This is a list of Mass Rapid Transit (MRT) lines in Singapore, with details on costs, construction timelines and route length.

Contents

North–South Line

StageDateLengthStretchStationsCost
Commencement
of construction
Service commencementNamesCodesElevatedAt-gradeUnderground
ContemporaryRetired
Phase 122 October 1983;42 years ago7 November 1987;38 years ago6 km [1] Yio Chu Kang - Toa Payoh NS15  -  NS19 N10 - N62
(
1
(
2
(
S$5 billion [a]
12 December 1987;38 years agoTBDToa Payoh - Raffles Place NS19  -  NS26 N6 - C1N/aN/a7
(
Phase 2BJune 1985;40 years ago20 December 1988;37 years agoTBDYio Chu Kang - Yishun NS15  -  NS13 N10 - N122
(
N/aN/a
Phase 2AJanuary 1985;41 years ago4 November 1989;36 years agoTBDRaffles Place - Marina Bay NS26  -  NS27 C1 - M1N/aN/a1
(
Phase 2B
(Branch Line)
June 1985;40 years ago10 March 1990;35 years ago6.5 kmJurong East - Choa Chu Kang NS1  -  NS4 W9 - B33
(
N/aN/a
Woodlands ExtensionTBD10 February 1996;29 years ago16 kmChoa Chu Kang - Yishun NS4  -  NS13 N/a6
(
N/aN/aS$1.2 billion [2]
North–South Line ExtensionDecember 2009;16 years ago [3] 23 November 2014;11 years ago1 kmMarina Bay - Marina South Pier NS27  -  NS28 N/aN/aN/a1
(
S$357.5 million [3]
Canberra station (infill)26 March 2016;9 years ago [4] 2 November 2019;6 years agoN/aCanberra NS12 N/a1
(
N/aN/aS$274 million [5]
Brickland station (infill)H1 20262034;8 years' timeN/aBrickland NS3A N/a1
(
N/aN/aS$281 million [6]
Sungei Kadut station (infill)Q2 20262035;9 years' timeN/aSungei Kadut NS6 N/a1
(
N/aN/aTBD
Total45 kmJurong East - Marina South Pier NS1  -  NS28 17
(
1
(
11
(
S$11.95 billion [b]
29
(

East–West Line

StageDateLengthStretchStationsCost
Commencement
of construction
Service commencementNamesCodesElevatedUnderground
ContemporaryRetired
Phase 1 22 October 1983;42 years ago12 December 1987;38 years agoTBDRaffles Place - Outram Park EW14  -  EW16 C1 - W2N/a2
(
S$5 billion [a]
Phase 1AJanuary 1984;42 years ago12 March 1988;37 years agoTBDOutram Park - Clementi EW16  -  EW23 W2 - W85
(
1
(
Phase 2BJuly 1984;41 years ago5 November 1988;37 years agoTBDClementi - Lakeside EW23  -  EW26 W8 - W113
(
N/a
Phase 2AJanuary 1985;41 years ago4 November 1989;36 years agoTBDCity Hall - Tanah Merah EW13  -  EW4 C2 - E97
(
2
(
June 1985;40 years ago16 December 1989;36 years agoTBDTanah Merah - Pasir Ris EW4  -  EW1 E9 - E123
(
N/a
Phase 2BJanuary 1988;38 years ago6 July 1990;35 years agoTBDLakeside - Boon Lay EW26  -  EW27 W11 - W121
(
N/a
Changi Airport ExtensionTBD10 January 2001;25 years agoTBDTanah Merah - Expo CG  -  CG1 N/a1
(
N/aS$850 million [7]
TBD8 February 2002;23 years agoTBDExpo - Changi Airport CG1  -  CG2 N/aN/a1
(
Dover station (infill)TBD18 October 2001;24 years agoN/aDover EW22 N/a1
(
N/aS$45 million [8]
Boon Lay ExtensionTBD28 February 2009;16 years ago3.8 kmBoon Lay - Joo Koon EW27  -  EW29 N/a2
(
N/aS$436 million [9]
Tuas West ExtensionTBD18 June 2017;8 years ago7.5 kmJoo Koon - Tuas Link EW29  -  EW33 N/a4
(
N/aS$3.5 billion [10]
Total56.7 kmPasir Ris - Tuas Link
Tanah Merah - Changi Airport
 EW1  -  EW33 
 CG  -  CG2 
27
(
8
(
S$11.95 billion [b]
35
(

