Crystal River Nuclear Plant | |
---|---|
Official name | Crystal River Nuclear Plant |
Country | United States |
Location | Crystal River, Florida |
Coordinates | 28°57.45′N82°41.90′W / 28.95750°N 82.69833°W |
Status | Being decommissioned |
Construction began | September 25, 1968 |
Commission date | March 13, 1977 |
Decommission date | – |
Construction cost | $1.436 billion (2007) [1] |
Owner | Duke Energy |
Nuclear power station | |
Reactor type | PWR |
Reactor supplier | Babcock & Wilcox |
Thermal capacity | 2568 |
Power generation | |
Nameplate capacity | 860 MW |
Capacity factor | 66.4% |
External links | |
Website | www |
The Crystal River Nuclear Plant also called the Crystal River 3 Nuclear Power Plant, or simply CR-3, is a closed nuclear power plant located in Crystal River, Florida. As of 2013 [update] the facility is being decommissioned, a process expected to last 60 years. [2] [3] The power plant was completed and licensed to operate in December 1976, and operated safely for 33 years until shutdown in September 2009. It was the third plant built as part of the 4,700-acre (1,900 ha) Crystal River Energy Complex (CREC) which contains a single nuclear power plant, while sharing the site with four operational fossil fuel power plants.
The Crystal River reactor went offline in September 2009 for refueling, OTSG replacement (once through steam generator), and 20% power up-rate outage. In preparing the containment building for making the opening to replace the two OTSG's, tendons in the containment building wall were detensioned. During the concrete removal in creating the opening workers discovered a large gap in the concrete of the containment building wall. The main cause of the gap, which further engineering analysis determined was a large delamination, was attributed to the scope and sequence of the tendon detensioning. [4] The plant had originally been scheduled to restart in April 2011, but the project encountered a number of delays. [5] Repairs were successful, but additional delamination began to occur in adjacent bays. After several months of analyzing options, Duke Energy senior executives announced in February 2013 that the Crystal River Nuclear Plant would be permanently shut down. [6] The costs were estimated at $1.18 billion over the next 60 years of decommissioning. [7]
The coal-fired units are not affected. [8]
Crystal River was originally owned by Florida Progress Corporation (and operated by its subsidiary, Florida Power Corporation) but, in 2000, it was bought by Carolina Power & Light to form the new company, Progress Energy. Progress Energy owned 91.8% of the plant; the remainder is owned by nine municipal utilities. Effective July 2, 2012, Duke Energy purchased Progress Energy and made it a wholly owned direct unit of Duke Energy. [9]
Crystal River 3 Nuclear Power Plant was an operating 860 MWe, PWR (pressurized water reactor plant). There are three main barriers that protect the public from the radiation hazards associated with nuclear operations. One of those barriers is known as the containment building which houses the fuel, the reactor, and the reactor cooling system. The Crystal River containment building is a steel lined post-tensioned (prestressed concrete) cylindrical concrete structure approximately 157 feet (48 m) in height with an outside diameter of about 138 feet (42 m). The containment has 42-inch thick concrete walls, has a flat foundation mat and a shallow torispherical dome. Post-tensioning is achieved by utilizing an outer array of horizontal tendons immediately adjacent to an inner array of vertical tendons that are embedded in the walls about 15 inches from the outside surface.
