Automatic Train Protection (United Kingdom)

Last updated

Automatic Train Protection (ATP) is a method of beacon based railway cab signalling developed by British Rail. The system is only installed on the Great Western Main Line between London Paddington and Bristol Temple Meads, and the Chiltern Main Line from London Marylebone to High Wycombe and Aylesbury.

Contents

History

Background

Automatic Train Protection notice on a then First Great Western InterCity 125 GWR HST ATP notice 1 (cropped).jpg
Automatic Train Protection notice on a then First Great Western InterCity 125

A noticeable uptick in signal passed at danger (SPAD) instances in the 1980s led to calls for a new safety system to be adopted that would entirely prevent their occurrence; specifically, the report into the Clapham Junction rail crash (itself not a SPAD accident) specifically stipulated that British Rail (BR) was to fully implement such a system on nationwide basis within five years. From the onset, it was recognised that considerable work would be involved both to develop and deploy the envisioned system. [1]

Accordingly, in 1988, BR launched a three-year program to develop and deploy this new system, with the aim of starting its implementation by 1992. It was assigned the name Automatic Train Protection (ATP), and was a considerably more comprehensive system than the Automatic Warning System (AWS) that was already in operation at that time. Whereas the AWS system only issued alerts to the train's driver, effectively an advisory arrangement that remained open to failure via human error, ATP would instead be able to take control of the train and override the driver to ensure it was driven in accordance with the signalling, as well as other conditions. [2]

As a means of risk mitigation, BR opted to perform two ATP pilot systems, the results from these separate schemes was intended to inform planners on what would be involved in a wider rollout as well as to identify which implementation was superior and thus should be installed nationally. [1] The routes used for the two pilot schemes were London Paddington to Bristol, and London Marylebone to High Wycombe and Aylesbury. [3] Each pilot scheme involved the installation and use of different equipment, nonetheless sharing the same purpose, designation, and numerous other characteristics. The Western scheme used equipment supplied by Ateliers de Constructions Electriques de Charleroi (ACEC), while the Chiltern route was furnished with GEC General Signal-built equipment. [1] [4]

Neither of the trial schemes involved systems that had been designed from scratch. The Western route's ATP was heavily based on Belgium's Transmission balise-locomotive (TBL) system, while the Chiltern route's ATP was adapted from Germany's Linienzugbeeinflussung system, known as SELCAB. [1] Both trials proved to be largely satisfactory in terms of their operations; following a comprehensive safety review process, Chiltern's ATP infrastructure system received independent safety assurance and thus changed from being a pilot system to being a regular system that was fully usable. [1]

Scale-back

At the onset of ATP's development, there was an expressed recommendation to expand its coverage across Britain's rail network within half a decade; at one point, BR's management declared that ATP was to be installed on "a large percentage of its network". [5] Railtrack, the agency that took over the management of Britain's railway infrastructure from BR in 1994, subsequently only committed to completion of the two pilot schemes, adaptation for new high-speed lines, and to search for a cheaper alternative for the rest of the network. [6]

One of the alternate schemes that was jointly explored by Railtrack and the train operators was Signal Passed At Danger (SPAD) Reduction And Mitigation (SPADRAM), the principal outcome of which was the Train Protection & Warning System (TPWS). [1] TPWS automatically stops trains that pass red signals or speed restrictions at too high a speed, but does not monitor speed constantly, hence only mitigating SPADs, rather than wholly preventing them. [7] In comparison to ATP, it was a considerably cheaper system that was able to achieve 70 per cent of the same preventable risk as ATP. [1] Following an evaluation period, it was determined that TPWS was more cost effective than ATP, thus railway planners opted to roll out TPWS instead. [8] The complete fitout of TPWS to all trains, and over 12,000 signals, 650 buffer stops, and around 1,000 permanent speed restrictions, was completed by December 2003; there was a significant reduction in SPADs observed in the years thereafter. [1]

The total cost of ATP was at one stage estimated to be £750 million, equivalent to £1.131 billion in 2020. [5] In 1994, British Rail and Railtrack estimated that a comprehensive deployment scheme would come at a cost of £14 million (£23 million today) per life saved, compared to the £4 million per life which they considered to be good value for money. [5] A Health and Safety Commission report later estimated a full installation of ATP would cost £11 million per life saved, or £5 million if only installed at high-risk locations; Railtrack stated that it concurred with these figures. [5] The high cost of the scheme was a major factor in the decision against ATP's further deployment. [1]

Later use and phase out

While the planned national rollout of ATP was permanently abandoned, the two trial schemes proved suitable for full and regular use. [1] Under the Railway Safety Regulations 1999 (RSR1999), which came into in force in January 2000, requires infrastructure and train operators to permit only trains with train protection equipment fitted to operate and, wherever it was reasonably practicable to fit ATP, the system had to be operational. As such, both the Chiltern and Western ATP systems have remained in service alongside TPWS for multiple decades. [1]

