Striven Hydro-Electric Scheme

Last updated

Striven
Hydro-Electric Scheme
Hydro-electric power station at Loch Striven (geograph 5875078).jpg
Striven power station and pipeline
Argyll and Bute UK relief location map.jpg
Red pog.svg
Location of Striven
Hydro-Electric Scheme in Argyll and Bute
CountryScotland
Location Ardtaraig, Argyll and Bute
Coordinates 56°00′33″N5°07′11″W / 56.0091°N 5.1197°W / 56.0091; -5.1197
PurposePower
StatusOperational
Opening date1951
Owner(s) SSE
Striven Hydro-Electric Scheme
BSicon uexKHSTaq.svg
BSicon uexABZ+lr.svg
BSicon uexKHSTeq.svg
Glen Tarsan tributaries
BSicon uexKHSTaq.svg
BSicon uexABZg+lr.svg
BSicon uexKHSTeq.svg
Tributaries
BSicon uexKHSTaq.svg
BSicon uexABZg+lr.svg
BSicon uexKHSTeq.svg
Tributaries
BSicon uexKHSTaq.svg
BSicon uexABZg+lr.svg
BSicon uexKHSTeq.svg
Tributaries
BSicon uexDOCKSa.svg
Loch Tarsan
BSicon uexDOCKSm.svg
BSicon uexKHSTa.svg
BSicon uexKHSTa.svg
BSicon uexDOCKSm.svg
BSicon utSTR+l.svg
BSicon uxWEIRg@G.svg
BSicon utSTRq.svg
BSicon uxWEIRg@G.svg
BSicon utENDEeq.svg
Conduit + intakes
BSicon uexDOCKSm.svg
BSicon uexRESVGDl.svg
BSicon uexSTRl.svg
BSicon uexABZql.svg
BSicon uexABZq+l.svg
BSicon uexABZq+l.svg
BSicon uexCONTfq.svg
Col Dam, Glen Lean
BSicon uexDOCKSm.svg
BSicon utSTRl.svg
BSicon utSTRq.svg
BSicon utSTRq.svg
BSicon uxWEIRf@F.svg
BSicon utSTRq.svg
BSicon uxWEIRf@F.svg
BSicon utENDEeq.svg
Aqueduct + intakes
BSicon uexDOCKSm.svg
BSicon uxWEIRfl.svg
BSicon utENDEa.svg
BSicon uexKHSTeq.svg
BSicon uexKHSTe.svg
BSicon uexKHSTe.svg
BSicon uexRESVGDa.svg
BSicon utKRWl.svg
BSicon utKRW+r.svg
Tarsan Dam
BSicon uexKRWl.svg
BSicon utSHI1+r.svg
BSicon uexKRW+r.svg
BSicon utSTR.svg
Glentarsan Burn
BSicon utSTR.svg
BSicon uexABZg+l.svg
BSicon uxWEIRfl.svg
BSicon utSTR.svg
BSicon uexSTRq.svg
BSicon uexKHSTeq.svg
BSicon utSTR.svg
BSicon uexABZg+l.svg
BSicon uxWEIRfl.svg
BSicon utENDEe.svg
BSicon uexSTRq.svg
BSicon uexKHSTeq.svg
Garbh Allt Mòr intake
BSicon utSTR.svg
BSicon uexSKRZ-Yu.svg
B836 road
BSicon utENDEa.svg
BSicon utENDEe.svg
BSicon uexSTRl.svg
BSicon uexSTR+r.svg
Tunnel and pipeline
BSicon utSTRl.svg
BSicon utSTR+r.svg
BSicon uexABZg+l.svg
BSicon uexSTRq.svg
BSicon uexKHSTeq.svg
Garbh Allt Beag
BSicon POINTERg@fq.svg
BSicon uexSTR+r.svg
BSicon utSTR.svg
BSicon uexSTR.svg
Balliemore Burn
BSicon uexSKRZ-Yu.svg
BSicon utSKRZ-Yu.svg
BSicon uexSTR.svg
B836 road
BSicon utSTRl.svg
BSicon utABZq+l.svg
BSicon utSTRq.svg
BSicon utSTRq.svg
BSicon uexBRUCKEu.svg
BSicon utABZg+r.svg
BSicon uexSTR.svg
Riddon pipeline
BSicon utSTR.svg
BSicon uDOCKSa.svg
BSicon PUMPSTNl.svg
BSicon utSTRr.svg
BSicon uexSTR.svg
Striven power station
BSicon POINTERg@fq.svg
BSicon uexSTR.svg
BSicon utSTR.svg
BSicon uDOCKSm.svg
BSicon uexSTR.svg
Tamhnich Burn
BSicon uxWEIRg@G.svg
BSicon uexENDEaq.svg
BSicon uexSTRq.svg
BSicon uexSTRr.svg
BSicon uDOCKSm.svg
BSicon uexSTR.svg
Tamhnich Burn intake
BSicon uexCONTf.svg
BSicon uDOCKSm.svg
BSicon uexSTRq.svg
BSicon uexSTRr.svg
BSicon uDOCKSm.svg
Loch Striven