CR-3 went offline in September 2009 for RFO-16. While the reactor was down, the old steam generators were to be replaced. There are 426 steel tendons within the concrete walls of the reactor containment dome which reinforce the dome. Plan developer Sargent & Lundy specified that 97 tendons be loosened. Progress rejected that number as excessive. The next proposal was to loosen 74 tendons, which was typical of other nuclear plants doing the procedure. According to a Progress employee, "de-tensioning the tendons is a very expensive and time-consuming effort", so the number was further reduced to 65. Progress engaged Bechtel to provide a 3rd party review, which agreed that 65 was appropriate. However, when the work was performed, only 27 tendons were loosened, and a foreman and supervisor sent emails questioning the way the tendons were loosened. [10]
When workers began to cut the access hole for the steam generators, a crack formed. That crack was repaired, but more cracks appeared. Engineers noticed that parts of the concrete had delaminated. This was repaired, and the concrete re-tensioned, but the same problem was found in other areas. The plant had originally been due to restart in April 2011 following the uprate, but in June 2011 Progress Energy said that it did not expect it to restart until 2014. Preliminary cost estimates for the repairs was put at between $900 million and $1.3 billion, [5] but this estimate was later called into question by Duke Energy. [11] In October 2012 an independent review estimated the repair cost at $1.5 billion, with a worst-case scenario of $3.4 billion. [12] In February 2013 Duke Energy announced that Crystal River would be permanently shut down and that they will recover $850 million in insurance claims. [6] A Duke spokesperson stated, "The company sought input from numerous engineering experts — internally and externally — and used proven industry-accepted practices when determining how to replace the steam generators. Analysis has shown that the 2009 delamination (cracking) could not have been predicted. The U.S. Nuclear Regulatory Commission confirmed these findings." [10]
Gregory Jaczko, former chairman of the Nuclear Regulatory Commission, stated, "That's a multi-billion dollar asset that had to be shut down because of improper work planning, improper understanding of how to properly do this containment retrofit". [10]
The NRC defines two emergency planning zones around nuclear power plants: a plume exposure pathway zone with a radius of 10 miles (16 km), concerned primarily with exposure to, and inhalation of, airborne radioactive contamination, and an ingestion pathway zone of about 50 miles (80 km), concerned primarily with ingestion of food and liquid contaminated by radioactivity. [13]
The 2010 U.S. population within 10 miles (16 km) of Crystal River was 20,695, an increase of 50.9 percent in a decade, according to an analysis of U.S. Census data for msnbc.com. The 2010 U.S. population within 50 miles (80 km) was 1,046,741, an increase of 32.4 percent since 2000. Cities within 50 miles include Ocala, (38 miles (61 km) to city center) and Spring Hill (34 miles (55 km) to city center). [14]
On September 10, 2006, a magnitude 5.8 earthquake occurred 300 miles southwest of the nuclear plant, [15] no damage occurred to the Crystal River Nuclear Power Plant from the rare quake. The odds of such a quake happening again in the near-term around Florida are low. [16]
The NRC's estimate of the risk each year of an earthquake intense enough to cause core damage to the reactor at Crystal River was 1 in 45,455, according to an NRC study published in August 2010. [17] [18]
Year | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Annual (Total) |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2001 | 634,065 | 573,248 | 634,548 | 611,651 | 333,209 | 592,487 | 621,776 | 617,633 | 560,076 | 108,249 | 611,764 | 615,487 | 6,114,193 |
2002 | 631,798 | 571,245 | 631,962 | 608,001 | 594,143 | 605,412 | 622,390 | 622,296 | 605,075 | 629,388 | 543,833 | 634,766 | 7,300,309 |
2003 | 634,097 | 574,608 | 639,946 | 603,558 | 626,708 | 609,293 | 626,598 | 627,104 | 518,590 | 44,698 | 444,060 | 630,171 | 6,579,431 |
2004 | 642,042 | 600,830 | 563,406 | 620,121 | 635,435 | 605,340 | 625,326 | 626,628 | 497,578 | 628,796 | 620,363 | 637,445 | 7,303,310 |
2005 | 640,517 | 578,738 | 640,285 | 533,727 | 628,281 | 597,563 | 625,955 | 623,747 | 609,988 | 527,344 | 0 | 344,792 | 6,350,937 |
2006 | 468,911 | 578,318 | 423,584 | 615,711 | 633,455 | 607,045 | 613,749 | 518,624 | 602,771 | 631,644 | 619,006 | 640,912 | 7,353,730 |
2007 | 640,692 | 497,379 | 639,665 | 619,406 | 637,476 | 611,760 | 626,878 | 627,563 | 613,504 | 621,924 | 38,434 | 498,209 | 6,673,890 |
2008 | 630,153 | 607,162 | 209,500 | 628,614 | 607,241 | 619,994 | 638,986 | 539,271 | 623,226 | 648,866 | 629,751 | 617,315 | 6,600,079 |
2009 | 584,227 | 539,566 | 649,282 | 623,484 | 644,394 | 617,713 | 639,129 | 574,115 | 515,827 | 0 | 0 | 0 | 4,388,737 |
2010 | 0 | 0 | 0 | 0 | 0 | 20 | 0 | 74 | 0 | 0 | 34 | 0 | 128 |
2011 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
The Duane Arnold Energy Center (DAEC) was Iowa's only nuclear power plant. It is located on a 500-acre (200 ha) site on the west bank of the Cedar River, two miles (3.2 km) north-northeast of Palo, Iowa, USA, or eight miles (13 km) northwest of Cedar Rapids.
