Breadalbane Hydro-Electric Scheme

Last updated

Breadalbane Hydro-Electric Scheme
Finlarig Dam.png
Lawers Dam was the first to be completed
Highland UK relief location map.jpg
Red pog.svg
Location of Breadalbane Hydro-Electric Scheme in Highland
CountryScotland
Location Perthshire
Coordinates 56°28′52″N4°17′53″W / 56.481°N 4.298°W / 56.481; -4.298
PurposePower
StatusOperational
Construction began1951
Opening date1961
Owner(s) SSE
7 power stations, 6 dams

The Breadalbane Hydro-Electric Scheme is a hydroelectric scheme in the Breadalbane area of Perthshire, Scotland. It comprises seven power stations which generate 120MW of power from the dams around Loch Lyon, Loch Earn and Loch Tay. [1]

Contents

History

The politician Tom Johnston during his time as Secretary of State for Scotland, [2] championed the Hydro-electric Development (Scotland) Act 1943, which created the North of Scotland Hydro-Electric Board. [3] Johnston's vision was for a public body that could build hydro-electric stations throughout the Highlands. Profits made by selling bulk electricity to the Scottish lowlands would be used to fund "the economic development and social improvement of the North of Scotland." Private consumers would be offered a supply of cheap electricity, and their connection to that supply would not reflect the actual cost of its provision in remote and sparsely-populated areas. [4]

The chairman of the new Board was to be Lord Airlie, who had initially been critical of the 1943 Act because its scope was too limited. The deputy chairman and chief executive was Edward MacColl, an engineer with wide experience of hydro-electric projects and electrical distribution networks. [5] It soon became clear that MacColl intended to push ahead with the aspirations of the Act at breakneck speeds. He produced a list of 102 potential sites in just three months, [6] and in June 1944, the first constructional scheme was published, for the large Loch Sloy scheme and two much smaller projects at Nostie Bridge and Morar. [7] The Breadalbane scheme and Breadalbane Amendments scheme were published as constructional schemes 25 and 25A. [8]

Construction began in autumn 1951. The first stage was the building of Lawers Dam, at the south-eastern end of Lochan na Lairige. This was a fairly small loch, but its level was raised by 90 feet (27 m), enabling it to store 460 million cubic feet (13,000 Ml) of water. From the dam, a tunnel and pipeline feeds the water to Finlarig power station, located on the shore of Loch Tay at its south-western end. Finlarig contains a single 30 MW Pelton turbine generating set, which is the largest Pelton turbine in Britain. [9] The dam is 1,129 feet (344 m) long and 138 feet (42 m) tall at its highest point. [10] [11] It is of the massive butress type, for which the dam at Loch Sloy was the prototype. [12] Water descends a vertical distance of 1,362 feet (415 m) from the dam to the power station, the highest drop of any hydro-electric scheme in Scotland for more than fifty years, [13] until it was exceeded by the Glendoe Hydro Scheme in 2009. [14]

To increase the amount of water available, the headwaters of streams that fed into Loch Tay, the River Lyon and the River Lochay were captured by a series of tunnels and aqueducts, increasing its catchment area to 17.4 square miles (45 km2). Additionally, headwaters from two tributaries of the River Lochay are fed directly into the tunnel supplying the power station. The dam has two control towers, on either side of the central spillway. One controls the release of compensation water to the Allt a Moirneas, while the other controls the flow of water into the tunnel to Finlarig power station, which was commissioned in 1955. [10] [15]

The scheme was expanded by the addition of six further power stations, with those to the west and north west of Finlarig comprising the Killin section and those to the south-east of Finlarig comprising the St Fillans section. [16]

