A Meter Point Administration Number, also known as MPAN, Supply Number or S-Number, is a 21-digit reference used in Great Britain to uniquely identify electricity supply points such as individual domestic residences. The system was introduced in 1998 to aid creation of a competitive environment for the electricity companies, and allows consumers to switch their supplier easily as well as simplifying administration. Although the name suggests that an MPAN refers to a particular meter, an MPAN can have several meters associated with it, [1] or indeed none where it is an unmetered supply. A supply receiving power from the network operator (DNO) has an import MPAN, while generation and microgeneration projects feeding back into the DNO network are given export MPANs. [1]

Contents

The equivalent for gas supplies is the Meter Point Reference Number and the water/wastewater equivalent for non-household customers is the Supply Point ID.

Structure

An MPAN is commonly separated into two sections: the core and the top line data. The core is the final 13 digits and is the unique identifier. The top line data gives information about the characteristics of the supply and is the responsibility of the supplier.

The full MPAN is required to be depicted on electricity bills (the boxes on the top and bottom line are generally unaligned). [2]

MPAN Format.jpg

The core data is on the second line, the supplementary data on the first. Only the last digit on the bottom row is the check digit.

Profile Class (PC)

The first two digits of a full MPAN reflect its profile class. [3]

00Half-hourly supply (import and export)
01Domestic unrestricted
02Domestic Economy meter of two or more rates
03Non-domestic unrestricted
04Non-domestic Economy 7
05Non-domestic, with maximum demand (MD) recording capability and with load factor (LF) less than or equal to 20%
06Non-domestic, with MD recording capability and with LF less than or equal to 30% and greater than 20%
07Non-domestic, with MD recording capability and with LF less than or equal to 40% and greater than 30%
08Non-domestic, with MD recording capability and with LF greater than 40% (also all non-half-hourly export MSIDs)

Profile class 00 supplies are half-hourly (HH) metered, i.e. they record electricity consumption for every half hour of every day, and supplies of the other profile classes are non-half-hourly (NHH) metered. A NHH supply must be upgraded to HH where: [4]

Any Metering System where the average of the maximum monthly electrical demands in the three months of highest demand, either in:

a. the previous twelve months; or
b. the period since the most recent Significant Change of Demand (whichever is the shorter)

exceeds 100kW.

HH data is recorded by the meter and collected by an onsite download, or by remote communication methods such as GSM, SMS, GPRS or telephone line. [2]

Domestic NHH import MPANs always have a profile class of 01 or 02. Domestic NHH export MPANs are allocated a profile class of 08. [3]

Meter Time Switch Code (MTC)

The MTC is a 3 digit code that reflects the various registers a meter may have, such as a single rate, day/night split, or a seasonal time of day. [5] [6]

MTC Ranges
001–399 DNO specific
400–499Reserved
500–509Codes for related Metering Systems – common across the Industry
510–799Codes for related Metering Systems – DNO specific
800–999Codes common across the Industry

Line Loss Factor Class (LLFC)

The Line Loss Factor Class or LLFC [7] is an alphanumeric code used to identify the related Distribution Use of System (DUoS) charges for the MPAN. The figure reflects both the amount of distribution infrastructure used to supply the exit point and the amount of energy lost through heating of cables, transformers, etc. [2]

Core

The MPAN core is the final 13 digits of the MPAN, and uniquely identifies an exit point. It consists of a two-digit Distributor ID, followed by an eight-digit unique identifier, then by two digits and a single check digit.

Distributor ID

Map of DNO licence areas Distribution Network Operators.PNG
Map of DNO licence areas

Great Britain is divided into fourteen distribution areas. For each area a single company, the distribution network operator, has a licence to distribute electricity. [8] They effectively carry electricity from the National Grid to the exit points (each having a unique MPAN and a possibility of several meters) where the customers are. The owner of the distribution network charges electricity suppliers for carrying the electricity in their network. Their DNO licensed regions are the same geographic areas as the former nationalised electricity boards. [8]

