Storr Lochs Hydro-Electric Scheme

Last updated

Storr Lochs
Hydro-Electric Scheme
Supply pipes to the Storr Lochs Power Station - geograph.org.uk - 3480659.jpg
Pipes running from Storr Lochs Dam towards the power station
Highland UK relief location map.jpg
Red pog.svg
Location of Storr Lochs
Hydro-Electric Scheme in Highland
CountryScotland
Location Isle of Skye
Coordinates 57°29′48″N6°08′44″W / 57.4967°N 6.1455°W / 57.4967; -6.1455
PurposePower
StatusOperational
Construction began1950
Opening date1952
Owner(s) SSE
Storr Lochs
Hydro-Electric Scheme
BSicon uDOCKSm.svg
BSicon uDOCKSm.svg
BSicon uDOCKSm.svg
BSicon uDOCKSm.svg
Sound of Raasay
BSicon uDOCKSe.svg
Bearreraig Bay
BSicon uxSTRbr.svg
BSicon utSTR+r.svg
BSicon ENDEa.svg
Storr Lochs power station
BSicon uexSTR.svg
BSicon utSTR.svg
BSicon STR.svg
BSicon uxWEIRf.svg
BSicon utSTR.svg
BSicon STR.svg
Waterfall
BSicon uexSTR.svg
BSicon utSTR.svg
BSicon ENDEe.svg
Funicular railway
BSicon uexSTR.svg
BSicon utSTR.svg
BSicon uexSTR.svg
BSicon PUMPSTNl@f.svg
BSicon utSTR3.svg
Valve house
BSicon uexRESVGDe.svg
Storr Lochs Dam
BSicon uexDOCKSm.svg
Loch Leathan
BSicon uexDOCKSe.svg
BSicon uexSTR.svg
BSicon uxWEIRf.svg
Weir
BSicon uexDOCKSa.svg
Loch Fada
BSicon uexDOCKSe.svg

Storr Lochs is a hydro-electric power station built on the Isle of Skye, Inner Hebrides, Scotland and commissioned in 1952. It was built by the North of Scotland Hydro-Electric Board, and used water from Lochs Leathan and Fada, to provide the first general supply of electricity to the island. Because the location of the turbine house was not easily accessible, it is served by an electric funicular railway.

Contents

The original two turbines were supplemented by a third in 1956, and it continued to operate until the 2010s. By that time, it was becoming difficult to maintain, and it was upgraded in 2017, when two new turbines were installed, and most of the ancillary services were upgraded, allowing it to be controlled from Scottish and Southern Energy's control centre in Perth.

History

The North of Scotland Hydro-Electric Board was created by the Hydro-electric Development (Scotland) Act 1943, [1] a measure championed by the politician Tom Johnston while he was Secretary of State for Scotland. [2] Johnston's vision was for a public body that could build hydro-electric stations throughout the Highlands. Profits made by selling bulk electricity to the Scottish lowlands would be used to fund "the economic development and social improvement of the North of Scotland." Private consumers would be offered a supply of cheap electricity, and their connection to that supply would not reflect the actual cost of its provision in remote and sparsely-populated areas. [3]

Prior to its construction, electricity supply on Skye was patchy. A diesel generator supplied power to parts of Portree, while the village of Broadford was supplied from the power station at Nostie Bridge on the Scottish mainland by a cable that run for 10 miles (16 km) under the sea. [4] [5] A switching-on ceremony was held at Kyleakin on 6 May 1947, to inaugurate the undersea supply from Nostie to Broadford, at which Lady Mackenzie presided. The cable was sized to supply 85 per cent of the population of Skye, but once the formal opening ceremony had been completed, Edward MacColl, the chief executive of the North of Scotland Hydro-Electric Board, was able to announce that the Storr Lochs scheme had just been approved by the Electricity Commissioners. [6]

The Board received permission to proceed with the construction of the project in late 1949, and work began in early 1950. Water was supplied by Loch Fada and Loch Leathan, which are situated between the main road from Portree to Staffin and the sea. The turbine house was located on the shore at Bearreraig Bay, [7] separated from the lochs by a 350-foot (110 m) cliff. In order to overcome the difficulties of accessing this site, a funicular railway was built at the start of the project, and used to transport men and materials down to the shore. The formation for the railway included 647 steps cast into the concrete. [8] The railway is standard gauge with a maximum gradient of 1 in 2, and an electric winch controls the movement of the single carriage. [9] Prior to its construction, the Board anticipated that materials could be brought to the beach by landing craft, but the loss of one vessel and all the equipment it was carrying due to the fierce tides resulted in this approach being abandoned. [10]

