European Offshore Wind Deployment Centre | |
---|---|
Country | Scotland |
Location | Aberdeen's Bay |
Coordinates | 57°13′N1°59′W / 57.217°N 1.983°W |
Status | Operational |
Commission date | September 2018 |
Construction cost | £335 million [1] |
Owner | European Offshore Wind Deployment Centre |
Wind farm | |
Type | Offshore |
Max. water depth | 32 m [1] |
Distance from shore | 3 km (2 mi) [1] |
Hub height | 120 m [1] |
Rotor diameter | 164 m [1] |
Site area | 19 km2 [1] |
Power generation | |
Units operational | 2 × 8.8 MW 9 × 8.4 MW |
Make and model | Vestas V164 8.4-8.8MW |
Units planned | 11 × 8.5 MW [1] |
Nameplate capacity | 92.4 MW |
External links | |
Website | group |
Commons | Related media on Commons |
The European Offshore Wind Deployment Centre (EOWDC), also known as the Aberdeen Bay Wind Farm [2] is an offshore wind test and demonstration facility located around 3 kilometres off the east coast of Aberdeenshire, in the North Sea, Scotland. It was developed by the European Offshore Wind Deployment Centre consortium. [3] The scheme is relatively small - it consists of 11 wind turbines with an installed capacity of 93.2 megawatts. [4] It is located between Blackdog and Bridge of Don near Aberdeen. [5] First power was generated in July 2018, [6] with full commissioning following in September 2018. [4]
The wind farm was initially proposed by the Aberdeen Renewable Energy Group (AREG) in 2003. [7] The original plan was for 20 two-megawatt turbines in an eight kilometres long row about 1 kilometre offshore. [7] A geological survey of Aberdeen Bay was begun in 2007, [8] and a grant of 40 million euros was offered by the European Commission in 2009. [5] The proposal at that stage was for a maximum of 23 turbines. [5]
A planning application was lodged in August 2011. [9] The application was submitted by Aberdeen Renewable Energy Group (AREG) in cooperation with two other companies, Vattenfall and Technip. [9] The proposal was for 11 turbines. [9] Planning consent was granted by the Scottish government in March 2013. [10]
In May 2013 Vattenfall announced plans to reduce its stake in the project. [11] In October 2013 Aberdeenshire councillors rejected a planning application to build an electricity substation. [12] In December 2013 it was announced that construction would be delayed for two years, with connection of the grid occurring in 2017. [13] In January 2014 an appeal against the substation vote was lodged. [14] The developers won the appeal in July 2014. [15]
Vattenfall decided to proceed with the 92 MW wind farm in July 2016. [16] The plan was for 11 turbines each of 8 MW placed 3 km from land, [1] with a contract for the assembly of suction bucket foundations for the turbines contracted out to Smulders Projects UK. [17]
American billionaire Donald Trump purchased a large part of the Menie estate near the village of Balmedie in 2006. He proposed to build a golf course, with a hotel, holiday homes and a residential village. [18] He expressed his concerns about the wind farm in April 2006 stating that "I want to see the ocean, I do not want to see windmills." [19]
In 2006 RSPB Scotland expressed concern about the effect both the wind farm and Donald Trump's golf course would have on the wildlife on the Aberdeenshire coast. [19] In 2011 the RSPB called for "more planning, research and monitoring ... to ensure we truly understand the impact this site may have on local birds." [20]
In September 2011 the Trump Organization filed an objection to the planning application. [21]
By 2012 the RSPB dropped its opposition to the wind farm following the reduction in the number of turbines and a change in the layout." [22]
In May 2013 Trump launched a legal challenge against the Scottish government's decision to grant planning permission for the wind farm. [23] The hearing began at the Court of Session in November 2013, [24] but was rejected in February 2014. [25] An appeal against the decision was heard at the Court of Session in January 2015, [26] but Trump lost the appeal in June 2015. [27] After the decision Trump said he would appeal before both the Supreme Court of the UK and the European Courts. [27] Trump's appeal was unanimously dismissed by the UK Supreme Court in December 2015. [28]
Connection work began in early 2017. The turbines are mounted on unusual suction bucket foundations. The sea cables are 66kV. [29] There are more than four miles of high voltage underground cable between the substation in Dyce (on the outskirts of Aberdeen) and the wind farm's onshore substation at Blackdog. [30] The first foundation was installed offshore in March 2018, [31] and the first turbine was installed in April. [32] The eleventh and final turbine was erected near the end of May. [33] First power was generated in July 2018, [6] with full commissioning following in September 2018. [4]
Balmedie is a large village in Aberdeenshire in Scotland. It lies north of the city of Aberdeen, in the civil parish of Belhelvie. The long and wide beach is bordered by an extensive dune system that stretches 14 miles (23 km) from Aberdeen to just north of the Ythan Estuary at Newburgh. The dynamic dunes have marram grass as the principal vegetation. They support a large array of wildlife. Two watercourses make their way to the sea within the area creating ribbons of wetland vegetation along their course. The village is near the Sands of Forvie Site of Special Scientific Interest, the fifth largest sand dune system in Britain; this is an integral part of the Ythan Estuary, which separates the sands from Balmedie Beach.
