Browns Ferry Nuclear Power Plant | |
---|---|
Country | United States |
Location | Athens, Limestone County, Alabama |
Coordinates | 34°42′14″N87°7′7″W / 34.70389°N 87.11861°W |
Status | Operational |
Construction began | Units 1–2: May 1, 1967 Unit 3: July 1, 1968 |
Commission date | Unit 1: August 1, 1974 Unit 2: March 1, 1975 Unit 3: March 1, 1977 |
Construction cost | $4.79 billion (2023 USD) [1] |
Owner | Tennessee Valley Authority |
Operator | Tennessee Valley Authority |
Nuclear power station | |
Reactor type | BWR |
Reactor supplier | General Electric |
Cooling towers | 7 × Mechanical Draft (supplemental only) [lower-alpha 1] |
Cooling source | Wheeler Lake |
Thermal capacity | 3 × 3,952 MWth |
Power generation | |
Units operational | 1 × 1,256 MW 1 × 1,259 MW 1 × 1,260 MW |
Make and model | BWR-4 (Mark 1) |
Nameplate capacity | 3,775 MWe |
Capacity factor | 96.04% (2017) 78.07% (lifetime) |
Annual net output | 31,053 GWh (2021) |
External links | |
Website | Browns Ferry Nuclear Plant |
Commons | Related media on Commons |
The Browns Ferry Nuclear Power Plant is located on the Tennessee River near Decatur and Athens, Alabama, on the north side (right bank) of Wheeler Lake. The site has three General Electric boiling water reactor (BWR) nuclear generating units and is owned entirely by the Tennessee Valley Authority (TVA). With a generating capacity of nearly 3.8 gigawatts, it is the third most powerful nuclear power plant in the United States, behind the Palo Verde Nuclear Power Plant in Arizona and the Vogtle Nuclear Power Plant in Georgia, and the most powerful generating station operated by TVA.
The nuclear power plant is named after a ferry that operated at the site until the middle of the 20th century. (Brown's Ferry) Browns Ferry was TVA's first nuclear power plant; its approval occurred on June 17, 1966 and construction began in September 1966. [2] In 1974, the time of its initial operation, it was the largest nuclear plant in the world. It was the first nuclear plant to use units capable of generating more than 1 gigawatt of power. [3] The lake provides main cooling, and 7 additional Mechanical Draft "helper" cooling towers assist during limitations on water temperature. [1] [4] The 600 ft concrete chimney vents gases. [5] [4]
In 2006, the Nuclear Regulatory Commission (NRC) renewed the licenses for all three reactors, extending their operation for an additional twenty years past their original 40-year licensing period.
TVA employs 1,500 people at the plant, making it the second largest employer in Limestone County, Alabama after only the Toyota-Mazda factory near Greenbrier [6] [7]
During the January 2024 Snowstorms, the Browns Ferry Plant reached its capacity of 3,954mw, and was serving 2 million customers within the Tennessee Valley area. [8]
On August 16, 2017, the NRC approved TVA's request for a 14.3% uprate of each reactor's output. Each unit's gross electrical output was 1,155 MWe (1,101 MWe net), but after power uprates during refueling outages in Fall 2018 for Unit 1, Spring 2019 for Unit 2, and Spring 2018 for Unit 3, the gross electrical output for each unit was increased to 1,310 MWe (1,256 MWe net). The uprate for Unit 3 was completed in July 2018, [9] and in January 2019 for Unit 1. [10] The final uprate, for Unit 2, was completed in August 2019, completing the $475 million project. [11]
The electrical power increase of each unit was facilitated by the maximum operating thermal output of each reactor being increased from 3,458 MWth to 3,952 MWth. [12]
The graph represents the annual electricity generation at the site in GWh.
