Loch Gair Hydro-Electric Scheme

Last updated

Loch Gair
Hydro-Electric Scheme
Glashan Dam - geograph.org.uk - 328469.jpg
Glashan Dam feeds the power station
Argyll and Bute UK relief location map.jpg
Red pog.svg
Location of Loch Gair
Hydro-Electric Scheme in Argyll and Bute
CountryScotland
Location Lochgair, Argyll and Bute
Coordinates 56°03′56″N5°20′10″W / 56.0656°N 5.3360°W / 56.0656; -5.3360
PurposePower
StatusOperational
Opening date1961
Owner(s) SSE
Loch Gair
Hydro-Electric Scheme
BSicon uexKHSTa.svg
Source of Allt Meallach
Loch Sidheannach
BSicon uexKBHFa.svg
BSicon uexSTR.svg
BSicon uexKHSTaq.svg
BSicon uexABZg+lr.svg
BSicon uexKHSTeq.svg
BSicon utSTR+l.svg
BSicon utENDEeq.svg
BSicon uexRESVa.svg
BSicon uexSTR.svg
Dam + sluice
River Add
BSicon uexSTR.svg
BSicon utSTR.svg
BSicon uexSTR.svg
Tunnel + Crarae Burn
Dam + weir
BSicon uxWEIRg@G.svg
BSicon uexENDEaq.svg
BSicon uexSTR+r.svg
BSicon utSTR.svg
BSicon uexSTR.svg
River Add + aqueduct
BSicon uexSTR.svg
BSicon uexSTR.svg
BSicon utSTR.svg
BSicon uexSTR.svg
BSicon uexSTR.svg
BSicon uexSTR.svg
BSicon uexKHSTa.svg
BSicon utSTR.svg
BSicon uexSTR.svg
Source
BSicon uexSTR.svg
BSicon uexSTR.svg
BSicon uexKHSTaq.svg
BSicon uexABZg+lr.svg
BSicon utSTRr.svg
BSicon uexSTRl.svg
BSicon uexCONTfq.svg
Crarae Burn
BSicon uexSTR.svg
BSicon uexSTR.svg
BSicon uexRESVa.svg
BSicon uexSTR.svg
Loch Feorlin dam
BSicon uexSTR.svg
BSicon uexSTR.svg
BSicon uexSTR+l.svg
BSicon POINTERg@fq.svg
BSicon uexSTRr.svg
Abhainn Bheag an Tunns
Allt Gobhain
BSicon uexKHSTa.svg
BSicon uexSTR.svg
BSicon uexSTR.svg
BSicon uexSTR.svg
BSicon uexRESVGa.svg
BSicon uexSTRq.svg
BSicon uexSTR+r.svg
Blackwater Loch dam
BSicon uexSTR.svg
BSicon uexKHSTa.svg
BSicon uexSTR.svg
BSicon uexSTR.svg
BSicon uexSTR.svg
BSicon uxWEIRg@G.svg
BSicon utENDEaq.svg
BSicon utSTR+r.svg
BSicon uexSTR.svg
dam + sluice
BSicon uexSTR.svg
BSicon uexKHSTa.svg
BSicon uexSTR.svg
BSicon uexSTR.svg
BSicon utSTR.svg
BSicon uexENDEaq.svg
BSicon uexRESVa.svg
BSicon uexSTR.svg
BSicon uexSTR+r.svg
BSicon uexSTR.svg
BSicon utSTR.svg
BSicon uexSTR.svg
Fish ladder + dam
Intakes
BSicon uxWEIRg@G.svg
BSicon utENDEaq.svg
BSicon uxWEIRg@G.svg
BSicon utSTRq.svg
BSicon uxWEIRg@G.svg
BSicon utSTRq.svg
BSicon utSTR+r.svg
BSicon uexABZg+l.svg
BSicon utSTR.svg
BSicon uexKRZuwq.svg
BSicon uexABZqr.svg
BSicon utSTR.svg
BSicon uexKRZuwq.svg
BSicon uexSTRr.svg
BSicon utSTR.svg
BSicon uexSTR.svg
BSicon uexABZg+l.svg
BSicon uexSTRr.svg
BSicon uexSTR.svg
BSicon utSTR.svg
BSicon uexSTR.svg
BSicon uexSTR+l.svg
BSicon utSTR.svg
BSicon uexSTRq.svg
BSicon uexSTRr.svg
BSicon utSTRq.svg
BSicon utSTRq.svg
BSicon utSTRr.svg
BSicon uexKBHFe.svg
Loch Bealach Ghearran
Gleann Airigh pipe bridge
BSicon uexABZg+l.svg
BSicon uexSTRq.svg
BSicon uexABZqr.svg
BSicon utSTR.svg
BSicon uexKRZuwq.svg
BSicon uexSTRr.svg
BSicon uexDOCKSa.svg
River Add to Loch Crinan
BSicon uexCONTf.svg
BSicon utSTRl.svg
BSicon utSTRq.svg
BSicon uexDOCKSm.svg
BSicon uexRESVGDa.svg
Loch Glashan Dam
BSicon utSTR+1.svg
BSicon uexSTR.svg
BSicon utSTR.svg
BSicon uexSTR.svg
Tunnel + Abhainn Mhór
BSicon utENDEa.svg
BSicon utENDEe.svg
BSicon uexSTR.svg
Tunnel/pipeline junction
BSicon RAq.svg
BSicon utKRZuw.svg
BSicon uexSKRZ-Au.svg
A816 road
BSicon utSTRbm.svg
BSicon uexSTR.svg
Loch Gair power station
BSicon uexSTRl.svg
BSicon uDOCKSa.svg
Loch Gair
BSicon uDOCKSm.svg
BSicon uDOCKSm.svg
BSicon uDOCKSm.svg
Loch Fyne