Killin section

Breadalbane hydro-electric scheme
BSicon uexCONTg.svg
River Tay
BSicon uexSTRc2.svg
BSicon uexSTR3+l.svg
BSicon uexABZgr.svg
River Lyon
BSicon uexSTRc2.svg
BSicon uexSTR3+1.svg
BSicon uexSTRc4.svg
BSicon uDOCKSa.svg
Loch Tay
BSicon uexSTRc2.svg
BSicon uexSTR3+1.svg
BSicon uexSTRc4.svg
BSicon uDOCKSm.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utENDEa.svg
BSicon uexABZq+l.svg
BSicon uexCONTfq.svg
River Almond
BSicon uexSTRc2.svg
BSicon uexSTR3+1.svg
BSicon uexSTRc4.svg
BSicon uDOCKSm.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utSTR.svg
BSicon uexSTRr.svg
BSicon uexSTRc2.svg
BSicon uexSTR3+1.svg
BSicon uexSTRc4.svg
BSicon uDOCKSm.svg
BSicon utSTR.svg
BSicon uexSTRc2.svg
BSicon uexSTR+1.svg
BSicon uexSTRc4.svg
BSicon uDOCKSm.svg
BSicon utSTR+l.svg
BSicon utHSTRbr.svg
BSicon uexDOCKSl.svg
BSicon uexRESVGDl.svg
BSicon uexCONTfq.svg
Lednock power station
BSicon uexSTR.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utENDEa.svg
BSicon uexSTRq.svg
BSicon uDOCKSm.svg
BSicon utSTR.svg
BSicon utSTR.svg
BSicon uexSTR+l.svg
BSicon uexCONTfq.svg
River Earn
BSicon uexSTR.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utSTR.svg
BSicon uexSTRq.svg
BSicon uDOCKSm.svg
BSicon utSTR.svg
BSicon utSTR.svg
BSicon uxSTRbr.svg
BSicon utSTR+r.svg
Dalchonzie power station
BSicon uexSTR.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utSTR.svg
BSicon uexSTRq.svg
BSicon uDOCKSm.svg
BSicon utSTR.svg
BSicon utSTR+l.svg
BSicon utTEEeq.svg
BSicon uxWEIRr.svg
BSicon utSTRr.svg
BSicon uexSTR.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utSTR.svg
BSicon uexSTRq.svg
BSicon uDOCKSm.svg
BSicon utSTR.svg
BSicon utSTR2.svg
BSicon PUMPSTNr.svg
BSicon utSTRl.svg
BSicon uDOCKSa.svg
St Fillans power station
BSicon uexABZgl.svg
BSicon uxWEIRfl.svg
BSicon utENDEa.svg
BSicon uexKHSTeq.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utSTR.svg
BSicon uexSTRq.svg
BSicon uDOCKSm.svg
BSicon utSTR.svg
BSicon utSTR+4.svg
BSicon uDOCKSm.svg
BSicon uexSTR.svg
BSicon utSTR.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utSTR.svg
BSicon uexSTRq.svg
BSicon uDOCKSm.svg
BSicon utSTR.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utSTR.svg
BSicon uDOCKSm.svg
BSicon uexABZgl.svg
BSicon uxWEIRfl.svg
BSicon utSTR.svg
BSicon uexKHSTeq.svg
BSicon utSTR3.svg
BSicon uDOCKSm.svg
BSicon uexSTRq.svg
BSicon uexRESVGl.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utENDEe.svg
BSicon uDOCKSm.svg
Loch Breaclaich
BSicon uexSTR.svg
BSicon utSTRl.svg
BSicon uexDOCKSl.svg
BSicon uexRESVGDl.svg