DNOs
ID [8] NameOperatorPhone NumberMarket Participant ID [9] GSP Group ID [10]
10Eastern England UK Power Networks 0800 029 4285EELC_A
11East Midlands National Grid (formerly Western Power Distribution)0800 096 3080EMEB_B
12London UK Power Networks 0800 029 4285LOND_C
13Merseyside and Northern Wales SP Energy Networks 0330 10 10 444MANW_D
14West Midlands National Grid (formerly Western Power Distribution)0800 096 3080MIDE_E
15North Eastern England Northern Powergrid 0800 011 3332NEEB_F
16North Western England Electricity North West 0800 048 1820NORW_G
17Northern Scotland Scottish & Southern Electricity Networks 0800 048 3516HYDE_P
18Southern Scotland SP Energy Networks 0330 10 10 444SPOW_N
19South Eastern England UK Power Networks 0800 029 4285SEEB_J
20Southern England Scottish & Southern Electricity Networks 0800 048 3516SOUT_H
21Southern Wales National Grid (formerly Western Power Distribution)0800 096 3080SWAE_K
22South Western England National Grid (formerly Western Power Distribution)0800 096 3080SWEB_L
23Yorkshire Northern Powergrid 0800 011 3332YELG_M

In addition to the distribution network operators noted above who are licensed for a specific geographic area, there are also independent distribution network operators (IDNOs). These own and operate electricity distribution networks which are mostly network extensions connected to the existing distribution network, e.g. to serve new housing developments.

Scottish Hydro Electric Power Distribution also provide distribution services in South Scotland as an IDNO and Southern Electric Power Distribution provide IDNO services in all other England and Wales areas. Other IDNOs have no "base" area. [11]

Independent Distribution Network Operators
ID[ citation needed ]NameLicensee [12] Market Participant Id [9]
24GTCIndependent Power Networks LimitedIPNL
25ESP EnergyESP EnergyLENG
26Energetics / Last MileLast Mile Electricity LimitedGUCL
27GTCThe Electricity Network Company LtdETCL
28EDF IDNOUK Power Networks (IDNO) LtdEDFI (no longer live)
29Harlaxton Energy Networks LtdHARL
30Peel Electricity Networks LtdPENL
31UK Power Distributions LtdUKPD
32Energy Assets NetworksEnergy Assets Networks LtdUDNL
33EPNEclipse Power Networks LtdGGEN
34Murphy Power Distribution LimitedMPDL
35Fulcrum Electricity AssetsFulcrum Electricity Assets LtdFEAL
36Vattenfall NetworksVattenfall Network LimitedVATT
37Forbury Assets LimitedForbury Assets LimitedFORB
38Indigo Power LimitedIndigo Power LimitedINDI
39Squire Energy Metering LtdSquire Energy Metering LtdSTRK
40Utility Assets LimitedUtility Assets LimitedUTAL
42Advanced Electricity NetworksAdvanced Electricity NetworksAENL
43IDCS LtdIDCS LtdIDCS

MPAN state

The supply identified by the MPAN can be in one of four states: disconnected, de-energised, live, and new.

These terms are by no means standardised. For example, a disconnected supply might be referred to as a 'dead' supply.

Export MPANs

The vast majority of MPANs are import MPANs, where energy is being consumed. However, if a supply exports to the distribution network, then an export MPAN is issued. If a supply both imports and exports, then both an import MPAN and export MPAN are issued.

Microgeneration

Formerly, export MPANs required a half-hourly compliant meter to be installed. Since 2003, it has been possible for microgeneration projects, with a capacity of 30 kW or below, to have a non-half-hourly meter to measure export back into the distribution network. Uptake was slow, with the first microgeneration export MPAN being issued in June 2005. Some suppliers may not bother to register the export MPAN in MPAS as the revenue is so small.[ citation needed ]

Following the closure of the feed-in tariffs, in January 2020 Ofgem introduced the Smart Export Guarantee (SEG) arrangements, where an export MPAN is allocated to allow a supplier to pay a customer for export of low-carbon energy. [13] [14]

Export capacity over 30 kW is required to be half-hourly metered. As part of the Marketwide Half Hourly Arrangements (MHHS), all export consumption will be required to be registered and settled on a half-hourly basis.[ citation needed ]

Metered Supply Point

The Metered Supply Point (MSP) is the point at which the meter measuring a customer's consumption is located. It is thus also the point at which either the distribution network operator's supply, or the building network operator's lateral cable, terminates and the customer's equipment begins. In order to firmly establish a supply's MSP, the MPAN needs to be associated with a meter serial number.

