Network 2011 was a plan for transit expansion created in 1985 by the Toronto Transit Commission. It was centred on three proposed subway lines: the Downtown Relief Line, Eglinton West Line, and the Sheppard Line. Only a portion of the Sheppard Line was built. The Eglinton West and Downtown Relief Lines were cancelled; they were superseded by the Eglinton Crosstown light rail line and the Ontario Line respectively.

Contents

The plan

The 1970s had seen the end of new expressway construction in Toronto, and the preservation of the Downtown streetcar system. In 1972, while construction was underway on the Spadina Subway line, the provincial government of Bill Davis introduced the GO-Urban transit plan for the Toronto region. Rather than build either subways or light rail, the plan would build a network of innovative maglevs to ring Metro Toronto. The maglev project failed, and the province switched to supporting UTDC's Intermediate Capacity Transit System. An initial line was built, the Scarborough RT, but it went greatly over budget and no further lines were attempted.

Network 2011 was designed to meet the needs of a rapidly growing city where building new expressways was politically impossible. There was also strong resistance to further intensification of the downtown core. The same spirit of activism that had stopped the Spadina Expressway and saved the streetcars also blocked residential redevelopment projects such as the plans for Trefann Court and Kensington Market. Community activists also opposed more downtown office towers, and as a result the city plan called for the creation of three suburban "subcentres" that would become central business districts independent of the core: North York City Centre, Scarborough City Centre, and Etobicoke City Centre. Improving transit to these areas was a central focus of the plan. [1]

The GO-Urban and ICTS experiments being failures, the TTC was unwilling to again risk anything experimental, and the plan called for future transit expansion to use subways of the same design as the existing lines. The plan did not consider using the CLRV and ALRV streetcars which were being delivered at the time to run on the downtown tracks.

Under the lead of planner Jiri Pill, the TTC delivered a plan to Metro Toronto in May 1985 calling for a near doubling of Toronto's rapid transit lines. The Network 2011 plan had five elements to be built over the next 28 years and would cost an estimated $2.7 billion:

Debates

The plan was well received by most in Toronto, and was approved by Metro Council in June 1986. Most of the debate was over which sections should be built first. The mayors of York and Etobicoke wanted the Eglinton Line moved up in priority, while North York and Scarborough pushed for the Sheppard Line to be built first, and for the entire line to be built at once rather than in two sections. [3] The Eglinton line had been discussed since 1975, and the need for a Downtown Relief Line has also previously been discussed. The call for a subway along suburban Sheppard was unexpected. [4] Sheppard was prioritized because the bus lines were overloaded, and putting it first could win support from suburban councillors who were less enthused to invest in transit. [5] The creation of the Sheppard Line would add enough passengers onto the Yonge Line to overload Yonge-Bloor Station, requiring the Downtown Relief Line to be the next built. This angered councillors from York and Etobicoke, who wanted the Eglinton Line to have higher priority. The governments of Mississauga and Peel also wanted the Eglinton Line built sooner, and put pressure on the province, who was paying 75% of the cost, to have its schedule advanced. [6]

One critic of the plan was Steve Munro, of Streetcars for Toronto, the group that had saved the Toronto streetcar system in the 1970s. He argued that the TTC planners were too focused on subways, and this made the programme too expensive and less likely to be built. He argued that options such as underground LRT were not considered by the TTC, and would have met requirements with a lower price. [7] The opposition to the plan was led by the Better Transportation Coalition, under the leadership of Gord Perks. Perks argued that a streetcar in a separate right-of-way along Sheppard would easily address the needed ridership, at a fraction of the cost. [8]

There were also concerns over the Downtown Relief Line. Munro noted that a line running from Danforth to downtown would serve mostly as a transfer for passengers coming from further east and would have little benefit to the local community, and should instead extend further north, additionally serving Don Mills. Local councillor Dale Martin agreed that the line mainly served the interests of developers looking for intensification rather than local residents. [9] Jack Layton emerged as the leader of the councillors opposed to the DRL, concerned it would lead to further intensification downtown. Layton and his allies were strong followers of Jane Jacobs, and believed in preserving downtown neighbourhoods as they were and redirecting office developments to the suburbs. The new developments in the suburbs would allow true urban communities to develop there, and create a multi-directional traffic that would make far better use of existing downtown infrastructure. [10]

