HMCS Harry DeWolf under way in September 2021 | |
Class overview | |
---|---|
Name | Harry DeWolf class |
Builders | Halifax Shipyards |
Operators |
|
Preceded by | None |
Cost | |
Built | 2016–present |
In commission | 2021–present |
Planned | 8 (6 for RCN and 2 for CCG) |
Building | 2 (for CCG) |
Completed | 6 |
Active | 4 |
General characteristics | |
Type | Arctic/offshore patrol vessel |
Displacement | 6,615 t (6,511 long tons) |
Length | 103.6 m (339 ft 11 in) [4] |
Beam | 19 m (62 ft 4 in) [4] |
Draught | 5.7 m (18 ft 8 in) [5] |
Ice class | Polar Class 5 |
Installed power | 4 × MAN 6L32/44CR [5] (4 × 3.6 MW) [6] |
Propulsion |
|
Speed | |
Range | 6,800 nmi (12,600 km; 7,800 mi) at 14 kn (26 km/h; 16 mph) |
Boats & landing craft carried |
|
Complement | 65 (RCN). Accommodation for 87 [11] |
Sensors and processing systems | SATCOM (Link 16), Multichannel VHF/HF Radio, Anti-missile detect systems; OSI Maritime Systems, Integrated Bridge Navigational System; Kelvin Hughes SharpEye X and S-band navigation radars; BlueNaute inertial navigation system; Terma SCANTER 6002 surveillance radar system; SAGEM Damage/Machinery Control Systems |
Armament |
|
Aircraft carried |
|
Aviation facilities |
|
Harry DeWolf-class offshore patrol vessels are warships of the Royal Canadian Navy (RCN) built within the Government of Canada Arctic and Offshore Patrol Ship (AOPS) procurement project, part of the National Shipbuilding Strategy. In July 2007 the federal government announced plans for acquiring six to eight icebreaking warships for the RCN. [12] [13] [14] [15] [16] [17] [18]
The vessels are modelled on the Norwegian Coast Guard NoCGV Svalbard and as of 2007 were projected to cost CA$3.5 billion to construct with a total project procurement budgeted to cost $4.3 billion in order to cover maintenance over the 25-year lifespan of the vessels. [19] [20] In 2018 it was reported that the cost of the first six ships had increased by $810 million over previous projections. [2] In 2023 it was reported that the cost for the first six ships had increased by a further $780 million and that of the two envisaged vessels for the Coast Guard by an additional $100 million. [21]
The lead ship of the class was announced as Harry DeWolf in September 2014, and four additional ships were named in 2015. Construction of the ships Harry DeWolf and Margaret Brooke started at the Halifax Shipyards in September 2015 and September 2016, respectively. Harry DeWolf and Margaret Brooke were originally planned to be delivered in 2019 and 2020 respectively. [22] Harry DeWolf was officially launched on 15 September 2018. [23] Margaret Brooke was launched on 10 November 2019. [24] Max Bernays began construction in December 2017 and William Hall was also planned to begin in 2017, although construction was delayed to early 2019. Max Bernays was launched in October 2021, and was followed by William Hall in 2022. [25] [22] Frédérick Rolette was scheduled to begin construction in 2019, with construction on Robert Hampton Gray expected to begin in 2021. They were originally planned to be completed by 2022 and 2023, respectively. [22] [26] [27] [28] However, in 2020 it was confirmed that ships five and six (Frédérick Rolette and Robert Hampton Gray) would not begin construction until 2021 and 2022 respectively. [29]
On 22 May 2019, an official announcement was made to begin the process of building two vessels for the Canadian Coast Guard, bringing the total number of ships in the class to eight. [30]
In 2006 Prime Minister Stephen Harper had spoken about building three to four icebreakers capable of travelling through thick ice in the Arctic Ocean. [31] [32] [33] In 2007 it was announced that the Canadian Armed Forces would purchase six to eight patrol ships having an ice class of Polar Class 5, meaning that they were capable of limited icebreaking, [34] based on the Norwegian Svalbard class. [19] This announcement was met with some controversy, and the proposed ships have been called "slush-breakers", by Dr. Gary Stern, a scientist aboard CCGS Amundsen, and Jack Layton of the NDP. [35] [36] However, it was notable that in 2005 of the nineteen Canadian Coast Guard icebreakers then in service, only six had an ice class higher than Polar Class 5. [37]
In 2010 the Arctic and Offshore Patrol Ship Project was grouped with several other federal government ship procurement projects for the Royal Canadian Navy and Canadian Coast Guard into the National Shipbuilding Procurement Strategy (NSPS). The NSPS announced on 19 October 2011 that Irving Shipbuilding would be awarded the $25 billion contract to build six to eight Arctic patrol ships as well as fifteen other warships for the RCN over the next two decades. [38]