Striven Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1951. It is located near Ardtaraig on the Cowal peninsula, part of Argyll and Bute in Scotland. It is sometimes known as the Cowal Hydro-Electric Scheme. It was originally designed to supply power to the remote communities on the peninsula, but is now connected to the National Grid.

Contents

History

The North of Scotland Hydro-Electric Board was created by the Hydro-electric Development (Scotland) Act 1943, [1] a measure championed by the politician Tom Johnston while he was Secretary of State for Scotland. [2] Johnston's vision was for a public body that could build hydro-electric stations throughout the Highlands. Profits made by selling bulk electricity to the Scottish lowlands would be used to fund "the economic development and social improvement of the North of Scotland." Private consumers would be offered a supply of cheap electricity, and their connection to that supply would not reflect the actual cost of its provision in remote and sparsely-populated areas. [3]

The chairman of the new Board was to be Lord Airlie, who had initially been critical of the 1943 Act because its scope was too limited. The deputy chairman and chief executive was Edward MacColl, an engineer with wide experience of hydro-electric projects and electrical distribution networks. [4] It soon became clear that MacColl intended to push ahead with the aspirations of the Act at breakneck speeds. He produced a list of 102 potential sites in just three months, [5] and in June 1944, the first constructional scheme was published. This was for the Loch Sloy scheme, which had a ready market for bulk supplies to nearby Clydeside, but it included two smaller schemes, to demonstrate the Board's commitment to supplying remote areas. [6]

Striven was another small-scale scheme, and when it was commissioned in 1951, it supplied power to the remote communities of the Cowal peninsula. [7] The turbine house and cottages for the staff were designed by the architect Reginald Fairlie, who was one of the architectural advisors for the North of Scotland Hydro-Electric Board. [8] The Board appointed three Scottish architects to act as architectural advisors in 1943, and their role was to judge competitive entries submitted by others, but by 1947 this model had been abandoned, and Fairlie, together with James Shearer and Harold Tarbolton designed the buildings themselves. [9] With a steeply pitched roof and large rectangular windows, Striven turbine house looks almost ecclesiastical, and fits in well with other buildings in the locality. [7]

The Glentarsan Burn drained a large area to the east of the power station site, and a water supply was provided by building Tarsan Dam across the valley, to create Loch Tarsan. [10] The dam is around 1,000 feet (300 m) long and 90 feet (27 m) high. [11] To prevent water overflowing down Glen Lean as the water levels rose, Col Dam was constructed at the head of Glen Lean, thus giving Loch Tarsan a triangular shape. A large number of small streams which drain the foothills of the surrounding peaks combine in Glen Tarsan to feed the reservoir. [10] These are supplemented by an aqueduct, which collects water from the Corrachaive Glen and several streams that would otherwise drain into Glen Lean. [8] A second conduit runs along the north-west side of Glen Lean, where intakes intercept streams that drain the foothills of Sgorach Mòr. Both feed into the reservoir near Col Dam, while another conduit collects water from Garbh Allt Mòr and another un-named stream close to Tarsan Dam. From a valve tower at Tarsan Dam, [10] a pressure tunnel carries water through the hills to the north-west of the dam, and a surface pipeline completes the route to the turbine house. [8] The pressure tunnel is around 4,000 feet (1,200 m) long and has a cross section which is horse-shoe shaped. It is fully lined, and around 6.5 feet (2.0 m) in width. [12] This provides a head of 400 feet (120 m) to the horizontal Francis turbines in the turbine house, [11] which is located next to the B836 road on the shores of Loch Striven, to the north of the hamlet of Ardtaraig. [10]

The Riddon pipeline collects water from streams to the west of the power station Riddon no. 2 pipeline - geograph.org.uk - 572679.jpg
The Riddon pipeline collects water from streams to the west of the power station