The turbine house had a slate roof and was clad in local stone, so that it would blend in with its surroundings. [11] A dam was constructed across the Bearreraig River to raise the level of Loch Leathan, which included screens to prevent debris entering the pipeline. A long wing wall was built across the surrounding hillside, to provide additional stability to the dam, because of the boggy nature of the terrain. [12] A single pipeline was initially run from the valve house by the dam to the turbine house, but the formation was made wide enough to accommodate a second pipeline, and this was added in 1956. [13]

The turbine house was equipped with two 1 MW Francis turbines, which was sufficient to supply the whole of Skye. [14] The consulting engineers were Blyth and Blyth of Edinburgh, while construction was carried out by James Miller and Partners, also from Edinburgh. [15] The official opening took place on 31 May 1952, when Lady Rachel Stuart, wife of the Secretary of State for Scotland, James Stuart, started the turbines. Tom Johnston was by this time chairman of the North of Scotland Hydro-Electric Board, and used the occasion to say that despite those who felt that electricity was unnecessary, because the Highlanders were satisfied with their oil lamps, 850 houses were already connected to the grid, and this total would rise to 2500 during 1953. [16] The cost of the scheme was £247,000, and initially it could supply 5.5 GWh of electricity per year. The population of Skye at the time was 10,500. [17]

A house for the station attendant called Bearreraig Cottage was built on the Portree to Staffin road, and a second house for another attendant was constructed near the winch house in the 1960s. [14] In 1956, the scheme was upgraded. The single 42-inch (1,100 mm) pipeline was duplicated, [18] and a third 1 MW generator was added in the turbine house. Subsequently, Loch Fada was connected to Loch Leathan by constructing a channel between the two, so that its water could be used to supplement the supply from Loch Leathan at times when rainfall was low. [14]

The station could produce 2.85 MW of power. [19] Loch Leathan covers an area of 300 acres (120 ha) and draws its water from a catchment of 3,586 acres (1,451 ha). Its surface level is 136 metres (446 ft) above Ordnance datum (AOD). [20] Loch Fada is smaller, covering an area of 82 acres (33 ha) and having a catchment of 1,024 acres (414 ha). Its surface level is 476 feet (145 m) AOD. [21]

Upgrade

After nearly 70 years of operation, during which time it produced around 8 GWh of power per year, the station was becoming difficult to maintain, and the lack of automation meant that site visits were necessary whenever adjustments needed to be made. In the mid-2010s Scottish and Southern Energy (SSE), who inherited the scheme when the electricity industry was privatised, decided that a complete upgrade of the station was necessary. The original turbines were replaced by two new ones, supplied by Voith Group, which incorporate automatic adjustment of the guide vanes by an autonomous hydraulic control unit. It was the first time that this system had been used for a small hydro-electricity plant. Most of the testing could be carried out off-site, significantly reducing disruption to the generation of power. [4]

Site Drilling Specialists were responsible for removal of the original turbines, and used a diamond wire saw to cut the concrete foundations into blocks small enough to enable them to be removed by the funicular railway. [22] In parallel with the turbine replacement, the low-voltage distribution and protection systems were replaced, and a modern control system using programmable logic controllers was installed, linked to a graphical display system, which is accessible from SSE's main control centre in Perth. Servelec Controls supplied the automation, which included telemetry links between the turbine house, the winch house and the valve house. All of the upgrade work was completed by the end of 2017. [4]

Related Research Articles

<span class="mw-page-title-main">Loch Awe</span> Lake in Argyll and Bute, Scotland

Loch Awe is a large body of freshwater in Argyll and Bute, Scottish Highlands. It has also given its name to a village on its banks, variously known as Loch Awe or Lochawe. There are islands within the loch such as Innis Chonnell and Inishail.

<span class="mw-page-title-main">Falls of Foyers</span> Waterfall in Highland, Scotland

The Falls of Foyers are two waterfalls on the River Foyers, which feeds Loch Ness, in Highland, Scotland, United Kingdom. They are located on the lower portion of the River Foyers, and consist of the upper falls, with a drop of 46 feet (14 m) and the lower falls, which drop 98 feet (30 m).

<span class="mw-page-title-main">River Shin</span> River in northern Scotland

The River Shin is a river in the Scottish North West Highlands.

<span class="mw-page-title-main">North of Scotland Hydro-Electric Board</span> UK hydroelectric government body (1943–1990)

The North of Scotland Hydro-Electric Board (1943–1990) was founded to design, construct and manage hydroelectricity projects in the Highlands of Scotland. It is regarded as one of the major achievements of Scottish politician Thomas Johnston, who chaired the board from 1945 to 1959.

