primary construction compound at Atlas Road and Old Oak Common Station, the launch site for the Northolt East and Euston TBMs, [10] through which construction materials such as the precast concrete lining segments will be brought into the site and spoil removed. [11] Boring on the Atlas Road Logistics Tunnel began with the launch of TBM Lydia (formerly TBM Ellie on the Crossrail project before being refurbished for HS2 by Herrenknecht) [12] on April 12, 2023, [13] and finished on January 23, 2024. [14]

Related Research Articles

<span class="mw-page-title-main">Tunnel</span> Underground passage made for traffic

A tunnel is an underground or undersea passageway. It is dug through surrounding soil, earth or rock, or laid under water, and is enclosed except for the entrance and exit, commonly at each end. A pipeline is not a tunnel, though some recent tunnels have used immersed tube construction techniques rather than traditional tunnel boring methods.

<span class="mw-page-title-main">Euston railway station</span> Central London railway terminus

Euston railway station is a central London railway terminus managed by Network Rail in the London Borough of Camden. It is the southern terminus of the West Coast Main Line, the UK's busiest inter-city railway. Euston is the tenth-busiest station in Britain and the country's busiest inter-city passenger terminal, being the gateway from London to the West Midlands, North West England, North Wales and Scotland.

<span class="mw-page-title-main">Crossrail</span> Railway project in London, England

Crossrail is a railway construction project centred around London. Its aim is to provide a high-frequency hybrid commuter rail and rapid transit system crossing the capital from suburbs on the west to east, by connecting two major railway lines terminating in London: the Great Western Main Line and the Great Eastern Main Line. The project was approved in 2007, and construction began in 2009 on the central section and connections to existing lines that became part of the route, which has been named the Elizabeth line in honour of Queen Elizabeth II who opened the line on 17 May 2022 during her Platinum Jubilee. The central section of the line between Paddington and Abbey Wood opened on 24 May 2022, with 12 trains per hour running in each direction through the core section in Central London.

<span class="mw-page-title-main">Tunnelling shield</span> Protective structure used during the excavation of tunnels

A tunnelling shield is a protective structure used during the excavation of large, man-made tunnels. When excavating through ground that is soft, liquid, or otherwise unstable, there is a potential health and safety hazard to workers and the project itself from falling materials or a cave-in. A tunnelling shield can be used as a temporary support structure. It is usually in place for the short-term from when the tunnel section is excavated until it can be lined with a permanent support structure. The permanent structure may be made up of, depending on the period, bricks, concrete, cast iron, or steel. Although modern shields are commonly cylindrical, the first "shield", designed by Marc Isambard Brunel, was actually a large, rectangular, scaffold-like iron structure with three levels and twelve sections per level, with a solid load-bearing top surface. The structure protected the men from cave-ins as they laboured within it, digging the tunnel out in front of the shield.

<span class="mw-page-title-main">Euston tube station</span> London Underground station

Euston is a London Underground station. It directly connects with Euston main line station above it. The station is in Travelcard Zone 1.

<span class="mw-page-title-main">Tunnel boring machine</span> Device used to excavate tunnels

A tunnel boring machine (TBM), also known as a "mole", is a machine used to excavate tunnels. Tunnels are excavated through hard rock, wet or dry soil, or sand, each of which requires specialized technology.

<span class="mw-page-title-main">Old Oak Common railway station</span> Planned railway station in London

Old Oak Common (OOC) is a railway station under construction on the site of the Old Oak Common traction maintenance depot to the west of London in Old Oak Common, approximately 500 m (1,600 ft) south of Willesden Junction station. When built, it is expected to be one of the largest rail hubs in London, at about 800 m (2,600 ft) in length and 20 m (66 ft) below surface level.

<span class="mw-page-title-main">High Speed 2</span> High-speed railway under construction in England

High Speed 2 (HS2) is a planned high-speed railway line and network of passenger train services in Great Britain. The new railway line, which is currently under construction in England, is to run between the West Midlands and London, with a spur to Birmingham. A network of train services will use the new line and existing conventional track to reach their destinations in the Midlands, North West England, and Scotland. HS2 is to be Britain's second purpose-built high-speed line after High Speed 1, which connects London to the Channel Tunnel. The majority of the project is planned to be completed between 2029 and 2033.

<span class="mw-page-title-main">Herrenknecht</span>

Herrenknecht AG is a German company that manufactures tunnel boring machines, headquartered in Allmannsweier, Schwanau, Baden-Württemberg. It is the worldwide market leader for heavy tunnel boring machines. Roughly two-thirds of its 5,000 employees work at the company's headquarters in the installation of hydraulic and electronic components and final inspection. Approximately 300 work at three locations across China. The company has 82 subsidiaries around the world and has worked on 2,600 projects.

The Bosphorus Water Tunnel or Bosporus aqueduct is an undersea aqueduct in Istanbul, Turkey, crossing the Bosphorus strait. It was constructed in 2012 to transfer water from the Melen Creek in Düzce Province to the European side of Istanbul.

The Lee Tunnel, also known as the Stratford to East Ham deep tunnel, is an overflow sewer in East London for storage and conveyance of foul sewage mixed with rainwater. It was built as part of the Thames Tideway Scheme and runs from Abbey Mills Pumping Station down to pumps and storage tanks at Jenkins Lane, Beckton Sewage Treatment Works. It is wholly under the London Borough of Newham.