Loch Gair Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1956. It is located near Lochgair, a hamlet to the north-east of Lochgilphead, Argyll and Bute in Scotland. It was originally designed to supply power to Lochgilphead and the surrounding communities, but is now connected to the National Grid.

Contents

History

The North of Scotland Hydro-Electric Board was created by the Hydro-electric Development (Scotland) Act 1943, [1] a measure championed by the politician Tom Johnston while he was Secretary of State for Scotland. [2] Johnston's vision was for a public body that could build hydro-electric stations throughout the Highlands. Profits made by selling bulk electricity to the Scottish lowlands would be used to fund "the economic development and social improvement of the North of Scotland." Private consumers would be offered a supply of cheap electricity, and their connection to that supply would not reflect the actual cost of its provision in remote and sparsely-populated areas. [3]

The chairman of the new Board was to be Lord Airlie, who had initially been critical of the 1943 Act because its scope was too limited. The deputy chairman and chief executive was Edward MacColl, an engineer with wide experience of hydro-electric projects and electrical distribution networks. [4] It soon became clear that MacColl intended to push ahead with the aspirations of the Act at breakneck speeds. He produced a list of 102 potential sites in just three months, [5] and in June 1944, the first constructional scheme was published. This was for the Loch Sloy scheme, which had a ready market for bulk supplies to nearby Clydeside, but it included two smaller schemes, to demonstrate the Board's commitment to supplying remote areas. [6]

Loch Gair was another small-scale scheme, and when it was commissioned in 1961, [7] it supplied power to Lochgilphead and the surrounding communities. It was designed by the architect Ian Gordon Lindsay. [8] When the North of Scotland Hydro-Electric Board was created, a panel of architectural advisors was set up, consisting of Reginald Fairlie, Harold Tarbolton and James Shearer. They were to judge designs submitted by other architects, but soon designed the schemes themselves. However, only Shearer was still alive by 1952, [9] and others became involved in the design panel, including Lindsay. [10] Shearer was an opponent of Modernist architecture, and Lindsay was one of several Traditionalist architects that were employed by the Board. [11] His design for the turbine house on the shore of Loch Gair used stone recovered from a castle which would become submerged as the level of Loch Glashan, the main reservoir for the scheme, rose. The quality of his work was recognised when the building won a Civic Trust Award in 1962. [8]

