NTPC Ramagundam

Last updated

NTPC Ltd., Ramagundam
Rstps4.jpg
NTPC Ramagundam
CountryIndia
Location Ramagundam, Telangana
Coordinates 18°45′18″N79°27′22″E / 18.75500°N 79.45611°E / 18.75500; 79.45611
StatusOperational
Commission date Unit 1 November 1983
Unit 2 May 1984
Unit 3 December 1984
Unit 4 June 1988
Unit 5 March 1989
Unit 6 October 1989
Unit 7 August 2004
OperatorNTPC Ltd.
Thermal power station
Primary fuel Coal
Cooling sourcePlain water (Sriram Sagar Project)
Power generation
Units operational3 × 200 MW
4 × 500 MW
Nameplate capacity 2600 MW
Annual net output 21,594.653 MU
External links
Website www.ntpc.co.in/power-generation/coal-based-power-stations/ramagundam
Commons Related media on Commons

NTPC Ramagundam, a part of National Thermal Power Corporation, [1] is a 2,600 megawatt (MW) Super thermal power station situated at Ramagundam in Peddapalli district in Telangana, India. It is the current largest power station in South India. It is the first ISO 14001 certified "Super Thermal Power Station" in India. [2]

Contents

The TG Hall

Turbo-Generator Hall, UNIT#7, NTPC Ltd., Ramagundam TG HALL 1.jpg
Turbo-Generator Hall, UNIT#7, NTPC Ltd., Ramagundam

The TG Hall or the Turbo-Generator hall or the Turbine-Generator Hall is the hall or space where the turbine-generator sets are present.

NTPC Ltd., Ramagundam has two TG Halls one for STAGE-I and the other common for STAGE-II and STAGE-III. These TG halls are equipped with heavy overhead cranes that assist in transportation of material within the TG hall. These cranes find their use greatly during overhauls. [3]

Unit-wise power generation

The whole plant is divided into 3 stages, each stage being planned at one time.

STAGE 1 (3×200 MW)

This stage consists of three units (Unit-1, Unit-2, Unit-3) each with a generation capacity of 200 MW. The turbines for these three units were manufactured by The Ansaldo Energia Ltd. The construction began in the late 1970s and these units have performed well over a long period, setting many records regarding maintenance and generation over the other two stages. But stage (1, 2, 3) cwp motors are manufactured by BHEL and all motors are manufactured by Ansaldo.[ clarification needed ] S-I coal mill motors are 240 KW and PA fans are 400 KW.

The first phase of the project, a 800 MW unit, was inaugurated by Prime Minister Narendra Modi on 3 October 2023. [4]

STAGE 2 (3×500 MW)

This stage also consists of three units (Unit-4, Unit-5, Unit-6) each with a generation capacity of 500MW. The turbines for these three units were manufactured by Bharat Heavy Electricals Limited (BHEL).

Outside view of STAGE-III (Unit#7) STAGE III.jpg
Outside view of STAGE-III (Unit#7)

Stage 3 (1×500 MW)

This stage comprises only one unit (Unit-7). It is a first of its kind in South India, being a computer operated unit. A wide disparity may be seen between the control rooms of the other two stages and this computerised unit. To this day,[ when? ] many Power plant engineers train in this unit to upgrade themselves to this new mode of operation.

Overhauls

Once every two years, these units are stopped and overhauled, one unit at a time. The overhauls are usually taken up from June to September as the monsoons increase hydropower generation which substitutes for the power generation lost due to the overhaul of the unit. The same practice is followed throughout the country. The overhauls usually take 15 to 20 days per unit provided there is no major repair involved. Major repairs include turbine casing, turbine rotor damage and other damages that require transporting the equipment to another location (usually the manufacturer). The overhauls are the dissipators of the annual PLF of any power plant.[ jargon ]

Generation distribution

States

As NTPC Ltd. is a Public Sector Undertaking (PSU), the generation is almost uniformly distributed to 5–6 states, all of which share about 20–25% of the output. These States include:

Electrical substation

The substation is the place where the station last interacts with the power it produces. The switchyard links the power generated to the southern power grid. The major transmission points are:

Inputs

Water

The power station is provided water periodically by the Sriram Sagar Project (SRSP). This water is stored in the balance reservoir. The water level in the balance reservoir is monitored daily.