BSicon uexSTRq.svg
BSicon uexSTRq.svg
BSicon uDOCKSm.svg
BSicon uexSTRq.svg
BSicon uxWEIRfl.svg
BSicon utSTR.svg
BSicon uexKHSTeq.svg
BSicon uDOCKSm.svg
Lochan na Lairige dam
BSicon uexABZgl.svg
BSicon uexSTRq.svg
BSicon uxWEIRfl.svg
BSicon utSTR.svg
BSicon uexKHSTeq.svg
BSicon utSTRl+4.svg
BSicon utHSTRbr.svg
BSicon uDOCKSe.svg
BSicon uexSTRq.svg
BSicon uxWEIRfl.svg
BSicon utENDEe.svg
BSicon uexKHSTeq.svg
BSicon uDOCKSm.svg
Finlarig power station
BSicon uexSTR.svg
BSicon uexABZg+l.svg
BSicon uxWEIRfl.svg
BSicon utENDEe.svg
BSicon uexKHSTeq.svg
BSicon uexSTR+l.svg
BSicon uexABZgr.svg
BSicon uDOCKSm.svg
River Lochay
BSicon uexSTRc2.svg
BSicon uexABZ23.svg
BSicon uexSTRc3.svg
BSicon uexSTR2.svg
BSicon uexSTRc3.svg
BSicon uexSTR.svg
BSicon uexSTR.svg
BSicon uDOCKSe.svg
Loch Earn
BSicon uexSTR+1.svg
BSicon uexSTRc14.svg
BSicon uexSTRc1.svg
BSicon uexSTR+4.svg
BSicon uexSTR2+4.svg
BSicon utSTR3+l.svg
BSicon uexSTRc3.svg
BSicon utSTRq.svg
BSicon uxSTRbl.svg
BSicon uexSTR2.svg
BSicon uexSTRc3.svg
Lochay power station
BSicon uexRESVGDe.svg
BSicon utHSTRbr.svg
BSicon uexRESVGDe.svg
BSicon uexSTRc1.svg
BSicon utSTRr+1.svg
BSicon uexSTR2+4.svg
BSicon uexSTRc23.svg
BSicon uexSTR3.svg
BSicon uexSTRc1.svg
BSicon uexSTR+4.svg
Cashlie power stations
BSicon uexDOCKSm.svg
BSicon uexDOCKSe.svg
BSicon uexSTRc12.svg
BSicon uexSTR1+4.svg
BSicon uexSTR3+1.svg
BSicon uexSTRc4.svg
BSicon uexSTR.svg
Stronuich Reservoir
BSicon uexDOCKSe.svg
BSicon uexSTRc2.svg
BSicon uexSTR3.svg
BSicon uexSTR+1.svg
BSicon uexSTRc4.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utENDEa.svg
BSicon uexABZgr.svg
Loch an Daimh
BSicon uexSTR+1.svg
BSicon uexSTRc4.svg
BSicon uexSTR.svg
BSicon utSTR+l.svg
BSicon utSTRq.svg
BSicon utTEEeq.svg
BSicon uexSTR.svg
BSicon uxSTRbr.svg
BSicon uexABZgl.svg
BSicon uxWEIRfl.svg
BSicon utSTR.svg
BSicon uexKHSTeq.svg
BSicon utSTR.svg
BSicon uexSTR.svg
Lubreoch power station
BSicon uexRESVGDe.svg
BSicon utSTRq.svg
BSicon utABZq+r.svg
BSicon uexSTR.svg
BSicon utSTRq.svg
BSicon utTEEeq.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utSTR.svg
BSicon uexABZgr.svg
Loch Lyon dam
BSicon uexDOCKSl.svg
BSicon uexDOCKSm.svg
BSicon utSTR.svg
BSicon uexABZgl.svg
BSicon uxWEIRfl.svg
BSicon utENDEe.svg
BSicon uexKHSTeq.svg
BSicon utSTR.svg
BSicon uexSTR.svg
BSicon uexDOCKSe.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utENDEe.svg
BSicon uexABZgr.svg
BSicon uexKHSTaq.svg
BSicon uxWEIRfr.svg
BSicon utENDEe.svg
BSicon uexABZgr.svg
BSicon uexCONTf.svg
BSicon uexSTR.svg
River Lochay
BSicon uexCONTf.svg
River Dochart

