The United Kingdom became the world leader of offshore wind power generation in October 2008 when it overtook Denmark. [1]
Government direction in the development of offshore wind power advanced in 2016 with the development of strategies and systems.
The total offshore wind power capacity installed in the United Kingdom at the start of 2022 was 11.3 GW. By 2023, the United Kingdom had over 11,000 wind turbines with a total installed capacity of 30 gigawatts (GW): 15 GW onshore and 15 GW offshore, [2]
The UK has set a target to have 50GW of offshore wind capacity by 2030. [3]
The United Kingdom has been estimated to have over a third of Europe's total offshore wind resource, which is equivalent to three times the electricity needs of the nation at current rates of electricity consumption [4] (In 2010 peak winter demand was 59.3 GW, [5] in summer it drops to about 45 GW).
One estimate calculates that wind turbines in one third of United Kingdom waters shallower than 25 metres (82 ft) would, on average, generate 40 GW; turbines in one third of the waters between 25 metres (82 ft) and 50 metres (164 ft) depth would on average generate a further 80 GW, i.e. 120 GW in total. [6] An estimate of the theoretical maximum potential of the United Kingdom's offshore wind resource in all waters to 700 metres (2,300 ft) depth gives the average power as 2200 GW. [7]
The first developments in United Kingdom offshore wind power came about through the now discontinued Non-Fossil Fuel Obligation (NFFO), leading to two wind farms, Blyth Offshore and Gunfleet sands. [8] The NFFO was introduced as part of the Electricity Act 1989 and obliged United Kingdom electricity supply companies to secure specified amounts of electricity from non-fossil sources, [9] which provided the initial spur for the commercial development of renewable energy in the United Kingdom.
Offshore wind projects completed in 2010–2011 had a levelised cost of electricity of £136/MWh, which fell to £131/MWh for projects completed in 2012–14 and £121/MWh for projects approved in 2012–2014; the industry hopes to get the cost down to £100/MWh for projects approved in 2020. [10]
The construction price for offshore windfarms has fallen by almost a third since 2012 while technology improved and developers think a new generation of even larger turbines will enable yet more future cost reductions. [11] In 2017 the UK built 53% of the 3.15 GW European offshore wind farm capacity. [12] In 2020, Boris Johnson pledged that, by the end of the decade, offshore wind would generate enough energy to power every UK home. [13]
In 2013, the 175-turbine London Array wind farm, located off the Kent coast, became the largest offshore wind farm in the world; this was surpassed in 2018 by the Walney 3 Extension.
In 2013 the Offshore Energy Strategic Environmental Assessment (SEA) was first published and has been updated regularly. It is the guiding document from the UK government on offshore energy. [14]
In 2016 the government created the Low Carbon Contracts Company as the party low carbon developers will contract with in the Contracts for Difference (CfD) scheme, the developers having won bids in government auctions. The developers would be paid a flat, index linked rate, for electricity for 15 years. Each contract would have a strike price being the price for electricity reflecting the cost of investing in that specific technology with the developer paid the difference between the strike price and the average market price for electricity. [15]
At the start of 2022 there was a total of 11.26 GW of installed offshore wind capacity. [16] During 2022 an additional 3.2 GW of capacity was added with the commissioning of the Moray East, Triton Knoll and Hornsea Project Two wind farms. [17] [18] [19] A further 13.6 GW of capacity is either under construction (Neart Na Gaoithe, Sofia, Seagreen & Doggerbank A) or has been awarded a Contract for Difference in Round 3 [20] or Round 4. [21]
In 1998, the British Wind Energy Association (now RenewableUK) began discussions with the government to draw up formal procedures for negotiating with the Crown Estate, the owner of almost all the United Kingdom coastline out to a distance of 12 nautical miles (22.2 km), to build offshore wind farms. The result was a set of guidelines published in 1999, to build "development" farms designed to give developers a chance to gain technical and environmental experience. The projects were limited to 10 km2 (3.9 square miles) in size and with a maximum of 30 turbines. Locations were chosen by potential developers and a large number of applications were submitted.
