| Gadarwara Super Thermal Power Station | |
|---|---|
| NTPC Gadarwara Thermal Power Plant | |
| Official name | Gadarwara Super Thermal Power Station |
| Country | India |
| Location | Gadarwara, Narsinghpur district, Madhya Pradesh |
| Coordinates | 22°51′22″N78°51′24″E / 22.85611°N 78.85667°E |
| Status | Operational (Stage-I); Stage-II Approved |
| Construction began | 2014 |
| Commission date | 2019–2021 |
| Operator | NTPC Limited |
| Thermal power station | |
| Primary fuel | Coal |
| Turbine technology | Supercritical |
| Power generation | |
| Units operational | 2 × 800 MW |
| Units planned | 2 × 800 MW (Stage-II) |
| Nameplate capacity | 1,600 MW (operational) |
| External links | |
| Website | www |
| |
Gadarwara Super Thermal Power Station is a coal-based thermal power station located near Gangai village in Gadarwara tehsil of Narsinghpur district in the Indian state of Madhya Pradesh. [1] The power station is owned and operated by NTPC Limited, India's largest power generation utility. [2] With a planned ultimate capacity of 3,200 MW (4×800 MW), it is one of the major supercritical thermal power projects in central India. [3]
As of 2024, Stage-I of the project, comprising two units of 800 MW each (total 1,600 MW), is fully operational and in commercial operation. [4] Stage-II, consisting of an additional two units of 800 MW each, received investment approval from the NTPC Board in November 2024. [5]
The Gadarwara Super Thermal Power Project was conceived as part of NTPC's expansion plan during India's 12th Five-Year Plan period to add over 14,000 MW of capacity. [6] The project received environmental clearance from the Ministry of Environment, Forest and Climate Change (MoEFCC) on 22 March 2013. [7]
The foundation stone for the project was laid in February 2014 with an initial cost estimate of approximately ₹25,000 crore (US$3.4 billion). [8] NTPC awarded the EPC contract to Bharat Heavy Electricals Limited (BHEL) for the execution of Stage-I of the project. [9]
The first unit (800 MW) achieved grid synchronization on 30 August 2018 at 05:12 AM IST, marking a significant milestone in the project's development. [9] The unit was declared in commercial operation on 30 April 2019, with the revised cost estimate for Stage-I finalized at ₹15,105.22 crore. [1]
The second unit (800 MW) was included in the installed capacity on 18 February 2021 and declared in commercial operation on 1 March 2021. [4] With the commissioning of both units, NTPC's commercial capacity reached 52,115 MW, and the NTPC Group's total capacity reached 64,880 MW as of March 2021. [4]
The Stage-II expansion (2×800 MW) received investment approval of ₹20,445.69 crore from the NTPC Board on 5 November 2024. [5] The expansion was initially proposed to the Expert Appraisal Committee (EAC) in March 2024 but required additional environmental information. [10] A revised proposal was submitted in August 2024, and tendering for the project commenced in early 2025. [3]
The Gadarwara Super Thermal Power Station employs supercritical technology, which operates at higher pressures and temperatures compared to conventional subcritical plants. [11] This technology results in improved thermal efficiency of approximately 38–40% and reduced greenhouse gas emissions per unit of electricity generated. [12]
BHEL's comprehensive scope for Stage-I included the design, engineering, manufacturing, supply, erection, and commissioning of major equipment including: [9]
The equipment was manufactured at various BHEL facilities across India, including Trichy (boilers), Haridwar (turbines), Bhopal (auxiliaries), Ranipet (transformers), Hyderabad (control systems), and Jhansi (boiler auxiliaries). [11]
The plant is designed to operate at a Plant Load Factor (PLF) of 90%, ensuring high availability and efficient power generation. [1] Both operational units utilize advanced emission control systems to meet India's stringent environmental norms. [13]
The project is being developed in two stages:
| Stage | Unit Number | Capacity (MW) | Date of Commercial Operation | Status |
|---|---|---|---|---|
| Stage-I | 1 | 800 | 30 April 2019 [1] | Operational |
| 2 | 800 | 1 March 2021 [4] | Operational | |
| Stage-II | 3 | 800 | TBD | Approved (under development) [5] |