The Killin section consists of three power stations, Cashlie, Lubreoch and Lochay, with two major dams and a third smaller one. Furthest west, Lubreoch dam was constructed at the eastern end of Loch Lyon by James Miller and Partners. It was 1,740 feet (530 m) long and 129 feet (39 m) high from the foundations to the crest. It was of the massive butress type and was completed in 1958. The catchment area was increased by building a network of tunnels and aqueducts to the south of the dam, picking up the headwaters of a number of tributaries of both the River Lochay and the River Dochart. Lubreoch power station is located below the dam, and was commissioned in 1958. It has a gross head of 98 feet (30 m) and can generate 4 MW. To the north of the power station is Loch an Daimh, which is dammed at its eastern end by Giorra dam. The structure was built by Edmund Nuttall and is 1,518 feet (463 m) long, with a maximum height of 114 feet (35 m). It is also of the massive butress type, and was completed in 1959. Its catchment has been increased by tunnels and aqueducts to the south and east, picking up tributaries of the River Lyon. A tunnel runs from the dam to Cashlie power station, which discharges into Stronuich Reservoir. It has a gross head of 466 feet (142 m), can generate 11 MW, and was commissioned in 1959. [17]

Stronuich Reservoir is formed by the Stronuich dam, a long low structure that dams the River Lyon. It stores water from the tailraces of Lubreoch and Cashlie power stations. Compensation water to maintain the flow in the River Lyon passes through a generator set below the dam. An intake gatehouse tower is located at the southern end of the dam, and controls the flow of water to Lochay power station. [18] A long tunnel from the reservoir supplies water to Lochay power station, which discharges into the River Lochay a short distance before it joins the River Dochart and enters Loch Tay. It has a gross head of 591 feet (180 m), can generate 47 MW, and was commissioned in 1958. [15]

St Fillans section

The St Fillans section consists of another three power stations, Lednock, St Fillans and Dalchonzie, with two major dams, Breaclaich and Lednock. Lochan Breaclaich dam prevents water flowing into the Loch Tay catchment. It is a rockfill dam, with a concrete panels on the upstream side and coursed rubble on the downstream side. A gatehouse controls the inlet to a tunnel and pipeline which feeds Lednock power station. [19] A tunnel collects headwaters from streams flowing into Loch Tay to the south-west of the reservoir, while another tunnel conveys water to Lednock power station. [15] This contains a single 4 MW turbine, which is protected by a surge tower to the north-west of the station. The water discharges into Loch Lednock. [20] The power station has a gross head of 299 feet (91 m) and was commissioned in 1961. [15]

Loch Lednock is contained by a diamond-headed butress dam at its eastern end. The dam was constructed by Taylor Woodrow, is 950 feet (290 m) long and 133 feet (41 m) high. It was completed in 1957. The catchment of Loch Lednock is supplemented by a tunnel collecting the headwaters of the River Almond. [15] There is only one other diamond-headed butress dam in Scotland, at Errochty. Because it is close to the Highland Boundary Fault, it was designed to cope with earthquakes. A dispersal valve discharges compensation water through the dam to maintain the flow in the River Lednock. There is an intake gatehouse around half way along the loch, which controls the flow of water to St Fillans power station. [21] This was the first of the additional power stations to be commissioned when it was completed in 1957. It has a gross head of 830 feet (250 m) and can generate 21 MW. The power station is constructed underground, whereas all of the others have buildings on the surface. It discharges into Loch Earn, which in turn supplies the River Earn. [15] A small weir just below the outlet from the loch diverts some of the flow into a tunnel to provide power for Dalchonzie power station. It contains a single 4 MW turbine, [22] and discharges back into the Earn. Its gross head is 95 feet (29 m) and it was commissioned in 1958. [15]

Development

Dalhonzie power station and tailrace Dalhonzie power station outfow, power station in the background - geograph.org.uk - 660108.jpg
Dalhonzie power station and tailrace