Although it is common for an MPAN to be associated with one meter serial number, in some cases there is a many-to-many relationship. For example, one meter could be associated with both an import and an export MPAN, or one MPAN could be measured by three separate meters.

Metering Code of Practice

Code of Practice [15]
CodeRangeConfiguration
COP10less than 72 kWOne HH whole current meter installed. Introduced for February 2009. [16]
COP5less than 1MWOne HH meter installed.
COP31MW to 10MWTwo meters installed, main and check, both recording the same load. The main meter being used for billing.
COP210MW to 100MWTwo meters installed as in COP3, but higher-accuracy class meters.
COP1> 100MWVery few sites in the UK at this level, generally power stations and connections with the National Grid.

Unmetered supplies

It is possible for small predictable supplies to be unmetered. [17] Examples are street lights, traffic signals, signs, bollards, telephone kiosks, CCTV and advertising displays.

For an item of equipment to be connected to the distribution network via an unmetered connection, its consumption should typically not exceed 500 watts and it should operate in a predictable manner, with no provision for it to be manually turned on/off at the end user's request. Generally the equipment would either be in operation and taking a supply of electricity 24 hours a day, or be controlled by a photocell, as is often the case for street lights.

It is the customer's responsibility to maintain an accurate and up-to-date inventory of unmetered supplies, and to inform the UMSO (UnMetered Supplies Operator) of all changes to the connected equipment within one month of the change.

Larger local authorities generally have unmetered supplies with a demand over 100kW and are required to trade their unmetered energy on a half-hourly basis. To do so, they employ a meter administrator [18] [19] who will use daily data from a photo-electric control unit (PECU) array which is then used to calculate the energy consumption. A PECU array is a device that holds a representative number of the photocells that authority uses on their street lights or traffic signals. [20] By trading energy as unmetered half-hourly the authority will accurately pay for the energy consumed by their declared unmetered equipment, and because the data is downloaded daily the authority will see their energy invoices change throughout the year to represent the changes in the seasonal daily lighting levels.

If, however, the unmetered supplies are being traded as non half-hourly the UMSO undertakes the responsibility to calculate an EAC (Estimated Annual Consumption). This is done using a simple formula which takes into account the circuit watts of the equipment and the annual hours of operation. For example, a piece of equipment that is in use 24 hours per day will have annual hours of 8766. For, say, a CCTV camera rated at 24 circuit watts the EAC would be 210.384kWh, calculated as circuit watts × annual hours divided by 1000. As a result of Ofgem's decision to progress with Marketwide Half Hourly Settlement (MHHS) all new unmetered supplies from April 2024 will be half hourly and existing non half-hourly unmetered supplies will move to half hourly trading during 2024.

If the equipment is street lighting the same process is used for non half-hourly; however, the annual hours will change as each photocell is assigned a set number of annual hours which indicate how and when the lights turn on and off. These annual hours have been set by Elexon and are not locally agreed with the UMSO by the customer.

Once an EAC calculation has taken place, an EAC Certificate is provided to the customer's appointed electricity supplier for billing, with an electronic copy of the EAC being sent to the appointed data collector. The DNO make a Distribution Use of System charge on the electricity supplier for the delivery of the electricity to the customer's unmetered equipment.

Standard Settlement Configuration (SSC)

Each non-half-hourly supply has a four digit code called the Standard Settlement Configuration (SSC), which specifies the number of registers a meter has, and the times that each register is recording electricity usage. The times that a register is recording is specified with a five digit code Time Pattern Regime (TPR). So for example a supply with SSC 0943 has two registers with TPRs 00404 and 00405. The 00404 TPR register records from 01:00 to 02:30 and 08:00 to 23:30, and the 00405 register records for the rest of the time. [21]

Meter Point Administration System

Each DNO operates a Meter Point Administration System (MPAS) which holds the following information for each MPAN:

MPRS is the name of the software package that implements the MPAS system for all DNOs. [22] Since MPRS is used by most DNOs it is often used interchangeably with the term MPAS.