North East Line

StageDateLengthStretchStationsCost
Commencement
of construction
Service commencementNamesCodes
N/a25 November 1997;28 years ago20 June 2003;22 years ago20 kmHarbourFront - Punggol NE1 
 NE3  -  NE10 
 NE12  -  NE14 
 NE16  -  NE17 
14S$4.6 billion
Buangkok station15 January 2006;20 years agoBuangkok NE15 1TBD
Woodleigh station20 June 2011;14 years agoWoodleigh NE11 1TBD
North East Line ExtensionTBD10 December 2024;13 months ago1.6 kmPunggol - Punggol Coast NE17  -  NE18 1S$79 million [11]
Total21.6 kmHarbourFront - Punggol Coast NE1  -  NE18 17S$5.39 billion [c]

Circle Line

StageDateLengthStretchStationsCost
Commencement
of construction
Service commencementNamesCodes
ContemporaryRetired
Stage 3May 2003;22 years ago28 May 2009;16 years ago5.7 km [12] Bartley - Marymount CC12  -  CC16 N/a5TBD
Stage 25 September 2002;23 years ago17 April 2010;15 years ago5.5 km [13] [12] Bartley - Mountbatten CC12  -  CC7 N/a5TBD
Stage 15 March 2002;23 years ago5.5 km [12] Mountbatten - Dhoby Ghaut CC7  -  CC1 N/a6TBD
Stage 4January 2005;21 years ago8 October 2011;14 years ago9.8 kmMarymount - Kent Ridge CC16  -  CC17 
 CC19  -  CC24 
N/a7TBD
Stage 56.8 kmKent Ridge - HarbourFront CC24  -  CC29 N/a5TBD
Circle Line ExtensionNovember 2007;18 years ago [14] 14 January 2012;14 years ago2.4 kmPromenade - Marina Bay CC4  -  CC33  CC4  -  CE2 2S$811.4 million [15] [ unreliable source? ] [d]
Stage 62017;9 years ago [16] By June 2026;5 months' time4.0 kmHarbourFront - Marina Bay CC29  -  CC33  CC29  -  CE2 3S$4.85 billion [17]
Bukit Brown station (infill)TBDTBDN/aBukit Brown CC18 N/a1TBD
Total39.7 kmDhoby Ghaut - Bayfront
 CC1  -  CC34 34S$15.67 billion [e]

Downtown Line

StageDateLengthStretchStationsCost
Commencement
of construction
Service commencementNamesCodes
Stage 1TBD22 December 2013;12 years ago4.3 kmBugis - Chinatown DT14  -  DT19 6TBD
Stage 23 July 2009;16 years ago27 December 2015;10 years ago16.6 kmBugis - Bukit Panjang DT14  -  DT5 
 DT3  -  DT1 
12TBD
Stage 3TBD21 October 2017;8 years ago21.0 kmChinatown - Expo DT19  -  DT35 16TBD
Hume station (infill)28 February 2021;4 years ago28 February 2025;10 months agoN/aHume DT4 1S$259.5 million
Stage 3 Extension21 July 2016;9 years ago [18] 2026;0 years ago2.2 kmExpo - Sungei Bedok DT35  -  DT37 2TBD
Stage 2 ExtensionQ2 20262035;9 years' time4.0 kmBukit Panjang - Sungei Kadut DT1  -  DE2 2S$326 million [f] [19]
Total48.1 kmSungei Kadut - Sungei Bedok DE2  -  DT37 39TBD

