Transit City

Last updated

Promotional billboard indicating the original seven proposed LRT lines. Transit City billboard.jpg
Promotional billboard indicating the original seven proposed LRT lines.

Transit City was a plan for developing public transport in Toronto, Ontario, Canada. It was first proposed and announced on 16 March 2007 by Toronto mayor David Miller and Toronto Transit Commission (TTC) chair Adam Giambrone. The plan called for the construction of seven new light rail lines along the streets of seven priority transit corridors, which would have eventually been integrated with existing rapid transit, streetcar, and bus routes. [1] Other transit improvements outlined in the plan included upgrading and extending the Scarborough RT line (Line 3 Scarborough), implementing new bus rapid transit lines, and improving frequency and timing of 21 key bus routes. [2] [3] The plan integrated public transportation objectives outlined in the City of Toronto Official Plan, the TTC Ridership Growth Strategy and Miller's 2006 election platform.

Contents

By 2009, preliminary engineering work and environmental impact assessments had been done for the construction of the light rail lines. [4] Construction of one of the lines began in December 2009.

On 1 December 2010, Rob Ford took office as the city's new mayor based on an election promise to expand the subway system, instead of implementing light rail lines. As a result, he cancelled the Transit City initiative. [5] However, in early 2012, Toronto City Council voted in favour of motions to resume work on the Sheppard East LRT, Eglinton Crosstown LRT and Etobicoke–Finch West LRT lines and to replace the Scarborough RT, defeating Rob Ford's campaign for subways. [6] [7] The master agreement for these lines was signed on 28 November 2012. While these projects were originally proposed under Transit City, they became part of Metrolinx's implementation of The Big Move regional transportation plan. [8]

In 2016, the City of Toronto directed its staff to resurrect and update the 2009 Transit City plan for the Scarborough Malvern LRT, renaming the project as the Eglinton East LRT. Until 2021, the city considered making the EELRT an eastward extension of Line 5 Eglinton (a.k.a. the Eglinton Crosstown LRT), but by 2022, it decided that the Eglinton East LRT should be a standalone line. [9] :11,12 By 2018, the province had decided to abandon the Sheppard East LRT, instead proposing to extend Line 4 Sheppard to McCowan Road in Scarborough, [10] after which the city decided to incorporate the eastern portion of the Sheppard East LRT into its proposal for the Eglinton East LRT. [9] :22

As of 2023, two light rail lines originally proposed as part of Transit City are under construction: Line 5 Eglinton and Line 6 Finch West.

Projects

Map of proposed light rail and bus rapid transit lines
Transit City.jpg

A map of the proposed light rail transit (LRT) and bus rapid transit (BRT) lines according to Transit City. The "existing subway / RT" lines include the proposed northern extension of the Yonge–University–Spadina line and the proposed eastern extension of the Scarborough RT. Future stations to be built, both subway and LRT, are in italics. Proposed LRT stops on each LRT line are not shown. Note that the Scarborough RT is shown as an existing subway / RT line, although its revitalization plan was part of Transit City.

The plan proposed 120 km (74.6 mi) of tram or electric light rail along seven routes. The proposed network would carry 175 million riders a year, of which 75 million would be new Toronto Transit Commission (TTC) users. [11] The seven proposed corridors were divided into two project priority phases: current and planned. In May 2009, Metrolinx CEO Robert Prichard announced that after further study, the proposed project was being scaled down, with shortened routes or deferrals to fit within the dedicated provincial funding for Transit City, not factoring in the province's March 2010 announcement that it was deferring $4 billion in funding. [12]

The TTC was prepared to fund the entire cost of the network over a longer period of time. The highest priority was assigned to the Sheppard East, Eglinton Crosstown and Etobicoke–Finch West LRT lines, and to the revitalization of the Scarborough RT line (Line 3 Scarborough), which was projected to be built by 2020. In addition to the mentioned lines, it was likely that some sort of link would be established between the two lines, so that they could share a single storage facility. The TTC completed the environmental impact assessments for most of these lines, the first one being completed for the Sheppard East line. [13] The construction of this line commenced in December 2009 [14] but was stopped a year later by newly elected mayor Rob Ford. [15]

Light rail transit

As of 2023, the following two light-rail lines were under construction. Both lines originated from the Transit City proposal but with some modifications. These are Metrolinx projects.