<span class="mw-page-title-main">River Conon</span> River in Scotland

The River Conon is a river in the Highlands of Scotland. It begins at Loch Luichart, and flows in a south-easterly direction to be joined by the River Meig at Scatwell before passing through Loch Achonachie. It is joined by the Black Water at Moy Bridge, and the River Orrin at Urray, before flowing past Conon Bridge and into the Cromarty Firth.

<span class="mw-page-title-main">Tummel hydro-electric power scheme</span> Dam in Perth and Inverness

The Tummel hydro-electric power scheme is an interconnected network of dams, power stations, aqueducts and electric power transmission in the Grampian Mountains of Scotland. Roughly bounded by Dalwhinnie in the north, Rannoch Moor in the west and Pitlochry in the east it comprises a water catchment area of around 1,800 square kilometres and primary water storage at Loch Ericht, Loch Errochty, Loch Rannoch and Loch Tummel, in Perth and Kinross. Water, depending on where it originates and the path it takes, may pass through as many as five of the schemes nine power stations as it progresses from north-west to south-east. The scheme was constructed in the 1940s and 50s incorporating some earlier sites. It is managed by SSE plc.

<span class="mw-page-title-main">Affric-Beauly hydro-electric power scheme</span> Power stations on River Affric and River Beauly in Scottish Highlands

The Affric-Beauly hydro-electric power scheme for the generation of hydro-electric power is located in the western Highlands of Scotland. It is based around Glen Strathfarrar, Glen Cannich and Glen Affric, and Strathglass further downstream.

<span class="mw-page-title-main">Loch Errochty</span> Loch in Perth and Kinross, Scotland

Loch Errochty is a man made freshwater loch situated within the Perth and Kinross council area at the edge of the Scottish Highlands near the Highland Boundary Fault where the topography changes to lowland.

<span class="mw-page-title-main">Glendoe Hydro Scheme</span> Hydro-electric power scheme in Scotland

The Glendoe Hydro Scheme for the generation of hydro-electric power is located near Fort Augustus, above Loch Ness in the Highlands of Scotland.

<span class="mw-page-title-main">Nostie</span> Human settlement and power station in Scotland

Nostie is a small remote hamlet, lying on Nostie Bay, an inlet at the northeastern end of the sea loch, Loch Alsh in the Scottish Highlands and is in the council area of Highland. Nostie lies a short distance from one of Scotland's popular tourist attractions, Eilean Donan Castle.

<span class="mw-page-title-main">River Garry, Inverness-shire</span> River and power stations in Scotland

The River Garry in Inverness-shire is a Scottish river punctuated by two long Lochs, in the region of Lochaber. It flows broadly west to east through Glen Garry, starting in a wilderness to the east of Knoydart and ending at Loch Oich in the Great Glen, which forms part of the Caledonian Canal. There are a few tiny settlements within Glen Garry, but the only village of any size near to the river is Invergarry, at its mouth. Loch Quoich at the western end of the watercourse is dammed by the largest mass earth fill dam in Scotland, and supplies water to Quoich hydroelectric power station. Loch Garry is dammed by a much smaller dam in the gorge where the river begins its descent to Invergarry, and supplies water to Invergarry hydroelectric power station, close to the mouth of the river. Both hydroelectric schemes were built in the 1950s, with the aim of stimulating economic regeneration in the area. They have altered the ecology of the river, as both lochs were made considerably bigger as a result of constructing the dams.

<span class="mw-page-title-main">Cruachan Power Station</span> Hydroelectric power station in Scotland

The Cruachan Power Station is a pumped-storage hydroelectric power station in Argyll and Bute, Scotland. The scheme can provide 440 MW of power and produced 705 GWh in 2009.

<span class="mw-page-title-main">Loch Sloy Hydro-Electric Scheme</span> Dam in Argyll and Bute

The Loch Sloy Hydro-Electric Scheme is a hydro-electric facility situated between Loch Sloy and Inveruglas on the west bank of Loch Lomond in Scotland.

<span class="mw-page-title-main">River Moriston</span> River and power stations in Scotland

The River Moriston is a river in Inverness-shire, Scotland. It flows broadly east-north-east from the outfall of the dam at Loch Cluanie to Loch Ness. Its waters and those of its tributaries have been harnessed to generate hydro-electric power.

<span class="mw-page-title-main">Breadalbane Hydro-Electric Scheme</span> Multiple power stations in Scotland

The Breadalbane Hydro-Electric Scheme is a hydroelectric scheme in the Breadalbane area of Perthshire, Scotland. It comprises seven power stations which generate 120MW of power from the dams around Loch Lyon, Loch Earn and Loch Tay.