Thomson-East Coast Line

StageDateLengthStretchStationsCost
Commencement
of construction
Service commencementNamesCodesElevatedUnderground
ContemporaryRetired
Stage 127 June 2014;11 years ago [20] 31 January 2020;5 years ago2.9 km Woodlands North - Woodlands South  TE1  -  TE3 N/aN/a3
(
TBD
Stage 228 August 2021;4 years ago11.4 kmWoodlands South - Caldecott  TE3  -  TE9 N/aN/a6
(
TBD
Stage 313 November 2022;3 years ago13.5 kmCaldecott - Gardens by the Bay  TE9 
 TE11  -  TE20 
 TE22 
N/aN/a11
(
TBD
Mount Pleasant station (infill)TBD Mount Pleasant  TE10 N/aN/a1
(
TBD
Marina South station (infill)TBD Marina South  TE21 N/aN/a1
(
TBD
Stage 421 July 2016;9 years ago [18] 23 June 2024;18 months ago10.1 kmGardens by the Bay - Bayshore  TE22  -  TE29 N/aN/a7
(
TBD
Stage 52026;0 years ago2.5 kmBayshore - Sungei Bedok  TE29  -  TE31 N/aN/a2
(
TBD
Founders' Memorial station (infill)2028;2 years' timeN/a Founders' Memorial  TE22A N/aN/a1
(
TBD
Thomson–East Coast Line ExtensionTBDmid-2030s14.0 kmSungei Bedok - Tanah Merah  TE31  -  TE35  TE31  -  CG 2
(
2
(
TBD
Tagore station (infill)TBDTBDN/aTagore TE4A N/aN/a1
(
TBD
Total57 kmWoodlands North - Tanah Merah TE1  -  TE31 2
(
35
(
TBD
37
(

Jurong Region Line

StageDateLengthStretchStationsCost
Commencement
of construction
Service commencementNamesCodes
Stage 113 January 2023;3 years ago [21] 2027;1 year's timeTBD Choa Chu Kang - Boon Lay
Bahar Junction - Tawas
 JS1  -  JS8 
 JS7  -  JW2 
10TBD
Stage 22028;2 years' timeTBD Tengah - Pandan Reservoir  JS3  -  JE7 7TBD
Stage 32029;3 years' timeTBDBoon Lay - Jurong Pier
Tawas - Peng Kang Hill
 JS8  -  JS12 
 JW2  -  JW5 
7TBD
West Coast Extension Phase 1TBDlate-2030sTBDPandan Reservoir - West Coast  JE7  -  JE? TBDTBD
West Coast Extension Phase 2TBDearly-2040sTBDWest Coast - Kent Ridge  JE?  -  JE? TBDTBD
Total24 km [g] Choa Chu Kang - Jurong Pier
Tengah Plantation - Pandan Reservoir
Gek Poh - Peng Kang Hill
 JS1  -  JS12 
 JE1  -  JE7 
 JW1  -  JW5 
24 [g] TBD

Cross Island Line

StageDateLengthStretchStationsCost
Commencement
of construction
Service commencementNamesCodes
Phase 118 January 2023;3 years ago [22] 2030;4 years' time29.0 km Aviation Park - Bright Hill  CR2  -  CR13 12TBD
Cross Island Line Punggol Extension10 October 2023;2 years ago [23] 2032;6 years' time7.3 km Pasir Ris - Punggol  CP1  -  CP4 3TBD
Phase 27 July 2025;6 months ago [24] 2032;6 years' time15.0 kmBright Hill - Jurong Lake District  CR13  -  CR19 6TBD
Phase 3TBDTBDTBDJurong Lake District - Gul Circle  CR19  -  CR24 5TBD
Changi Airport extensionTBDmid-2030s5.8 kmAviation Park - Changi Terminal 5  CR2  -  CR1 1TBD
Total57.1 km [h] Changi Terminal 5 - Gul Circle
Pasir Ris - Punggol
 CR1  -  CR24 
 CP1  -  CP4 
27TBD

See also

Notes

  1. 1 2 Total cost of Phase 1 and 2 of the North–South Line and East–West Line.
  2. 1 2 Total cost of the North–South Line and East–West Line.
  3. Not inclusive of Buangkok and Woodleigh stations.
  4. S$348.4 million for Marina Bay CCL station; $463 million for Bayfront CCL + DTL station.
  5. The cost breakdown of Stages 1-5 is not available.
  6. Cost of DTL2e tunneling works.
  7. 1 2 Stages 1-3.
  8. Excluding Phase 3.