Davis–Besse Nuclear Power Station is an 894 megawatt (MW) nuclear power plant, located northeast of Oak Harbor, Ohio in Ottawa County, Ohio. It has a single pressurized water reactor. Davis–Besse is operated by Vistra Corporation.
Indian Point Energy Center (I.P.E.C.) is a now defunct three-unit nuclear power station located in Buchanan, just south of Peekskill, in Westchester County, New York. It sits on the east bank of the Hudson River, about 36 miles (58 km) north of Midtown Manhattan. The facility permanently ceased power operations on April 30, 2021. Before its closure, the station's two operating reactors generated about 2,000 megawatts (MWe) of electrical power, about 25% of New York City's usage. The station is owned by Holtec International, and consists of three permanently deactivated reactors, Indian Point Units 1, 2, and 3. Units 2 and 3 were Westinghouse pressurized water reactors. Entergy purchased Unit 3 from the New York Power Authority in 2000 and Units 1 and 2 from Consolidated Edison in 2001.
Three Mile Island Nuclear Generating Station is a shut-down nuclear power plant on Three Mile Island in Pennsylvania on the Susquehanna River just south of Harrisburg. It has two separate units, TMI-1 and TMI-2.
Turkey Point Nuclear Generating Station is a nuclear and gas-fired power plant located on a 3,300-acre (1,300 ha) site two miles east of Homestead, Florida, United States, next to Biscayne National Park located about 25 miles (40 km) south of Miami, Florida near the southernmost edge of Miami-Dade County. The facility is owned by Florida Power & Light.
The Brunswick nuclear power plant, named for Brunswick County, North Carolina, covers 1,200 acres (490 ha) at 20 feet (6.1 m) above sea level about 5 miles (8.0 km) from the Atlantic Ocean. The site is adjacent to the town of Southport, North Carolina, and to wetlands and woodlands, and was opened in 1975.
The Sequoyah Nuclear Plant is a nuclear power plant located on 525 acres (212 ha) located 7 miles (11 km) east of Soddy-Daisy, Tennessee, and 20 miles (32 km) north of Chattanooga, abutting Chickamauga Lake on the Tennessee River. The facility is owned and operated by the Tennessee Valley Authority (TVA).
The Watts Bar Nuclear Plant is a Tennessee Valley Authority (TVA) nuclear reactor pair used for electric power generation. It is located on a 1,770-acre (7.2 km²) site in Rhea County, Tennessee, near Spring City, between Chattanooga and Knoxville. Watts Bar supplies enough electricity for about 1.2 million households in the Tennessee Valley.
The Alvin W. Vogtle Electric Generating Plant, also known as Plant Vogtle, is a four-unit nuclear power plant located in Burke County, near Waynesboro, Georgia, in the southeastern United States. With a power capacity of 4,536 megawatts, it is the largest nuclear power plant, the largest source of low-carbon electricity, and largest power station overall in the United States. It is also the only nuclear plant in the country with four units. It is named after a former Alabama Power and Southern Company board chairman, Alvin Vogtle.
The Virgil C. Summer Nuclear Power Station occupies a site near Jenkinsville, South Carolina, in Fairfield County, South Carolina, approximately 20 miles (32 km) northwest of Columbia.