As of 2023, the following projects, originating from Transit City, are being pursued by the City of Toronto rather than Metrolinx. They are in the proposal stage.

As of 2023, the following Transit City projects were inactive or cancelled:

Scarborough RT

Part of the Transit City project was the revitalization and extension of the Scarborough RT. In 2010, the TTC and the City of Toronto completed an environmental assessment to convert the line to light rail and extend it to Malvern from its eastern terminus, McCowan station, with potential new stations at Bellamy Road, Centennial College's Progress Campus and Sheppard Avenue, with a possible additional station at Brimley Road between the existing Midland and Scarborough Centre stations. [27]

In 2007, the service's existing ICTS (intermediate capacity transit system) fleet was approaching the end of its operational lifespan; as trains were no longer built to that line's specification, a replacement was needed. A multi-year shutdown to modify the line's infrastructure would have been required regardless of whether light rail or an upgraded form of ICTS (Mark II Vehicles designed by Bombardier) was used. Thus, it was decided to implement light rail similar to other Transit City light-rail lines. [28]

During his 2010 mayoralty campaign, Rob Ford denounced the idea of light rail transit and instead proposed replacing the Scarborough RT with an extension of Line 2 Bloor–Danforth. [29] In 2011, the province persuaded Rob Ford to have the Scarborough RT replaced with an extension of the Eglinton Crosstown LRT so that the latter would run from Mount Dennis to Scarborough City Centre. [30]

In June 2013, Toronto City Council decided to replace the Scarborough RT with an extension of Line 2 Bloor–Danforth north to Sheppard Avenue rather than light rail. [31]

In April 2019, Premier Doug Ford announced that the province would finance and build a three-stop extension of the Line 2 to replace the Scarborough RT. [32]

Bus rapid transit

Transit City also called for six new bus rapid transit (BRT) right-of-way lines to be built once light rail transit construction had been completed. Originally to be TTC projects, one has been built, two proposed lines were taken over by Metrolinx, and the others have been abandoned. The proposed routes were: [33] :24–26,32

Funding and costs

In April 2009, the Finch West, Eglinton Crosstown, and the Scarborough RT upgrade and extension projects secured $7.2 billion in funding from the province, [34] while the Sheppard East LRT received $613 million in funding from the province and $317 million in federal funding. [35] In November 2007, the TTC provided an updated estimate of the costs of the proposal in its capital budget. [36] The project cost to be paid by the Government of Ontario was $8.3 billion.

On 15 June 2007, the Government of Ontario announced its MoveOntario 2020 plan, which called for a major overhaul and expansion of the Greater Toronto Area's transit systems, including the Transit City proposal, that was expected to cost an estimated $17.5 billion in provincial and federal funding over a 12-year period. [37] The provincial government proposed providing two-thirds of the funds ($11.5 billion) and asked the federal government to pay the remaining one-third ($6 billion). [37] However, Prime Minister Stephen Harper's government did not commit to this spending plan. [37] The province's $17.5 billion MoveOntario 2020 plan called for a total number of 52 transit projects in the GTA to be funded, with 95% of the projects to be completed by the year 2020. [38]

On 18 June 2009, Toronto mayor David Miller requested federal funding from the Harper government's $12-billion stimulus spending to purchase new streetcars as part of the Transit City plan. The city faced a deadline of 27 June 2009 to commit to the $1.2-billion deal signed with Bombardier for the 204 streetcars. Miller and Ontario premier Dalton McGuinty flew to Thunder Bay to announce their funding for the new streetcars, hoping to convince the Harper government to come up with its one-third share of the cost. Federal Transport Minister John Baird rejected the request outright. Baird stated that streetcar funding clearly failed to meet the stimulus bill's requirement that the funds would have to be spent in 2 years, as it was meant to put money into the economy quickly to buoy demand and stave off deflation, while Transit City was a long-term project. The stimulus also required funds to be spent on infrastructure in the municipality where the application was granted in order to create local employment, whereas the jobs created by building streetcars would be in Thunder Bay and not Toronto. Baird noted that Toronto was the only one of 2,700 applicants that did not meet the eligibility criteria. [39] [40] [41]