The North of Scotland Hydro-Electric Board were always looking for ways to improve their processes, and there is evidence of this at Breadalbane. The rock fill dam at Breaclaich was built to reduce the amount of cement used, and this technique had previously been used at Quoich. Fly ash was used to replace some of the cement used in the construction of the dams at Lednock, Lubreoch and Giorra. This causes the concrete to harden more slowly, but is less permeable once it has cured. [12] Although several of the dams are similar, they are different in detail, as new methods were used to reduce the amount of concrete and shuttering that was required. The massive butress dam proved to be considerably cheaper to build than a solid gravity dam, by about 30 per cent. [23]

There were advances in tunnelling techniques too. The main tunnels connected the reservoirs to the power stations, but there were also lots of tunnels used to divert water from other catchments. In total, the scheme involved some 60 miles (97 km) of tunnels, and the Board worked hard to train tunnellers and improve drilling techniques. The tunnel from Stronuich to Lochay is 13 feet 5 inches (4.09 m) in diameter, and some 4.73 miles (7.61 km) long. While a world record was claimed in October 1955 when a collecting tunnel in the St Fillans section advanced by 557 feet (170 m) in seven days, [24] the Lochay tunnellers hit a water-bearing fault which resulted in 50,000 imperial gallons (230 m3) per hour flowing into the workings, and flooding 5,000 feet (1,500 m) of the tunnel. The potential disaster was dealt with relatively easily, by pumping out the tunnel and using cast-iron segments to line a diversion. All of the tunnelling on the Killin section was completed nine months ahead of schedule. Most of the scheme was completed by late 1959, with only the Lednock station held up by issues with the Breaclaich section, resulting in it not being commissioned until March 1961. [25]

Related Research Articles

<span class="mw-page-title-main">St Fillans</span> Human settlement in Scotland

St Fillans is a village in Perthshire in the central highlands of Scotland, in the council area of Perth and Kinross. The village lies at the eastern end of Loch Earn, 5 miles (8 km) west of Comrie on the A85 road, at the point where the River Earn leaves the loch. St Fillans was a small clachan in the 18th century, known as Port of Lochearn, or Meikleport. In 1817 it was renamed St Fillans by Lord Gwydyr, the husband of Clementina Drummond, heiress to the Drummond Estate.

<span class="mw-page-title-main">River Shin</span> River in northern Scotland

The River Shin is a river in the Scottish North West Highlands.

<span class="mw-page-title-main">River Conon</span> River in Scotland

The River Conon is a river in the Highlands of Scotland. It begins at Loch Luichart, and flows in a south-easterly direction to be joined by the River Meig at Scatwell before passing through Loch Achonachie. It is joined by the Black Water at Moy Bridge, and the River Orrin at Urray, before flowing past Conon Bridge and into the Cromarty Firth.

<span class="mw-page-title-main">Tummel hydro-electric power scheme</span> Power stations in Perth and Inverness

The Tummel hydro-electric power scheme is an interconnected network of dams, power stations, aqueducts and electric power transmission in the Grampian Mountains of Scotland. Roughly bounded by Dalwhinnie in the north, Rannoch Moor in the west and Pitlochry in the east it comprises a water catchment area of around 1,800 square kilometres and primary water storage at Loch Ericht, Loch Errochty, Loch Rannoch and Loch Tummel, in Perth and Kinross. Water, depending on where it originates and the path it takes, may pass through as many as five of the schemes nine power stations as it progresses from north-west to south-east. The scheme was constructed in the 1940s and 50s incorporating some earlier sites. It is managed by SSE plc.

<span class="mw-page-title-main">Affric-Beauly hydro-electric power scheme</span> Power stations on River Affric and River Beauly in Scottish Highlands

The Affric-Beauly hydro-electric power scheme for the generation of hydro-electric power is located in the western Highlands of Scotland. It is based around Glen Strathfarrar, Glen Cannich and Glen Affric, and Strathglass further downstream.

<span class="mw-page-title-main">Glendoe Hydro Scheme</span> Hydro-electric power scheme in Scotland

The Glendoe Hydro Scheme for the generation of hydro-electric power is located in the Monadhliath Mountains near Fort Augustus, above Loch Ness in the Highlands of Scotland. The change in financial incentives following the publication of the Renewables Obligation in 2001 caused Scottish and Southern Energy (SSE) to reconsider a number of schemes that had been mothballed in the 1960s by the North of Scotland Hydro-Electric Board, and plans for the Glendoe scheme were resurrected.