Provincial revisions and cancellations

The complaints from Peel region were also matched by demands from York Region that the province fund Highway 407. The provincial government of David Peterson delayed approving the Network 2011 projects until a study analyzing transit needs across the entire Greater Toronto Area was completed. [11] In April 1990 the Peterson government announced their "Let's Move" program of $6.2 billion in transportation spending across the GTA over the next ten years. Let's Move added several components to the Network 2011 plan: a northern connection along Finch between the Yonge and Spadina Lines, extension of the Bloor Subway to Sherway Gardens, SRT extension to Sheppard, building an LRT along Eglinton into Mississauga. Missing from the plan was the Downtown Relief Line. It also deprioritized Sheppard, offering to fund it only if the private sector contributed a significant amount. [12]

Peterson's Liberals lost the 1990 provincial election to the New Democrats under Bob Rae. In 1993 the Rae government released its own transit plan, the Rapid Transit Expansion Program. It retained the Sheppard Line, but only to Don Mills; upgraded Eglinton to a full subway, but only to York City Centre; kept the Scarborough RT extension from the Let's Move proposal, and added an extension of the Spadina Line to York University. [13]

The Eglinton and Sheppard Lines were the initial priorities, and work began almost immediately. In 1995 the Progressive Conservatives under Mike Harris were elected, and they immediately launched a program of sharp cost cutting. Despite already being under construction the Eglinton Line was cancelled. Sheppard did go ahead, but any plans to go further east than Don Mills were shelved. The new Sheppard Line opened in 2002 at a cost of about $1 billion.

As of 2010, the only parts of the Network 2011 plan completed are the Sheppard line between Yonge and Don Mills, and the Spadina line extension to Downsview Station. In 2007, mayor David Miller unveiled the Transit City expansion plan, which proposed light rail lines along two of the Network 2011 corridors, Eglinton and Sheppard East. This plan was accepted, and partially funded by the provincial government's "Big Move" transit plan. In the 2010 municipal election, Rob Ford was elected mayor. He announced the cancellation of Transit City on the day that he took office. [14] In 2017, the Spadina line was realized by the opening of the Toronto–York Spadina subway extension (TYSSE), which did not loop back at Steeles Avenue back towards Finch Station and headed further north into York Region.

See also

Related Research Articles

<span class="mw-page-title-main">Toronto Transit Commission</span> Agency responsible for local public transit in Ontario, Canada

The Toronto Transit Commission (TTC) is the public transport agency that operates bus, subway, streetcar, and paratransit services in Toronto, Ontario, Canada, some of which run into the Peel Region and York Region. It is the oldest and largest of the urban transit service providers in the Greater Toronto Area, with numerous connections to systems serving its surrounding municipalities.

<span class="mw-page-title-main">Line 3 Scarborough</span> Defunct light rapid transit line in Toronto, Canada

Line 3 Scarborough, originally known as Scarborough RT (SRT), was a light rapid transit line that was part of the Toronto subway system in Toronto, Ontario, Canada. The line ran entirely within the eastern district of Scarborough, encompassing six stations and 6.4 kilometres (4.0 mi) of mostly elevated track. It connected with Line 2 Bloor–Danforth at its southwestern terminus, Kennedy, and terminated in the northeast at McCowan. Until its closure in July 2023, the system had a ridership of 3,908,000.

<span class="mw-page-title-main">Line 4 Sheppard</span> Rapid transit line in Toronto, Ontario

Line 4 Sheppard is the newest and shortest subway line of the Toronto subway system, operated by the Toronto Transit Commission (TTC). It opened on November 22, 2002, and has five stations along 5.5 kilometres (3.4 mi) of track, which is built without any open sections in the district of North York along Sheppard Avenue East between Yonge Street and Don Mills Road. All stations are wheelchair accessible and are decorated with unique public art.

<span class="mw-page-title-main">Toronto subway</span> Rapid transit system in Ontario, Canada

The Toronto subway is a rapid transit system serving Toronto and the neighbouring city of Vaughan in Ontario, Canada, operated by the Toronto Transit Commission (TTC). As of September 2023, the subway system is a rail network consisting of three heavy-capacity rail lines operating predominantly underground. As of December 2022, three new lines are under construction: two light rail lines and one subway line.

<span class="mw-page-title-main">Line 2 Bloor–Danforth</span> Rapid transit line in Toronto, Ontario

Line 2 Bloor–Danforth is a subway line in the Toronto subway system, operated by the Toronto Transit Commission (TTC). It has 31 stations and is 26.2 kilometres (16.3 mi) in length. It opened on February 26, 1966, and extensions at both ends were completed in 1968 and again in 1980.