In September 2014, Prime Minister Stephen Harper announced that the name of the first ship in the class would be Harry DeWolf, named in honour of wartime Canadian naval hero Harry DeWolf, and that the class would be named the Harry DeWolf class. [39] In December it was found that not enough money had been projected to cover the cost of building the six to eight planned ships and that the budget would need to be increased, delaying the signing of the contract. [40] However, in an effort to drive down costs, Irving Shipbuilding could only project building five ships with the option to build a sixth only if it came under budget. The budget for the project was increased from $3.1 billion to $3.5 billion to ensure a cash buffer. [41] However, by 2018 that approach had been abandoned and the budget for the first six ships had reportedly increased to $4.3 billion. [2]
On 13 April 2015 the government announced a second ship would be named Margaret Brooke in honour of Sub-Lieutenant Margaret Brooke, a Royal Canadian Navy Nursing Sister decorated for heroism for her efforts to save a fellow nursing sister after the sinking of the ferry SS Caribou during World War II. [42] The third ship will be named Max Bernays for Chief Petty Officer Max Bernays who served aboard HMCS Assiniboine during the Second World War and was decorated for his actions during the sinking of the German submarine U-210. [43] The fourth ship will be named for William Hall, a Victoria Cross (VC) recipient from Nova Scotia and the first black person to be awarded the VC, for his actions during the Siege of Lucknow. [44] [45] The fifth ship will be named for Frédérick Rolette, a French-Canadian sailor of Canada's Provincial Marine under the Royal Navy who, during the War of 1812, was second-in-command of the ship Lady Prevost at the Battle of Lake Erie, and led the capture of the American supply vessel Cayahoga Packet, in July 1812, an action instrumental in contributing to the capture of Detroit one month later. [46]
On 2 November 2018, the option for the sixth ship was taken up. [47] In 2020 it was confirmed that the sixth ship would be named for Robert Hampton Gray, posthumously awarded the Victoria Cross for gallantry during World War II while serving with the Royal Navy's Fleet Air Arm in the Pacific theatre. [48] The cost of the sixth vessel is expected to be higher due to the tariffs on steel and aluminum imposed by both Canada and the United States. [49]
On 22 May 2019, it was announced that two more ships would be built for the Canadian Coast Guard. [50]
The Fall 2022 Special Edition of the Maritime Engineering Journal (No. 102) was dedicated to a comprehensive review of the Arctic and Offshore Patrol Ship project with the subtitle: An insider's look at the Royal Canadian Navy's new capability. [51]
On 18 June 2015 it was reported that the construction of test modules for the lead ship of the class Harry DeWolf was underway. [52] The first sections of keel were placed on 11 March 2016, but the official laying of the keel of Harry DeWolf was held on 9 June 2016, marking the first naval construction in Canada since 1998, [53] [54] and the largest purposefully-built warship for the RCN in over 50 years. In September 2016, it was announced that construction had begun on Margaret Brooke and that 50 of 64 modular pieces of Harry DeWolf had been completed. [55] On 8 December 2017, the three main sections of Harry DeWolf were fitted into place. [56] The first steel for Max Bernays was cut on 19 December 2017. [57] Construction of William Hall started on 3 May 2019. [58] Margaret Brooke was launched on 10 November 2019. [59] First steel was cut for the fifth ship, Frédérick Rolette, in May 2021 [60] and for sixth ship, Robert Hampton Gray, in August 2022. [61]
During the COVID-19 pandemic, Irving Shipbuilding announced that construction would be halted for at least three weeks beginning in March 2020. [62] Harry DeWolf was delivered to the Navy in July 2020, and commissioned on 26 June 2021. Margaret Brooke was delivered on 15 July 2021 and commissioned on 28 October 2022. The two Coast Guard AOPS variants (ships seven and eight) were expected to begin construction in 2022 and 2023. [29] In January 2023, it was announced that work on the additional ships would begin in the course of 2023. [63]
On 9 December, 2024, the sixth and final ship, Robert Hampton Gray, was launched at Halifax Shipyard.