| 4 | 800 | TBD | Approved (under development) [5] | |
| Total Capacity | 3,200 | |||
The primary fuel source for the power station is coal from the Talaipalli coal block located in Chhattisgarh. [7] The plant requires approximately 8 million tonnes per annum (MTPA) of coal at 90% PLF for its ultimate capacity. [10] The Talaipalli coal block has received environment and forest clearances for coal mining operations. [14]
Water for the power station is sourced from the Narmada River, located approximately 30 kilometers from the project site. [6] A dedicated pipeline has been laid from the river to the plant site. [1] The Madhya Pradesh Water Resources Department constructed a small weir on the river to ensure adequate water supply without causing submergence of agricultural lands. [7]
According to the Environmental Clearance dated 22 March 2013, the total land requirement for the project is 1,990 acres (approximately 805 hectares). [7] As of 2024, a total of 2,250.40 acres (910.706 hectares) has been acquired for the project. [10]
The land acquisition comprised: [15]
The land acquisition affected six villages in the Gadarwara region: [6]
Approximately 500 farmers from these villages were affected by the land acquisition process. [15]
The project has faced significant opposition from local farmers since land acquisition began in 2013. [6] Major protests erupted in December 2017, with farmers alleging broken promises regarding employment opportunities made during the land acquisition phase. [6]
On 12 January 2018, farmers held protests and submitted a memorandum demanding jobs for displaced families. [6] Protests continued for over 15 days, with a massive agitation planned for New Delhi on 23 February 2018. [16] Intermittent protests have continued through subsequent years regarding rehabilitation and employment issues. [17]
Local communities have reported several environmental impacts: [15] [6]
NTPC has placed warnings on hand pumps in affected villages indicating that water is not potable, forcing villagers to use contaminated water sources. [15]
NTPC committed to a one-time investment of ₹45.60 crore for CSR activities during the construction phase and an annual commitment of ₹9.2 crore for development work in affected villages. [7] However, local advocacy groups and civil society organizations have raised concerns about inadequate implementation of these commitments. [17]
As of 2024, both units of Stage-I (1,600 MW) are fully operational and contribute to the national power grid. [4] The power generated from the station helps meet the energy demands of central India and supports the country's industrial and economic growth. [13]
Stage-II development is progressing with investment approval secured and tendering processes underway. [5] Upon completion of Stage-II, the Gadarwara Super Thermal Power Station will achieve its ultimate capacity of 3,200 MW, making it one of the largest thermal power generation facilities in Madhya Pradesh. [3]
The project is part of NTPC's broader plan to add approximately 13.6 GW of thermal capacity by fiscal year 2026-27, supporting India's target of adding 80 GW of thermal power capacity by 2031-32. [18]
{{cite news}}: |last= has generic name (help)CS1 maint: ref duplicates default (link){{cite news}}: |last= has generic name (help)CS1 maint: ref duplicates default (link){{cite web}}: CS1 maint: ref duplicates default (link){{cite web}}: CS1 maint: ref duplicates default (link){{cite web}}: CS1 maint: ref duplicates default (link){{cite report}}: CS1 maint: ref duplicates default (link){{cite report}}: CS1 maint: ref duplicates default (link){{cite news}}: CS1 maint: ref duplicates default (link){{cite news}}: CS1 maint: ref duplicates default (link){{cite web}}: CS1 maint: ref duplicates default (link){{cite news}}: CS1 maint: ref duplicates default (link){{cite web}}: CS1 maint: ref duplicates default (link){{cite web}}: CS1 maint: ref duplicates default (link){{cite report}}: CS1 maint: ref duplicates default (link){{cite press release}}: CS1 maint: ref duplicates default (link){{cite press release}}: CS1 maint: ref duplicates default (link){{cite web}}: CS1 maint: ref duplicates default (link){{cite news}}: CS1 maint: ref duplicates default (link)