The United Kingdom is the best location for wind power in Europe and one of the best in the world. The combination of long coastline, shallow water and strong winds make offshore wind unusually effective.
The Thanet Wind Farm is an offshore wind farm 7 miles (11 km) off the coast of Thanet district in Kent, England. On commissioning it was the world's largest offshore wind farm. It has a nameplate capacity of 300 MW and it cost £780–900 million (US$1.2–1.4 billion). Thanet is one of fifteen Round 2 wind projects announced by the Crown Estate in January 2004 but the first to be developed. It was officially opened on 23 September 2010, when it overtook Horns Rev 2 as the biggest offshore wind farm in the world. It has since been overtaken by many others.
The production of renewable energy in Scotland is a topic that came to the fore in technical, economic, and political terms during the opening years of the 21st century. The natural resource base for renewable energy is high by European, and even global standards, with the most important potential sources being wind, wave, and tide. Renewables generate almost all of Scotland's electricity, mostly from the country's wind power.
Wind power is the fastest-growing renewable energy technology in Scotland, with 16,648 megawatts (MW) of installed wind power capacity by Q2 2024. This included 9,756 MW from onshore wind in Scotland and 2,971 MW of offshore wind generators. The largest onshore wind farm in the UK is Whitelee, just south of Glasgow, with 215 turbines and a total capacity of 539 MW.
Robin Rigg Wind Farm, Scotland's first offshore wind farm, was constructed by E.ON at Robin Rigg in the Solway Firth, a sandbank midway between the Galloway and Cumbrian coasts. The wind farm first generated power for test purposes on 9 September 2009 and it was completed on 20 April 2010.
The Kentish Flats Offshore Wind Farm is a wind farm located off the coast of Kent, England on a large, flat and shallow plateau just outside the main Thames shipping lanes. The wind farm is operated by Vattenfall.
Neart Na Gaoithe is an offshore wind farm under construction in the outer Firth of Forth, 15.5 kilometres (9.6 mi) east of Fife Ness. It has a potential capacity of 450 MW. It is being developed by EDF Renewables and ESB. Offshore work began in 2020, with completion originally planned for 2023 but delayed due to supply chain challenges, the Covid pandemic and "construction woes" until summer 2025.
As of May 2024, wind power in the Netherlands has an installed capacity of 11,611 MW, 40.9% of which is based offshore. In 2022, the wind turbines provided the country with 18.37% of its electricity demand during the year. Windmills have historically played a major part in the Netherlands by providing an alternative to water driven mills.
The Ormonde Wind Farm is a wind farm west of Barrow-in-Furness in the Irish Sea. The wind farm covers an area of 8.7 square kilometres (3.4 sq mi). It has a total capacity of 150 MW and is expected to produce around 500 GWh of electricity per year.
The Beatrice Offshore Wind Farm now known as Beatrice Offshore Windfarm Ltd (BOWL) project, is an offshore wind farm close to the Beatrice oil field in the Moray Firth, part of the North Sea 13 km off the north east coast of Scotland.
Triton Knoll Wind Farm is an 857 MW round 2 offshore wind farm 33 kilometres (21 mi) off the coast of Lincolnshire, in the North Sea, England.
West of Duddon Sands Wind Farm (WoDS), occasionally also known as West Duddon Wind Farm is an offshore wind farm located 14 kilometres (8.7 mi) south west of Walney Island off the coast of Barrow-in-Furness in Cumbria, in the Irish Sea, England. It was developed by Scottish Power and Ørsted A/S.
Walney Wind Farms are a group of offshore wind farms 9 miles (14 km) west of Walney Island off the coast of Cumbria, England, in the Irish Sea. The group, operated by Ørsted, consists of Walney Phase 1, Phase 2 and the Walney Extension. The extension has a capacity of 659 MW and it was the world's second largest offshore wind farm in 2018.
Rampion is an offshore wind farm developed by E.ON, now operated by RWE, off the Sussex coast in the UK. The wind farm has a capacity of 400 MW, although 700 MW was originally planned. The wind farm was commissioned in April 2018 and was the first offshore wind farm on the south coast of England.
The East Anglia Array is a proposed series of offshore wind farms located around 30 miles off the east coast of East Anglia, in the North Sea, England. It has begun with the currently operational East Anglia ONE, that has been developed in partnership by ScottishPower Renewables and Vattenfall. Up to six individual projects could be set up in the area with a maximum capacity of up to 7.2 GW. The first project, East Anglia ONE at 714 MW, received planning consent in June 2014 and contracts in April 2016. Offshore construction began in 2018 and the project was commissioned in July 2020. It is expected to cost £2.5 billion.
Trump International Golf Club Scotland Ltd v Scotland [2015] UKSC 74 is a 2015 judgment of the Supreme Court of the United Kingdom on the authority of the Scottish government to allow windfarm applications, under the Electricity Act 1989. It is relevant for UK enterprise law and the regulation of UK wind power.
Trump International Golf Links, Scotland is a golf course in Balmedie, Aberdeenshire, Scotland, owned by Donald Trump. It opened in 2012.
Aberdeen Bay Wind Farm [..] The 11-turbine project, also known as the European Offshore Wind Deployment Centre (EOWDC)