Additional water is collected from the foothills of the Cruach nan Cuilean mountain to the north-west of the power station. There is a small dam on the Tamhnich Burn close to a hill called Tom a' Chodail. An open aqueduct, marked as a conduit on maps, runs from there eastwards following the 490-foot (150 m) contour, before turning to the north and entering a tunnel through A' Cruach. It emerges as a pipeline close to the 460-foot (140 m) contour and continues northwards, descending to around 312 feet (95 m) to join another pipeline, descending from further west. This collects water from several tributaries of the Balliemore Burn, although the intakes are not shown of Ordnance Survey maps. The pipeline continues down to the valley floor, passing under the B836 road and over the Balliemore Burn, to deliver water to the power station. [10]

The scheme was designed to serve residents on the Cowal Peninsula, together with the Isle of Bute and the Isle of Cumbrae. At the time, the population was 25,400, spread over an area of 508 square miles (1,320 km2). In order to achieve this, some 250 miles (400 km) of overhead high- and low-voltage power lines were constructed. The Isle of Bute was supplied by 22 kV submarine cables, and another submarine cable, 2.5 miles (4.0 km) long and operating at 11 kV connected Bute to Cumbrae. [12]

In early 1957, Lord Lucas of Chilworth asked questions in the House of Lords about the costs of Scottish hydro-electricity. Lord Strathclyde stated that for Striven, the capital cost of the project was £356 per kW, towards the higher end of the 27 schemes mentioned, and considerably higher than the average cost of £175 per kW. The scheme was the North of Scotland Hydro-Electric Board's Constructional Scheme No. 4 and No. 69, [13] and the first stage was commissioned in 1951. Payne states that the turbine could produce 6 MW, [14] but more recent accounts state that it can produce 8 MW, with the reservoir providing a head of 404 feet (123 m). [15]

Operation

The power station ran in its original form for around 45 years, although ownership changed in 1989/90, when the electricity industry was privatised, and all of the assets of the North of Scotland Hydro-Electric Board passed to Scottish Hydro-Electric. [16] The company merged with Southern Electric in 1998, to become Scottish and Southern Energy, [17] which since 2010 has been known as SSE. [18]

The new owners commissioned a noise reduction programme in June 1995, with acoustic consultants Spectrum managing a project to reduce the noise made by the Francis turbine, and noise in the turbine house generally. [19] The turbine was refurbished in 2002. [7]

Hydrology

The surface level of Loch Tarsan is 407 feet (124 m) above Ordnance datum (AOD), it covers 0.40 square miles (1.04 km2), and drains an area of 3.84 square miles (9.95 km2). [20]

GlenTarsan Burn, the river below Tarsan Dam, is not normally supplied with compensation water from the reservoir. In 2011 the Scottish Environment Protection Agency (SEPA) held a consultation on the effects on water quality where rivers had been modified by the construction of hydro-electric dams. The Tay District Salmon Fisheries Board made a response, which looked at all of the Scottish rivers classified as heavy modified water bodies under the Water Framework Directive because of hydro-electric schemes. Most had failed to reach good status by 2015, which was a key component of the directive. They estimated the quantities of compensation water that would be needed, and the amount by which electricity generation would be reduced if this amount of water was regularly discharged to maintain river habitats. [21] For the Glentarsan Burn, they estimated that 10.88 Megalitres per day (Mld) would be needed, and that this would reduce energy production by 1.119 GWh per year, while for the Bailliemore Burn the extra compensation flow would be 2 Mld, reducing production by a further 0.219 GWh per year. [22] This amounts to a reduction of about six per cent, since the scheme produces around 22 GWh per year. [23]

Bibliography

Related Research Articles

<span class="mw-page-title-main">Falls of Foyers</span> Waterfall in Highland, Scotland

The Falls of Foyers are two waterfalls on the River Foyers, which feeds Loch Ness, in Highland, Scotland. They are located on the lower portion of the River Foyers, and consist of the upper falls, with a drop of 46 feet (14 m) and the lower falls, which drop 98 feet (30 m).

<span class="mw-page-title-main">North of Scotland Hydro-Electric Board</span> UK hydroelectric government body (1943–1990)

The North of Scotland Hydro-Electric Board (1943–1990) was founded to design, construct and manage hydroelectricity projects in the Highlands of Scotland. It is regarded as one of the major achievements of Scottish politician Thomas Johnston, who chaired the board from 1945 to 1959.