ECOES

ECOES (formally the Electricity Central Online Enquiry Service) is now the Electricity Enquiry Service (EES) is a website that allows users and authorised industry parties to search for supply details (past and present) using such things as the 13-digit MPAN bottom line number, the meter serial number or the postcode. The user can determine a wide range of data relating to the supply including the full address, meter details, the current energisation status and also the appointed parties (i.e. the supplier, distributor, MOP, DC and DA). The site is populated from information sent from the supplier regarding the metering system. [23]

Only non-domestic users (with two valid MPANs that are not Profile Class 1 or 2) can register to access this service. [24]

Check digit modulus

Check digit

The final digit in the MPAN is the check digit, and validates the previous 12 (the core) using a modulus 11 test. The check digit is calculated thus:

  1. Multiply the first digit by 3
  2. Multiply the second digit by the next prime number (5)
  3. Repeat this for each digit (missing 11 out on the list of prime numbers for the purposes of this algorithm)
  4. Add up all these products
  5. The check digit is the sum modulo 11 modulo 10. [25]
MPAN verification examples
The algorithm in Java is:
intcheckDigit(StringtoCheck){int[]primes={3,5,7,13,17,19,23,29,31,37,41,43};intsum=0;for(inti=0;i<primes.length;i++){sum+=Character.getNumericValue(toCheck.charAt(i))*primes[i];}returnsum%11%10;}

In Matlab:

functioncheck=checkdigits(MPANCore)% MPANCore is a cell array of 13 digit strings.% Check is a boolean vector the same size as MPANCore.% (100,000 MPANs in 0.05 seconds.)core=double(char(MPANCore)')-48;c=core(1:12,:);p=[357131719232931374143]'*ones(1,size(c,2));m=mod(mod(sum(p.*c),11),10);k=core(13,:);check=m==k;

In Pascal / Delphi:

functionCheckDigit(MPANCore:arrayofByte):Integer;constPrimes:array[0..11]ofByte=(3,5,7,13,17,19,23,29,31,37,41,43);vari:integer;beginResult:=0;fori:=0to11doResult:=Result+(MPANCore[i]*Primes[i]);Result:=Resultmod11mod10;end;

In Ruby:

# where mpan is a stringdefcheck_digit(mpan)primes=[3,5,7,13,17,19,23,29,31,37,41,43](0..11).inject(0){|sum,n|sum+(mpan[n,1].to_i*primes[n])}%11%10end

In Visual Basic:

PublicFunctionmpancheck(mpanAsString)AsBoolean' Michael Diarmid (EDF)' Updated 04/08/2010 MD' Returns True / False if MPAN is validOnErrorGoToinvalDimcAsVariant,sumAsInteger,iasBytec=Array(0,3,5,7,13,17,19,23,29,31,37,41,43)Fori=1To12sum=sum+(Mid(mpan,i,1)*c(i))NextiIfRight(mpan,1)=((sumMod11)Mod10)Thenmpancheck=TrueElseinval:mpancheck=FalseEndIfEndFunction

In VisualBasic.Net 2010:

PublicFunctionmpancheck(mpanAsString)AsBoolean' Michael Diarmid (EDF)' Updated 04/08/2010 MD' Returns True / False if MPAN is valid' Revised by Tym Huckin (16/03/2012) for VB 2010OnErrorGoToinvalDimcAsObject,sumAsIntegerc=NewList(OfInteger)From{0,3,5,7,13,17,19,23,29,31,37,41,43}Fori=1To12sum=sum+(Mid(mpan,i,1)*c(i))NextiIfsRight(mpan,1)=((sumMod11)Mod10)ThenReturnTrueElseinval:ReturnFalseEndIfEndFunctionPublicFunctionsRight(sSTRINGAsString,iLENAsInteger)AsStringDimsRETAsString=""TryIfiLEN>=Len(sSTRING)ThensRET=sSTRINGEndIfsRET=Mid(sSTRING,Len(sSTRING)-(iLEN-1),iLEN)CatchexAsExceptionsRET=""EndTryReturnsRETEndFunction

Or VB.Net 2010, avoiding the use of VB6 Compatibility Library :