To provide a water supply, a dam was constructed across the outlet of Loch Glashan, to allow its water level to be raised. [12] In order to construct the dam, the water level was lowered in April 1960, and a crannog became visible. This prehistoric structure was excaved by Mr and Mrs J G Scott in July and August of that year, before water levels were raised again in the autumn of 1961. Most of the finds from the dig are stored at Kelvingrove Art Gallery and Museum in Glasgow. [13] The dam is a relatively small mass gravity structure, [12] completed in 1961 with a maximum height of 24 metres (79 ft), [14] from which water reaches the turbine house through a tunnel and a pressure pipeline at the lower end. [8] The tunnel ends on the hillside to the west of the turbine house, where there is surge shaft and valve house, and the pipeline runs on the surface, passing under the A816 road just before it reaches the power station. [15] Loch Glashan is fed by a few small streams, and water is diverted to it from several other river systems in order to increase its catchment. [16]

To the east of the loch, the outflow from Loch Bealach Ghearran flows northwards to Blackmill Loch, a reservoir constructed by building a small dam at its western end. [16] The dam is a rockfill structure constructed in 1964 and has a maximum height of 10.4 feet (3.17 m). Most of the other small dams were also constructed in 1964. [17] About 0.3 miles (0.5 km) below the dam is another dam and sluice, which diverts some of the flow into a tunnel. To the north of this, the Abhainn Bheag an Tunns has been dammed to create Loch Feolin, another small reservoir. [16] The dam is a rockfill structure with a maximum height of 13.7 feet (4.2 m). [17] Further downstream, another small dam with a fish ladder has been constructed, which diverts much of the water into a surface aqueduct. It is carried over the outflow from Blackmill Loch by a pipeline, and is joined by the tunnel from Blackmill Lock. It continues as a surface aqueduct, to empty into the northern end of Loch Glashan. Further north still, the Allt Mealach has been dammed to create Crarae Reservoir. A sluice at its northern end controls flow into a tunnel, which passes through higher ground to the west to discharge into a tributary of the Abhainn Bheag an Tunns. [16] [15] The dam is a concrete structure, with a maximum height of 45 feet (13.7 m). [17] Below the dam, the outlet continues as the Crarae Burn, [16] which flows through Crarae Forest Garden, a spectacular woodland garden in Himalayan style built up during the 20th century by three generations of the Campbell family. The gardens cover 126 acres (51 ha) and were given to the Charitable Trust, now the National Trust for Scotland, in 1978. [18]

The Gleann Airigh pipe bridge carries water from tributaries of the River Add to Loch Glashan Aqueduct crossing Gleann Airigh - geograph.org.uk - 284872.jpg
The Gleann Airigh pipe bridge carries water from tributaries of the River Add to Loch Glashan

The catchment is further extended by diverting water from the River Add. To the west of Cnoc Dubh ("Black Hill"), a dam has been constructed, with a fish ladder to allow migrating fish to access the upper reaches of the river. Maps show a pumping station, meter house and weir, and a surface aqueduct carries water along the left bank of the river for about 0.9 miles (1.4 km) before it enters a pipeline. This carries it over the Abhainn Bheag an Tunns and discharges into Loch Glashan. Finally there are three intakes on tributaries of the River Add, one on the Allt Gobhain and two more on unnamed streams to its east. These feed water into a tunnel, which emerges from the hillside as a pipeline to cross the River Add at high level and continues as a tunnel to Loch Glashan. [16] [15]

In early 1957, Lord Lucas of Chilworth asked questions in the House of Lords about the costs of Scottish hydro-electricity. Lord Strathclyde stated that for Loch Gair, the capital cost of the project was expected to be £239 per kW, towards the bottom end of the 27 schemes mentioned, although still higher than the average cost of £175 per kW. The costs were estimated since Loch Gair was one of four schemes where construction had not yet started. It was the North of Scotland Hydro-Electric Board's Constructional Scheme No. 71. [19] Loch Glashan provides a head of 358 feet (109 m) to the turbine house, which can generate 6 MW. [7]

Operation

In 2002, the Renewables Obligation (Scotland) legislation was introduced. It was conceived as a way to promote the development of small-scale hydro-electric, wave power, tidal power, photovoltaics, wind power and biomass schemes, but by the time it came into force, the definition of small scale had been increased from 5 MW to 10 MW and then 20 MW, and existing hydro-electric stations that had been refurbished to improve efficiency could be included. [20] Loch Gair at 6 MW thus became eligible when the limits were increased, and between 2004 and 2007 the station qualified for 59,324 Renewable Obligation Certificates, generating a subsidy for SSE of over £2,799,000. [21] Between 2005 and 2007, the station operated at an average load factor of 33.3 percent, although the load factor increased every year during that period. [22]