Seventeen of the applications were granted permission to proceed in April 2001, in what has become known as Round 1 of United Kingdom offshore wind development. [22]
In 2020, the Boris Johnson-led government decided to permit onshore wind power, and since December 2021 onshore wind developers have been able to compete in subsidy auctions with solar power and offshore wind. [23]
The first of the Round 1 projects was North Hoyle Wind Farm, completed in December 2003. The final project, Teesside, was completed in August 2013. Twelve Round 1 farms in total are in operation providing a maximum power generating capacity of 1.2 GW. Five sites were withdrawn, including the Shell Flat site off the coast of Lancashire. [24]
Lessons learnt from Round 1, particularly the difficulty in getting planning consent for offshore wind farms, together with the increasing pressure to reduce CO2 emissions, prompted the then Department of Trade and Industry (DTI) to develop a strategic framework for the offshore wind industry. This identified three restricted areas for larger scale development, Liverpool Bay, the Thames Estuary and the area beyond the Wash, called the Greater Wash, in the North Sea. Development was prevented in an exclusion zone between 8 and 13 km offshore to reduce visual impact and avoid shallow feeding grounds for sea birds. The new areas were tendered to prospective developers in a competitive bid process known as Round 2. The results were announced in December 2003 with 15 projects awarded with a combined power generating capacity of 7.2 GW. By far the largest of these is the 900 MW Triton Knoll. [26] As before a full Environmental Impact Assessment (EIA) would be needed along with an application for planning consent.
The first of the Round 2 projects was Gunfleet Sands II, completed in April 2010 and six others are now operational including the London Array, formerly the largest wind farm in the world. Four other Round 2 sites are currently under construction. [24]
In May 2010, the Crown Estate gave approval for seven Round 1 and 2 sites to be extended creating an additional 2 GW of offshore wind capacity. [27] Each wind farm extension required a complete new planning application including an Environmental Impact Assessment and full consultation. The sites are: [28]
Following on from the Offshore wind SEA announced by the Government in December 2007, the Crown Estate launched a third round of site allocations in June 2008. It followed the success of Rounds 1 and 2, from which important lessons were learnt; Round 3 was on a much bigger scale than the combined total of its predecessors (Rounds 1 and 2 allocated 8 GW of sites, while Round 3 alone could identify up to 25 GW).
The Crown Estate proposed nine offshore zones, within which a number of individual wind farms would be situated. It ran a competitive tender process to award leases to consortia of potential developers. The bidding closed in March 2009 with over 40 applications from companies and consortia and multiple tenders for each zone. The successful bidders were announced on 8 January 2010.
Following the allocation of zones, individual planning applications still had to be sought by developers. The first zone came on stream in 2018; several more have still to be completed, and some have been abandoned (see below).
During the bidding process there was considerable speculation over which companies had bid for the zones. The Crown Estate did not make the list public and most of the consortia also remained silent. The successful bidders for each zone were eventually announced as follows: [29]
Zone [30] | Zone name | Wind farm site names | Potential power (GW) | Developer | Notes |
---|---|---|---|---|---|
1 | Moray Firth | Beatrice | 1.3 (0.58) | Moray Offshore Renewables Ltd | Formed from EDP Renováveis and SeaEnergy Renewables Ltd (SERL) Project scaled down to 588 MW Commenced commercial operation in 2018 |
2 | Firth of Forth | Alpha/Bravo | 3.5 | Seagreen Wind Energy Ltd | Partnership between SSE Renewables and Fluor Ltd. SSE withdrawing support beyond the consent process. |
3 | Dogger Bank | Crekye A/B & Teesside A/B/C/D | 7.2 | Forewind Ltd | A consortium made up of SSE Renewables, RWE npower, Statkraft and Statoil. SSE withdrawing support beyond the consent process. Project scaled down to 4.8 GW in 2015 Expected to commence commercial operation in 2024 |