''' <summary>''' Validates an MPAN number''' </summary>''' <param name="mpan">At least the last 13 digits from the MPAN number, including the check digit, ''' expressed as a string</param>''' <returns>True for valid, otherwise false</returns>''' <remarks>Written by Martin Milan, May 2012, avoiding use of VB6 compatibility library, for .Net 4.0 Client Profile</remarks>PublicFunctionMPANIsValid(mpanAsString)AsBoolean' Set initial conditions.DimvalidationResultAsBoolean=FalseIfmpan.Length>12Then'Read the check digit into an Integer variable.DimintCheckDigitAsIntegerIfInteger.TryParse(mpan.Substring(mpan.Length-1),intCheckDigit)ThenDimstrTestAsString=mpan.Substring(mpan.Length-13,12)DimintPrimes()AsInteger={3,5,7,13,17,19,23,29,31,37,41,43}DimproductTotalAsInteger=0DimblnErrorAsBoolean=FalseForiAsInteger=0To11Step1DimintTestDigitAsIntegerIfInteger.TryParse(mpan.Substring(i,1),intTestDigit)ThenproductTotal+=(intTestDigit*intPrimes(i))ElseblnError=TrueExitForEndIfNextIfNotblnErrorThenvalidationResult=((productTotalMod11Mod10)=intCheckDigit)ElsevalidationResult=False' Due to a parsing error.    EndIfEndIfEndIfReturnvalidationResultEndFunction

In C#:

/// <summary>/// Validates an MPAN number./// </summary>/// <param name="mpan">At least the last 13 digits from the MPAN number, including the check digit, /// expressed as a string.</param>/// <returns>True for valid, otherwise false.</returns>publicstaticboolMpanIsValid(stringmpan){// Set initial conditions.boolvalidationResult=false;if(mpan.Length>12){// Read the check digit into an Integer variable.intintCheckDigit=0;if(int.TryParse(mpan.Substring(mpan.Length-1),outintCheckDigit)){stringstrTest=mpan.Substring(mpan.Length-13,12);int[]intPrimes={3,5,7,13,17,19,23,29,31,37,41,43};intproductTotal=0;boolblnError=false;for(inti=0;i<=11;i++){intintTestDigit=0;if(int.TryParse(strTest.Substring(i,1),outintTestDigit)){productTotal+=(intTestDigit*intPrimes[i]);}else{blnError=true;break;}}if(!blnError){validationResult=((productTotal%11%10)==intCheckDigit);}else{validationResult=false;// Due to a parsing error.    }}}returnvalidationResult;}

As a formula in Excel 365:

'MPAN in Cell A1=IF(RIGHT(MOD(SUM(MID(A1,SEQUENCE(12),1)*{3;5;7;13;17;19;23;29;31;37;41;43}),11))=RIGHT(A1),"Correct","Invalid MPAN")

In Python:

defcheck_digit(mpan):"""Check MPAN digit.    Args:      mpan -- The first 12 digits of the MPAN number, excluding the check digit.    """returnsum(prime*int(digit)forprime,digitin \             zip([3,5,7,13,17,19,23,29,31,37,41,43],mpan))%11%10

In PL/SQL:

createorreplacefunctionmpan_check(mpaninvarchar2)returnbooleanis--CDP ATKINSONresinteger:=0;TYPEprime_tabISVARRAY(12)OFinteger;primesprime_tab:=prime_tab(3,5,7,13,17,19,23,29,31,37,41,43);beginforiin1..12loopres:=res+to_number(substr(mpan,i,1))*primes(i);endloop;returnto_char(mod(mod(res,11),10))=substr(mpan,13,1);endmpan_check;

In JavaScript:

functioncheckMPAN(mpan){varprimes=[3,5,7,13,17,19,23,29,31,37,41,43];varsum=0;varm=mpan.toString();if(m.length-1===primes.length){for(vari=0;i<primes.length;i++){sum+=parseInt(m.charAt(i))*primes[i];}returnsum%11%10===parseInt(m.charAt(12));}returnfalse;}