On 25 March 2010, the Ontario provincial government announced their decision to postpone $4 billion of funding to Metrolinx for the MoveOntario 2020 project, which included funding for Transit City. Miller had expressed discontent and condemned McGuinty, who had earlier promised to provide full funding for Transit City in order for it to be built before the 2015 Pan American Games in Toronto. [42] The initial investment was projected to create approximately 100,000 jobs. [43] [44] The stated reason for the decision was a $21.3 billion deficit in the 2010 provincial operating budget. [45] Standard economic metrics, however, show that as stimulus, Transit City would have added significantly to provincial tax revenues, and, given the province's 50-year amortization, the plan overall would have reduced Ontario's annual budget deficit. [46] The funding deferral caused widespread debate, protests and criticism of Premier McGuinty by politicians and local groups. As a result of the postponement, the Transit City plan was scaled down and expected completion dates were pushed farther back. [47]

The delay in funding, according to Miller, meant that the priority LRT lines (Scarborough RT, Etobicoke–Finch West and Eglinton Crosstown) would not be able to meet their planned construction and opening dates, whereas work on the Sheppard East line was to proceed as its construction had already begun. [48] Despite the controversy over the funding, Metrolinx negotiated a deal with Bombardier Transportation for a new fleet of light rail vehicles which were to be used on future Transit City lines. [49]

After the announcement, the City of Toronto and community groups began a lobbying campaign to restore funding, similar to the campaign leading to the initial funding. Mayor Miller condemned the funding delay and requested riders contact their members of Provincial Parliament to have the government restore the funding. Other Transit City advocates petitioned and organized rallies to promote the immediate construction of the projects.[ citation needed ]

The Public Transit Coalition was launched by transit riders to counter the delay in Transit City funding. On 21 April 2010, the group held an event at the Toronto City Hall Council Chambers. [50]

Economic effect

Had the project been implemented as originally proposed, Transit City had been expected to create approximately 200,000 new jobs in Ontario from $8.3 billion invested. [51] This included operation, construction, and economic stimulus effect of spending. Unemployment reached 9% in 2010, the GTA's highest level since 1995. [52]

The Ontario government's promised funding for Transit City was projected to have created short-term economic growth of $12.4 billion per year, [53] adding in the near-term 2.1% to Ontario's GDP, according to the American Public Transportation Association. [54]

According to the Federation of Canadian Municipalities research, Transit City was to have produced a first-year GDP gain of $17.3 billion, were all the money to be spent in the first year. After five years, the project would have added $8.0 billion per year to GDP, with each $1 billion spent on transit adding 0.06% to Canada's GDP annually. This compared closely to US Congressional testimony, which showed infrastructure investment to stimulate annual GDP at a multiplier of 1.69 within one year, or $14 billion per year for Transit City. [55] Both studies counted direct impact of spending only. [56]

In addition to this direct consequence, long-term indirect effects on business costs, productivity, and consumer spending from reduced congestion and travel costs were projected to have added an additional $14.1 billion of value annually to Ontario's economy. [51] Other indirect effects not measured were improved air quality and public health and reduced carbon emissions from extending rapid transit to 1.1 million more people.

Ontario taxes capture 12% of Ontario's GDP, meaning that Transit City's stimulus effect would have directly added to provincial tax revenue. [57] [58] Transit City's projected direct economic impact of $12.4 billion per year would have netted the Ontario treasury $1.4 billion in annual tax revenue. Its indirect effects on congestion and transportation costs would have produced an additional $1.7 billion per year in tax revenue. In 2010, Government of Canada bonds offered 4% interest for a 10-year term. [58] Transit City's $8.3 billion expansion funding, if amortized over 10 years at prevailing bond rates in 2010, would have cost the province $1.2 billion per year. [59]

See also

Related Research Articles

<span class="mw-page-title-main">Line 3 Scarborough</span> Defunct light rapid transit line in Toronto, Canada

Line 3 Scarborough, originally known as Scarborough RT (SRT), is a defunct medium-capacity rapid transit line that was part of the Toronto subway system in Toronto, Ontario, Canada. The line ran entirely within the eastern district of Scarborough, encompassing six stations and 6.4 kilometres (4.0 mi) of mostly elevated track. It connected with Line 2 Bloor–Danforth at its southwestern terminus, Kennedy, and terminated in the northeast at McCowan. Until its closure in July 2023, the system had a ridership of 3,908,000 per year.

