Simhadri Super Thermal Power Station

Last updated

Simhadri Super Thermal Power Plant
N.T.P.C Simhadri Super Thermal PowerPlant.jpg
View of NTPC Simhadri Super thermal power plant
Simhadri Super Thermal Power Station
CountryIndia
Location Visakhapatnam, Andhra Pradesh
Coordinates 17°35′38″N83°05′23″E / 17.5938°N 83.0897°E / 17.5938; 83.0897
StatusOperational
Commission date 2002
Owner NTPC
Thermal power station
Primary fuel Coal
Power generation
Units operational4 X 500 MW
Nameplate capacity 2,000 MW
External links
Commons Related media on Commons

Simhadri Super Thermal Power Plant is a coal-fired power plant located in the outskirts of Visakhapatnam city in the Indian state of Andhra Pradesh. [1] The power plant is one of the coal fired power plants of NTPC, a Government of India enterprise. The coal for the power plant is sourced from Kalinga Block of Talcher Coal fields in Odisha. The plant is a national asset, and power generated is shared between multiple states, as the operator is national. Power generated by units 1 and 2, making up for 1,000 MW, is dedicated to power distribution companies owned by the Government of Andhra Pradesh and Telangana. The remaining 1,000 MW, generated by units 3 and 4, is allocated to the states of Odisha, Tamil Nadu, Karnataka, Andhra Pradesh, Telangana and Puducherry as per their shares as decided in PPA.

Contents

NTPC Simhadri is a modern coal-fired power plant, and is a combination of four independent generation units, with common water and fuel sources, and common ash ponds. Each of the four units has a nameplate capacity of 500 MW. Units 1 and 2 were built in the first phase of development, and were commissioned in February 2002 and August 2004, respectively, to meet urgent needs of power in the largely agrarian Coastal Andhra and North-Coastal Andhra regions. Units 3 and 4 were built in the second phase, and commissioned in March 2011 and March 2012, respectively. Since the operator of this plant is a Government of India enterprise, and since the plant was built with central government funds, power generated by units 3 and 4 are sold to distribution companies based in neighbouring states of Odisha, Tamil Nadu, and Karnataka, over the National Grid, as power stocks. The allocations are decided between NTPC and the three states' discoms. Unsold units are offered to discoms of Andhra Pradesh for purchase at market prices.

Coal for NTPC Simhadri is sourced from Talcher Coal Fields, Odisha, and transported by East Coast Railway (ECoR), over the Kolkata-Chennai trunk line, with a spur heading towards the plant at Duvvada. Unlike other coal-fired plants located in the Indian hinterlands, which use water of the same kind as working fluid and coolant, NTPC Simhadri, which operates out of a fresh water-deficient region of Andhra Pradesh, diversified its water sourcing, based on usage. It uses fresh water sourced from the Yeluru Canal as working fluid (steam which turns the turbines). For cooling, however, the plant uses seawater pumped in from the Bay of Bengal. Seawater, with its salt content, is unfit to be used as working fluid, without desalination.

Environment Protection Activities in NTPC Simhadri

Committed to producing Green Power, the Simhadri Super Thermal Power Station (2X500 MW in Stage-I & 2X500 MW in Stage-II) is the first coastal coal fired thermal power station of NTPC Limited. Simhadri Plant meets more than 85% of its water needs from sea, thereby contributing to the nation's efforts in conserving fresh water. Having spent nearly Rs. 1000 Cr towards various equipments and systems for mitigating pollution and protecting environment, NTPC Simhadri planted over 7.0 lakh trees for protection of environment. Besides, NTPC Simhadri is also a proud partner of "Green Visakha" Project and has planted 3.5 lakh trees additionally under this program and distributed 1.25 lakh fruit bearing plants. NTPC also contributed Rs. 6.0 Cr towards conservation of Olive Ridley turtles. Furthermore, the Power Station and Township premises are declared as plastic free zones. The Journey continues for adopting the latest environment norms leading to a World Class Power Plant.

Related Research Articles

<span class="mw-page-title-main">NLC India Limited</span> Central Public Sector Undertaking

NLC India Limited (NLC) is a central public sector undertaking under the administrative control of the Ministry of Coal, Government of India. It annually produces about 30 million tonnes of lignite from opencast mines at Neyveli in the state of Tamil Nadu in southern India and at Barsingsar in Bikaner district of Rajasthan state. The lignite is used at pithead thermal power stations of 3640 MW installed capacity to produce electricity. Its joint venture has a 1000 MW thermal power station using coal. Lately, it has diversified into renewable energy production and installed 1404 MW solar power plant to produce electricity from photovoltaic (PV) cells and 51 MW electricity from windmills.