<span class="mw-page-title-main">Loch Striven</span> Sea Loch in Argyll and Bute, Scotland.

Loch Striven is a sea loch extending off the Firth of Clyde, and forms part of the Cowal peninsula coast, in Argyll and Bute, Scotland.

<span class="mw-page-title-main">Tummel hydro-electric power scheme</span> Power stations in Perth and Inverness

The Tummel hydro-electric power scheme is an interconnected network of dams, power stations, aqueducts and electric power transmission in the Grampian Mountains of Scotland. Roughly bounded by Dalwhinnie in the north, Rannoch Moor in the west and Pitlochry in the east it comprises a water catchment area of around 1,800 square kilometres and primary water storage at Loch Ericht, Loch Errochty, Loch Rannoch and Loch Tummel, in Perth and Kinross. Water, depending on where it originates and the path it takes, may pass through as many as five of the schemes nine power stations as it progresses from north-west to south-east. The scheme was constructed in the 1940s and 50s incorporating some earlier sites. It is managed by SSE plc.

<span class="mw-page-title-main">Affric-Beauly hydro-electric power scheme</span> Power stations on River Affric and River Beauly in Scottish Highlands

The Affric-Beauly hydro-electric power scheme for the generation of hydro-electric power is located in the western Highlands of Scotland. It is based around Glen Strathfarrar, Glen Cannich and Glen Affric, and Strathglass further downstream.

<span class="mw-page-title-main">Glendoe Hydro Scheme</span> Hydro-electric power scheme in Scotland

The Glendoe Hydro Scheme for the generation of hydro-electric power is located in the Monadhliath Mountains near Fort Augustus, above Loch Ness in the Highlands of Scotland. The change in financial incentives following the publication of the Renewables Obligation in 2001 caused Scottish and Southern Energy (SSE) to reconsider a number of schemes that had been mothballed in the 1960s by the North of Scotland Hydro-Electric Board, and plans for the Glendoe scheme were resurrected.

<span class="mw-page-title-main">Nostie</span> Human settlement and power station in Scotland

Nostie is a small remote hamlet, lying on Nostie Bay, an inlet at the northeastern end of the sea loch, Loch Alsh in the Scottish Highlands and is in the council area of Highland. Nostie lies a short distance from one of Scotland's popular tourist attractions, Eilean Donan Castle.

<span class="mw-page-title-main">Loch Sloy Hydro-Electric Scheme</span> Dam in Argyll and Bute

The Loch Sloy Hydro-Electric Scheme is a hydro-electric facility situated between Loch Sloy and Inveruglas on the west bank of Loch Lomond in Scotland.

<span class="mw-page-title-main">River Moriston</span> River and power stations in Scotland

The River Moriston is a river in Inverness-shire, Scotland. It flows broadly east-north-east from the outfall of the dam at Loch Cluanie to Loch Ness. Its waters and those of its tributaries have been harnessed to generate hydro-electric power.

<span class="mw-page-title-main">Breadalbane Hydro-Electric Scheme</span> Multiple power stations in Scotland

The Breadalbane Hydro-Electric Scheme is a hydroelectric scheme in the Breadalbane area of Perthshire, Scotland. It comprises seven power stations which generate 120MW of power from the dams around Loch Lyon, Loch Earn and Loch Tay.

<span class="mw-page-title-main">Storr Lochs Hydro-Electric Scheme</span> Power station on Isle of Skye, Scotland

Storr Lochs is a hydro-electric power station built on the Isle of Skye, Inner Hebrides, Scotland and commissioned in 1952. It was built by the North of Scotland Hydro-Electric Board, and used water from Lochs Leathan and Fada, to provide the first general supply of electricity to the island. Because the location of the turbine house was not easily accessible, it is served by an electric funicular railway.

<span class="mw-page-title-main">Chliostair Hydro-Electric Scheme</span> Power station on Harris, Outer Hebrides, Scotland

Chliostair Hydro-Electric Scheme is a small scheme promoted by the North of Scotland Hydro-Electric Board on Harris, Outer Hebrides. It consists of a single power station powered with water from Loch Chliostair, and was commissioned in 1960.

<span class="mw-page-title-main">Gisla Hydro-Electric Scheme</span> Power station on Lewis, Outer Hebrides, Scotland

Gisla Hydro-Electric Scheme was a small scheme promoted by the North of Scotland Hydro-Electric Board on the Isle of Lewis, Outer Hebrides, Scotland. It consisted of a single power station powered with water from Loch Coirceabhat, and was commissioned in 1960.

