Doel Nuclear Power Station | |
---|---|
Official name | Kerncentrale Doel (KCD) |
Country | Belgium |
Location | Doel, East Flanders |
Coordinates | 51°19′29″N04°15′31″E / 51.32472°N 4.25861°E |
Status | Operational |
Construction began | July 1969 (Doel 1) |
Commission date | 15 February 1975 (Doel 1) |
Owner(s) | Electrabel, EDF Luminus |
Operator(s) | Electrabel |
Nuclear power station | |
Reactor type | PWR |
Reactor supplier | ACECOWEN FRAMACEC |
Cooling towers | 2 |
Cooling source | Scheldt river |
Thermal capacity | 2 × 1312 MWt 1 × 3064 MWt 1 × 3000 MWt |
Power generation | |
Units operational | 1 x 466 MW (gross) 1 x 466 MW (gross) 1 x 1056 MW (gross) 1 x 1090 MW (gross) |
Units cancelled | 1 |
Nameplate capacity | 2,935 MW |
Capacity factor | 91.8% (2021) |
Annual net output | 44.12 (2021) |
External links | |
Website | Doel Nuclear Power Station |
Commons | Related media on Commons |
The Doel Nuclear Power Station is one of two nuclear power plants in Belgium. The plant includes four reactors. The site is located on the bank of the Scheldt river, near the village of Doel in the Flemish province of East Flanders, on the outskirts of the city of Antwerp. The station is operated and majority-owned by vertically-integrated French energy corporation Engie SA through its 100%-owned Belgian subsidiary Electrabel. EDF Luminus has a 10.2% stake in the two newest units. The Doel plant employs 963 workers and covers an area of 80 hectares (200 acres). The plant represents about 15% of Belgium's total electricity production capacity [1] and 30% of the total electricity generation. [2] Nuclear energy typically provides half of Belgium's domestically-generated electricity and is the country's lowest-cost source of power. [3]
The station is located in the most densely populated area for any nuclear power station in Europe as of 2011, with 9 million inhabitants within a radius of 75 kilometres (47 mi). [4] [5] [6]
The power station was built by public utility EBES (Sociétés Réunies d'Energie du Bassin de l'Escaut), which in 1990 merged with Intercom and Unerg to become Electrabel. The plant was designed by the Belgian engineering firm Tractebel. Doel 1 and 2 are twin units that entered commercial operation in 1975. Doel 3 entered commercial operation in 1982 and Doel 4 in 1985. Doel 1, 2 and 4 were constructed by the ACECOWEN (ACEC-Cockerill-Westinghouse) consortium. While Doel 3 was constructed by FRAMACEC (Framatome-ACEC-Cockerill). [7]
Earthworks for Doel 5, a 1400 MW reactor also known as N8 (8th nuclear reactor in Belgium), were stopped in 1988. Participation in the French twin plant in Chooz continued. French industry was compensated for already ordered components. [8]
The plant consists of four second-generation pressurized water reactors with a total net capacity of 2,925 MWe, smaller than Belgium's other nuclear power plant at Tihange. [9] Its four units are rated as follows: [3]
Reactor [9] [10] | Loops | Supplier | Thermal power | Gross power | Net power | Start of construction | First criticality | Grid connection | Commercial operation | Licensed until |
---|---|---|---|---|---|---|---|---|---|---|
Doel 1 | 2 | ACECOWEN | 1312 MW | 466 MW | 445 MW | 1 July 1969 | 18 July 1974 | 28 August 1974 | 15 February 1975 | 2025 |
Doel 2 | 2 | ACECOWEN | 1312 MW | 466 MW | 445 MW | 1 September 1971 | 4 August 1975 | 21 August 1975 | 1 December 1975 | 2025 |
Doel 3 | 3 | FRAMACEC | 3064 MW | 1056 MW | 1006 MW | 1 January 1975 | 14 June 1982 | 23 June 1982 | 1 October 1982 | 2022 |
Doel 4 | 3 | ACECOWEN | 3000 MW | 1090 MW | 1039 MW | 1 December 1978 | 31 March 1985 | 8 April 1985 | 1 July 1985 | 2035 |
The design of the plant is reviewed completely every ten years through a TJH (tienjaarlijkse herziening), a legal obligation imposed by the Belgian state and the operation licence of the plant. The purpose of the review is to update the plant to the most recent international safety standards. [11]
Various weather conditions have been analysed including rain, seiches, tsunamis, floods, earthquakes, wind, tornados, lightning, snow, hail, extreme temperatures, cyclones, sandstorms and waterspouts. [12]
Since the design of Doel 3 and 4 and the first TJH of Doel 1 and 2 [12] : 50 the reactors were designed to be subject to earthquakes such as the Richter scale 5.6 Zulzeke-Nukerke quake in 1938. At a distance of 75 km to the epicentre, this is the most significant historical earthquake for Doel. The earthquake resulted in horizontal ground accelerations of up to 0.058 g [12] : 51 and formed the design base for Doel 1 and 2. Doel 3 and 4 were designed for peak ground accelerations of 0.1 g. [12] : 50 After the Fukushima Daiichi nuclear disaster probabilistic safety studies performed by the Royal Observatory of Belgium predicted an earthquake with peak ground acceleration of up to 0.081 g every 10,000 years. [12] : 52 The design was subsequently analysed for earthquakes up to 0.17 g, [12] : 70 which is equivalent to a 1 in 100,000 year earthquake. [12] : 48