4 | Hornsea | Hornsea One, Two, Three and Four (formerly Heron/Njord/Breesea/Optimus & SPC5/6/7/8) | 6 | Ørsted (formerly SMart Wind Ltd) | SMart Wind was a joint venture between Mainstream Renewable Power and Siemens Project Ventures. 100% acquired in 2015 by DONG Energy, which rebranded as Ørsted in 2017. Hornsea One (1.2 GW) became fully operational in December 2019. [31] Hornsea Two (1.32 GW) became fully operational on 31 August 2022. Development consent for Hornsea Three (2.4 GW) was granted on 31 December 2020 and Ørsted signed the CfD for the project on 3 August 2022. [32] Hornsea Four remains in development. |
5 | East Anglia | East Anglia ONE/TWO/THREE/ONE NORTH | 7.2 | East Anglia Offshore Wind Limited | Joint venture between ScottishPower Renewables and Vattenfall AB ONE commenced commercial operations in 2020. TWO is expected to be fully operational by 2022. THREE is expected to start construction in 2022 |
6 | Southern Array | Rampion | 0.6 (0.4) | E.ON Climate & Renewables / UK Southern Array Ltd | Located south of Shoreham-by-Sea and Worthing in the English Channel Commenced commercial operation in 2018 |
7 | West of Isle of Wight | Navitus Bay | 0.9 | Eneco Round 3 Development Ltd | West of the Isle of Wight; partnership between Eneco and EDF. Planning permission refused by government in September 2015 due to visual impact. [33] |
8 | Atlantic Array | Atlantic Array | Channel Energy Ltd (Innogy) | Withdrawn in November 2013 as "project uneconomic at current time" [34] | |
9 | Irish Sea | Celtic Array | Celtic Array Limited | Withdrawn in July 2014 due to "challenging ground conditions that make the project economically unviable". [35] | |
Total | 26.7 |
In 2009, during the Round 3 initial proposal stage 26.7 GW of potential capacity was planned. However, due to government planning permission refusal, challenging ground conditions and project financing issues, a number of proposed sites were withdrawn. A number of other sites were also reduced in scope.
Announced in 2014 with winners notified in February 2015, Contracts for Difference (CfD) Allocation Round 1 raised 1.1 GW of offshore wind development in two locations, East Anglia 1 (EA 1) and Neart na Gaoithe. The strike prices were £114.39 and £119.89. [36]
Announced in 2017, the winners of Allocation Round 2 had three offshore wind developments giving 3.2 GW of energy, Triton Knoll, Hornsea 2 and Moray Offshore. the strike price was £74.75 and £57.50. [37]
Called by the Government Contracts for Difference (CfD) Allocation Round 3 was announced in 2019 and represented the first large scale new leasing round in a decade. This offers the opportunity for up to 7 GW of new offshore capacity to be developed in the waters around England and Wales. [38] This is split into four bidding areas, Dogger Bank, Eastern Regions, South East and Northern Wales and Irish Sea.
Five commercial winners that would give a total capacity of 5.46 GW by 2024/25 at a strike price of £39 to £41 MWh were announced later in the year. Three at Doggerbank, Sofia Offshore Wind Farm Phase 1 and Seagreen Phase 1. [39]
Announced in 2021, the CfD Allocation Round 4 results, which included winners for all types of renewable energy, were announced in July 2022 with 6.99 GW by 2026/27 and included Inch Cape Phase 1, EA3 Phase 1, Norfolk Boreas Phase 1, Hornsea Project Three and Moray West Offshore all at a strike price of £37.35. [40]
Announced in 2022, the CfD Allocation Round 5 results announced in 2023 did not have any offshore wind, as the potential bidders did not believe the government had taken inflation and supply chain problems sufficiently into account. [41]
A consultation was announced in late 2023 with comments requested by January 2024, with plans for a CfD Allocation Round 6 being announced in March 2024. [42]
The UK has accelerated its decommissioning of coal power stations aiming for a 2024 phase-out date, [43] and recent British nuclear power stations have encountered significant technical issues and project overruns that have resulted in significant increases in project costs. [44] These issues have resulted in new UK nuclear projects failing to secure project financing. Similarly, SMR technology is not currently economically competitive with offshore wind in the UK. Following the Fukushima nuclear disaster public support for new nuclear has fallen. [45] In response, the UK government increased its previous commitment for 40 GW of Offshore wind capacity by 2030. [46] As of 2020, this represents a 355% increase over current capacity in 10 years. It is expected the Crown Estate will announce multiple new leasing Rounds and increases to existing bidding areas throughout the 2020–2030 period to achieve the government's aim of 40 GW.