References

  1. "Too popular, so trains skip Orchard stop". The Straits Times . December 20, 1987. Retrieved March 25, 2024.
  2. Thuluja, Naidu Ratnala. "Woodlands MRT line". National Library Board . Retrieved 2019-10-10.
  3. 1 2 "Projects". Land Transport Authority. May 3, 2010. Archived from the original on June 5, 2011. Retrieved October 10, 2019.
  4. "Work Starts for Canberra MRT Station on North–South Line". LTA. 26 March 2016. Archived from the original on 2017-10-11. Retrieved 11 October 2017.
  5. "Revenue & Expenditure Estimates". www.singaporebudget.gov.sg. Retrieved 2018-04-17.
  6. "LTA Awards Civil Contract for Design and Construction of NS3A Station and Viaduct on Existing North-South Line". Land Transport Authority. 30 December 2025. Retrieved 30 December 2025.
  7. "Major Milestones" (PDF). Changi Airport Group . Archived from the original (PDF) on February 26, 2021. Retrieved January 16, 2020.
  8. "DOVER MRT STATION". Building and Construction Authority . Archived from the original on January 15, 2020.
  9. Speech by Mrs. Lim Hwee Hua mot.gov.sg [ permanent dead link ]
  10. "MRT Tuas West Extension to soar above the ground". The Straits Times. February 3, 2015.
  11. "North-East Line extension: LTA awards S$79m contract to China State Construction Engineering - CNA". Archived from the original on March 7, 2020. Retrieved January 15, 2020.
  12. 1 2 3 "Singapore Tunnel News – sg/15, Circle Line - Metro –". Tunnelbuilder.com. Retrieved 2022-05-01.
  13. "Circle Line from Bartley to Dhoby Ghaut to Open 17 April". Archived from the original on June 21, 2011. Retrieved January 26, 2010.
  14. "2"&id="2"89gjpnks1d1xue5op98xv06ulyy4b1cnrc6eyyj89e413p2r7 "LTA | News Room".
  15. "Sembawang E&C bags $400m IR contract". February 29, 2008.
  16. Abdullah, Zhaki (5 March 2020). "Prince Edward MRT station contract awarded to China Railway Tunnel Group". The Straits Times. Archived from the original on 5 March 2020. Retrieved 5 March 2020.
  17. "Final stage of Circle Line to cost $4.85b". The Straits Times. April 11, 2019.
  18. 1 2 "Speech by Mr Khaw Boon Wan, Coordinating Minister For Infrastructure and Minister For Transport, at the Groundbreaking Ceremony of the Thomson-East Coast Line (East Coast Stretch), 21 July 2016". Ministry of Transport. 21 July 2016. Retrieved 18 September 2025.
  19. "LTA Awards First Civil Contract for the Downtown Line 2 Extension". Land Transport Authority. 15 January 2026. Retrieved 15 January 2026.
  20. "Celebrating the Groundbreaking of Thomson Line". Ministry of Transport. 27 June 2014. Archived from the original on 7 January 2020. Retrieved 7 January 2020.
  21. Lee, Nian Tjoe (13 January 2023). "Construction of Jurong Region Line begins, MRT stations to open in three stages from 2027 to 2029". The Straits Times . Retrieved 13 January 2023.
  22. Yeoh, Grace (18 January 2023). "Construction of Cross Island Line begins, with 12 stations in Phase 1". CNA . Retrieved 18 January 2023.
  23. Lee, Nian Tjoe (10 October 2023). "Work starts on Cross Island MRT Line Punggol extension; over 70,000 daily journeys to be shortened". The Straits Times . Retrieved 18 September 2025.
  24. Ong, Justin (Guang-Xi) (7 July 2025). "Construction begins on 6 Cross Island Line Phase 2 stations; targeted for 2032 completion". CNA . Retrieved 7 July 2025.