<span class="mw-page-title-main">Talcher</span> City in Odisha, India

Talcher, known as the "City Of Black Diamond" in Odisha, is a major industrial coal city and municipality. Talcher is one of the 4 sub-divisions of Angul district in the Indian state of Odisha.

<span class="mw-page-title-main">NTPC Dadri</span> Thermal power plant in Dadri, India

National Capital Power Station (NCPS) or NTPC Dadri is the power project to meet the power demand of National Capital Region (India). It has a huge coal-fired thermal power plant and a gas-fired plant and has a small township located in Uttar Pradesh, India for its employees. It is located in Gautam Budhh Nagar district of Uttar Pradesh about 25 km from Ghaziabad and about 9 km from Dadri. It is nearly 48 km from New Delhi towards Hapur. The township has an area of about 500 acres over all. NTPC Dadri is a branch of National Thermal Power Corporation (NTPC).

<span class="mw-page-title-main">Andhra Pradesh Power Generation Corporation Limited</span>

Andhra Pradesh Power Generation Corporation Limited is power generating organization in Andhra Pradesh. It undertakes operation and maintenance of the power plants and also setting up new power projects alongside upgrading the project's capacity, under the recommendations of Hittenbhayya committee setup by TDP Govt.

<span class="mw-page-title-main">NTPC Ramagundam</span> Coal-fired power plant in India

NTPC Ramagundam, a part of National Thermal Power Corporation, is a 2,600 megawatt (MW) Super thermal power station situated at Ramagundam in Peddapalli district in Telangana, India. It is the current largest power station in South India. It is the first ISO 14001 certified "Super Thermal Power Station" in India.

<span class="mw-page-title-main">Singrauli Super Thermal Power Station</span> Coal-fired power station in Uttar Pradesh

Singrauli Super Thermal Power Plant is located at Shaktinagar in Sonebhadra district in Indian state of Uttar Pradesh. The power plant is the first power plant of NTPC. It sources coal from Jayant and Bina mines and water from Rihand Reservoir. The states benefitting from this power plant are Uttar Pradesh, Uttarakhand, Rajasthan, Punjab, Haryana and Himachal Pradesh and the Union Territories of Delhi, Chandigarh and Jammu and Kashmir. An investment worth 11,907 million (US$140 million) has already been cleared. It even gets international assistance from IDA.

<span class="mw-page-title-main">Rihand Thermal Power Station</span> Coal power plant in Uttar Pradesh, India

Rihand Super Thermal Power Project is located at Renukut, Sonebhadra in Sonbhadra district in Indian state of Uttar Pradesh. The power plant is one of the coal based power plants of NTPC Limited.

Feroze Gandhi Unchahar Thermal Power Plant is located at Unchahar in Raebareli district in Indian state of Uttar Pradesh. The power plant is one of the coal based power plants of NTPC Limited. In the year 1992, Uttar Pradesh State Electricity Board (U.P.S.E.B.) transferred Unchahar Thermal Power Station to NTPC Limited against payment overdue and later on renamed it to Feroze Gandhi Unchahar Thermal Power Plant by NTPC Limited.

<span class="mw-page-title-main">NTPC Limited</span> This page is about Maharatna PSU in India

NTPC Limited, formerly known as National Thermal Power Corporation, is an Indian central Public Sector Undertaking (PSU) under the ownership of the Ministry of Power and the Government of India, who is engaged in the generation of electricity and other activities. The headquarters of the PSU are situated at New Delhi. NTPC's core function is the generation and distribution of electricity to State Electricity Boards in India. The body also undertakes consultancy and turnkey project contracts that involve engineering, project management, construction management, and operation and management of power plants.

<span class="mw-page-title-main">Vindhyachal Thermal Power Station</span> Coal-fired power plant in Madhya Pradesh, India

The Vindhyachal Thermal Power Station is located in Singrauli district in the Indian state of Madhya Pradesh. One of the coal-fired power stations of NTPC, it is the largest power station in India, and the 10th largest coal-fired power station in the world, with an installed capacity of 4,760 MW. The coal for the power plant is sourced from the Nigahi mines, and the water is sourced from the discharge canal of the Singrauli Super Thermal Power Station. The power plant is estimated to have been the coal-fired power plant which emitted the second most carbon dioxide in 2018, after Bełchatów Power Station, at 33.9 million tons, and relative emissions are estimated at 1.485 kg per kWh.

<span class="mw-page-title-main">Kahalgaon Super Thermal Power Station</span> Indian coal power plant

Kahalgaon Super Thermal Power Station (KhSTPP)is located in Kahalgaon in Bhagalpur district of Bihar. The power plant is one of the coal based power plants of NTPC. The coal for the power plant is sourced from Rajmahal coalfield of Eastern Coalfields Limited. Source of water for the power plant is Ganga River.