In addition to the 25 GW scoped under the Round 3 SEA, the Scottish Government and the Crown Estate also called for bids on potential sites within Scottish territorial waters. These were originally considered as too deep to provide viable sites, but 17 companies submitted tenders and the Crown Estate initially signed exclusivity agreements with 9 companies for 6 GW worth of sites. Following publication of the Scottish Government's sectoral marine plan for offshore wind energy in Scottish territorial waters in March 2010, [47] six sites were given approval subject to securing detailed consent. Subsequently, 4 sites have been granted agreements for lease. [48]
In 2022 Crown Estate announced the outcome of its application process for ScotWind Leasing, the first Scottish offshore wind leasing round in over a decade and the first ever since the management of offshore wind rights were devolved to Scotland. 17 projects were selected with a capacity of 25 GW.
Farm | Commissioned | Estimated completion | Power (MW) | No. Turbines | Operator | Notes | Round |
---|---|---|---|---|---|---|---|
Race Bank | February 2018 [51] | 573 | 91 | Ørsted and Macquarie Group | Consent granted July 2012 [52] | 2 | |
Aberdeen Bay (EOWDC) | September 2018 [53] | 92 | 11 | Vattenfall | Demonstration site for new turbines. Consent granted March 2013. [54] Project under construction. Use of 8 MW turbines planned utilising the Vestas "short tower" option. | Demo | |
Kincardine (Phase 1) | October 2018 | 2 | 1 | Kincardine Offshore Wind | Consent granted March 2017 [55] [56] [57] [58] Commercial scale demonstration of a floating wind farm. [59] [60] | Demo | |
Rampion | November 2018 [61] | 400 | 116 | RWE, Green Investment Bank, Enbridge | Construction began in January 2016. [2] First electricity delivered to the grid in November 2017. [62] RWE (50.1%) Green Investment Bank (25%) Enbridge (24.9%) [63] | 3 | |
Beatrice | July 2019 [64] | 588 | 84 | SSE plc, Copenhagen Infrastructure Partners and Red Rock Power LTD | Offshore pile construction has started. [65] Eligible for government CfD. First power generated in July 2018. [66] Fully operational in June 2019 [67] Uses Siemens Gamesa 7 MW turbines. | STW. | |
Hornsea Project One | January 2020 [68] | 1218 | 174 | Ørsted, Global Infrastructure Partners | Offshore construction began in January 2018. [69] First power in March 2019. [70] Eligible for government CfD. Use of Siemens Gamesa 7 MW turbines. [70] | 3 | |
East Anglia ONE | July 2020 [71] | 714 | 102 | Vattenfall and Scottish Power Renewables | Consent granted June 2014. [72] [73] Uses Siemens Gamesa 7 MW turbines. Turbine installation was completed in April 2020. [74] | 3 | |
Kincardine (Phase 2) | August 2021 [75] | 48 | 5 | Kincardine Offshore Wind | Consent granted March 2017 [55] First turbine towed into place in August 2018 and first power generated in October 2018. [56] [57] [58] Commercial scale demonstration of a floating wind farm. [59] [60] | Demo | |
Moray East | April 2022 [76] | 950 | 100 | EDP Renewables, Engie, Diamond Green, China Three Gorges | Consent granted March 2014. [77] Use of Vestas 9.5MW turbines planned. First turbine installed January 2021. [78] EDP Renewables (33.3%), Engie (23.3%), Diamond Green Limited (33.4%) and China Three Gorges (10%) [79] | 3 | |
Triton Knoll | April 2022 [19] | 855 | 90 | RWE, J-Power, Kansai Electric Power | Consent granted July 2013 [80] Uses Vestas 9.5MW turbines. All foundations completed in August 2020, first power in March 2021. [81] [82] RWE (59%), J-Power (24%) and Kansai Electric Power (16%) [18] | 2 | |