The Chiltern route's SELCAB ATP equipment was initially supported by Alcatel and subsequently by Thales. [1] However, due to its nature as a bespoke, complex, and unique systems, it was considered to be difficult to keep operational for beyond its first decade of operation. During 2011, roughly 21 years after ATP's instigation, Thales issued a formal advisory that the SELCAB system was to be declared obsolete within the near future. [1] The announcement motivated railway managers to perform large final purchases of spare equipment and components so that there was sufficient stock to sustain ATP's infrastructure and fleet fitment alike for the medium term. In spite of a life extension programme performed during the 2010s, the decommissioning of ATP has been viewed as inevitable as a long term outcome. [1]

According to railway industry periodical Rail Engineer, by 2020, the availability of ATP was at considerable risk of becoming unsustainable. [1] The European Train Control System (ETCS) has been viewed as a natural replacement to ATP, which is gradually being rolled out across the British rail network as its principal signalling solution. While ETCS is planned to be operational on the Chiltern route by around 2035, it was not realistic to expect ATP to remain viable until then. [1] It was concluded that, with enhancements, TPWS was capable of replacing ATP as a bridging measure without much loss in functionality. This substitution required an exemption from RSR1999 stipulations by regulatory authorities along with a review of all existing TPWS installations along the Chiltern route, which upgrades being performed where relevant. [1]

Function and operation

The aim of ATP is to prevent trains from both exceeding speed restrictions, and from passing signals at danger. [9] [10] The system is beacon based, with information transmitted to the train at fixed intervals via stationary beacons at key points along the line. The on board computer takes track and signal information from the beacons, and calculates the maximum speed of the train. [1] [11] When the maximum permitted speed decreases, such as when approaching a signal at danger, three braking curves are calculated: the indication curve, which is the ideal deceleration to the new limit; the warning curve, 3 miles per hour (4.8 km/h) above the indication curve, which causes a warning to the driver; and the intervention curve, 6 miles per hour (9.7 km/h) above the indication curve. At this point, the train will apply the brakes automatically. [12]

ATP can be deployed either as a continuous system or intermittently. [1] While a continuous ATP system would be constantly communicating with each train throughout its journey, an intermittent arrangement could only communicate with a train when it was at specific fixed locations along the track where data could be transmitted; such locations would normally be around signals, junctions, and locations between signals that had been identified as being high-risk. [1] Thus, intermittent ATP is normally viewed as an add-on to conventional lineside signals. The Chiltern route's ATP system, known as SELCAB, can also supervise train speeds around Permanent Speed Restrictions (PSRs) and pre-programmed Temporary Speed Restrictions (TSRs), but not Emergency Speed Restrictions (ESRs); in contrast, the Western route's ATP system is not capable of this level of speed supervision. [1]

Related Research Articles

The Ladbroke Grove rail crash was a rail accident which occurred on 5 October 1999 at Ladbroke Grove in London, England, when two passenger trains collided almost head-on after one of them had passed a signal at danger. With 31 people killed and 417 injured, it was one of the worst rail accidents in 20th-century British history.

<span class="mw-page-title-main">Great Western Main Line</span> Important railway corridor in England, UK

The Great Western Main Line (GWML) is a main line railway in England that runs westwards from London Paddington to Bristol Temple Meads. It connects to other main lines such as those from Reading to Penzance and Swindon to Swansea. Opened in 1841, it was the original route of the first Great Western Railway which was merged into the Western Region of British Railways in 1948. It is now a part of the national rail system managed by Network Rail with the majority of passenger services provided by the current Great Western Railway franchise.

The Train Protection & Warning System (TPWS) is a train protection system used throughout the British passenger main-line railway network, and in Victoria, Australia.

<span class="mw-page-title-main">Signal passed at danger</span> Train passing stop signal without authority

A signal passed at danger (SPAD), known in the United States as a stop signal overrun (SSO) and in Canada as passing a stop signal, is an event on a railway where a train passes a stop signal without authority. This is also known as running a red.

<span class="mw-page-title-main">Balise</span> Beacon or transponder used on railways

A balise is an electronic beacon or transponder placed between the rails of a railway as part of an automatic train protection (ATP) system. The French word balise is used to distinguish these beacons from other kinds of beacons.

<span class="mw-page-title-main">Southall rail crash</span> 1997 high-speed rail crash near London

The Southall rail crash occurred on 19 September 1997, on the Great Western Main Line at Southall, West London. An InterCity 125 high speed passenger train (HST) failed to slow down in response to warning signals and collided with a freight train crossing its path, causing seven deaths and 139 injuries.

<span class="mw-page-title-main">Automatic Warning System</span>

Automatic Warning System (AWS) is a railway safety system invented and predominantly used in the United Kingdom. It provides a train driver with an audible indication of whether the next signal they are approaching is clear or at caution. Depending on the upcoming signal state, the AWS will either produce a 'horn' sound, or a 'bell' sound. If the train driver fails to acknowledge a warning indication, an emergency brake application is initiated by the AWS. However if the driver correctly acknowledges the warning indication by pressing an acknowledgement button, then a visual 'sunflower' is displayed to the driver, as a reminder of the warning.