<span class="mw-page-title-main">Line 4 Sheppard</span> Rapid transit line in Toronto, Ontario

Line 4 Sheppard is the newest and shortest rapid transit line of the Toronto subway system, operated by the Toronto Transit Commission (TTC). It opened on November 22, 2002, and has five stations along 5.5 kilometres (3.4 mi) of track, which is built without any open sections in the district of North York along Sheppard Avenue East between Yonge Street and Don Mills Road. All stations are wheelchair accessible and are decorated with unique public art.

<span class="mw-page-title-main">Toronto subway</span> Rapid transit system in Ontario, Canada

The Toronto subway is a rapid transit system serving Toronto and the neighbouring city of Vaughan in Ontario, Canada, operated by the Toronto Transit Commission (TTC). As of September 2023, the subway system is a rail network consisting of three heavy-capacity rail lines operating predominantly underground. As of December 2022, three new lines are under construction: two light rail lines and one subway line.

<span class="mw-page-title-main">Line 2 Bloor–Danforth</span> Rapid transit line in Toronto, Ontario

Line 2 Bloor–Danforth is a rapid transit line in the Toronto subway system, operated by the Toronto Transit Commission (TTC). It has 31 stations and is 26.2 kilometres (16.3 mi) in length. It opened on February 26, 1966, and extensions at both ends were completed in 1968 and again in 1980.

<span class="mw-page-title-main">Malvern, Toronto</span> Neighbourhood in Toronto, Ontario, Canada

Malvern is a neighbourhood in the city of Toronto, Ontario, Canada, with a population of 44,315. It is located in the northeast corner of the city.

<span class="mw-page-title-main">Scarborough Centre station</span> Toronto subway station

Scarborough Centre is a bus terminal in Toronto, Ontario, Canada, serving multiple bus routes of the Toronto Transit Commission (TTC) and one Durham Regional Transit (DRT) bus route. It was also a rapid transit station serving Line 3 Scarborough of the Toronto subway system until Line 3's closure on July 24, 2023. It is located north of Ellesmere Road between Brimley and McCowan Roads, just south of Highway 401. It was adjacent to the former Scarborough Centre Bus Terminal, which was a station for GO Transit buses and other intercity coach services until the TTC modified the facility for TTC buses.

The Eglinton West line was a proposed east–west subway line in Toronto, Ontario, Canada, whose construction began in 1994 but was cancelled in 1995. It was to start from the existing Eglinton West station on the Toronto Transit Commission's Yonge–University–Spadina line, travel underneath Eglinton Avenue West, and terminate at Black Creek Drive in its initial phase.

<span class="mw-page-title-main">History of the Toronto Transit Commission</span>

The history of public transportation in Toronto in Canada dates back to the middle 19th century under many different private companies, organizations and owners, which were all later unified as a single government-run entity during the 1920s.

The Relief Line was a proposed rapid transit line for the Toronto subway system, intended to provide capacity relief to the Yonge segment of Line 1 and Bloor–Yonge station and extend subway service coverage in the city's east end. Several plans for an east–west downtown subway line date back to the early 20th century, most of which ran along Queen Street.

<span class="mw-page-title-main">Line 5 Eglinton</span> Under construction light rail line in Toronto, Ontario

Line 5 Eglinton, also known as the Eglinton Crosstown LRT or the Crosstown, is a light rail transit line that is under construction in Toronto, Ontario, Canada, to expand and improve public transportation in the Greater Toronto Area. Owned by Metrolinx and operated by the Toronto Transit Commission (TTC), the line will be part of the Toronto subway system. The Crosstown was conceived in 2007 during the administration of Toronto mayor David Miller as part of Transit City, a large-scale transit expansion plan. The line is being constructed in two phases.

The Don Mills LRT was a proposed light rail line in Toronto, Ontario, Canada. It was part of the Transit City proposal announced March 16, 2007, to be operated by the Toronto Transit Commission (TTC). It was expected to cost approximately $675 million, with construction to begin in 2012, and an expected opening in 2016. It would have been the fifth of the seven Transit City lines to be complete after the Sheppard East, Finch West, Waterfront West, and Eglinton lines. Ridership was estimated to be 21.2 million trips in 2021.

The Sheppard East LRT was a proposed light rail line in Toronto, Ontario, Canada. It was first announced as part of the Transit City proposal in 2007. The Sheppard East LRT as proposed was to be 13 kilometres (8.1 mi) long, travel along Sheppard Avenue from Don Mills subway station to east of Morningside Avenue, and be operated by the Toronto Transit Commission (TTC).