In order to prevent salmon smolts from entering the pipeline from Loch Glashan and being carried down through the turbines, SSE plc used a system of ten removable intake screens. The process of removing them for cleaning and then replacing them was a labour-intensive task, as it had to be done once a day between February and November, when smolts could be migrating. It required some 900 hours of staff time per year, with maintenance costs reaching £40,000 per year. In 2015, the screens were replaced with four travelling water screens, manufactured by Hydrolox. Because the site is remote, they were delivered by helicopter, and since installation have reduced the time and money spent on maintenance by 93 percent, to 60 hours and £2,500 per year. Flow through the screens is around 48 cubic feet (1.35 m3) per second when the power station is operational. [23]

Hydrology

The surface level of Loch Glashan is 367 feet (112 m) above Ordnance datum (AOD), it covers 0.70 square miles (1.81 km2), and drains an area of 3.72 square miles (9.63 km2). [24] Compensation water discharged through the dam maintains the habitat in the Abhainn Mhòr, which flows in a south-easterly direction and is crossed by the A83 road before discharging into the sea at Loch Gair. [16] Blackmill Loch is at 432 feet (132 m) AOD, has an area of 35 acres (14 ha) and drains 0.91 square miles (2.36 km2). [25] Loch Bealach Ghearran is smaller, covering just 15 acres (6 ha), and is located at 584 feet (178 m) AOD. [26] The unnamed loch on the Abhainn Bheag an Tunns is at 364 feet (111 m) AOD and covers an area of 2.5 acres (1 ha). [27]

Loch Feorlin, the reservoir on the upper Abhainn Bheag an Tunns, is at 495 feet (151 m) AOD, and covers 15 acres (6 ha), with a catchment area of 1.38 square miles (3.57 km2). [28] Loch Crarae, which is on the Allt Mealach, is at 166 metres (545 ft) AOD. [29]

Bibliography

Related Research Articles

<span class="mw-page-title-main">Falls of Foyers</span> Waterfall in Highland, Scotland

The Falls of Foyers are two waterfalls on the River Foyers, which feeds Loch Ness, in Highland, Scotland. They are located on the lower portion of the River Foyers, and consist of the upper falls, with a drop of 46 feet (14 m) and the lower falls, which drop 98 feet (30 m).

<span class="mw-page-title-main">River Shin</span> River in northern Scotland

The River Shin is a river in the Scottish North West Highlands.

<span class="mw-page-title-main">River Conon</span> River in Scotland

The River Conon is a river in the Highlands of Scotland. It begins at Loch Luichart, and flows in a south-easterly direction to be joined by the River Meig at Scatwell before passing through Loch Achonachie. It is joined by the Black Water at Moy Bridge, and the River Orrin at Urray, before flowing past Conon Bridge and into the Cromarty Firth.

<span class="mw-page-title-main">Tummel hydro-electric power scheme</span> Power stations in Perth and Inverness

The Tummel hydro-electric power scheme is an interconnected network of dams, power stations, aqueducts and electric power transmission in the Grampian Mountains of Scotland. Roughly bounded by Dalwhinnie in the north, Rannoch Moor in the west and Pitlochry in the east it comprises a water catchment area of around 1,800 square kilometres and primary water storage at Loch Ericht, Loch Errochty, Loch Rannoch and Loch Tummel, in Perth and Kinross. Water, depending on where it originates and the path it takes, may pass through as many as five of the schemes nine power stations as it progresses from north-west to south-east. The scheme was constructed in the 1940s and 50s incorporating some earlier sites. It is managed by SSE plc.

<span class="mw-page-title-main">River Add</span> A river in Argyll and Bute, Scotland

The River Add is a river which runs through Argyll and Bute on the west coast of Scotland. Historically, it was known as the river Airigh but to avoid confusion with the Aray, it was renamed the River Add.