<span class="mw-page-title-main">Shira Hydro-Electric Scheme</span> Power stations near Loch Fyne, Scotland

The Shira Hydro-Electric Scheme is a project initiated by the North of Scotland Hydro-Electric Board to use the waters of the River Shira, the River Fyne and other small streams to generate hydroelectricity. It is located between Loch Fyne and Loch Awe in Argyll and Bute, western Scotland. It consists of three power stations and three impounding dams.

<span class="mw-page-title-main">Awe Hydro-Electric Scheme</span> Power stations near Loch Awe, Scotland

The Awe Hydro-Electric Scheme was the penultimate scheme developed by the North of Scotland Hydro-Electric Board. It centres around Loch Awe, in Argyll and Bute, on the southern edge of the Scottish Highlands. It consists of three power stations, two conventional hydro-electric stations, and the Cruachan power station, the first large pumped storage scheme built by the Board. It was completed in 1965.

<span class="mw-page-title-main">Lussa Hydro-Electric Scheme</span> Power station near Peninver, Scotland

Lussa Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1956. It is located near Peninver on the Kintyre peninsula, part of Argyll and Bute in Scotland. It was originally designed to supply power to Campbeltown, but is now connected to the National Grid.

<span class="mw-page-title-main">Kerry Falls Hydro-Electric Scheme</span> Power station near Peninver, Scotland

Kerry Falls Hydro-Electric Scheme, sometimes known as Gairloch is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1952. It is located near Gairloch in Wester Ross, part of the Highlands of Scotland. It was originally designed to supply power to local communities in this remote area, but is now connected to the National Grid.

<span class="mw-page-title-main">Loch Dubh Hydro-Electric Scheme</span> Power station near Ullapool, Scotland

Loch Dubh Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1955. It is located near Ullapool in Ross and Cromarty, Scotland. It was originally designed to supply power to the remote communities around Ullapool, but is now connected to the National Grid.

<span class="mw-page-title-main">Kilmelfort Hydro-Electric Scheme</span> Power station near Kilmelford, Scotland

Kilmelfort Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1956. It is located near Kilmelford in Argyll and Bute, Scotland. It was originally designed to supply power to the local communities around Kilmelford, but is now connected to the National Grid.

<span class="mw-page-title-main">Loch Gair Hydro-Electric Scheme</span> Power station near Lochgilphead, Scotland

Loch Gair Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1956. It is located near Lochgair, a hamlet to the north-east of Lochgilphead, Argyll and Bute in Scotland. It was originally designed to supply power to Lochgilphead and the surrounding communities, but is now connected to the National Grid.

References

  1. Payne 1988, pp. 50, 298.
  2. Miller 2002, pp. 19–20.
  3. Wood 2002, pp. 58–59.
  4. Payne 1988, pp. 50–51.
  5. Payne 1988, p. 55.
  6. Payne 1988, pp. 60–61.
  7. 1 2 3 "Loch Striven, Striven Power Station". Canmore. Archived from the original on 13 February 2023.
  8. 1 2 3 "Cowal Hydro-Electric Power Scheme". Gazeteer for Scotland. Archived from the original on 21 December 2023.
  9. Fleetwood 2010, p. 40.
  10. 1 2 3 4 5 Ordnance Survey, 1:25000 map
  11. 1 2 NoSHEB 1948, p. 23.
  12. 1 2 NoSHEB 1948, p. 22.
  13. "North of Scotland Hydro-Electric Costs". Hansard. 22 January 1957. Archived from the original on 14 June 2023.
  14. Payne 1988, p. 232.
  15. Reeves 2018, p. 99.
  16. Miller 2002, pp. 246, 248.
  17. "SSE Group history". SSE. Archived from the original on 27 May 2010.
  18. "First press release with new branding". Archived from the original on 7 August 2011.
  19. "Hydro Power Generation" (PDF). Spectrum Acoustic Consultants. October 2010. p. 2. Archived (PDF) from the original on 14 August 2022.
  20. "Loch Tarsan Water body ID 25391". UK Centre for Ecology & Hydrology. Archived from the original on 28 December 2023.
  21. Summers 2012, pp. 1–2.
  22. Summers 2012, p. 4.
  23. Miller 2002, p. 256.

Commons-logo.svg Media related to Striven hydro-electric scheme at Wikimedia Commons