Coal

BOBRN class hopper cars freight rakes used by Indian Railways BOBRN class Hopper cars Freight rakes at Samalkot Junction 01.jpg
BOBRN class hopper cars freight rakes used by Indian Railways

NTPC Ramagundam is a Coal-fired power station. This coal is available at a large scale from the Singareni Coal mining company nearby and is transported using the MGR (Merry-go-round) system, wherein a train travels on one rail route, delivers coal and returns on another route. The hopper wagons arriving by this route are taken for coal collection where a mechanism provided underneath the wagons opens on application of air pressure and drops the coal it is carrying. A separate department (MGR Dept.) handles this process.

Coal also arrives by the Indian Railways. The open wagons are routed via Ramagundam railway station to the separate plant line and these wagons arrive at the wagon tippler. The wagons arriving in this manner must be tilted at the wagon tippler to unload the coal as they do not have the drop mechanism underneath.

Other petroleum products required

The station also requires various oils for the following purposes:

These are periodically purchased as per requirement from the Indian oil corporation IOCL establishment nearby.

Departments

The plant classifies its departments as O&M (operation and maintenance) and Non-O&M.

Departments under O&M

Operation

The operation department has the greatest number of employees. It manages the operation of the various equipment and controls in the plant. The operation department takes care of the unit control rooms (UCBs). Since the plant operates nonstop, the operation department works in shifts to take care of the units at all times.

Electrical Maintenance

Switchyard of NTPC Ltd., Ramagundam SWITCHYARD 1.jpg
Switchyard of NTPC Ltd., Ramagundam

This is the largest department under the Maintenance section. This department takes care of all the electrical aspects of the plant. It takes care of the following sections:

Civil Maintenance

Civil Maintenance takes care of all the civil activities in the plant such as non-mechanical constructions, maintenance of locations, scrap removal and ensuring a proper working condition of minor equipment.

MGR (Merry-go-Round) Department

This department takes care of the coal transport to the plant.

CHP (Coal Handling Plant)

This department takes care of all coal handling processes.

  • Coal collection
  • Coal storage
  • Coal crushing
  • Coal convey system
  • Subsequent milling

Mechanical Maintenance

This department has the following sections:

Boiler Maintenance
  • Boiler feeders
  • Primary and secondary air pumps
  • Boiler feed pumps
  • Boiler core parts
Turbine Maintenance
  • Turbine core parts
  • Turbine governing system

Control & Instrumentation

This department deals with the maintenance of various control devices and instruments. It is considered to be a part of the maintenance section. It has got the following sections.

Departments under non-O&M

Staff

The plant is headed by the Executive Director (ED) to whom the General Managers (GMs) report. The O&M group is headed by the Chief of General Managers (O&M) again to whom the GMs of concerned departments report.

Township

The temporary township (TTS) was constructed during the early stages of the plant. Secondary employees of the organisation [note 1] now reside there.

The permanent township (PTS) is where most of the employees reside with their families. It is known for its serenity, cleanliness, vegetation and parks.

Schools

The township has three schools. St. Claire High school, Kendriya Vidyalaya NTPC Ramagundam and the Sachdeva school of excellence (formerly Chinmaya Vidyalaya).

Shopping

The township has a main shopping centre and four small shopping centres where the residents may shop for groceries and other regular needs.

Facilities

The township is well facilitated with banking (The State Bank of India with an on-site ATM), postal services, telephone and internet services (BSNL), adequate water supply, 24/7 electricity from the plant, civil services and its own security.

TSRTC-Godavarikhani bus depot runs city and long distance buses from the NTPC bus stop to Ramagundam railway station and various local areas.

Guest Houses and Restaurants

There are two guest houses: "Jyothi bhavan" for executives and "Godavari Bhavan" (Field Hostel) for other employees, students and trainees. There is the Satavahana Restaurant for families. These are maintained by the Indian Coffee House employees and are equipped with dining facilities thus forming as restaurants for the township residents.

Parks

The township has various parks, namely the Ambedkar park, the Chacha Nehru park, the Priyadarshini park, amongst others.

Notes

  1. Secondary employees include: contractors, allied organisation employees, and employees of service organisations to the township, such as Dooradarshan Aliautomobiles.

Related Research Articles

<span class="mw-page-title-main">Steel Authority of India Limited</span> Indian public sector steel manufacturer

Steel Authority of India Limited (SAIL) is an Indian public sector steel manufacturing corporation based in New Delhi. It is the largest government-owned steel producer, with an annual production of 18.29 million metric tons. Incorporated on 24 January 1973, SAIL has 54,431 employees and is under the administrative control of the Ministry of Steel.