<span class="mw-page-title-main">Station box</span>

A station box is a term in the construction industry: It describes a box-like underground structure for a transportation system, for example a metro or tube station.

The Tuen Mun - Chek Lap Kok TBM is the world's largest tunnel boring machine launched in June 2015 by Herrenknecht in Germany. The TBM is used to drill a 5 km tunnel connecting Tuen Mun to the Hong Kong International Airport, part of the Tuen Mun–Chek Lap Kok Link project. The machine has a diameter of 17.6 metres (57.7 ft), 0.1 metres (0.3 ft) more than Bertha, the previous largest tunnel boring machine.

<span class="mw-page-title-main">Tunnel construction</span> The construction method for building a tunnel

Tunnels are dug in types of materials varying from soft clay to hard rock. The method of tunnel construction depends on such factors as the ground conditions, the ground water conditions, the length and diameter of the tunnel drive, the depth of the tunnel, the logistics of supporting the tunnel excavation, the final use and shape of the tunnel and appropriate risk management. Tunnel construction is a subset of underground construction.

<span class="mw-page-title-main">Stepney Green cavern</span> Underground junction where Crossrail splits into two branches

Stepney Green cavern is an underground junction which contains the junction where Crossrail divides into two branches: one to Shenfield and one to Abbey Wood. It is located below Stepney Green Park.

<span class="mw-page-title-main">Woodsmith Mine Tunnel</span> Tunnel in North Yorkshire, England

The Woodsmith Mine Tunnel is a 23-mile (37 km) long tunnel that will stretch between Woodsmith Mine at Sneatonthorpe near Whitby in North Yorkshire and the Wilton International complex on Teesside, England. The tunnel has been in development since 2016, but cutting of the tunnel bore did not start until April 2019, with a projected finish date of 2021, but it was still not complete by the end of 2023. By the end of July 2020, over 4 miles (6.4 km) of tunnel had been dug.

<span class="mw-page-title-main">Colne Valley Viaduct</span> HS2 Railway Bridge in Harefield

The Colne Valley Viaduct is a bridge, under construction as of 2023, which will carry the High Speed 2 railway over the Colne Valley Regional Park and the Grand Union Canal, in Hillingdon, west London. When completed, its length of 3.4 kilometres (2.1 mi) and a weight of 116,000 tonnes will make it the largest railway bridge in the UK. It is one of the largest single civil engineering works of HS2 Phase 1.

<span class="mw-page-title-main">Euston Square Gardens</span>

Euston Square Gardens is a public garden on Euston Road in the London Borough of Camden.

The Chiltern Tunnel is a high-speed railway tunnel currently under construction in Buckinghamshire and Hertfordshire, England, and will upon completion carry the High Speed 2 (HS2) railway line under the Chiltern Hills. The twin-bore tunnels, which are 16.04 km long, will be the longest on the HS2 line. Each tunnel will also have additional 220 m (720 ft) entry and 135 m (443 ft) exit perforated concrete portals to reduce sudden changes in air pressure and subsequent noise.

<span class="mw-page-title-main">Northolt tunnel</span> Twin-bore tunnel for HS2 railway

The Northolt Tunnel is a high-speed railway tunnel currently under construction in Greater London, England, and will upon completion carry the High Speed 2 (HS2) railway line under the West London suburbs. The twin-bore tunnels will run for 8.4 miles (13.5 km) between Old Oak Common and Ruislip. As of January 2024, the first tunnel boring machine has completed 35% of its bore length.

References

  1. 1 2 3 4 5 6 7 8 "Giant tunnelling machines contract for London tunnels signed by HS2 Ltd". Global Railway Review. 12 October 2020. Retrieved 16 August 2021.
  2. "London tunnels". hs2.org.uk. Retrieved 10 October 2021.
  3. "First Look at HS2's Euston Tunnel Site (Video)". roofingtoday.co.uk. 5 October 2018.
  4. Horgan, Rob (20 January 2020). "Homeowner clears legal hurdle in bid to stop 'catastrophic' Euston tunnel design". architectsjournal.co.uk.
  5. "High Court backs HS2 in Euston tunnel case". environment-analyst.com. 10 June 2020.
  6. 1 2 3 O'Connor, Rob (4 August 2021). "First tunnel segment contract award for HS2's London tunnels". Infrastructure Intelligence. Retrieved 16 August 2021.
  7. 1 2 "Euston approaches". hs2.org.uk. Retrieved 10 October 2021.
  8. "HS2 to use 3D printing at Euston station tunnels". ianvisits.co.uk. 10 August 2021.
  9. "Engineering brick cladding for HS2's Euston headhouse". The Construction Index. 17 February 2021. Retrieved 16 August 2021.
  10. "Atlas Road Logistics Tunnel". HS2. Retrieved 17 September 2023.
  11. Long Branch, Mike (22 February 2021). "HS2 Prepares for 21km tunnels under London (Tunneltalk)". londonreconnections.com.
  12. "Crossrail TBM upcycled for HS2 logistics tunnel drive". Construction Enquirer. Retrieved 17 September 2023.
  13. May, Tiana (13 April 2023). "HS2 Launches Third Tunnel Boring Machine in London". Railway-News. Retrieved 17 September 2023.
  14. "HS2: Tunnel completion takes line closer to Euston, engineers say". BBC News. 23 January 2024. Retrieved 23 January 2024.