The Eglinton East LRT (EELRT), also known as Line 7 Eglinton East and formerly known as the Scarborough Malvern LRT, is a proposed light rail line in Toronto, Ontario, Canada. The line would be entirely within the district of Scarborough. It was originally part of Transit City, a 2007 plan to develop new light rail lines along several priority transit corridors in the city.

The Jane LRT is an inactive proposal for a light rail line in Toronto, Ontario, Canada. It was originally proposed in 2007, cancelled in 2010, and later revived in the 2013 "Feeling Congested?" report by the City of Toronto, where it was labelled as a "Future Transit Project". However, in April 2019, Ontario Premier Doug Ford announced the province's plans for rapid transit development and funding for the Greater Toronto Area that omitted the Jane LRT.

<span class="mw-page-title-main">Line 6 Finch West</span> Under construction light rail line in Toronto, Ontario

Line 6 Finch West, also known as the Finch West LRT, is a light rail transit line under construction in Toronto, Ontario, Canada, to be operated by the Toronto Transit Commission. The 10.3-kilometre (6.4 mi), 18-stop line is to extend from Finch West station on Line 1 Yonge–University to the North Campus of Humber Polytechnic in Etobicoke under the former name of Humber College. The line will operate in a dedicated above-ground right-of-way, much of it within Finch Avenue, segregated from street traffic. The line will use transit signal priority and standard gauge rather than the broad Toronto gauge. The line is forecast to carry about 14.6 million rides a year or 40,000 a day by 2031 and will replace the 36B Finch West bus route, which is one of the three busiest bus routes in Toronto. Line 6 was originally expected to open within the first half of 2024, with an estimated cost of CA$2.5 billion. For budget purposes, the TTC made the assumption that Line 6 would open no earlier than September 2024. However, the builder, Mosaic Transit Group, expects the line to open by the end of 2024.

MoveOntario 2020 was a 2007 plan proposed by the Government of Ontario that would fund 52 rapid-transit projects throughout the Greater Toronto and Hamilton Area in Ontario, Canada. It was succeeded by The Big Move and GO Transit's Go 2020.

Network 2011 was a plan for transit expansion created in 1985 by the Toronto Transit Commission. It was centred on three proposed subway lines: the Downtown Relief Line, Eglinton West Line, and the Sheppard Line. Only a portion of the Sheppard Line was built. The Eglinton West and Downtown Relief Lines were cancelled; they were superseded by the Eglinton Crosstown light rail line and the Ontario Line respectively.

SmartTrack is a municipal proposal to enhance GO Transit rail service within Toronto, Ontario, Canada. It takes advantage of the province's existing GO Transit Regional Express Rail plans. SmartTrack has evolved since it was originally proposed by Toronto mayor John Tory as the centrepiece of his 2014 mayoral election campaign.

The Big Move is a regional transportation plan (RTP) published in 2008 and consisting of 62 rapid transit projects to be implemented across the Greater Toronto and Hamilton Area (GTHA). These rapid transit projects are intended to form a seamlessly integrated regional rapid transit network, which is the first priority action in the regional transportation plan. These projects form two long-term templates with 15 and 25 year horizons. These templates outline broad projects; specific details about technology, alignment, stations and service levels for each project are subsequently determined though a cost–benefit analysis or an environmental assessment process.