The Doel plant was originally designed for a 10,000 year flood of 9.13 m TAW (Tweede Algemene Waterpassing). [12] : 90 The highest measured level was 8.10 m TAW during the North Sea flood of 1953. [12] : 78 The site was filled to 8.86 m TAW during construction and fitted with a seadyke of 12.08 m TAW. The other dykes around the site have a height of 11 m TAW. [12] : 20 Probabilistic studies performed after Fukushima showed the height of a 10,000 year flood had slightly increased to 9.35 m TAW, 22 cm higher than the studies performed in the 1960s. [12] : 91 The highest possible tsunami is lower than 0.5 m. [12] : 77 During post-Fukushima stress tests a dyke failure with a water level of 10.2 m was simulated. Due to the presence of bulkheads and pedestals in the buildings no safety functions were endangered. [12] : 98–108
Besides regular primary level safety systems, in common with most nuclear power plants in the world, Doel has secondary level safety systems that can autonomously keep the power plant safe during large external accidents such as the crash of an aircraft, external explosions or loss of the primary level. [12] : 30 [12] : 14 The primary level systems have a redundancy of three or four times.: 26–29 The secondary level systems are 2x100% or 3x50%. [12] : 30–33 and have their own heatsink separate from the primary heatsink, the Scheldt river. Doel 1 and 2 have aircoolers [12] : 32 while Doel 3 and 4 have three separate artificial cooling ponds. [12] : 33
Nuclear plants are designed with multiple physical barriers to prevent fission products escaping into the environment. In the case of a pressurized water reactor there are three barriers: the fuel cladding which surround the fuel pallets, the primary circuit which houses the fuel rods and finally the containment building in which the primary circuit is built. In Belgium it was decided to add an extra double containment barrier. [13] The primary containment, a steel sphere in Doel 1 and 2 and a pre-stressed concrete cylinder with steel liner in Doel 3 and 4, is surrounded by a secondary containment made of 1.2 to 1.3 m thick reinforced concrete. The space between both containments is kept at sub-atmospheric pressure and filters are used to filter potential leaks of the primary containment. [12] : 14
In answer to a question of die Grünen in the Bundestag, the German parliament, the German government replied that the Belgian nuclear power plants do not have filtered containment venting systems installed. In German nuclear reactors these were already built in after the Chernobyl disaster in 1986. Other countries followed this example, latest after the Fukushima nuclear disaster. This kind of system allows for the containment pressure to be relieved in the event of a severe accident. The non-condensible gases that cause pressure within containment to rise are released through a stack (or chimney) via a filtration system that removes large quantities of fission products from the effluent. [14] [15]
As part of the stress tests following the Fukushima incident, this issue had already been identified to be included in the stress-test action plan (BEST). Construction of containment filter venting systems at Doel 3 and 4 was completed in 2017, with Doel 1 and 2 scheduled to be operational in 2020. [16] [17]
Every reactor has at least one steam driven feedwater pump which can supply the steam generators with water to cool down the reactor. These turbine driven pumps can cool down the plant even when no electrical power is available to power the motor driven feedwater pumps during a station blackout like the Fukushima Daiichi nuclear disaster. [12] : 147 In a boiling water reactor, like those in Fukushima, the heat removal capacity of the pumps is limited as the steam that drives the turbines is radioactive and thus has to be stored. [18] This is not the case with a PWR due to the use of steam generators. Steam can simply be removed via a chimney. Water supplies on site are sufficient to keep the plant safe for dozens of days. [12] : 147
While Unit 1 and 2 have no cooling towers, Unit 3 has one 169.48 metres tall and Unit 4 has one 172.61 metres tall. The latter is the tallest cooling tower in Belgium.