The Fort Calhoun Nuclear Generating Station is a shut-down nuclear power plant located on 660 acres (2.7 km2) between Fort Calhoun, and Blair, Nebraska adjacent to the Missouri River between mile markers 645.6 and 646.0. The utility has an easement for another 580 acres (2.3 km2) which is maintained in a natural state. The power plant is owned by the Omaha Public Power District of Omaha, Nebraska. When operational, the plant accounted for 25 percent of OPPD's net generation capabilities.
River Bend Nuclear Generating Station is a nuclear power station on a 3,300-acre (1,300 ha) site near St. Francisville, Louisiana in West Feliciana Parish, approximately 30 miles (50 km) north of Baton Rouge. The station has one sixth generation General Electric boiling water reactor that has a nominal gross electric output of about 1010 MWe. Commercial operation began on June 16, 1986. In 2003, owners applied and were approved for a power upgrade of approximately 52 megawatts in 2003. The nameplate capacity is 974 MW.
The Waterford Steam Electric Station, Unit 3, also known as Waterford 3, is a nuclear power plant located on a 3,000-acre (1,200 ha) plot in Killona, Louisiana, in St. Charles Parish, about 25 miles (40 km) west of New Orleans.
Donald C. Cook Nuclear Plant is a nuclear power plant located just north of the city of Bridgman, Michigan which is part of Berrien County, on a 650-acre (260 ha) site 11 miles south of St. Joseph, Michigan, United States. The plant is owned by American Electric Power (AEP) and operated by Indiana Michigan Power, an AEP subsidiary. It has two nuclear reactors and is currently the company's only nuclear power plant.
The Palisades Nuclear Generating Station is a moth-balled nuclear power plant located on Lake Michigan, in Van Buren County's Covert Township, Michigan, on a 432-acre (175 ha) site 5 miles (8.0 km) south of South Haven, Michigan, USA. Palisades was operated by the Nuclear Management Company and owned by CMS Energy prior to the sale to Entergy on April 11, 2007.
St. Lucie Nuclear Power Plant is a twin nuclear power station located on Hutchinson Island, near Port St. Lucie in St. Lucie County, Florida. Both units are Combustion Engineering pressurized water reactors. Florida Power & Light commissioned the station in 1976 and continues to operate the station. Minor shares of Unit 2 are owned by the Florida Municipal Power Agency (8.81%) and the Orlando Utilities Commission (6.08%).
The AP1000 is a nuclear power plant designed and sold by Westinghouse Electric Company. The plant is a pressurized water reactor with improved use of passive nuclear safety and many design features intended to lower its capital cost and improve its economics.
In the United States, nuclear power is provided by 94 commercial reactors with a net capacity of 97 gigawatts (GW), with 63 pressurized water reactors and 31 boiling water reactors. In 2019, they produced a total of 809.41 terawatt-hours of electricity, which accounted for 20% of the nation's total electric energy generation. In 2018, nuclear comprised nearly 50 percent of US emission-free energy generation.
The McGuire Nuclear Station is a nuclear power plant located about 17 miles (27 km) northwest of Charlotte, North Carolina, on the state's largest lake, Lake Norman. It is a 32,500-acre (13,200 ha) lake created in 1963 by Duke Power for the Cowans Ford Hydroelectric Station. The McGuire units use the lake's water for cooling.
The Levy County Nuclear Power Plant was a proposed nuclear power plant in Levy County, Florida. Progress Energy Florida originally estimated that the reactors would cost $5 billion and would commence operation in 2016. It later became clear that the Levy County reactors would not have started operation until at least 2026. Since Progress filed its application for the new plant in 2008 demand for electricity had been growing very slowly, and natural gas prices were extremely low at the time. The utility estimated that the reactors would cost between $17 billion and $22 billion, not counting financing charges and cost overruns. According to economist Mark Cooper, opposition to the project has mounted, threatening a rerun of the 1970s and 1980s, when the majority of nuclear construction plans were canceled or abandoned.