Year | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Annual (Total) |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2001 | 1,667,851 | 1,491,373 | 1,242,131 | 858,030 | 1,661,829 | 1,604,300 | 1,588,001 | 1,649,106 | 1,609,700 | 1,687,338 | 1,637,830 | 1,499,258 | 18,196,747 |
2002 | 1,685,408 | 1,512,905 | 1,420,713 | 1,096,179 | 1,649,564 | 1,606,134 | 1,548,390 | 1,620,345 | 1,499,973 | 1,313,155 | 1,601,472 | 1,617,101 | 18,171,339 |
2003 | 1,532,983 | 1,128,827 | 1,025,450 | 1,585,491 | 1,679,977 | 1,309,029 | 1,533,262 | 1,645,966 | 1,604,957 | 1,537,308 | 1,421,201 | 1,690,504 | 17,694,955 |
2004 | 1,686,540 | 1,470,106 | 841,601 | 1,599,570 | 1,658,995 | 1,590,997 | 1,537,823 | 1,622,276 | 1,600,575 | 1,675,792 | 1,527,243 | 1,676,286 | 18,487,804 |
2005 | 1,675,267 | 1,348,879 | 1,295,379 | 1,113,629 | 1,660,128 | 1,553,197 | 1,608,386 | 1,561,362 | 1,504,885 | 1,631,346 | 1,335,128 | 1,668,300 | 17,955,886 |
2006 | 1,487,987 | 1,402,006 | 1,036,077 | 1,614,448 | 1,499,088 | 1,581,572 | 1,621,685 | 1,501,443 | 1,579,135 | 1,334,246 | 1,621,170 | 1,592,617 | 17,871,474 |
2007 | 1,560,924 | 1,022,936 | 831,703 | 1,021,159 | 1,650,880 | 2,045,566 | 2,372,923 | 1,991,492 | 2,088,068 | 2,256,012 | 2,070,380 | 2,315,217 | 21,227,260 |
2008 | 1,893,721 | 2,323,817 | 2,059,198 | 1,577,956 | 1,955,015 | 2,326,307 | 2,312,684 | 2,140,764 | 2,171,358 | 2,151,422 | 1,617,818 | 2,389,356 | 24,919,416 |
2009 | 2,495,915 | 1,773,377 | 2,085,348 | 2,219,185 | 1,637,825 | 1,664,921 | 2,391,731 | 2,279,194 | 2,106,496 | 2,188,309 | 2,422,544 | 2,477,782 | 25,742,627 |
2010 | 2,323,753 | 2,193,597 | 1,518,364 | 2,137,333 | 2,460,077 | 2,178,911 | 1,936,632 | 1,326,214 | 2,294,697 | 2,235,307 | 1,799,306 | 2,366,946 | 24,771,137 |
2011 | 2,355,215 | 2,200,794 | 1,678,032 | 1,898,038 | 295,548 | 2,313,208 | 2,365,264 | 2,257,444 | 2,289,458 | 2,449,347 | 2,448,450 | 2,374,074 | 24,924,872 |
2012 | 2,523,614 | 2,276,390 | 2,488,182 | 1,743,743 | 1,676,274 | 2,229,333 | 2,378,452 | 2,396,206 | 2,372,908 | 2,147,256 | 1,623,684 | 2,222,193 | 26,078,235 |
2013 | 2,492,365 | 1,802,735 | 1,705,836 | 1,619,918 | 2,347,845 | 2,353,628 | 2,419,741 | 2,421,309 | 2,351,218 | 2,480,664 | 2,318,275 | 2,404,579 | 26,718,113 |
2014 | 2,496,150 | 1,857,823 | 1,930,723 | 2,419,669 | 2,357,300 | 2,323,768 | 2,428,341 | 2,105,116 | 2,202,519 | 1,690,915 | 2,410,915 | 2,515,061 | 26,738,300 |
2015 | 2,522,630 | 2,275,914 | 1,980,313 | 2,050,289 | 2,418,863 | 2,353,346 | 2,402,549 | 2,390,292 | 2,281,649 | 2,498,807 | 2,256,646 | 2,238,396 | 27,669,694 |
2016 | 2,346,937 | 1,913,869 | 1,683,786 | 2,404,699 | 2,467,542 | 2,348,575 | 2,223,936 | 2,306,757 | 2,166,078 | 1,629,619 | 2,244,099 | 2,478,726 | 26,214,623 |
2017 | 2,361,245 | 1,959,361 | 1,663,795 | 2,372,881 | 2,474,116 | 2,356,377 | 2,440,385 | 2,371,276 | 2,391,880 | 2,498,096 | 2,428,665 | 2,529,802 | 27,847,879 |
2018 | 2,427,645 | 1,614,094 | 1,541,633 | 2,199,272 | 2,286,602 | 2,382,452 | 2,518,277 | 2,395,000 | 2,214,383 | 1,372,576 | 1,826,143 | 2,619,704 | 25,397,781 |