In PHP:

functioncheckMPAN($mpan){$primes=array(3,5,7,13,17,19,23,29,31,37,41,43);$sum=0;$mpan=str_split($mpan);if((count($mpan)-1)==count($primes)){for($i=0;$i<count($primes);$i++){$sum+=$mpan[$i]*$primes[$i];}return(($sum%11%10)==end($mpan))?true:false;}else{returnfalse;}}

In SQL Server:

CREATEFUNCTIONis_valid_mpan(@mpanVARCHAR(50))RETURNSINTASBEGIN--TimFoster(2013-01-04)DECLARE@is_mpanINT,@xINT=1,@sumINT=0DECLARE@arrTABLE(idINTIDENTITY(1,1),valINT)INSERTINTO@arr(val)VALUES(3),(5),(7),(13),(17),(19),(23),(29),(31),(37),(41),(43)WHILE@x<=12BEGINSELECT@sum=@sum+(SUBSTRING(@mpan,@x,1)*val)FROM@arrWHEREid=@xSELECT@x=@x+1ENDIFRIGHT(@mpan,1)=((@sum%11)%10)BEGINSELECT@is_mpan=1ENDELSEBEGINSELECT@is_mpan=0ENDRETURN@is_mpanEND

In MySQL:

CREATEDEFINER=`root`@`%`FUNCTION`is_valid_mpan`(mpanvarchar(13))RETURNSint(11)beginDECLAREis_mpanINT;DECLARExINT;DECLAREsumINT;declareretint;setx=1;setsum=0;CREATETEMPORARYTABLEIFNOTEXISTSarrSELECT1`id`,3`val`unionallSELECT2`id`,5`val`unionallSELECT3`id`,7`val`unionallSELECT4`id`,13`val`unionallSELECT5`id`,17`val`unionallSELECT6`id`,19`val`unionallSELECT7`id`,23`val`unionallSELECT8`id`,29`val`unionallSELECT9`id`,31`val`unionallSELECT10`id`,37`val`unionallSELECT11`id`,41`val`unionallSELECT12`id`,43`val`;WHILEx<=12DOSELECT(SUBSTRING(mpan,x,1)*val)intoretFROMarrWHEREid=x;setsum=sum+ret;setx=x+1;ENDwhile;IFRIGHT(mpan,1)=((sum%11)%10)thensetis_mpan=1;ELSEsetis_mpan=0;endif;dropTEMPORARYtablearr;RETURNis_mpan;end;

In Swift 3 is:

funcisValid(mpan:String)->Bool{letprimes=[3,5,7,13,17,19,23,29,31,37,41,43]letchars=Array(mpan.characters).map({Int(String($0))}).flatMap({$0})returnzip(primes,chars).reduce(0){$0+$1.0*$1.1}%11%10==chars.last!}

In Apex (Salesforce):

/**    * @description Validates an MPAN. Written by Adam Dry June 2018. Apex version 43    * @param mpan the 13 digit MPAN including the check digit on the end    */publicBooleanmpanIsValid(Stringmpan){List<Integer>primes=newList<Integer>{3,5,7,13,17,19,23,29,31,37,41,43};// Read the check digit into an Integer variableIntegercheckDigit=Integer.valueOf(mpan.right(1));StringstrTest=mpan.substring(0,12);IntegerproductTotal=0;for(Integeri=0;i<=11;i++){IntegertestDigit=Integer.valueOf(strTest.Substring(i,i+1));productTotal+=(testDigit*primes[i]);}IntegercomputedCheck=Math.mod(Math.mod(productTotal,11),10);BooleanvalidationResult=(computedCheck==checkDigit);returnvalidationResult;}

See also

Related Research Articles

Electricity retailing is the final sale of electricity from generation to the end-use consumer. This is the fourth major step in the electricity delivery process, which also includes generation, transmission and distribution.

<span class="mw-page-title-main">Scottish Power</span> British energy company

Scottish Power Limited is a vertically integrated energy company based in Glasgow, Scotland. It is a subsidiary of Spanish utility firm Iberdrola.

<span class="mw-page-title-main">National Grid (Great Britain)</span> High-voltage electric power transmission network in Great Britain

The National Grid is the high-voltage electric power transmission network serving Great Britain, connecting power stations and major substations, and ensuring that electricity generated anywhere on the grid can be used to satisfy demand elsewhere. The network serves the majority of Great Britain and some of the surrounding islands. It does not cover Northern Ireland, which is part of the Irish single electricity market.