Light and intermediate level waste, which represents 99% of the volume of waste, [19] is treated on site in the WAB (Water and Waste Treatment Building). [20] Category A waste with half lives of less than 30 years is transported to Belgoprocess in Dessel for surface disposal. [21]
High level waste was originally recycled to MOX fuel, and re-used in the Doel 3 reactor. In 1993, the Belgian federal government placed a moratorium on the reprocessing activities in order to research other options. [22] Pending further decisions regarding the moratorium, spent fuel was stored on site in dry cask storage. Final disposal of the waste is being researched at the HADES underground laboratory 225m deep in the Boom Clay. [23] Nuclear transmutation of the waste is also being researched with the MYRRHA project.
In October 2013, NIRAS suspended Electrabel's licence to treat two types of waste, concentrate and resins, after foam was discovered on previously treated waste due to an alkali–silica reaction. Electrabel has started a licensing procedure to use the process used in Tihange to process future waste. This process can take up to two years and in the meantime the waste in question is stored on site. [24]
There has been one INES-2 incident on the International Nuclear Event Scale. After the replacement of an auxiliary feedwater turbopump, during the 2009-outage, one of the three feedwater pumps of the first level was adjusted to a lower level of rotational speed, delivering insufficient flow rates during certain circumstances. [25] [26] The two other first level feedwater pumps and three second level feedwater pumps were still available. The incident was rated 2 on the scale rather than 1 because the "Federal Agency for Nuclear Control felt that Electrabel waited a little too long to report the incident". [27]
In June 2012 Doel 3 was shut down for its third scheduled 10-year in-service inspection. Ultrasound inspections revealed a number of cracks in the lowest forged ring of the reactor pressure vessel. The cracks were determined to be an original manufacturing defect, not related to tension, and theoretically of no risk. [28] [29] [30] [31]
The reactor remained offline for further inspections and assessment for a year. Eventually the nuclear regulator judged short-term safety concerns initially raised had been solved in a satisfactory manner and that the reactor could operate safely, and it was restarted in June 2013. [32] [33]
In August 2014, there was a major incident in the non-nuclear part of the plant. The main turbine overheated while operating without oil. A valve had been deliberately opened, which rapidly evacuated 65,000 litres of oil to an underground storage tank. The procedure was normally used in case of fire. The valve was normally secured by a padlock. [34] Authorities and the plant operator suspected an act of deliberate sabotage. The unit was eventually back on grid by 19 December 2014. Combined with the outage of Doel 3 and Tihange 2, blackouts were not ruled out for the winter period of 2014–2015. [35]
In December 2016, Electrabel requested that the justice department in Brussels prolong the search for the perpetrator of the turbine sabotage. Repairs cost more than 100 million euros. [36]
The power plant has two electrical substations. Two transmission lines run to Zandvliet and Kallo from the 150 kV station. The 380 kV station has three lines to Avelgem, Mercator in Kruibeke and Zandvliet. Elia is the transmission system operator. [37]
The line to Zandvliet crosses the Scheldt River using one of the highest transmission towers in Europe. The tower is 170 metres (560 ft) high and built on a caisson in the middle of the river. The line is part of the interconnection between the Dutch and Belgian grids.