In December 2022, it was discovered that the potable water systems of all the delivered and launched ships had suspected lead contamination from fittings and valves that were manufactured from alloys that exceeded the allowable amount of lead. The ships affected by the contamination were Harry DeWolf, Margaret Brooke, and Max Bernays. William Hall would be tested for the contamination after the completion of construction. [64]
The Harry DeWolf class has been criticized for its design and effectiveness, as critics believe that the class is ineffective in its designated role of Arctic and offshore patrol. Some criticism focuses on the fact that the ships are slow and, compared to the similarly sized Russian Project 23550 patrol ships armed with 3M-54 Kalibr anti-ship missiles, underarmed. However, others believe that the ships' capabilities are sufficient given their largely constabulary mission, and are in line with existing naval and coast guard vessels of other Arctic nations. [65]
In April 2013, the Rideau Institute and the Canadian Centre for Policy Alternatives released a report on the proposed AOPS. The report was written by UBC Professor Michael Byers and Stewart Webb. The report's conclusion was that Canada would be better suited to have purpose-built ships, namely icebreakers for the Arctic and offshore patrol vessels for the Pacific and Atlantic coasts. [66]
In May 2013, the CBC reported that the cost of the design phase of the project was many times what other countries paid for design, construction, and full-up operational deployment of similar ships. The projected design cost of the AOPS, $288 million, was compared primarily to the Norwegian icebreaking offshore patrol vessel Svalbard that was designed and built for less than $100 million in 2002, and whose basic design documentation package was purchased by Canada for $5 million. Shipbuilding experts interviewed by CBC estimated that the design cost of the AOPS should have been $10–20 million even if accounting for cost of adapting the Norwegian design to Canadian service. [20] The $288 million design cost was further compared to two European offshore patrol vessel classes that, while significantly cheaper to design and build, have only one third of the AOPS' displacement. Furthermore, the Danish Knud Rasmussen class has much lower ice-going capability than the AOPS and the Irish Samuel Beckett class is not ice-capable at all. [67] Additionally, the AOPS have far more significant aviation capabilities than either the Danish or Irish ships.
As the Harry Dewolf-class ships started to enter service, comments appeared in Canadian professional military journals suggesting that they might be useful as small amphibious ships carrying up to 50 to 60 soldiers/marine infantry into the Arctic. [68]
A 2024 defence policy report included the intent to purchase ocean surveillance sensors for the ships. [69]
In 2017, the decision was made to have each of the six ships affiliate with one of the six Inuit regions in Northern Canada; Qikiqtaaluk, Kitikmeot, Kivalliq, Nunavik, Nunatsiavut, and Inuvialuit. These affiliations are meant to build connections with Inuit communities where the Harry DeWolf class serve. [70]
In November 2023, Vice-Admiral Angus Topshee, the commander of the RCN, released a statement indicating that due to serious personnel recruitment and retention problems in the navy, notably an absence of marine technicians, only one of the new Harry DeWolf-class ships was actually being manned at any given time. [71] [72] By February/March 2024 these crewing problems had been reduced/solved, as demonstrated by the simultaneous deployments of Max Bernays (sailing between Canada's Atlantic and Pacific coasts via the Panama Canal) and Margaret Brooke (to the Caribbean Sea). [73] Both Harry DeWolf and Margaret Brooke participated in Nanook 2024, which was led by the Canadian Armed Forces. [74]
The AOPS was initially envisaged to feature azimuth thrusters and a double-acting hull form that would incorporate a moderate icebreaking bow for cruising in open water and light ice, and an icebreaking stern designed for heavier ice conditions. [75] After a conventional twin-shaft layout similar to existing Canadian Coast Guard icebreakers was selected following a cost-benefit analysis, the hull form was optimized for bow-first icebreaking with a rounded spoon-shaped stem. [76] The vessels' ice class is Polar Class 5, but the bow region is further strengthened to higher Polar Class 4 level. [77] A bow thruster enables manoeuvering and berthing without tug assistance. [7]
In 2008, a contract was awarded to BMT Fleet Technology and STX Canada Marine to assist in developing technical specifications and a design for the project. The technical specifications were to be used to draft a request for proposals. The government later awarded a design contract to BMT Fleet Technology and STX Canada Marine to develop the design of the vessel for issue to the selected NSPS proponent.