References

  1. Kalinowski, Tess (24 April 2009). "TTC picks Bombardier to supply streetcars". Toronto Star . Retrieved 25 April 2009.
  2. Kalinowski, Tess (21 August 2009). "TTC unveils proposal to improve bus service". Toronto Star. Retrieved 21 August 2009.
  3. "Transit City Bus Plan" (PDF). Toronto Transit Commission. 21 August 2009. Archived from the original (PDF) on 2 August 2021. Retrieved 8 October 2021.
  4. "Transit City Light Rail Plan: Status Update for February 2009" (PDF). Toronto Transit Commission. 18 February 2009. Archived from the original (PDF) on 28 July 2017. Retrieved 8 October 2021.
  5. "Rob Ford: 'Transit City is over'". CBC News. Toronto. 1 December 2010. Archived from the original on 4 October 2013. Retrieved 8 October 2021.
  6. Church, Elizabeth (8 February 2012). "TTC chair defeats Rob Ford, wins bid to bring transit above-ground". The Globe and Mail . Toronto. Retrieved 8 February 2012.
  7. Church, Elizabeth; Kelly Grant (23 March 2012). "Transit defeat leaves Ford on rocky ground". The Globe and Mail . Toronto. Retrieved 23 March 2012.
  8. Tess Kalinowski (28 November 2012). "TTC, Metrolinx finally sign off on LRTs". Toronto Star . Retrieved 28 November 2012.
  9. 1 2 3 4 City of Toronto; Toronto Transit Commission (May 2023). Eglinton East Light Rail Transit (EELRT)–Functional (10%) Design Phase (PDF). Eglinton East LRT: Public Consultation. Phase One Virtual Public Meetings. Archived (PDF) from the original on 18 May 2023. Retrieved 18 May 2023.
  10. 1 2 "How Doug Ford's $28.5-billion transit overhaul compares with Toronto's existing plans". Toronto Star . 10 April 2019. Retrieved 16 October 2019.
  11. Kalinowski, Tess; John Spears (17 March 2007). "Success driven by TTC: Miller". Toronto Star . pp. B.1. Retrieved 17 June 2007.
  12. Kalinowski, Tess (5 May 2010). "Toronto's Trancity slower, shorter". Toronto Star . Retrieved 5 May 2010.
  13. Sheppard Avenue East Light Rail Transit (LRT) – Background Archived 6 June 2011 at the Wayback Machine
  14. "Transit City begins: Officials launch construction of the Sheppard East LRT - Transit Toronto - Weblog".
  15. "Latest Breaking News, Headlines & Updates | National Post".
  16. 1 2 3 4 5 6 "Transit City Report". Toronto Transit Commission Report. City of Toronto. 21 March 2007. Archived from the original on 8 July 2007. Retrieved 17 June 2007.
  17. "What you need to know about Doug Ford's contentious plan for transit in the GTA". CBC News. Canadian Broadcasting Corporation. 10 April 2019. Retrieved 21 December 2019.
  18. Steve Munro (23 November 2006). "Waterfront West LRT plans". Archived from the original on 3 March 2015. Retrieved 2 March 2015.
  19. Inside Toronto: LRT planned for 2015 to run along Lake Shore Boulevard West has now been shelved by city officials
  20. "Waterfront Transit "Reset"" (PDF). www.toronto.ca. Retrieved 28 July 2024.
  21. "Waterfront Transit Update" (PDF). Archived from the original (PDF) on 28 January 2018. Retrieved 8 January 2018.
  22. University of Toronto Scarborough: Re-Imagine: Benefit students now and in the future Archived 30 January 2010 at the Wayback Machine
  23. "New Scarborough transit plan 'buys peace in the land'". Toronto Star . 20 January 2016.
  24. "Delay to Sheppard East LRT raises hopes of possible subway line". Scarborough Mirror. 24 August 2012. Retrieved 25 October 2012.
  25. Spurr, Ben (23 June 2017). "Federal funding shuffle casts doubt on Sheppard LRT". The Toronto Star. ISSN   0319-0781 . Retrieved 6 November 2017.
  26. McLaughlin, Amara (10 April 2019). "Doug Ford commits $11.2B for 4 major Toronto-area transit projects". Canadian Broadcasting Corporation. Retrieved 15 August 2019.
  27. "Extension of the Scarborough Rapid Transit & Kennedy Station Improvements". City of Toronto. 29 May 2012. Archived from the original on 6 October 2012. Retrieved 10 March 2013.
  28. Kalinowski, Tess (15 November 2015). "Skip the Scarborough subway and modernize the SRT, says transit expert". Toronto Star . Retrieved 20 November 2015.
  29. "Rob Ford: 'Transit City is over'". CBC News. 1 December 2010. Archived from the original on 5 December 2010.
  30. "Ontario And Toronto Moving Forward On Public Transit". Ontario Newsroom. 31 March 2011.
  31. Moore, Oliver (2 July 2013). "Metrolinx to Toronto: Subway is yours". The Globe and Mail . Retrieved 3 July 2013.