With a height of 169 metres(554 feet), [38] the two cooling towers are the most visible structures in the Port of Antwerp. Due to their proximity to the Dutch-Belgian border, the towers and the accompanying wet steam can be seen over large areas of the Dutch provinces of Zeeland and western North Brabant. Since the spring of 1996, one of the cooling towers has hosted a nest of peregrine falcons. [39]
On 15 March 2016, the federal government of Belgium decided 140 soldiers would guard the nuclear sites and that Electrabel should cover the costs. [40] In late 2015 it had already been decided that a specially trained department of the federal police would guard the nuclear sites. [41] After the 2016 Brussels bombings, on 22 March the nuclear powerplants of Doel and Tihange were preventively evacuated, the standard procedure when the threat level in Belgium reaches Level 4. The powerplants continued running with minimal staff. [42]
SCK CEN, until 2020 shortened as SCK•CEN, is the Belgian nuclear research centre located in Mol, Belgium. SCK CEN is a global leader in the field of nuclear research, services, and education.
A nuclear power phase-out is the discontinuation of usage of nuclear power for energy production. Often initiated because of concerns about nuclear power, phase-outs usually include shutting down nuclear power plants and looking towards fossil fuels and renewable energy. Three nuclear accidents have influenced the discontinuation of nuclear power: the 1979 Three Mile Island partial nuclear meltdown in the United States, the 1986 Chernobyl disaster in the USSR, and the 2011 Fukushima nuclear disaster in Japan.
Nuclear energy policy is a national and international policy concerning some or all aspects of nuclear energy and the nuclear fuel cycle, such as uranium mining, ore concentration, conversion, enrichment for nuclear fuel, generating electricity by nuclear power, storing and reprocessing spent nuclear fuel, and disposal of radioactive waste. Nuclear energy policies often include the regulation of energy use and standards relating to the nuclear fuel cycle. Other measures include efficiency standards, safety regulations, emission standards, fiscal policies, and legislation on energy trading, transport of nuclear waste and contaminated materials, and their storage. Governments might subsidize nuclear energy and arrange international treaties and trade agreements about the import and export of nuclear technology, electricity, nuclear waste, and uranium.
Electrabel SA is a Belgian energy corporation. It is a subsidiary of French multinational utility company Engie S.A..
Nuclear power in Switzerland is generated by three nuclear power plants, with a total of four operational reactors (see list below). Since 1985, nuclear power has been contributing approximately 40% of Switzerland's electrical energy. In 2022, it produced 23 terawatt-hours (TWh) of electricity, and accounted for 37% of the nation's gross electricity generation of 62 TWh, while 55% was produced by hydroelectric plants and 8% came from conventional thermal power stations and non-hydro renewable energy sources.
The Fukushima Daiichi Nuclear Power Plant is a disabled nuclear power plant located on a 3.5-square-kilometre (860-acre) site in the towns of Ōkuma and Futaba in Fukushima Prefecture, Japan. The plant suffered major damage from the magnitude 9.1 earthquake and tsunami that hit Japan on March 11, 2011. The chain of events caused radiation leaks and permanently damaged several of its reactors, making them impossible to restart. The working reactors were not restarted after the events.
The Beznau nuclear power plant is a nuclear power plant of the Swiss energy utility Axpo, located in the municipality Döttingen, Canton of Aargau, Switzerland, on an artificial island in the Aare river. The plant has been operating since September 1969.
The Tihange Nuclear Power Station is one of two nuclear energy power plants in Belgium and contains three nuclear reactors. The site is located on the bank of the Meuse river, near the village of Tihange in the Walloon province of Liège. The station is operated and majority-owned by vertically-integrated Belgian energy corporation Electrabel. EDF Luminus has a 50% stake in the oldest unit and a 10% stake in the two newest units. It employs 1074 workers and covers an area of 75 hectares. The plant represents about 15% of Belgium's total electricity production capacity. Nuclear energy typically provides between 40%-50% of Belgium's domestically-generated electricity. In order to extend the lifetime of Tihange 3, the operator will receive subsidies through a Contract of Difference arrangement.
The three primary objectives of nuclear reactor safety systems as defined by the U.S. Nuclear Regulatory Commission are to shut down the reactor, maintain it in a shutdown condition and prevent the release of radioactive material.
Energy in Belgium describes energy and electricity production, consumption and import in Belgium.
Tinne Van der Straeten is a Belgian politician who has been serving as Minister of Energy in the De Croo Government since October 2020. She is a member of the Groen party. She previously served in the Chamber of Representatives for Brussels-Halle-Vilvoorde from 2007 to 2010 and later for Brussels from 2019 until 2020, when she resigned to become energy minister.