Hornsea Project Two | August 2022 [83] | 1386 | 165 | Ørsted | Consent granted August 2016 for phase 2 (Breesea & Optimus Wind – 900MW each). [84] Use of Siemens Gamesa 8.4MW turbines. First power in December 2021. [85] | 3 | |
Seagreen (Phase 1) | October 2023 [86] | 1140 | 114 | SSE and Total | Consent granted October 2014 for phase 1 (Alpha & Bravo – 525MW each) [17] Successful in the spring 2019 capacity auction. [20] The project is projected to grow to 1,500 MW after phase 1. Vestas 10 MW turbines to be used. [87] First foundation laid October 2021. [88] First power in August 2022. [89] | 3 | |
Dogger Bank A | 2024 [20] [90] [91] | 1235 | 95 | SSE, Equinor, Eni | Consent granted February 2015 for phase 1 (Creyke Beck A & B – 1235MW each) [92] Successful in the spring 2019 capacity auction. [20] The wind farm will use 95 of the GE Haliade-X 13 MW. [93] Equinor (40%), SSE Renewables (40%) and Eni (20%). [94] First foundation laid in July 2022. [95] First power transmitted 10 October 2023 [96] | ||
Neart Na Gaoithe | 2024 [97] | 448 | 54 | EDF Renewables, ESB | Consent granted October 2014. [17] Use of Siemens Gamesa 8MW turbines planned. Construction began in August 2020. [98] EDF (50%) and ESB (50%). [99] Delayed until 2024. | STW | |
Moray West | Early 2025 [100] | 882 [101] | 60 [101] | EDP Renewables, ENGIE [101] | Consent granted June 2019. [102] Partially successful ln CFD Round 4 for 294 MW of the project [103] Offshore construction started early October 2023 [104] | ||
Dogger Bank B | 2024–25 [20] | 1235 | 95 | SSE, Equinor, Eni | Consent granted February 2015 for phase 1 (Creyke Beck A & B – 1235MW each) [92] Successful in the spring 2019 capacity auction. [20] The wind farm will use 95 of the GE Haliade-X 13 MW. [93] Equinor (40%), SSE Renewables (40%) and Eni (20%). [94] | 3 | |
Dogger Bank C | 2024–25 (Phase 1), [20] [105] revised completion 2026 | 1218 | 87 | SSE and Equinor | Formerly known as Teesside A. Consent granted August 2015. [106] Successful in the spring 2019 capacity auction. [20] The wind farm is planning to use the Haliade-X 14 MW from GE, the world's largest wind turbine. [107] | 3 | |
East Anglia THREE | 2026–27 [103] | 1372 [103] | 100 | Scottish Power Renewables, Vattenfall and OPR | Consent granted August 2017. [108] Successful ln CFD Round 4 [103] Construction started July 2022. [109] | 3 | |
Sofia | 2023–24 (Phase 1), [20] revised completion 2026 | 1400 | 100 | RWE | Consent granted August 2015. [106] Formerly known as Dogger Bank Teesside B. Successful in the spring 2019 capacity auction. [20] Use of Siemens Gamesa 14 MW turbines planned. | 3 | |
Hornsea Project Three | 2026–27 [103] | 2852 [103] | 231 | Ørsted | Consent granted in 2020. [110] Final investment decision confirmed December 2023 [111] Successful in CFD Round 4 [103] | 3 | |
ForthWind Offshore Wind Demonstration Project | 2023–24 [20] | 12 | 2 | Cierco | Consent granted December 2016. [112] | ||
Inch Cape | 2026–27 [103] | 1080 [103] | 72 | Red Rock Power and ESB | Consent granted October 2014. [17] RSPB Judicial Review overturned. [113] Project downsized to 784 MW following issues raised during consultations. New application in August 2018 with fewer but taller turbines. [114] Successful in CFD Round 4 [103] | STW | |
Dounreay Trì | 2026 [115] | 10 | 2 | Hexicon AB and Dounreay Tri | Consent granted March 2017. [116] Has since been put on hold [117] | ||