<span class="mw-page-title-main">Nostie</span> Human settlement and power station in Scotland

Nostie is a small remote hamlet, lying on Nostie Bay, an inlet at the northeastern end of the sea loch, Loch Alsh in the Scottish Highlands and is in the council area of Highland. Nostie lies a short distance from one of Scotland's popular tourist attractions, Eilean Donan Castle.

<span class="mw-page-title-main">River Garry, Inverness-shire</span> River and power stations in Scotland

The River Garry in Inverness-shire is a Scottish river punctuated by two long Lochs, in the region of Lochaber. It flows broadly west to east through Glen Garry, starting in a wilderness to the east of Knoydart and ending at Loch Oich in the Great Glen, which forms part of the Caledonian Canal. There are a few tiny settlements within Glen Garry, but the only village of any size near to the river is Invergarry, at its mouth. Loch Quoich at the western end of the watercourse is dammed by the largest mass earth fill dam in Scotland, and supplies water to Quoich hydroelectric power station. Loch Garry is dammed by a much smaller dam in the gorge where the river begins its descent to Invergarry, and supplies water to Invergarry hydroelectric power station, close to the mouth of the river. Both hydroelectric schemes were built in the 1950s, with the aim of stimulating economic regeneration in the area. They have altered the ecology of the river, as both lochs were made considerably bigger as a result of constructing the dams.

<span class="mw-page-title-main">Loch Sloy Hydro-Electric Scheme</span> Dam in Argyll and Bute

The Loch Sloy Hydro-Electric Scheme is a hydro-electric facility situated between Loch Sloy and Inveruglas on the west bank of Loch Lomond in Scotland.

<span class="mw-page-title-main">River Morar</span> River and power station in Scotland

The River Morar is a river that flows from Loch Morar in the west Highlands of Scotland. It flows from the western end of the loch to the estuary of Morar Bay, an inlet of the Sound of Sleat. It is one of Scotland's shortest rivers, and is known for its white sands beaches where it flows through Morar Bay.

<span class="mw-page-title-main">Gisla Hydro-Electric Scheme</span> Power station on Lewis, Outer Hebrides, Scotland

Gisla Hydro-Electric Scheme was a small scheme promoted by the North of Scotland Hydro-Electric Board on the Isle of Lewis, Outer Hebrides, Scotland. It consisted of a single power station powered with water from Loch Coirceabhat, and was commissioned in 1960.

<span class="mw-page-title-main">Mucomir Hydro-Electric Scheme</span> Power station near Spean Bridge, Scotland

Mucomir Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1962. It is located on the Mucomir Cut, a waterway created by Thomas Telford during the building of the Caledonian Canal to replace the existing coarse of the River Lochy below Loch Lochy, so that the old course could be used for the canal. The power station was substantially upgraded in 2017.

<span class="mw-page-title-main">Shira Hydro-Electric Scheme</span> Power stations near Loch Fyne, Scotland

The Shira Hydro-Electric Scheme is a project initiated by the North of Scotland Hydro-Electric Board to use the waters of the River Shira, the River Fyne and other small streams to generate hydroelectricity. It is located between Loch Fyne and Loch Awe in Argyll and Bute, western Scotland. It consists of three power stations and three impounding dams.

<span class="mw-page-title-main">Awe Hydro-Electric Scheme</span> Power stations near Loch Awe, Scotland

The Awe Hydro-Electric Scheme was the penultimate scheme developed by the North of Scotland Hydro-Electric Board. It centres around Loch Awe, in Argyll and Bute, on the southern edge of the Scottish Highlands. It consists of three power stations, two conventional hydro-electric stations, and the Cruachan power station, the first large pumped storage scheme built by the Board. It was completed in 1965.