The Fukushima nuclear accident was a major nuclear accident at the Fukushima Daiichi nuclear power plant in Ōkuma, Fukushima, Japan which began on 11 March 2011. The proximate cause of the accident was the 2011 Tōhoku earthquake and tsunami, which resulted in electrical grid failure and damaged nearly all of the power plant's backup energy sources. The subsequent inability to sufficiently cool reactors after shutdown compromised containment and resulted in the release of radioactive contaminants into the surrounding environment. The accident was rated seven on the INES by NISA, following a report by the JNES. It is regarded as the worst nuclear incident since the Chernobyl disaster in 1986, which was also rated a seven on the INES.
Fukushima Daiichi is a multi-reactor nuclear power site in the Fukushima Prefecture of Japan. A nuclear disaster occurred there after a 9.0 magnitude earthquake and subsequent tsunami on 11 March 2011. The earthquake triggered a scram shut down of the three active reactors, and the ensuing tsunami crippled the site, stopped the backup diesel generators, and caused a station blackout. The subsequent lack of cooling led to explosions and meltdowns, with problems at three of the six reactors and in one of the six spent-fuel pools.
Belgium has two nuclear power plants operating with a net capacity of 5,761 MWe. Electricity consumption in Belgium has increased slowly since 1990 and in 2016 nuclear power provided 51.3%, 41 TWh per year, of the country's electricity.
Belgium has the 7th largest CO2 emission per capita in the EU. The CO2 emissions have dropped 19.0% since in comparison with 1990 levels. The average temperature has risen 1.9 degrees Celsius since measurements began in 1890, with an acceleration since 1954.
The Fukushima disaster cleanup is an ongoing attempt to limit radioactive contamination from the three nuclear reactors involved in the Fukushima Daiichi nuclear disaster that followed the earthquake and tsunami on 11 March 2011. The affected reactors were adjacent to one another and accident management was made much more difficult because of the number of simultaneous hazards concentrated in a small area. Failure of emergency power following the tsunami resulted in loss of coolant from each reactor, hydrogen explosions damaging the reactor buildings, and water draining from open-air spent fuel pools. Plant workers were put in the position of trying to cope simultaneously with core meltdowns at three reactors and exposed fuel pools at three units.
The Fukushima Daiichi reactor, was 1 out of 4 reactors seriously affected during the Fukushima Daiichi nuclear disaster on 11 March 2011. Overall, the plant had 6 separate boiling water reactors originally designed by General Electric (GE), and maintained by the Tokyo Electric Power Company (TEPCO). At the time of the earthquake, Reactor 4 had been de-fueled while 5 and 6 were in cold shutdown for planned maintenance.
The Fukushima Daiichi reactor, was 1 out of 4 reactors seriously affected during the Fukushima Daiichi nuclear disaster on 11 March 2011. Overall, the plant had 6 separate boiling water reactors originally designed by General Electric (GE), and maintained by the Tokyo Electric Power Company (TEPCO). At the time of the earthquake, Reactor 4 had been de-fueled while 5 and 6 were in cold shutdown for planned maintenance. Unit 1 was immediately shut down automatically after the earthquake, and emergency generators came online to control electronics and coolant systems. However, the tsunami following the earthquake quickly flooded the low-lying rooms in which the emergency generators were housed. The flooded generators failed, cutting power to the critical pumps that must continuously circulate coolant water through the reactor core. While the government tried pumping fresh water into the core, it was already too late due to overheat. In the hours and days that followed, Unit 1 experienced a full meltdown.
The Fukushima Daiichi reactor, was 1 out of 4 reactors seriously affected during the Fukushima Daiichi nuclear disaster on 11 March 2011. Overall, the plant had 6 separate boiling water reactors originally designed by General Electric (GE), and maintained by the Tokyo Electric Power Company (TEPCO). In the aftermath, Unit 3 experienced hydrogen gas explosions and suffered a partial meltdown, along with the other two reactors in operation at the time the tsunami struck. Reactor 4 had been de-fueled while 5 and 6 were in cold shutdown for planned maintenance.