<span class="mw-page-title-main">Line 1 Yonge–University</span> Rapid transit line in the Greater Toronto Area, Ontario

Line 1 Yonge–University is a rapid transit line of the Toronto subway. It serves Toronto and the neighbouring city of Vaughan in Ontario, Canada. It is operated by the Toronto Transit Commission, has 38 stations and is 38.4 km (23.9 mi) in length, making it the longest line on the subway system. It opened as the "Yonge subway" in 1954 as Canada's first underground passenger rail line and was extended multiple times between 1963 and 2017. As of 2010, Line 1 was the busiest rapid transit line in Canada, and one of the busiest lines in North America. In 2022, it averaged over 670,000 riders per weekday.

<span class="mw-page-title-main">Cancelled expressways in Toronto</span> Unbuilt freeways in Toronto, Canada

The cancelled expressways in Toronto were a planned series of expressways in Toronto, Ontario, Canada that were only partially built or cancelled due to public opposition. The system of expressways was intended to spur or handle growth in the suburbs of Toronto, but were opposed by citizens within the city of Toronto proper, citing the demolition of homes and park lands, air pollution, noise and the high cost of construction. The Spadina Expressway, planned since the 1940s, was cancelled in 1971 after being only partially constructed. After the Spadina cancellation, other expressway plans, intended to create a 'ring' around the central core, were abandoned.

The Eglinton West line was a proposed east–west subway line in Toronto, Ontario, Canada, whose construction began in 1994 but was cancelled in 1995. It was to start from the existing Eglinton West station on the Toronto Transit Commission's Yonge–University–Spadina line, travel underneath Eglinton Avenue West, and terminate at Black Creek Drive in its initial phase.

The Queen Street subway line was a proposed subway line for the city of Toronto, Ontario, Canada. It was one of many subway lines planned for, but has yet to be built by the Toronto Transit Commission.

<span class="mw-page-title-main">History of the Toronto Transit Commission</span>

The history of public transportation in Toronto in Canada dates back to the middle 19th century under many different private companies, organizations and owners, which were all later unified as a single government-run entity during the 1920s.

The Relief Line was a proposed rapid transit line for the Toronto subway system, intended to provide capacity relief to the Yonge segment of Line 1 and Bloor–Yonge station and extend subway service coverage in the city's east end. Several plans for an east–west downtown subway line date back to the early 20th century, most of which ran along Queen Street.

Accessibility for people with disabilities on the Toronto Transit Commission (TTC) system is incomplete but improving. Most of the Toronto subway system was built before wheelchair access was a requirement under the Ontarians with Disabilities Act (ODA). However, all subway stations built since 1996 are equipped with elevators, and elevators have been installed in 44 stations built before 1996. Over 75 percent of Toronto's subway stations are accessible. The original plan was to make all stations accessible by 2025; however, a few stations might not be accessible until 2026.

<span class="mw-page-title-main">Transit City</span> Proposed Toronto public transit plan

Transit City was a plan for developing public transport in Toronto, Ontario, Canada. It was first proposed and announced on 16 March 2007 by Toronto mayor David Miller and Toronto Transit Commission (TTC) chair Adam Giambrone. The plan called for the construction of seven new light rail lines along the streets of seven priority transit corridors, which would have eventually been integrated with existing rapid transit, streetcar, and bus routes. Other transit improvements outlined in the plan included upgrading and extending the Scarborough RT line, implementing new bus rapid transit lines, and improving frequency and timing of 21 key bus routes. The plan integrated public transportation objectives outlined in the City of Toronto Official Plan, the TTC Ridership Growth Strategy and Miller's 2006 election platform.

The Don Mills LRT was a proposed light rail line in Toronto, Ontario, Canada. It was part of the Transit City proposal announced March 16, 2007, to be operated by the Toronto Transit Commission (TTC). It was expected to cost approximately $675 million, with construction to begin in 2012, and an expected opening in 2016. It would have been the fifth of the seven Transit City lines to be complete after the Sheppard East, Finch West, Waterfront West, and Eglinton lines. Ridership was estimated to be 21.2 million trips in 2021.

The Eglinton East LRT (EELRT), also known as Line 7 Eglinton East and formerly known as the Scarborough Malvern LRT, is a proposed light rail line in Toronto, Ontario, Canada. The line would be entirely within the district of Scarborough. It was originally part of Transit City, a 2007 plan to develop new light rail lines along several priority transit corridors in the city.