The ships are built in three large megablocks: centre, aft and bow. Each megablock consists of 62 smaller building blocks. The first steel was cut on Harry DeWolf in September 2015. [4]
The ships are designed to displace 6,440 metric tons (6,340 long tons ), making them the largest class of naval vessels produced in Canada in the past 50 years, with the previous being the retired Protecteur-class replenishment oiler. [78] They are capable of outfitting multiple payload options such as shipping containers, underwater survey equipment, or a landing craft. The vessels have a 20-tonne and a 3-tonne crane to self-load/unload, and a vehicle bay to carry vehicles for deployment over the ice. [79] The design also calls for an enclosed cable deck and forecastle to better cope with the Arctic environment. On the open sea, the ships have fin stabilizers to reduce roll that are retractable during ice operations. [6]
In August 2015, BAE Systems won the contract to provide up to six modified Mk 38 Mod 3A 25 mm cannon for the naval ships in the class (the coast guard ships will be unarmed, as CCG has no enforcement mandate). This contract also covers the service life of the weapons. [80]
The vessels have a hangar and flight deck capable of employing and maintaining the same maritime helicopter as the RCN's other vessels: the CH-148 Cyclone. [18]
In 2014 OSI Maritime Systems Ltd. was selected by Lockheed Martin Canada to design the integrated bridge and navigation system for the AOPS program, this was followed by a contract for the Implementation Phase in 2015. Since, OSI has built and installed all AOPS Integrated Bridge and Navigation ship sets. [81] [82]
The vessels have a diesel-electric powertrain with four 3.6-megawatt (4,800 hp) MAN 6L32/44CR [5] four-stroke medium-speed diesel generators producing electricity for two 4.5-megawatt (6,000 hp) propulsion motors driving twin shaft lines with bolted propellers. [6]
In September 2015, it was announced that the ships would be outfitted with SAGEM BlueNaute inertial navigation systems. [83] On 7 October 2015, Thales IFF system was selected for use on the class. [84] Terma currently provides its SCANTER 6002 surveillance radar system to Lockheed Martin Canada as part of the Combat Management System (CMS 330), which was selected by Irving Shipbuilding Inc. for the AOPS. [85] The vessel also has Kelvin Hughes SharpEye X and S-band navigation radars. [86]
The Canadian Coast Guard version will be built to a slightly modified design. Modifications include a new bridge layout and accommodations for a non-military crew subject to Transport Canada requirements. Some areas are to be changed to meet the needs of coast guard equipment and there will be modifications to the deck. [87] Despite the supposedly limited modifications, the cost of the two Coast Guard variants was reported in 2022 as likely to be significantly higher than that of the naval variants. [88] In 2023, it was reported that the cost of the two Coast Guard variants had increased by a further $100 million, going from $1.5 billion to $1.6 billion. [21] A further increase to $2.1 billion was reported in early 2024. [3] The first of the Coast Guard ships was laid down during a ceremony on 31 July 2024. [89] The first ship is named CCGS Donjek Glacier after Donjek Glacier in Kluane National Park in Yukon. While the second Coast Guard ship named CGS Sermilik Glacier takes its name from Sermilik Glacier found in Sirmilik National Park in Nunavut.