Hornsea Project Four | 2027 | 180 | Ørsted | Anticipated development consent order is expected to be submitted in 2020. [118] The wind farm is expected to start construction in 2023, and operation at 2027 at the earliest [119] The project's capacity is unknown by Orsted due to the ever increasing size of available wind turbines to the project. | |||
Norfolk Vanguard | Mid 2020s | 1800 | 90–180 | Vattenfall | A development consent order was given for the project in June 2020. [120] The project aims to install all of the offshore cabling for the Vanguard location as well as the sister wind farm, Boreas which is located adjacent to the project. [121] | 3 | |
Norfolk Boreas (Phase 1) | 2026–27 [103] | 1396 [103] | unknown | Vattenfall, now RWE | Consent Granted December 2021. Successful in CFD Round 4. [103] Development was suspended in July 2023 due to rising costs. [122] Development was purchased by RWE and is expected to resume. [123] | ||
Dogger Bank D | 1320 | unknown | SSE and Equinor | Initial surveys started in mid-August and are expected to run until the end of November 2022 [124] | |||
Dogger Bank South | 3000 | unknown | RWE | Go ahead to enter lease agreement with Crown Estate July 2022. [125] Survey work complete October 2022. [126] | 4 | ||
Seagreen 1A | 500 [127] | 36 [127] | SSE and Total | Consent from Scottish Government to increase the capacity of this phase from 360 MW to 500 MW October 2022 [127] | |||
Rampion 2 | 2026 | 1200 [128] | 90 [129] | RWE | RWE is aiming to submit final proposals to the Planning Inspectorate in 2023 [129] | ||
North Falls | 2030 | 504 [130] | up to 72 [130] | RWE | Secured Agreements for Lease with the Crown Estate in 2020 [131] | ||
Sheringham Shoal Wind Farm Extension | 719 [132] | up to 56 [132] | Equinor | Application for Sheringham Shoal Wind Farm Extension submitted [133] | |||
Dudgeon Wind Farm Extension | Shared with Sheringham Shoal | Shared with Sheringham Shoal | Equinor | Application for Dudgeon Offshore Wind Farm Extension submitted [133] | |||
Awel y Môr | 2030 [134] | estimated 500 | up to 50 [135] | RWE | DCO granted September 2023. [136] Application for Marine License submitted. |
A wind farm or wind park, also called a wind power station or wind power plant, is a group of wind turbines in the same location used to produce electricity. Wind farms vary in size from a small number of turbines to several hundred wind turbines covering an extensive area. Wind farms can be either onshore or offshore.
The United Kingdom is the best location for wind power in Europe and one of the best in the world. The combination of long coastline, shallow water and strong winds make offshore wind unusually effective.
The Thanet Wind Farm is an offshore wind farm 7 miles (11 km) off the coast of Thanet district in Kent, England. On commissioning it was the world's largest offshore wind farm. It has a nameplate capacity of 300 MW and it cost £780–900 million (US$1.2–1.4 billion). Thanet is one of fifteen Round 2 wind projects announced by the Crown Estate in January 2004 but the first to be developed. It was officially opened on 23 September 2010, when it overtook Horns Rev 2 as the biggest offshore wind farm in the world. It has since been overtaken by many others.
The production of renewable energy in Scotland is a topic that came to the fore in technical, economic, and political terms during the opening years of the 21st century. The natural resource base for renewable energy is high by European, and even global standards, with the most important potential sources being wind, wave, and tide. Renewables generate almost all of Scotland's electricity, mostly from the country's wind power.