2019 | 2,677,940 | 2,351,969 | 1,645,879 | 2,278,510 | 2,693,784 | 2,608,289 | 2,619,186 | 2,681,415 | 2,339,956 | 2,509,767 | 2,332,120 | 2,781,085 | 29,519,900 |
2020 | 2,658,509 | 2,255,363 | 1,924,789 | 2,510,217 | 2,596,221 | 2,446,549 | 2,106,817 | 2,690,416 | 2,498,959 | 1,924,626 | 2,411,481 | 2,750,903 | 28,774,850 |
2021 | 2,783,476 | 2,418,303 | 1,887,703 | 1,986,456 | 2,801,025 | 2,663,214 | 2,758,676 | 2,733,946 | 2,683,156 | 2,823,124 | 2,735,754 | 2,778,719 | 31,053,552 |
2022 | 2,384,111 | 2,252,918 | 1,873,268 | 2,545,845 | 2,768,072 | 2,616,572 | 2,624,500 | 2,662,134 | 2,396,078 | 1,975,040 | 2,687,882 | 2,529,041 | 29,325,461 |
2023 | 2,743,612 | 2,045,599 | 2,072,567 | 2,393,573 | 2,645,017 | 2,635,230 | 2,677,374 | 2,673,932 | 2,607,559 | 2,788,151 | 2,724,619 | 2,813,277 | 30,820,510 |
2024 | 2,575,389 | 2,115,631 | 2,030,905 | 2,521,649 | 2,551,598 | 2,553,939 | 2,657,955 | 2,591,634 | 19,898,700 | ||||
This section needs additional citations for verification .(August 2020) |
Unit 1 is a 1,256 MWe net BWR/4 built by General Electric. Construction started on Unit 1 on September 12, 1966 [2] and first powered up for testing on December 20, 1973. Commercial operation began on August 1, 1974. [14] It was licensed to operate through December 20, 2013. [15] Unit 1 was shut down for a year after a fire in 1975 damaged the unit. The unit was subsequently repaired and operated from 1976 through March 3, 1985, when all three Browns Ferry units were shut down for operational and management issues.
Starting in 2002, TVA undertook an effort to restore Unit 1 to operational status, spending $1.8 billion USD to do so. The NRC approved the restart of Unit 1 on May 15, 2007 and the reactor was brought up to criticality on May 22. [16] During initial testing after restart, on May 24, 2007, a leaky hydraulic control pipe in the turbine hall burst, spilling about 600 US gallons (2,300 L; 500 imp gal) of non-radioactive fluid, and the newly restarted reactor was temporarily powered down. Reactor power-up and tests resumed on May 27 and the unit started supplying power to the electricity supply grid on June 2, 2007, reaching full power on June 8. The Browns Ferry restart was estimated to pay for itself in five years. [17]
On May 4, 2006, NRC issued a renewed license, adding twenty years to operate through December 20, 2033. [15]
Unit 1 generated 9,801 GWh of electricity in 2017, achieving a capacity factor of 101.62%.
On March 22, 1975 a fire started when a worker using a candle to search for air leaks accidentally set a temporary cable seal on fire. At Browns Ferry, foamed plastic, covered on both sides with two coats of a flame retardant paint, was used as a firestop. The fire spread from the temporary seal into the foamed plastic, causing significant damage to the reactor control cabling in the station. [18]
An NRC bulletin explained the circumstances of the fire.