Class | Ship name | Number | First steel cut | Laid down | Launched | Delivered | Commissioned | Northern affiliation | Status |
---|---|---|---|---|---|---|---|---|---|
Harry DeWolf class | Harry DeWolf | AOPV 430 [90] | 1 September 2015 [91] | 11 March 2016 | 15 September 2018 [92] | 31 July 2020 [93] | 26 June 2021 [94] | Qikiqtani | Ship in active service [95] |
Margaret Brooke | AOPV 431 [90] | August 2016 [55] | 29 May 2017 [96] | 10 November 2019 | 15 July 2021 [97] | 28 October 2022 [98] | Nunatsiavut | Ship in active service [99] | |
Max Bernays | AOPV 432 [90] | 19 December 2017 [57] | 5 December 2018 [100] | 23 October 2021 [101] | 2 September 2022 [102] | 3 May 2024 [103] | Kitikmeot | Ship in active service [103] | |
William Hall | AOPV 433 [90] | 3 May 2019 [58] | 17 February 2021 [104] | 27 November 2022 [105] | 31 August 2023 [106] | 16 May 2024 [107] | Kivalliq | Ship in active service [107] | |
Frédérick Rolette | AOPV 434 [90] | May 2021 [60] | 29 June 2022 [108] | 9 December 2023 [109] | 29 August 2024 [110] | Nunavik | Delivered [110] | ||
Robert Hampton Gray [111] [48] | AOPV 435 [90] | August 2022 [61] | 21 August 2023 [112] | 9 December 2024 [113] | Inuvialuit | Fitting out [114] | |||
AOPS – Coast Guard variant | Donjek Glacier | 8 August 2023 [115] | 31 July 2024 [89] | Projected 2026 | Under construction | ||||
Sermilik Glacier | 28 June 2024 [116] | Projected 2027 | Under construction |
NoCGV Svalbard (W303) is a Norwegian Coast Guard icebreaker and offshore patrol vessel constructed by Langsten at Tangen Verft shipyard in Kragerø and launched on 17 February 2001. She was named 15 December 2001 in Tomrefjord with Minister of Defence Kristin Krohn Devold as godmother, and delivered to the Coast Guard on 18 January 2002. She entered service in mid-2002 and is homeported in Sortland. Her primary operating area is in the Arctic waters north of Norway, the Barents Sea and around the Svalbard islands.
The Royal Canadian Navy is the naval force of Canada. The navy is one of three environmental commands within the Canadian Armed Forces. As of February 2024, the RCN operates 12 Halifax-class frigates, 12 Kingston-class coastal defence vessels, 4 Victoria-class submarines, 4 Harry DeWolf-class offshore patrol vessels, 8 Orca-class patrol vessels, and several auxiliary vessels. The RCN consists of 8,400 Regular Force and 4,100 Primary Reserve sailors, supported by 3,800 civilians. Vice-Admiral Angus Topshee is the commander of the Royal Canadian Navy and chief of the Naval Staff.
HMCS Goose Bay is a Kingston-class coastal defence vessel that has served in the Canadian Forces since 1998. Goose Bay is the eighth ship of her class which is the name for the Maritime Coastal Defence Vessel Project. She is the first vessel to be named Goose Bay. The coastal defence vessel is assigned to Maritime Forces Atlantic (MARLANT) and is homeported at CFB Halifax.
HMCS Moncton is a Kingston-class coastal defence vessel that has served in the Canadian Forces since 1998. Moncton is the ninth ship of her class. She is the second vessel to use the designation HMCS Moncton. The ship is assigned to Maritime Forces Atlantic (MARLANT) and is homeported at CFB Halifax.
The Protecteur class of naval auxiliaries for the Royal Canadian Navy (RCN) began as the Joint Support Ship Project, a Government of Canada procurement project for the RCN that is part of the National Shipbuilding Procurement Strategy. It will see the RCN acquire two multi-role vessels to replace the earlier Protecteur-class auxiliary oiler replenishment vessels.
The Damen Group is a Dutch defence, shipbuilding, and engineering conglomerate company based in Gorinchem, Netherlands.
The River-class destroyer, formerly the Canadian Surface Combatant (CSC), and Single Class Surface Combatant Project is the procurement project that will replace the Iroquois and Halifax-class warships with up to 15 new ships beginning in the early 2030s as part of the National Shipbuilding Procurement Strategy.
Vice Admiral Henry George DeWolf was a Canadian naval officer who was famous as the first commander of HMCS Haida during the Second World War.
The Halifax Shipyard Limited is a Canadian shipbuilding company located in Halifax, Nova Scotia.
Polar Class (PC) refers to the ice class assigned to a ship by a classification society based on the Unified Requirements for Polar Class Ships developed by the International Association of Classification Societies (IACS). Seven Polar Classes are defined in the rules, ranging from PC 1 for year-round operation in all polar waters to PC 7 for summer and autumn operation in thin first-year ice.
