Hunterston B nuclear power station | |
---|---|
Official name | Hunterston B |
Country | Scotland |
Location | North Ayrshire, Ayrshire and Arran |
Coordinates | 55°43′20″N4°53′24″W / 55.7221°N 4.8901°W |
Status | Defuelling (as of 19 May 2022 [update] ) |
Construction began | November 1, 1967 [1] [2] |
Commission date | |
Decommission date | |
Owner | EDF Energy |
Operator | EDF Energy |
Nuclear power station | |
Reactor type | GCR - AGR [1] [2] |
Reactor supplier | TNPG |
Thermal capacity | 2 x 1,496 MWt [1] [2] |
Lifetime electricity generated | 287.22 TWh (1,034.0 PJ) [1] [2] |
Power generation | |
Units decommissioned | |
Nameplate capacity | 1,248 MWe |
Capacity factor | |
Annual net output | 6,423.24 GWh (23,123.7 TJ) (2021) [1] [2] |
External links | |
Website | Hunterston B power station | EDF |
Commons | Related media on Commons |
grid reference NS183514 |
Hunterston B nuclear power station is a shut-down AGR nuclear power station in North Ayrshire, Scotland. Located about six miles (ten kilometres) south of Largs and about 2+1⁄2 miles (4 kilometres) northwest of West Kilbride on the Firth of Clyde coast. It is currently operated by EDF Energy. The station began producing electricity in 1976, and was permanently shut down in 2022. [3]
Hunterston B is similar in design to sister station Hinkley Point B, which ceased operations in August 2022.
The construction of Hunterston B was undertaken by a consortium known as The Nuclear Power Group (TNPG). [4] The two advanced gas-cooled reactors (AGR) were supplied by TNPG and the turbines by C. A. Parsons & Co. [5] Hunterston B began to generate electricity on 6 February 1976.
On 3 December 1977, The Times reported that seawater had entered the reactor through a modification of the secondary cooling system. [6] The secondary cooling system used fresh water to cool parts including the bearings of the gas circulators, which circulated the carbon dioxide (CO2) coolant through the reactor to the boilers. A small leak of CO2 through a seal had developed, and a bypass pipe was installed to remove the water contaminated with CO2 to the seawater cooling ponds. When maintenance work was carried out on the reactor and the pressure in the gas cooling system was reduced, sea water was able to flow back up this bypass pipe and into the reactor. The residual heat of the reactor was such that the seawater evaporated rapidly, leaving deposits of salt in the reactor around the gas circuit.
It was estimated at the time that the reactor could be out of operation for a year, that the repairs could cost £14 million, and that electricity tariffs would have to rise by between 1 and 2 per cent. Extensive modelling work was performed in the Nuclear Power Company's (NPC) Whetstone, Leicestershire, fluid flow laboratories to determine where the salt would have been deposited, and the salt was successfully removed by technicians using vacuum cleaners and the plant returned to operation.
In February 1997, there was concern that contaminated CO2 gas from the plant had entered three road tankers and then entered the food chain via soft drinks and beers. [7] [8] Carlsberg-Tetley withdrew all its gas cylinders in Scotland as a result of finding contamination in one. [9]
In December 1998, an INES Level 2 incident occurred after severe winds and sea spray disabled all four power lines to the site during the Boxing Day Storm of 1998. After multiple grid failures in a short period of time, emergency diesel generators failed to start. Normally, in the absence of power for the reactor cooling pumps, the reactor would be passively cooled. However, the emergency control system which would have initiated passive cooling failed to act, as it had not been reset. Reactor cooling was reinstated after four hours. There was considerable confusion and delay in restoring power as plant schematics and security systems were computerised but were rendered inoperable due to lack of electrical power.