Greater Gabbard is a 504 MW wind farm, built on sandbanks 23 kilometres (14 mi) off the coast of Suffolk in England at a cost of £1.5 billion. It was completed on 7 September 2012 with all of the Siemens SWT3.6–107 turbines connected. Developed as a joint venture between Airtricity and Fluor, it is now jointly owned by SSE Renewables and RWE.
Wind power is the fastest-growing renewable energy technology in Scotland, with 11,482 megawatts (MW) of installed wind power capacity by Q1 2023. This included 9,316 MW from onshore wind in Scotland and 2,166 MW of offshore wind generators.
Atlantic Array was a proposed offshore wind farm in the Bristol Channel, off the coast of North Devon and South Wales, United Kingdom. It was a development by RWE Npower Renewables. With a planned 1.2 gigawatt capacity, it would have been one of the world's largest offshore wind farms. The project was cancelled in November 2013.
Rhyl Flats Offshore Wind Farm is a 25 turbine wind farm approximately 8 km north east of Llandudno in North Wales. It is Wales' second offshore wind farm and the third offshore wind farm to be built within Liverpool Bay. It has a maximum rated output of 90 MW.
Gwynt y Môr is a 576-megawatt (MW) offshore wind farm located off the coast of north Wales and is the fifth largest operating offshore windfarm in the world. The farm has 160 wind turbines of 150 metres (490 ft) tip height above mean sea level.
The Beatrice Offshore Wind Farm now known as Beatrice Offshore Windfarm Ltd (BOWL) project, is an offshore wind farm close to the Beatrice oil field in the Moray Firth, part of the North Sea 13 km off the north east coast of Scotland.
Triton Knoll Wind Farm is an 857 MW round 2 offshore wind farm 33 kilometres (21 mi) off the coast of Lincolnshire, in the North Sea, England.
Bladt Industries A/S is an international steel contractor specialising in large-scale and highly complex steel structures. It operate within three key areas of business providing steel solutions for the wind and renewable energy sector, for the oil and gas industry and for infrastructure.
Teesside Wind Farm, or alternatively referred to as Redcar Wind Farm, is a 27 turbine 62 MW capacity offshore wind farm constructed just to the east of the mouth of the River Tees and 1.5 km north of Redcar off the North Yorkshire coast, in the North Sea, England.
Dogger Bank Wind Farm is a group of offshore wind farms under construction 130 to 200 kilometres off the east coast of Yorkshire, England in the North Sea. It is considered to be the world's largest offshore windfarm. It was developed by the Forewind consortium, with three phases envisioned - first phase, second phase and third phase. In 2015, the third phase was abandoned, while the first and second phases were granted consent. It was initially expected that the Dogger Bank development will consist of four offshore wind farms, each with a capacity of up to 1.2 GW, creating a combined capacity of 4.8 GW. As of 2024, a total of 8.1 GW generating capacity is expected to be installed on Dogger Bank.
The East Anglia Array is a proposed series of offshore wind farms located around 30 miles off the east coast of East Anglia, in the North Sea, England. It has begun with the currently operational East Anglia ONE, that has been developed in partnership by ScottishPower Renewables and Vattenfall. Up to six individual projects could be set up in the area with a maximum capacity of up to 7.2 GW. The first project, East Anglia ONE at 714 MW, received planning consent in June 2014 and contracts in April 2016. Offshore construction began in 2018 and the project was commissioned in July 2020. It is expected to cost £2.5 billion.
Hornsea Wind Farm is a Round 3 wind farm which began construction in 2018. Sited in the North Sea 120 km (75 mi) off the east coast of England, the eventual wind farm group is planned to have a total capacity of up to 6 gigawatt (GW).
Contracts for Difference (CfD) are the main market support mechanism for low carbon generation in the UK. The scheme replaced the Renewables Obligation which closed to new generation in March 2017. It is administered by the Low Carbon Contracts Company (LCCC), which is owned by the UK Government.
{{cite web}}
: CS1 maint: bot: original URL status unknown (link){{cite web}}
: CS1 maint: bot: original URL status unknown (link)