The fire started in the cable spreading room at a cable penetration through the wall between the cable spreading room and the reactor building for Unit 1. A slight differential pressure is maintained (by design) across this wall, with the higher pressure being on the cable spreading room side. The penetration seal originally present had been breached to install additional cables required by a design modification. Site personnel were resealing the penetration after cable installation and were checking the airflow through a temporary seal with a candle flame prior to installing the permanent sealing material. The temporary sealing material was highly combustible, and caught fire. Efforts were made by the workers to extinguish the fire at its origin, but they apparently did not recognize that the fire, under the influence of the draft through the penetration, was spreading on the reactor building side of the wall. The extent of the fire in the cable spreading room was limited to a few feet from the penetration; nonetheless, the presence of the fire on the other side of the wall from the point of ignition was not recognized until significant damage to cables related to the control of Units 1 and 2 had occurred. [19]
This later resulted in the Nuclear Regulatory Commission making significant additions to the standards for fire protection through the publication of 10CFR50.48 and Appendix R. According to the Nuclear Information and Resource Service, the newly restarted Unit 1 does not comply with these standards.[ citation needed ] Unit 3 was not affected by the accident. This event was pivotal not just for firestopping in the nuclear field, but also in commercial and industrial construction. While the nuclear field went to installations of silicone foam, a wider array of firestops became prevalent in non-nuclear construction.[ citation needed ]
Unit 2 is a 1,259 MWe net BWR/4 built by General Electric that originally came online on August 2, 1974, and is licensed to operate through June 28, 2034. Unit 2 generated 8,396 GWh of electricity in 2017, achieving a capacity factor of 86.81%.
Unit 2 returned to service in 1991, after all three reactors were shut down in 1985. [20] During a drought in August 2007, Unit 2 was shut down for one day because water temperature in the Tennessee River rose too high for the water to be used for cooling and then discharged back into the river. [21]
Beginning in 2005 Unit 2 was loaded with BLEU (Blended Low Enriched Uranium) recovered by the DOE from weapons programs. This fuel contains quantities of U-236 and other contaminants because it was made from reprocessed fuel from weapons program reactors and therefore has slightly different characteristics when used in a reactor as compared to fresh uranium fuel. By making use of this fuel, which would otherwise have been disposed of as waste, the TVA is saving millions of dollars in fuel costs and accumulating a database of recycled uranium reactions in LWR use. [22]
Unit 3 is a 1,260 MWe net BWR/4 built by General Electric that originally came online on August 18, 1976 with a capacity of 1,105 MWe net, and is licensed to operate through July 2, 2036. Unit 3 returned to service in 1995 after all three units were shut down in 1985 for maintenance and repairs. [20] Unit 3 generated 9,651 GWh in 2017, achieving a capacity factor of 99.70%. The power update of 155 MWe was completed in July 2018.
TVA decided to shut the entire plant down and keep it shut down indefinitely in order to focus on making improvements to all three units in order to bring it back into regulatory compliance following extremely negative assessments from the NRC. [23] Unit 2 finally resumed operation on May 24, 1991, with Unit 3 following it on November 1, 1995, although Unit 1 did not resume operation until June 2, 2007.