<span class="mw-page-title-main">River Garry, Inverness-shire</span> River and power stations in Scotland

The River Garry in Inverness-shire is a Scottish river punctuated by two long Lochs, in the region of Lochaber. It flows broadly west to east through Glen Garry, starting in a wilderness to the east of Knoydart and ending at Loch Oich in the Great Glen, which forms part of the Caledonian Canal. There are a few tiny settlements within Glen Garry, but the only village of any size near to the river is Invergarry, at its mouth. Loch Quoich at the western end of the watercourse is dammed by the largest mass earth fill dam in Scotland, and supplies water to Quoich hydroelectric power station. Loch Garry is dammed by a much smaller dam in the gorge where the river begins its descent to Invergarry, and supplies water to Invergarry hydroelectric power station, close to the mouth of the river. Both hydroelectric schemes were built in the 1950s, with the aim of stimulating economic regeneration in the area. They have altered the ecology of the river, as both lochs were made considerably bigger as a result of constructing the dams.

<span class="mw-page-title-main">River Moriston</span> River and power stations in Scotland

The River Moriston is a river in Inverness-shire, Scotland. It flows broadly east-north-east from the outfall of the dam at Loch Cluanie to Loch Ness. Its waters and those of its tributaries have been harnessed to generate hydro-electric power.

<span class="mw-page-title-main">Feorlin</span> Reservoir in Minard, Scotland

Feorlin is an impounding reservoir located 2 kilometres west of Minard. The loch is part of the Lochgair Hydroelectric Scheme. The rockfill dam is 4.19 metres high and was completed in 1964. When not diverted for hydroelectric purposes, the loch feeds a tributary of the River Add.

<span class="mw-page-title-main">Breadalbane Hydro-Electric Scheme</span> Multiple power stations in Scotland

The Breadalbane Hydro-Electric Scheme is a hydroelectric scheme in the Breadalbane area of Perthshire, Scotland. It comprises seven power stations which generate 120MW of power from the dams around Loch Lyon, Loch Earn and Loch Tay.

<span class="mw-page-title-main">Storr Lochs Hydro-Electric Scheme</span> Power station on Isle of Skye, Scotland

Storr Lochs is a hydro-electric power station built on the Isle of Skye, Inner Hebrides, Scotland and commissioned in 1952. It was built by the North of Scotland Hydro-Electric Board, and used water from Lochs Leathan and Fada, to provide the first general supply of electricity to the island. Because the location of the turbine house was not easily accessible, it is served by an electric funicular railway.

<span class="mw-page-title-main">Chliostair Hydro-Electric Scheme</span> Power station on Harris, Outer Hebrides, Scotland

Chliostair Hydro-Electric Scheme is a small scheme promoted by the North of Scotland Hydro-Electric Board on Harris, Outer Hebrides. It consists of a single power station powered with water from Loch Chliostair, and was commissioned in 1960.

<span class="mw-page-title-main">Gisla Hydro-Electric Scheme</span> Power station on Lewis, Outer Hebrides, Scotland

Gisla Hydro-Electric Scheme was a small scheme promoted by the North of Scotland Hydro-Electric Board on the Isle of Lewis, Outer Hebrides, Scotland. It consisted of a single power station powered with water from Loch Coirceabhat, and was commissioned in 1960.

<span class="mw-page-title-main">Shira Hydro-Electric Scheme</span> Power stations near Loch Fyne, Scotland

The Shira Hydro-Electric Scheme is a project initiated by the North of Scotland Hydro-Electric Board to use the waters of the River Shira, the River Fyne and other small streams to generate hydroelectricity. It is located between Loch Fyne and Loch Awe in Argyll and Bute, western Scotland. It consists of three power stations and three impounding dams.

<span class="mw-page-title-main">Awe Hydro-Electric Scheme</span> Power stations near Loch Awe, Scotland

The Awe Hydro-Electric Scheme was the penultimate scheme developed by the North of Scotland Hydro-Electric Board. It centres around Loch Awe, in Argyll and Bute, on the southern edge of the Scottish Highlands. It consists of three power stations, two conventional hydro-electric stations, and the Cruachan power station, the first large pumped storage scheme built by the Board. It was completed in 1965.

<span class="mw-page-title-main">Inver Hydro-Electric Scheme</span> Power station on Jura, Inner Hebrides, Scotland

Inver Hydro-Electric Scheme is a remote hydro-electric plant on the Scottish island of Jura, part of the Inner Hebrides. Construction began in 2011, and it was operational by June 2012. It is the third scheme built on the Inver Estate, but the first to be connected to the National Grid. It can produce 2 MW of electric power.