<span class="mw-page-title-main">Bharat Heavy Electricals Limited</span> Indian government-owned manufacturer

Bharat Heavy Electricals Limited (BHEL) is an Indian central public sector undertaking and the largest government-owned electrical/ industrial technology company. It is owned by the Government of India, with administrative control by the Ministry of Heavy Industries. Established in 1956 with the help of Soviet technology, BHEL is based in New Delhi.

<span class="mw-page-title-main">Thermal power station</span> Power plant that generates electricity from heat energy

A thermal power station, also known as a thermal power plant, is a type of power station in which the heat energy generated from various fuel sources is converted to electrical energy. The heat from the source is converted into mechanical energy using a thermodynamic power cycle. The most common cycle involves a working fluid heated and boiled under high pressure in a pressure vessel to produce high-pressure steam. This high pressure-steam is then directed to a turbine, where it rotates the turbine's blades. The rotating turbine is mechanically connected to an electric generator which converts rotary motion into electricity. Fuels such as natural gas or oil can also be burnt directly in gas turbines, skipping the steam generation step. These plants can be of the open cycle or the more efficient combined cycle type.

<span class="mw-page-title-main">Lakeview Generating Station</span>

The Lakeview Generating Station was an Ontario Power Generation coal-burning power station located in Mississauga, Ontario, Canada, in the Lakeview neighbourhood on Lakeshore Road just east of Cawthra Road. The former station, constructed in 1958–1962, had four smokestacks known as the Four Sisters; the eight boilers of the generating plant all 'twinned' their emissions into common stacks. The station was a landmark for years and was shut down in April, 2005, after 43 years of service. The four stacks, which could be seen from as far away as Burlington to the west and downtown Toronto to the east, were demolished on June 12, 2006. The rest of the building was demolished on June 28, 2007.

<span class="mw-page-title-main">High Marnham Power Station</span> Former coal-fired power station in England

High Marnham Power Station was a coal fuelled power station in Nottinghamshire, to the west of the River Trent, approximately 0.5 miles (0.8 km) north of the village of High Marnham. Construction site clearance began in November 1955, No. 1 Unit power generation commenced in October 1959, and the station became fully operational in June 1962. The plant operated until 2003 when it was decommissioned, though the cooling towers weren't demolished until 2012.

Rihand Nagar is a township, named after the Rihand River, a tributary of the Sone River. It is located near Bijpur and lies in the Sonebhadra district of Uttar Pradesh. This township is situated near the border of Uttar Pradesh and Madhya Pradesh in India. This township has been developed by National Thermal Power Corporation (NTPC) under its Power Project Scheme, wherein it established a coal-based power station of 3000 MW capacity.

Nashik Thermal Power Plant is located at Eklahare village near Nashik in Maharashtra. The power plant is one of the coal based power plants of Maharashtra State Power Generation Company (Mahagenco)

<span class="mw-page-title-main">Durgapur Thermal Power Station</span> Power station in West Bengal, India

Durgapur Thermal Power Station is located near Waria Railway Station, 6 km from Durgapur railway station in West Bengal. The power plant is one of the coal based power plants of DVC.

<span class="mw-page-title-main">Badarpur Thermal Power Station</span>

Badarpur Thermal Power Station was a Power Station located at Badarpur area in NCT Delhi. The power plant was one of the coal based power plants of NTPC. The National Power Training Institute (NPTI) for North India Region under Ministry of Power, Government of India was established at Badarpur in 1974, within the Badarpur Thermal power plant (BTPS) complex. The power plant permanently shut down on 15 October 2018.

<span class="mw-page-title-main">Rihand Thermal Power Station</span> Coal power plant in Uttar Pradesh, India

Rihand Super Thermal Power Project is located at Renukut, Sonebhadra in Sonbhadra district in Indian state of Uttar Pradesh. The power plant is one of the coal based power plants of NTPC Limited.

<span class="mw-page-title-main">NTPC Limited</span> This page is about Maharatna PSU in India

NTPC Limited, formerly known as National Thermal Power Corporation, is an Indian central Public Sector Undertaking (PSU) under the ownership of the Ministry of Power and the Government of India, who is engaged in the generation of electricity and other activities. The headquarters of the PSU are situated at New Delhi. NTPC's core function is the generation and distribution of electricity to State Electricity Boards in India. The body also undertakes consultancy and turnkey project contracts that involve engineering, project management, construction management, and operation and management of power plants.