Due to the inherent safety margins of the AGR reactor design, there was no reactor damage, and the plant would have tolerated loss of cooling for 20 hours. The subsequent investigation made several recommendations: redesign of the insulators on the 400 kV power lines, installation of an additional 132 kV power line for emergency power, a second diesel generator building remote from the first, installation of an uninterruptible power supply for the reactor safety systems and for essential computer equipment, provision of hard copy plant schematics and emergency protocols, and revised staff training procedures including simulation of multiple simultaneous system failures. [10]
In 2006, concerns were raised in a report commissioned by Greenpeace that the graphite moderator core in each of the twin reactors at Hunterston B might have developed structural problems in the form of cracking of the bricks (as at similar AGR power stations). [11]
Its net electrical output was 1,215 MW. In 2007, the reactors were restricted to operating at a reduced level of around 70% of full output (around 850 MWe net). Subsequent work during maintenance shutdowns resulted in Reactor 3 operating at around 82% (540 Mwe net) in early 2011, and Reactor 4 at around 73% (480 MWe net). In total this equated to around 1,020 MWe gross output from the generators. Internal load of 90 MWe brought net output to approximately 930 MWe. Hunterston B was capable of supplying the electricity needs of over 1 million homes. [12]
Hunterston B was originally planned to operate until 2011. In 2007, planned operation was extended by five years to 2016. [13] In December 2012, EDF said it could (technically and economically) operate until 2023. [14]
In October 2014, it was reported that cracks had been found in one of the reactors at the plant following routine inspections which began in August 2014. Two of about 3,000 graphite bricks in the core of reactor four at Hunterston were affected. The plant's operator, EDF Energy, said the cracking was predicted to occur as the station ages and said that the issue would not affect the safe operation of the reactor. [15]
In October 2016, it was announced that super-articulated control rods would be installed in the reactor because of concerns about the stability of the reactors' graphite cores. The Office for Nuclear Regulation (ONR) had raised concerns over the number of fractures in keyways that lock together the graphite bricks in the core. An unusual event, such as an earthquake, might destabilise the graphite so that ordinary control rods that shut the reactor down could not be inserted. Super-articulated control rods should be insertable even into a destabilised core. [16]
In early 2018, a higher rate of new keyway root cracks than modelled was observed in Reactor 3 during a scheduled outage, and EDF announced in May 2018: "While Hunterston B Reactor 3 could return to operation from the current outage, it will remain offline while the company works with the regulator to ensure that the longer term safety case reflects the findings of the recent inspections and includes the results obtained from other analysis and modelling." [17] [18]
In December 2018, EDF pushed back their estimated return to service date to March 2019 for Reactor 4 and April 2019 for Reactor 3, to allow for further modelling work and a new seismic analysis. [19] In March 2019, pictures of the cracking were released with EDF stating that it intended to seek permission from the ONR to restart reactor 3 by raising the operational limit for the number of cracks. About 370 fractures were discovered, on average 2 mm (3⁄32 in) wide, in about 10% of the graphite bricks in the reactor core. This was above the operational limit of 350 fractures, and EDF intended to present a new safety case for an operational limit of 700 cracks. [20] [21]
One reactor was restarted on 25 August 2019 then shut down again on 10 December 2019. In August 2020, EDF received regulatory approval to restart the two reactors, in August and September 2020 respectively, before moving to defuel and decommission the plant starting no later than 7 January 2022. [22]
Reactor 3 was taken offline for the final time at midday on 26 November 2021. [23] Reactor 4 was shut down at midday on 7 January 2022, ending 46 years of generation at the station. [3]
On 19 May 2022, EDF announced that defueling had started on the two Hunterston B units. This process is expected to take over three years to complete, and it involves the complete emptying of all fuel channels from both reactors. This amounts to over 300 channels from each reactor, each containing 8 fuel elements. Fully loaded flasks containing the used fuel are scheduled to be dispatched from the site by rail to Sellafield at a maximum rate of three per week. [24] [3]
In October 2023, the ONR announced that the defuelling of reactor 3 had been completed, and that the defuelling of reactor 4 was to begin "shortly." [25] Defuelling of reactor 4 is due to be completed in 2025. [26]
Once both reactors have been fully defuelled, EDF Energy will transfer control of the site to the Nuclear Decommissioning Authority to continue the decommissioning process. [25]
The Advanced Gas-cooled Reactor (AGR) is a type of nuclear reactor designed and operated in the United Kingdom. These are the second generation of British gas-cooled reactors, using graphite as the neutron moderator and carbon dioxide as coolant. They have been the backbone of the UK's nuclear power generation fleet since the 1980s.
The pebble-bed reactor (PBR) is a design for a graphite-moderated, gas-cooled nuclear reactor. It is a type of very-high-temperature reactor (VHTR), one of the six classes of nuclear reactors in the Generation IV initiative.
Torness nuclear power station is a nuclear power station located approximately 30 miles (50 km) east of Edinburgh at Torness Point near Dunbar in East Lothian, Scotland. It was the last of the United Kingdom's Advanced Gas-cooled Reactors to be fully commissioned. Construction of this facility began in 1980 for the then South of Scotland Electricity Board (SSEB) and it was commissioned in 1988. It is a local landmark, highly visible from the A1 trunk road and East Coast Main Line railway.
Pickering Nuclear Generating Station is a Canadian nuclear power station located on the north shore of Lake Ontario in Pickering, Ontario. It is one of the oldest nuclear power stations in the world and Canada's third-largest, with eight CANDU reactors. Since 2003, two of these units have been defuelled and deactivated. The remaining six produce about 16% of Ontario's power and employ 3,000 workers.