<span class="mw-page-title-main">Lussa Hydro-Electric Scheme</span> Power station near Peninver, Scotland

Lussa Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1956. It is located near Peninver on the Kintyre peninsula, part of Argyll and Bute in Scotland. It was originally designed to supply power to Campbeltown, but is now connected to the National Grid.

<span class="mw-page-title-main">Striven Hydro-Electric Scheme</span> Power station near Ardtaraig, Scotland

Striven Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1951. It is located near Ardtaraig on the Cowal peninsula, part of Argyll and Bute in Scotland. It is sometimes known as the Cowal Hydro-Electric Scheme. It was originally designed to supply power to the remote communities on the peninsula, but is now connected to the National Grid.

<span class="mw-page-title-main">Kerry Falls Hydro-Electric Scheme</span> Power station near Peninver, Scotland

Kerry Falls Hydro-Electric Scheme, sometimes known as Gairloch is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1952. It is located near Gairloch in Wester Ross, part of the Highlands of Scotland. It was originally designed to supply power to local communities in this remote area, but is now connected to the National Grid.

<span class="mw-page-title-main">Loch Dubh Hydro-Electric Scheme</span> Power station near Ullapool, Scotland

Loch Dubh Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1955. It is located near Ullapool in Ross and Cromarty, Scotland. It was originally designed to supply power to the remote communities around Ullapool, but is now connected to the National Grid.

<span class="mw-page-title-main">Kilmelfort Hydro-Electric Scheme</span> Power station near Kilmelford, Scotland

Kilmelfort Hydro-Electric Scheme is a small-scale hydro-electric power station, built by the North of Scotland Hydro-Electric Board and commissioned in 1956. It is located near Kilmelford in Argyll and Bute, Scotland. It was originally designed to supply power to the local communities around Kilmelford, but is now connected to the National Grid.

References

  1. Payne 1988, pp. 50, 298.
  2. Miller 2002, pp. 19–20.
  3. Wood 2002, pp. 58–59.
  4. Payne 1988, pp. 50–51.
  5. Payne 1988, p. 55.
  6. Payne 1988, pp. 60–61.
  7. 1 2 Reeves 2018, p. 99.
  8. 1 2 3 "Loch Gair Power Station". Canmore. Archived from the original on 4 March 2023.
  9. Fleetwood 2010, p. 40.
  10. Fleetwood 2010, p. 49.
  11. Glendinning, MacInnes & MacKechnie 1996, pp. 417–418.
  12. 1 2 "Loch Glashan". Canmore. Archived from the original on 18 January 2024.
  13. "Loch Glashan". Canmore. Archived from the original on 2 December 2021.
  14. Environmental Protection Officer 2012, pp. 6–7.
  15. 1 2 3 Ordnance Survey, 1:2500 map
  16. 1 2 3 4 5 6 7 Ordnance Survey, 1:25000 map
  17. 1 2 3 Environmental Protection Officer 2012, pp. 2–3.
  18. Historic Environment Scotland. "Crarae (Garden and Designated Landscape) (GDL00118)".
  19. "North of Scotland Hydro-Electric Costs". Hansard. 22 January 1957. Archived from the original on 14 June 2023.
  20. Swap 2005, pp. 5–7.
  21. Dekker 2008, p. 29.
  22. Dekker 2008, p. 120.
  23. "Hydrolox Solution Reduces Labor Hours, Maintenance Costs by More Than 93%". Hydrolox. Archived from the original on 3 June 2023.
  24. "Loch Lashan Water body ID 25035". UK Centre for Ecology & Hydrology.
  25. "Blackmill Loch Water body ID 25009". UK Centre for Ecology & Hydrology.
  26. "Loch Bealach Ghearran Water body ID 25028". UK Centre for Ecology & Hydrology.
  27. "unnamed Water body ID 25010". UK Centre for Ecology & Hydrology.
  28. "Loch Feorlin Water body ID 24975". UK Centre for Ecology & Hydrology.
  29. "unnamed Water body ID 24954". UK Centre for Ecology & Hydrology.

Commons-logo.svg Media related to Loch Gair hydro-electric scheme at Wikimedia Commons