<span class="mw-page-title-main">Electricity meter</span> Device used to measure electricity use

An electricity meter, electric meter, electrical meter, energy meter, or kilowatt-hour meter is a device that measures the amount of electric energy consumed by a residence, a business, or an electrically powered device.

<span class="mw-page-title-main">Office of Gas and Electricity Markets</span> United Kingdom government non-ministerial department

The Office of Gas and Electricity Markets (Ofgem), supporting the Gas and Electricity Markets Authority, is the government regulator for the electricity and downstream natural gas markets in Great Britain. It was formed by the merger of the Office of Electricity Regulation (OFFER) and Office of Gas Supply (Ofgas).

<span class="mw-page-title-main">Radio teleswitch</span> Electric grid operating device

A radio teleswitch is a device used in the United Kingdom primarily to allow electricity suppliers to switch large numbers of electricity meters between different tariff rates, by broadcasting an embedded signal in broadcast radio signals. Radio teleswitches are also used to switch on/off consumer appliances to make use of cheaper differential tariffs such as Economy 7.

<span class="mw-page-title-main">Load profile</span> Graph of the variation in the electrical load versus time

In electrical engineering, a load profile is a graph of the variation in the electrical load versus time. A load profile will vary according to customer type, temperature and holiday seasons. Power producers use this information to plan how much electricity they will need to make available at any given time. Teletraffic engineering uses a similar load curve.

E.ON UK is a British energy company and one of the largest suppliers of energy in the UK, following its acquisition of Npower. It is a subsidiary of E.ON of Germany and one of the Big Six energy suppliers. It was founded in 1989 as Powergen, and was listed on the London Stock Exchange and was once a constituent of the FTSE 100 Index. It has been a subsidiary of E.ON since 1 July 2002.

Southern Electric plc was a public limited energy company in the United Kingdom between 1990 and 1998, when it merged with Scottish Hydro-Electric plc to form Scottish and Southern Energy plc. The company had its origins in the southern England region of the British nationalised electricity industry. Created in 1948 as the Southern Electricity Board, in 1990 it was privatised by being floated on the London Stock Exchange.

A distribution network operator (DNO), also known as a distribution system operator (DSO), is the operator of the electric power distribution system which delivers electricity to most end users. Each country may have many local distribution network operators, which are separate from the transmission system operator.

<span class="mw-page-title-main">British Gas</span> Energy and home services provider in the United Kingdom

British Gas is an energy and home services provider in the United Kingdom. It is the trading name of British Gas Services Limited and British Gas New Heating Limited, both subsidiaries of Centrica. Serving around twelve million homes in the United Kingdom, British Gas is the biggest energy supplier in the country, and is considered one of the Big Six dominating the gas and electricity market in the United Kingdom. Their lines are open from 8am to 5pm on weekdays, and 9am to 6pm on weekends.

Economy 10 is the name of a tariff provided by United Kingdom electricity suppliers created in 2004. Similar to Economy 7 this is designed to be used with high thermal mass heating such as storage heaters, underfloor heating, and is also used with electrical boilers driving radiators or water-based heat stores.

<span class="mw-page-title-main">Green electricity in the United Kingdom</span>

The availability and uptake of green electricity in the United Kingdom has increased in the 21st century. There are a number of suppliers offering green electricity in the United Kingdom. In theory these types of tariffs help to lower carbon dioxide emissions by increasing consumer demand for green electricity and encouraging more renewable energy plant to be built. Since Ofgem's 2014 regulations there are now set criteria defining what can be classified as a green source product. As well as holding sufficient guarantee of origin certificates to cover the electricity sold to consumers, suppliers are also required to show additionality by contributing to wider environmental and low carbon funds.

In the United Kingdom, an electricity supplier is a retailer of electricity. For each supply point the supplier has to pay the various costs of transmission, distribution, meter operation, data collection, tax etc. The supplier then adds in energy costs and the supplier's own charge. Regulation of the charging of customers is covered by the industry regulator Ofgem.