Magnox is a type of nuclear power / production reactor that was designed to run on natural uranium with graphite as the moderator and carbon dioxide gas as the heat exchange coolant. It belongs to the wider class of gas-cooled reactors. The name comes from the magnesium-aluminium alloy, used to clad the fuel rods inside the reactor. Like most other "Generation I nuclear reactors", the Magnox was designed with the dual purpose of producing electrical power and plutonium-239 for the nascent nuclear weapons programme in Britain. The name refers specifically to the United Kingdom design but is sometimes used generically to refer to any similar reactor.
The Dungeness nuclear power stations are a pair of non-operational nuclear power stations located on the Dungeness headland in the south of Kent, England.
British Energy was the UK's largest electricity generation company by volume, before being taken over by Électricité de France (EDF) in 2009. British Energy operated eight former UK state-owned nuclear power stations and one coal-fired power station.
Chapelcross nuclear power station is a former Magnox nuclear power station undergoing decommissioning. It is located in Annan in Dumfries and Galloway in southwest Scotland, and was in operation from 1959 to 2004. It was the sister plant to the Calder Hall nuclear power station plant in Cumbria, England; both were commissioned and originally operated by the United Kingdom Atomic Energy Authority. The primary purpose of both plants was to produce weapons-grade plutonium for the UK's nuclear weapons programme, but they also generated electrical power for the National Grid. Later in the reactors' lifecycle, as the UK slowed the development of the nuclear deterrent as the cold war came to a close, power production became the primary goal of reactor operation.
Wylfa nuclear power station is a Magnox nuclear power station undergoing decommissioning. Wylfa is situated west of Cemaes Bay on the island of Anglesey, off the northwestern coast of Wales. Construction of the two 490 MW nuclear reactors, known as Reactor 1 and Reactor 2, began in 1963. They became operational in 1971. Wylfa was located on the coast because seawater was used as a coolant.
Hartlepool nuclear power station is a nuclear power station situated on the northern bank of the mouth of the River Tees, 2.5 mi south of Hartlepool in County Durham, North East England. The station has a net electrical output of 1,185 megawatts, which is 2% of Great Britain's peak electricity demand of 60 GW. Electricity is produced through the use of two advanced gas-cooled reactors (AGR). Hartlepool was only the third nuclear power station in the United Kingdom to use AGR technology. It was also the first nuclear power station to be built close to a major urban area.
Nuclear power in the United Kingdom generated 16.1% of the country's electricity in 2020. As of August 2022, the UK has 9 operational nuclear reactors at five locations, producing 5.9 GWe. It also has nuclear reprocessing plants at Sellafield and the Tails Management Facility (TMF) operated by Urenco in Capenhurst.
EDF Energy is a British integrated energy company, wholly owned by the French state-owned EDF, with operations spanning electricity generation and the sale of natural gas and electricity to homes and businesses throughout the United Kingdom. It employs 11,717 people, and handles 5.22 million business and residential customer accounts.
The Heysham nuclear power stations are operated by EDF Energy in Heysham, Lancashire, England. On the site two separate nuclear power stations, Heysham 1 and Heysham 2 operate independently, only with joint entry protocol, both with two reactors of the advanced gas-cooled reactor (AGR) type.
Scottish Nuclear was formed as a precursor to the privatisation of the electricity supply industry in Scotland on 1 April 1990. A purpose-built headquarters was built in 1992 in the new town of East Kilbride.
Hinkley Point B nuclear power station was a nuclear power station near Bridgwater, Somerset, on the Bristol Channel coast of south west England. It was the first commercial Advanced Gas Cooled reactor to generate power to the National Grid in 1976 and shares its design with sister station Hunterston B nuclear power station. It ceased operations permanently on 1 August 2022.
Hinkley Point A nuclear power station is a former Magnox nuclear power station. It is located on a 19.4-hectare (48-acre) site in Somerset on the Bristol Channel coast, 5 miles (8 km) west of the River Parrett estuary. The ongoing decommissioning process is being managed by Nuclear Decommissioning Authority licensee Magnox Ltd.
The Sizewell nuclear site consists of two nuclear power stations, one of which is still operational, located near the small fishing village of Sizewell in Suffolk, England. Sizewell A, with two Magnox reactors, is now in the process of being decommissioned. Sizewell B has a single pressurised water reactor (PWR) and is the UK's newest nuclear power station. A third power station, to consist of twin EPR reactors, is planned to be built as Sizewell C.
Scotland has a long history of nuclear research and electricity generation. Nuclear energy consistently accounts for 20-80% of the electric supply in Scotland depending on weather conditions for wind power generation and electricity demand. As of 2022, there is only one remaining operating nuclear power station in Scotland (Torness).
Hunterston A nuclear power station is a former Magnox nuclear power station located at Hunterston in Ayrshire, Scotland, adjacent to Hunterston B. The ongoing decommissioning process is being managed by Nuclear Decommissioning Authority (NDA) subsidiary Magnox Ltd.