<span class="mw-page-title-main">Lussa Hydro-Electric Scheme</span> Power station near Peninver, Scotland

Lussa Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1956. It is located near Peninver on the Kintyre peninsula, part of Argyll and Bute in Scotland. It was originally designed to supply power to Campbeltown, but is now connected to the National Grid.

<span class="mw-page-title-main">Striven Hydro-Electric Scheme</span> Power station near Ardtaraig, Scotland

Striven Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1951. It is located near Ardtaraig on the Cowal peninsula, part of Argyll and Bute in Scotland. It is sometimes known as the Cowal Hydro-Electric Scheme. It was originally designed to supply power to the remote communities on the peninsula, but is now connected to the National Grid.

<span class="mw-page-title-main">Kerry Falls Hydro-Electric Scheme</span> Power station near Peninver, Scotland

Kerry Falls Hydro-Electric Scheme, sometimes known as Gairloch is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1952. It is located near Gairloch in Wester Ross, part of the Highlands of Scotland. It was originally designed to supply power to local communities in this remote area, but is now connected to the National Grid.

<span class="mw-page-title-main">Loch Dubh Hydro-Electric Scheme</span> Power station near Ullapool, Scotland

Loch Dubh Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1955. It is located near Ullapool in Ross and Cromarty, Scotland. It was originally designed to supply power to the remote communities around Ullapool, but is now connected to the National Grid.

<span class="mw-page-title-main">Kilmelfort Hydro-Electric Scheme</span> Power station near Kilmelford, Scotland

Kilmelfort Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1956. It is located near Kilmelford in Argyll and Bute, Scotland. It was originally designed to supply power to the local communities around Kilmelford, but is now connected to the National Grid.

<span class="mw-page-title-main">Loch Gair Hydro-Electric Scheme</span> Power station near Lochgilphead, Scotland

Loch Gair Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1956. It is located near Lochgair, a hamlet to the north-east of Lochgilphead, Argyll and Bute in Scotland. It was originally designed to supply power to Lochgilphead and the surrounding communities, but is now connected to the National Grid.

References

  1. "Power from the Glens" (PDF). SSE. 2005. Archived from the original (PDF) on 11 May 2019. Retrieved 3 May 2014.
  2. Miller 2002, pp. 19–20.
  3. Payne 1988, pp. 50, 298.
  4. Wood 2002, pp. 58–59.
  5. Payne 1988, pp. 50–51.
  6. Payne 1988, p. 55.
  7. Payne 1988, p. 61.
  8. Payne 1988, p. 189.
  9. Payne 1988, pp. 161–162.
  10. 1 2 "Lawers Dam". Canmore. Archived from the original on 3 May 2014. Retrieved 2 May 2014.
  11. Simeons 1980, p. 309.
  12. 1 2 Payne 1988, p. 162.
  13. "Breadalbane Hydro-Electric Power Scheme". The Gazetteer for Scotland. Archived from the original on 29 May 2022. Retrieved 2 May 2014.
  14. "Project Overview". Scottish and Southern Energy. Archived from the original on 25 October 2009.
  15. 1 2 3 4 5 6 7 Payne 1988, p. 165.
  16. Payne 1988, pp. 164–165.
  17. Payne 1988, pp. 164, 165, 168.
  18. "Stronuich Dam And Sluice". Canmore. Archived from the original on 9 January 2024.
  19. "Lochan Breaclaich Reservoir And Dam". Canmore. Archived from the original on 9 January 2024.
  20. "Lednock Power Station". Canmore. Archived from the original on 21 February 2017.
  21. "Loch Lednock Reservoir And Dam". Canmore. Archived from the original on 9 January 2024.
  22. "Dalchonzie Power Station". Canmore. Archived from the original on 30 November 2021.
  23. Payne 1988, p. 164.
  24. Payne 1988, p. 171.
  25. Payne 1988, pp. 173–174.

Bibliography

Commons-logo.svg Media related to Breadalbane hydro-electric scheme at Wikimedia Commons