A meter operator in the UK energy industry is an organization responsible for installing and maintaining electricity and gas meters. Since 1998 there has been full competition for meter operators, allowing the meter operator for a particular supply to be contracted with the energy supplier by either the supplier's discretion or at the customer's direction. Consumption data from the installed metering is then collected by the appointed data collector to be submitted for billing.

In the UK electricity system, a data collector (DC) is responsible for determining the amount of electricity supplied so that the customer can be correctly billed.

Electricity North West Limited is a British electricity distribution network operator, responsible for the administration and maintenance of the network, that distributes electricity to the North West of England excluding Merseyside and parts of Cheshire.

<span class="mw-page-title-main">UK Power Networks</span>

UK Power Networks (UKPN) is a distribution network operator for electricity covering South East England, the East of England and London. It manages three licensed distribution networks which together cover an area of 30000 square kilometres and approximately eight million customers.

The Big Six were the United Kingdom's largest retail suppliers of gas and electricity, who dominated the market following liberalisation in the late 1990s. By 2002, six companies – British Gas, EDF Energy, E.ON, RWE npower, Scottish Power and SSE – had emerged from the 15 former incumbent monopoly suppliers.

Scottish and Southern Electricity Networks is one of two energy companies in the UK to be involved both in electricity transmission and distribution.

References

  1. 1 2 Elexon. "Settlement of Microgeneration Export" (PDF). Archived from the original (PDF) on 9 October 2007.
  2. 1 2 3 Energy Linx (2007). "MPAN (Meter Point Administration Number)" . Retrieved 22 February 2007.
  3. 1 2 Elexon. "BSCP516 – Balancing and Settlement Code" (PDF). Archived from the original (PDF) on 19 March 2012. Retrieved 25 July 2011.
  4. Elexon (25 June 2015). "Change of Measurement Class and Change of Profile Class" (PDF). Archived from the original (PDF) on 17 August 2016. Retrieved 5 July 2016.
  5. MRASCo. "The Rough Guide To MTCs" (PDF). Archived from the original (PDF) on 13 January 2016. Retrieved 5 February 2011.
  6. Elexon. "Meter Timeswitch Class table". Archived from the original on 26 April 2011. Retrieved 23 August 2011.
  7. "Line Loss Factor Class(es)". Elexon Glossary. Retrieved 27 January 2013.
  8. 1 2 3 "MPAN (Meter Point Administration Number)". Energylinx. Retrieved 23 October 2023.
  9. 1 2 Elexon. "Market Participant Role" . Retrieved 20 December 2009.[ dead link ]
  10. Elexon. "GSP Group" . Retrieved 22 June 2010.[ dead link ]
  11. Ofgem. "Notice under section 11 of the Electricity Act 1989" (PDF). Archived from the original (PDF) on 30 December 2005. Retrieved 22 February 2007.
  12. Ofgem. "List of all electricity licensees including suppliers" . Retrieved 21 September 2021.
  13. "Smart Export Guarantee (SEG)". Ofgem. Retrieved 4 March 2022.
  14. "Smart Export Guarantee (SEG) Terms and Conditions" (PDF). OVO Energy. 23 December 2019. Retrieved 4 March 2022.
  15. See "ELEXON - Codes of Practice". Archived from the original on 13 August 2007. Retrieved 16 November 2008.
  16. "Change Implementation".[ dead link ]
  17. "Unmetered Supplies". ELEXON. Retrieved 3 January 2019.
  18. Power Data Associates Ltd. "Meter Administrator".
  19. ICTIS (UK) Ltd. "Meter Administrator".
  20. "Photo Electric Control Unit Arrays". Power Data Associates. Retrieved 4 March 2022.
  21. Elexon (12 December 2011). "What are Standard Settlement Configurations?" . Retrieved 5 July 2016.
  22. St. Clements Services Ltd. "Metering Point Registration System" . Retrieved 29 May 2008.
  23. MRASCO. "Access to ECOES Data" . Retrieved 11 July 2009.
  24. "Briefing_Note_on_Customer_Access_NDC_2" (PDF). ECOES. MRASCO. Retrieved 25 June 2015.
  25. Energy Retail Association. "Data Item Definition v1 final" (PDF). p. 23. Archived from the original (PDF) on 25 September 2007. Retrieved 25 February 2014.