<span class="mw-page-title-main">Talcher Thermal Power Station</span>

Talcher Thermal Power station is located in Talcher sub-division of Angul district in the Indian state of Odisha Pin.759101. The existing plant was closed on 31 March 2021 with the plans to set up a new plant still in discussion phase. The power plant is one of the coal-based plants of NTPC. The coal for the power plant is sourced from Jagannath Mines of Mahanadi Coalfields Limited. Source of water for the plant is from Brahmani River. It has its own railway station and is well connected to three other important stations in close vicinity: Talcher Road, Angul and Talcher Stations. This power plant has been ranked among the best power plants in the country despite being the oldest plant in the state. It has consistently topped the charts in NTPC for the last four years and was also the nation's top power plant in 2015-16.

<span class="mw-page-title-main">Simhadri Super Thermal Power Station</span> Building in India

Simhadri Super Thermal Power Plant is a coal-fired power plant located in the outskirts of Visakhapatnam city in the Indian state of Andhra Pradesh. The power plant is one of the coal fired power plants of NTPC, a Government of India enterprise. The coal for the power plant is sourced from Kalinga Block of Talcher Coal fields in Odisha. The plant is a national asset, and power generated is shared between multiple states, as the operator is national. Power generated by units 1 and 2, making up for 1,000 MW, is dedicated to power distribution companies owned by the Government of Andhra Pradesh and Telangana. The remaining 1,000 MW, generated by units 3 and 4, is allocated to the states of Odisha, Tamil Nadu, Karnataka, Andhra Pradesh, Telangana and Puducherry as per their shares as decided in PPA.

Bihar State Power Holding Company Limited (BSPHCL), formerly Bihar State Electricity Board (BSEB) is a state-owned electricity regulation board operating within the state of Bihar in India. BSEB was established in 1958 as a statutory corporation under the Electricity (Supply) Act, 1948. As of November 2012, BSEB has nearly 1,700 officers and 14,850 employees. The derated capacity comes to just 530 MW. The BSEB was unbundled on 2 August 2011. Power Finance Corporation was the main consultant for BSEB's restructuring.

<span class="mw-page-title-main">Barh Super Thermal Power Station</span>

Barh Super Thermal Power Station or NTPC Barh is located in Barh in the Indian state of Bihar. NTPC Barh is located barely four kilometres (2.5 mi) east of the Barh sub-division on National Highway-31 in Patna district. The project has been named a mega power project, and is owned by Indian energy company National Thermal Power Corporation.

Kudgi Super Thermal Power Station is a power station located at Kudgi village of Basavana Bagewadi Taluq in Bijapur district, Karnataka in Indian state of Karnataka. This is one of the coal based thermal power plants of NTPC Limited.

<span class="mw-page-title-main">Vallur Thermal Power Station</span> Coal-fired power station in Tamil Nadu

Vallur Thermal Power Station is a power plant located in Vallur, Thiruvallur district, India. The power plant is operated by NTPC Tamil Nadu Energy Company Limited, a joint venture between NTPC Limited and TANGEDCO and has three units with 500 MW each.

Butibori Power Project is a coal-based thermal power plant located at Butibori near Nagpur in the Indian state of Maharashtra. The power plant is operated by the Reliance Power.

Bongaigaon Thermal Power Station is an under construction power project located at Salakati near Bongaigaon in Kokrajhar district in Indian state of Assam. The power plant is one of the coal based power plants of NTPC.

<span class="mw-page-title-main">Singareni Thermal Power Plant</span>

The Singareni Thermal Power Plant (STPP) is a coal-fired power station in Pegadapalli, a village in Jaipur mandal in Mancherial district of Telangana, India. The power plant has an installed capacity of 1200 MW, consisting of two 600 MW units, and is operated by the Singareni Collieries Company.

References

  1. "Coal Based Power Stations". Archived from the original on 24 February 2021. Retrieved 24 February 2021.
  2. "Archived copy". Archived from the original on 23 May 2010. Retrieved 11 December 2009.{{cite web}}: CS1 maint: archived copy as title (link)
  3. "Steam Turbine Maintenance | PDF | Valve | Turbine". Scribd. Retrieved 1 February 2024.
  4. www.ETEnergyworld.com. "PM Modi inaugurates 800 MW unit of NTPC's Telangana super thermal power project - ET EnergyWorld". ETEnergyworld.com. Retrieved 30 January 2024.