<span class="mw-page-title-main">Talcher Thermal Power Station</span>

Talcher Thermal Power station is located in Talcher sub-division of Angul district in the Indian state of Odisha Pin.759101. The existing plant was closed on 31 March 2021 with the plans to set up a new plant still in discussion phase. The power plant is one of the coal-based plants of NTPC. The coal for the power plant is sourced from Jagannath Mines of Mahanadi Coalfields Limited. Source of water for the plant is from Brahmani River. It has its own railway station and is well connected to three other important stations in close vicinity: Talcher Road, Angul and Talcher Stations. This power plant has been ranked among the best power plants in the country despite being the oldest plant in the state. It has consistently topped the charts in NTPC for the last four years and was also the nation's top power plant in 2015-16.

Talcher Super Thermal Power Station or NTPC Talcher Kaniha located in Angul district of the Indian state of Odisha is the first mega power plant of India to have an installed generation capacity of 3000MW. The power plant is one of the coal-based power plants of NTPC. The coal for the power plant is sourced from Lingraj Block & Kaniha coal block of Mahanadi Coalfields Ltd. Source of water for the power plant is from Samal Barrage Reservoir on Brahmani River.

Sri Damodaram Sanjeevaiah Thermal Power Station is located in Nelatur Village, near Krishnapatnam and at a distance of 23 km from Nellore city of Andhra Pradesh. The power plant is one of the coal-based power plants of Andhra Pradesh Power Development Company Limited (APPDCL). It is the Special Purpose Vehicle (SPV), a joint venture company of APGENCO and IL AND FS partnership.

<span class="mw-page-title-main">Jharsuguda–Vizianagaram line</span> Railway line in India

The Jharsuguda–Vizianagaram line is a railway line in eastern India. It connects Jharsuguda,516 km (321 mi) from Howrah on the Howrah–Nagpur–Mumbai line, and Titlagarh, which in turn is connected with Vizianagaram, 820 km (510 mi) from Howrah on the Howrah–Chennai main line, and Raipur Junction, 830 km (516 mi) from Howrah on the Howrah–Nagpur–Mumbai line. There are several branch lines, like the 176 km (109 mi) line connecting Rayagada with Koraput on the Kothavalasa–Kirandul line. The line traverses Western Odisha and connects the Howrah–Nagpur–Mumbai line with the Howrah–Chennai main line. It covers small portions of Chhattisgarh and Andhra Pradesh.

<span class="mw-page-title-main">Vallur Thermal Power Station</span> Coal-fired power station in Tamil Nadu

Vallur Thermal Power Station is a power plant located in Vallur, Thiruvallur district, India. The power plant is operated by NTPC Tamil Nadu Energy Company Limited, a joint venture between NTPC Limited and TANGEDCO and has three units with 500 MW each.

<span class="mw-page-title-main">Economy of Visakhapatnam</span>

Visakhapatnam is the largest city of Andhra Pradesh. Visakhapatnam has a GDP of $43.5 billion. It is the 9th richest city in India. Fishing industry, road–rail connectivity, many heavy industries like Hindustan Petroleum, Visakhapatnam Steel Plant, Hindustan Shipyard, Visakhapatnam Port Trust, National Thermal Power, Bharat Heavy Electricals, BARC, Naval Science and Technological Laboratory, Naval Dockyard, Dredging Corporation of India, Strategic Petroleum Reserve, NMDC, CONCOR, Andhra Pradesh Medtech Zone etc..

<span class="mw-page-title-main">Power sector of Andhra Pradesh</span>

Power sector of Andhra Pradesh is divided into 4 categories namely Regulation, Generation, Transmission and Distribution. Andhra Pradesh Electricity Regulatory Commission (APERC) is the regulatory body. APGENCO deals with the electricity production and also maintenance, proposes new projects and upgrades existing ones as well. The APGENCO also set up a Special Purpose Vehicle (SPV), named as Andhra Pradesh Power Development Company Limited (APPDCL), a joint venture company of APGENCO and IL&FS to set up Krishnapatanam thermal power project.

The Nabinagar Thermal Power Station Project (NTPS) of Bhartiya Rail Bijlee Company Limited is a wholly owned subsidiary of the Indian Railways, Ministry of Railways, Government of India. It installs a 4X 250 MW thermal power plant at Nabinagar in Aurangabad district, Bihar, India. Nearly 90 per cent of the electricity generated from the plant is supplied to the railways to meet nationwide requirements and remaining 10 per cent is given to Bihar.

References