  32. Pagliaro, Jennifer (10 April 2019). "Doug Ford vows 3-stop Scarborough subway. The timeline could leave riders on buses for years". Toronto Star . Archived from the original on 21 December 2019. Retrieved 15 March 2020.
  33. "Transit City Bus Plan" (PDF). Toronto Transit Commission. August 2009. Archived from the original (PDF) on 7 October 2009.
  34. "Province Moving Transit Projects Forward" (Press release). Ontario Ministry of Transportation. 1 April 2009. Retrieved 28 October 2009.
  35. "Ontario Moves Forward With Sheppard Transit Line" (Press release). Premier of Ontario. 15 May 2009. Retrieved 28 October 2009.
  36. 2008-2012 Capital Program and 10-Year Capital Forecast
  37. 1 2 3 Gray, Jeff (16 June 2007). "Ontario planning $11.5-billion in public transit". The Globe and Mail . Toronto. Retrieved 18 June 2007.[ permanent dead link ]
  38. Kalinoswski, Tess (16 June 2007). "A$17,5B transit promise". Toronto Star . Retrieved 17 June 2007.
  39. John Baird's profane truth - The Globe and Mail
  40. High stakes in streetcar game - Toronto Star
  41. Baird says no to stimulus money for T.O. streetcars - CTV Toronto News
  42. "McGuinty deals a blow to Toronto by delaying LRT funds". The Globe and Mail. 26 March 2010. Retrieved 6 November 2017.
  43. Economic Impact of Public Transportation Investment (PDF), American Public Transportation Association, October 2009 (pg. 28, Exhibit 3-3, Jobs Generated in the US per Billion Dollars of Spending on Public Transportation)
  44. Todd Litman (23 February 2010), Evaluating Public Transit Benefits and Costs: Best Practices Guidebook (PDF), Victoria Transport Policy Institute (pg. 59, Economic Development Impacts)
  45. "2010 Ontario Budget: Backgrounder Managing Responsibly". www.fin.gov.on.ca. Ontario Ministry of Finance. Archived from the original on 20 April 2021. Retrieved 28 July 2024.
  46. "It's a money train: Transit City's a fast track to boom, not a ticket to budget doom". Now Magazine. Archived from the original on 15 October 2012.
  47. Kalinowski, Tess; Rider, David (29 April 2010). "Province's pledge: 4 Transit City lines in 10 years". Toronto Star . Retrieved 29 April 2010. "Initial work by Metrolinx suggests that the four Transit City projects can reasonably be completed in 10 years, while achieving the required savings of $4 billion in the first five years," says the 27 April letter to City Manager Joe Pennachetti obtained by the Toronto Star.
  48. "Budget slashes billions from Toronto transit expansion". CBC News. 26 March 2010. Archived from the original on 30 March 2010.
  49. Kalinowski, Tess (12 April 2010). "Metrolinx negotiations signal green light for Transit City". The Star. Toronto.
  50. "Toronto riders rally to save transit city project". 21 April 2010.
  51. 1 2 Economic Impact of Public Transportation Investment (PDF), American Public Transportation Association, October 2009 (pg. iii, Table within Summary)
  52. "Unemployment hits 15-year high in Ontario", Toronto Star , 6 June 2009
  53. Economic Impact of Public Transportation Investment (PDF), American Public Transportation Association, October 2009 (pg. ii, Table within Summary, Summary of the Short-term Economic Impact per Billion Dollars of National Investment in Public Transportation)
  54. "2010 Ontario Budget: Chapter II: Ontario's Economic Outlook and Fiscal Plan, Section C: Ontario's Economic Outlook". Archived from the original on 14 February 2022.
  55. Mark Zandi (21 January 2009), Congressional Testimony for the 2009 US Stimulus Bill (PDF) pg. 9, Table 2. Fiscal Stimulus Bang for the Buck
  56. Macroeconomic Impacts of Spending and Level-of-Government Financing (PDF), Federation of Canadian Municipalities, 31 May 2008, archived from the original (PDF) on 18 July 2011 (pg. 6, Table 1. GDP Impacts of Additional Infrastructure Spending)
  57. "2010 Ontario Budget: Chapter II: Ontario's Economic Outlook and Fiscal Plan Section D: Ontario's Revenue Outlook". www.fin.gov.on.ca. Archived from the original on 13 May 2021.
  58. 1 2 "2010 Ontario Budget: Chapter II: Ontario's Economic Outlook and Fiscal Plan, Section B: 2009–10 Interim Fiscal Performance". www.fin.gov.on.ca. Archived from the original on 14 February 2022.
  59. Amortization calculator