<span class="mw-page-title-main">River Morar</span> River and power station in Scotland

The River Morar is a river that flows from Loch Morar in the west Highlands of Scotland. It flows from the western end of the loch to the estuary of Morar Bay, an inlet of the Sound of Sleat. It is one of Scotland's shortest rivers, and is known for its white sands beaches where it flows through Morar Bay.

<span class="mw-page-title-main">Chliostair Hydro-Electric Scheme</span> Power station on Harris, Outer Hebrides, Scotland

Chliostair Hydro-Electric Scheme is a small scheme promoted by the North of Scotland Hydro-Electric Board on Harris, Outer Hebrides. It consists of a single power station powered with water from Loch Chliostair, and was commissioned in 1960.

<span class="mw-page-title-main">Gisla Hydro-Electric Scheme</span> Power station on Lewis, Outer Hebrides, Scotland

Gisla Hydro-Electric Scheme was a small scheme promoted by the North of Scotland Hydro-Electric Board on the Isle of Lewis, Outer Hebrides, Scotland. It consisted of a single power station powered with water from Loch Coirceabhat, and was commissioned in 1960.

<span class="mw-page-title-main">Mucomir Hydro-Electric Scheme</span> Power station near Spean Bridge, Scotland

Mucomir Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1962. It is located on the Mucomir Cut, a waterway created by Thomas Telford during the building of the Caledonian Canal to replace the existing coarse of the River Lochy below Loch Lochy, so that the old course could be used for the canal. The power station was substantially upgraded in 2017.

<span class="mw-page-title-main">Awe Hydro-Electric Scheme</span> Power stations near Loch Awe, Scotland

The Awe Hydro-Electric Scheme was the penultimate scheme developed by the North of Scotland Hydro-Electric Board. It centres around Loch Awe, in Argyll and Bute, on the southern edge of the Scottish Highlands. It consists of three power stations, two conventional hydro-electric stations, and the Cruachan power station, the first large pumped storage scheme built by the Board. It was completed in 1965.

References

  1. Payne 1988, pp. 50, 298.
  2. Miller 2002, pp. 19–20.
  3. Wood 2002, pp. 58–59.
  4. 1 2 3 Patel 2018.
  5. "Railway at Storr Lochs Hydro-Electric Scheme". Am Baile - Highland History and Culture. Archived from the original on 12 June 2023.
  6. Miller 2002, p. 51.
  7. "Storr Lochs Hydro-Electric Dam". Am Baile - Highland History and Culture. Archived from the original on 12 June 2023.
  8. "Storr Lochs Hydro-Electric Winch House". Am Baile - Highland History and Culture. Archived from the original on 12 June 2023.
  9. "Storr Lochs Power Station". RailScot. 15 April 2015. Archived from the original on 12 June 2023.
  10. "Hydro-Electric Generating Station at Bearreraig Bay". Am Baile - Highland History and Culture. Archived from the original on 31 July 2023.
  11. "Storr Lochs Hydro-Electric Generating Station". Am Baile - Highland History and Culture. Archived from the original on 12 June 2023.
  12. "Storr Lochs Hydro-Electric Dam". Am Baile - Highland History and Culture. Archived from the original on 12 June 2023.
  13. "Storr Lochs Hydro-Electric Pipeline". Am Baile - Highland History and Culture. Archived from the original on 12 June 2023.
  14. 1 2 3 "Skye, Storr Lochs Dam". Canmore. Archived from the original on 12 June 2023.
  15. "Plaque at Storr Lochs Hydro-Electric Scheme". Am Baile - Highland History and Culture. Archived from the original on 12 June 2023.
  16. "Opening Day, Storr Lochs Hydro-Electric Station". Am Baile - Highland History and Culture. Archived from the original on 12 June 2023.
  17. Miller 2002, p. 53.
  18. "Storr Lochs Hydro-Electric Dam". Am Baile - Highland History and Culture. Archived from the original on 12 June 2023.
  19. Payne 1988, Frontpiece.
  20. "Loch Leathan Water body ID 16986". UK Centre for Ecology and Hydrology.
  21. "Loch Fada Water body ID 17329". UK Centre for Ecology and Hydrology.
  22. "Storr Lochs Power Station: Isle of Skye". Site Drilling Specialists. Archived from the original on 12 June 2023.

Bibliography

Commons-logo.svg Media related to Storr Lochs hydroelectric station at Wikimedia Commons