<span class="mw-page-title-main">Automatic train control</span> Class of train protection systems for railways

Automatic train control (ATC) is a general class of train protection systems for railways that involves a speed control mechanism in response to external inputs. For example, a system could effect an emergency brake application if the driver does not react to a signal at danger. ATC systems tend to integrate various cab signalling technologies and they use more granular deceleration patterns in lieu of the rigid stops encountered with the older automatic train stop (ATS) technology. ATC can also be used with automatic train operation (ATO) and is usually considered to be the safety-critical part of a railway system.

<span class="mw-page-title-main">Linienzugbeeinflussung</span> In-cab signalling and train protection system

Linienzugbeeinflussung is a cab signalling and train protection system used on selected German and Austrian railway lines as well as on the AVE and some commuter rail lines in Spain. The system was mandatory where trains were allowed to exceed speeds of 160 km/h (99 mph) in Germany and 220 km/h (140 mph) in Spain. It is also used on some slower railway and urban rapid transit lines to increase capacity. The German Linienzugbeeinflussung translates to continuous train control, literally: linear train influencing. It is also called linienförmige Zugbeeinflussung.

<span class="mw-page-title-main">Punktförmige Zugbeeinflussung</span> German railway signal system

PZB or Indusi is an intermittent cab signalling system and train protection system used in Germany, Austria, Slovenia, Croatia, Romania, Israel, Serbia, on two lines in Hungary, on the Tyne and Wear Metro in the UK, and formerly on the Trillium Line in Canada.

<span class="mw-page-title-main">UK railway signalling</span> Rail traffic control systems used in the United Kingdom

The railway signalling system used across the majority of the United Kingdom rail network uses lineside signals to control the movement and speed of trains.

<span class="mw-page-title-main">Double junction</span> Railway junction

A double junction is a railway junction where a double-track railway splits into two double track lines. Usually, one line is the main line and carries traffic through the junction at normal speed, while the other track is a branch line that carries traffic through the junction at reduced speed.

<span class="mw-page-title-main">Watford rail crash</span> 1996 rail crash in England

In the early evening of 8 August 1996, a Class 321 passenger train operated by Network SouthEast travelling from London Euston on the West Coast Main Line Down Slow line at around 110 km/h (68 mph) passed a signal at danger. Having applied the brakes it eventually stopped 203 m (222 yd) past the signal and was traversing the junction between the Down Slow line and the Up Fast line. An empty Class 321 coaching stock train approaching at roughly 80 km/h (50 mph) collided with the stationary passenger train approximately 700 m south of Watford Junction whilst progressing across the connections from the Up Slow line to the Up Fast line.

<span class="mw-page-title-main">Cowden rail crash</span> 1994 collision in Kent, England

The Cowden rail crash occurred on 15 October 1994, near Cowden Station in Kent (UK), when two trains collided head-on, killing five and injuring thirteen, after one of them had passed a signal at danger and entered a single-line section. The cause was driver error, possibly involving a guard who was in the cabin against regulations.

<span class="mw-page-title-main">Spa Road Junction rail crash</span>

The Spa Road Junction rail crash was an accident on the British railway system which occurred during the peak evening rush hour of 8 January 1999 at Spa Road Junction in Bermondsey, in South East London.

The history of rail transport in Great Britain 1948–1994 covers the period when the British railway system was nationalised under the name of 'British Railways', latterly known as British Rail until its eventual privatisation in 1994.

<span class="mw-page-title-main">InterCity 250</span> Cancelled electric railway project

The InterCity 250 was an electric railway project undertaken by British Rail in the late 1980s. The InterCity 250 train would have consisted of a Class 93 electric locomotive, nine Mark 5 coaches and a Mark 5 Driving Van Trailer operating in a push-pull formation. The British Rail project was cancelled in July 1992.

The Chinese Train Control System is a train control system used on railway lines in People's Republic of China. CTCS is similar to the European Train Control System (ETCS).

<span class="mw-page-title-main">2015 Wootton Bassett rail incident</span> Charter train passed a signal at danger

On 7 March 2015, a steam-hauled charter train passed a signal at danger and subsequently came to a stand across a high-speed mainline junction near Wootton Bassett Junction, Wiltshire, England. Another train, which had right of way, had passed through the junction 44 seconds earlier and no collision occurred nor was any damage done.

Kavach is an automatic train protection (ATP) system indigenously developed by Indian Railways through Research Designs & Standards Organisation (RDSO). Initial development of Kavach started in 2012 under the name Train Collision Avoidance System (TCAS) and completed development in 2022.

References

Citations

  1. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 Darlington, Paul (16 October 2020). "Chiltern ATP obsolescence". railengineer.co.uk.
  2. Gourvish (2002), pp. 355–356.
  3. Nguyen (2012).
  4. Gourvish (2002), p. 356.
  5. 1 2 3 4 Hamer (1995).
  6. Gourvish (2002), p. 358.
  7. RSSB (2015), p. 10.
  8. Watts (1997).
  9. Nguyen (2012), p. 3.
  10. BBC News (28 September 2000). "How the safety systems work". Archived from the original on 8 March 2020. Retrieved 8 March 2020.
  11. Network Rail (2019), p. 24.
  12. Nguyen (2012), p. 6.

Bibliography