GO-Urban was a planned mass transit project for Greater Toronto to be operated by GO Transit. The system envisioned the use of automated guideway transit vehicles set up in hydro corridors and other unused parcels of land to provide rapid transit services without the expense of constructing tunnels. GO-Urban would serve high-density areas in the downtown core, but also be able to accelerate to high speed between distant stations in the outskirts of the city. Similar deployments were planned for Hamilton and Ottawa.

<span class="mw-page-title-main">Public transportation in Toronto</span>

Public transportation in the Canadian city of Toronto dates back to 1849 with the creation of a horse-drawn stagecoach company. Today, Toronto's mass transit is primarily made up of a system of subways, buses, and streetcars, covering approximately 1,200 km (750 mi) of routes operated by the Toronto Transit Commission (TTC) and inter-regional commuter rail and bus service provided by GO Transit.

SmartTrack is a municipal proposal to enhance GO Transit rail service within Toronto, Ontario, Canada. It takes advantage of the province's existing GO Transit Regional Express Rail plans. SmartTrack has evolved since it was originally proposed by Toronto mayor John Tory as the centrepiece of his 2014 mayoral election campaign.

The Big Move is a regional transportation plan (RTP) published in 2008 and consisting of 62 rapid transit projects to be implemented across the Greater Toronto and Hamilton Area (GTHA). These rapid transit projects are intended to form a seamlessly integrated regional rapid transit network, which is the first priority action in the regional transportation plan. These projects form two long-term templates with 15 and 25 year horizons. These templates outline broad projects; specific details about technology, alignment, stations and service levels for each project are subsequently determined though a cost–benefit analysis or an environmental assessment process.

<span class="mw-page-title-main">Ontario Line</span> Rapid transit line under construction in Toronto

The Ontario Line is an under-construction rapid transit line in Toronto, Ontario, Canada. Its northern terminus will be at Eglinton Avenue and Don Mills Road, at Science Centre station, where it will connect with Line 5 Eglinton. Its southern terminus will be at the existing Exhibition GO Station on the Lakeshore West line. The Ontario Line was announced by the Government of Ontario on April 10, 2019. As of November 2022, the estimated cost for the 15.6-kilometre (9.7 mi) line is CA$17 to $19 billion with an estimated completion in 2031. Originally, the cost was estimated at $10.9 billion with completion by 2027. A groundbreaking ceremony for the project took place on March 27, 2022. Upon opening, the plan is for the line to assume the "Line 3" name, which was used by Line 3 Scarborough until its closure in July 2023.

References

  1. Robin Harvey. "Shaping tomorrow's suburbs." Toronto Star. April 7, 1984. pg. A22
  2. Michael Smith. "$2.7 Billion Metro transit plan called affordable." Toronto Star. May 29, 1985. pg. A1
  3. Michael Smith. "Plans for future top priority after banner TTC year." Toronto Star. December 21, 1985. pg. A6
  4. Michael Smith. "A subway surprise: The Sheppard line." Toronto Star. February 8, 1986. pg. B6
  5. Michael Smith. "$2.7 Billion Metro transit plan called affordable." Toronto Star. May 29, 1985. pg. A1
  6. Michael Smith. "Eglinton transit line gets top billing in 2011." Toronto Star. June 3, 1986. pg. WE6
  7. Michael Smith. "A subway surprise: The Sheppard line." Toronto Star. February 8, 1986. pg. B6
  8. Royson James. "Transit advocates fight transit expansion." Toronto Star. Nov 13, 1993. Sec. C. pg. B.4
  9. Michael Smith. "Network 2001: The Battle over who gets what." Toronto Star. February 8, 1986. pg. B6
  10. Alfred Holden. "Rail lands spark classic city hall fight." Toronto Star. June 18, 1986. pg. A22
  11. Michael Smith. "Province considering new subways TTC says." Toronto Star. April 5, 1987. pg. A3
  12. Jim Byers. "Metro-aera transit plan could cost $4 billion." Toronto Star. April 5, 1990. pg. A1
  13. Royson James. "Deciding which train to take." Toronto Star. March 8, 1994. pg. A15
  14. Mayor Rob Ford: “Transit City is over” Archived 2013-01-19 at the Wayback Machine Toronto Life December 1, 2010