Irving Shipbuilding Inc. is a Canadian shipbuilder and in-service support provider.
The National Shipbuilding Strategy (NSS), formerly the National Shipbuilding Procurement Strategy (NSPS), is a Government of Canada program operated by the Department of Public Works and Government Services. The NSS was developed under the Stephen Harper Government in an effort to renew the fleets of the Royal Canadian Navy (RCN) and the Canadian Coast Guard (CCG). The strategy was broken into three sections; the combat package, the non-combat package and the smaller vessel package. The companies who won the bids for the larger ships were not permitted to bid on the smaller vessel package. In 2019, the Trudeau Government decided to add a third shipyard to the NSS specializing in the construction of icebreakers for the Coast Guard. The agreement to incorporate Davie as a third shipyard within the NSS was finally signed in April 2023.
HMCS Harry DeWolf is the lead ship of its class of offshore patrol vessels for the Royal Canadian Navy (RCN). The class was derived from the Arctic Offshore Patrol Ship project as part of the National Shipbuilding Procurement Strategy and is primarily designed for the patrol and support of Canada's Arctic regions. Named after Vice Admiral Harry DeWolf, a former head of the RCN, the vessel was ordered in 2011, laid down in 2016 and launched in 2018. The vessel completed contractors sea trials in July 2020, was delivered to the RCN on 31 July 2020 and began post-acceptance sea trials. Harry DeWolf was commissioned on 26 June 2021.
HMCS Margaret Brooke is the second Harry DeWolf-class offshore patrol vessel for the Royal Canadian Navy (RCN). The class was derived from the Arctic Offshore Patrol Ship project as part of the National Shipbuilding Procurement Strategy and is primarily designed for the patrol and support of Canada's Arctic regions. Named after Sub-Lieutenant Margaret Brooke, an RCN nursing sister who tried to save another person during the sinking of the ferry SS Caribou during World War II. Margaret Brooke was ordered in 2011, laid down in 2016 and launched in 2019. The vessel began contractor sea trials in May 2021, and she was delivered to the Royal Canadian Navy for post-acceptance sea trials on 15 July 2021. The official naming ceremony for the ship was conducted on 29 May 2022 in conjunction with that for sister ship Max Bernays. The vessel was commissioned on 28 October 2022.
HMCS William Hall. is the fourth Harry DeWolf-class offshore patrol vessel for the Royal Canadian Navy. The class was derived from the Arctic Offshore Patrol Ship project as part of the National Shipbuilding Procurement Strategy and is primarily designed for the patrol and support of Canada's Arctic regions. Named after Quartermaster William Nelson Edward Hall, who was the first African Canadian to receive the Victoria Cross. He received the medal for his actions in the 1857 Siege of Lucknow during the Indian Rebellion.
HMCS Max Bernays is the third Harry DeWolf-class offshore patrol vessel for the Royal Canadian Navy. The class was derived from the Arctic Offshore Patrol Ship project as part of the National Shipbuilding Procurement Strategy and is primarily designed for the patrol and support of Canada's Arctic regions.
Frédérick Rolette will be the fifth Harry DeWolf-class offshore patrol vessel for the Royal Canadian Navy. The class was derived from the Arctic Offshore Patrol Ship project as part of the National Shipbuilding Procurement Strategy and is primarily designed for the patrol and support of Canada's Arctic regions.
Robert Hampton Gray will be the sixth Harry DeWolf-class offshore patrol vessel for the Royal Canadian Navy. The class was derived from the Arctic Offshore Patrol Ship project as part of the National Shipbuilding Procurement and is primarily designed for the patrol and support of Canada's Arctic regions. It is expected to be the last naval AOPV to be built and will be followed by two more non-armed vessels for the Canadian Coast Guard.
Limited as an icebreaker, critics have disparaged AOPS as 'slush breakers' of limited utility. As offshore patrol vessels (OPVs), AOPS are burdened with the vast weight of icebreaking hulls unnecessary for that role. Carrying that extra bulk around in temperate seas mean that AOPS will be relatively slow while fuel costs and similar operating expenses are very high.