Cooling tower #4 (which was 90 feet (27 m) wide, 300 feet (91 m) long, and four stories tall) was destroyed in a fire caused by sparks from the electrical cooling fans in the tower hitting the abnormally dry redwood slats within the tower on May 10, 1986. During normal operation, water was kept flowing near-continuously over the redwood slats within the tower, but after close to two months of inactivity, the slats were very dry and extremely flammable. [24] [25] $5 million of damage was done. [26]
Cooling tower #3 (which was in the process of being refurbished at the time) was heavily damaged in a fire on May 23, 1996, with about 80% of the tower destroyed. [26]
At 11:05 AM on August 19, 2006, Unit 3 was manually scrammed due to loss of both the 3A and 3B Reactor Recirculation pumps. The initial investigation found the Variable Frequency Drive (VFD) microprocessors non-responsive. The root cause of the event was that the VFD controls malfunctioned due to excessive traffic on the connected plant Integrated Control System (ICS) network. Corrective actions included installing network firewalls that limit the connections and traffic to the VFD controllers. [27]
At 5:01 PM on April 27, 2011, all three reactors scrammed due to loss of external power caused by a tornado in the vicinity of the plant. Control rod insertion and cooling procedures operated as designed with no physical damage or release of radiation. Diesel backup generators provided power after a brief period of outage. An NRC Unusual Event, the lowest level of emergency classification, was declared due to loss of power exceeding 15 minutes. Additionally, a small oil leak was found on one generator. Due to widespread transmission grid damage from the storms, Browns Ferry was unable to produce power for the grid and significant blackouts occurred throughout the Southeastern United States. [28] [29]
A drain line leaked 100-200 gallons of water containing tritium levels above acceptable EPA drinking water standards. The leak was fixed within three hours of when it was discovered and was largely contained within the plant area. [30]
The Nuclear Regulatory Commission found that 5 contract workers failed to conduct roving fire watch patrols as required by NRC. As a result, Tennessee Valley Authority was fined $140,000 for failing to maintain adequate fire watches in 2015 at Browns Ferry. [31]
The 2010 U.S. population within 10 miles (16 km) of Browns Ferry was 39,930, an increase of 12.3 percent in a decade, according to an analysis of U.S. Census data for msnbc.com. In 2020, the population within 50 miles (80 km) was about 1.4 million, an increase of 43 percent since 2010. Cities within 50 miles include Huntsville (28 miles to city center). [32] [33]
According to an NRC study using geological data from 1989 to 2008 which was published in August 2010, the estimated risk of an earthquake intense enough to cause core damage to reactor one was 1 in 270,270, and for reactors two and three, the risk was 1 in 185,185. [34] [35]
The Duane Arnold Energy Center (DAEC) was Iowa's only nuclear power plant. It is located on a 500-acre (200 ha) site on the west bank of the Cedar River, two miles (3.2 km) north-northeast of Palo, Iowa, USA, or eight miles (13 km) northwest of Cedar Rapids.
The Salem Nuclear Power Plant is a two-unit pressurized water reactor nuclear power plant located in Lower Alloways Creek Township, in Salem County, New Jersey, United States. It is owned by PSEG Nuclear LLC and Constellation Energy.
Hope Creek Nuclear Generating Station is a thermal nuclear power plant located in Lower Alloways Creek Township, in Salem County, New Jersey, United States, on the same site on Artificial Island as the two-unit Salem Nuclear Power Plant. The plant is owned and operated by PSEG Nuclear LLC. It has one unit, a boiling water reactor (BWR) manufactured by GE. The complex was designed for two units, but the second unit was cancelled in 1981. It has a generating capacity of 1,268 MWe. The plant came online on July 25, 1986, licensed to operate until 2026. In 2009, PSEG applied for a 20-year license renewal, which it received in 2011 to operate until 2046. With its combined output of 3,572 megawatts, the Salem-Hope Creek complex is the largest nuclear generating facility in the Eastern United States and the second largest nationwide, after the Palo Verde Nuclear Generating Station in Arizona.
Dresden Generating Station is the first privately financed nuclear power plant built in the United States. Dresden 1 was activated in 1960 and retired in 1978. Operating since 1970 are Dresden units 2 and 3, two General Electric BWR-3 boiling water reactors. Dresden Station is located on a 953-acre (386 ha) site in Grundy County, Illinois near the city of Morris. It is at the head of the Illinois River, where the Des Plaines River and Kankakee River meet. It is immediately northeast of the Morris Operation—the only de facto high-level radioactive waste storage site in the United States. It serves Chicago and the northern quarter of the state of Illinois, capable of producing 867 megawatts of electricity from each of its two reactors, enough to power over one million average American homes.
The Millstone Nuclear Power Station is the only nuclear power plant in Connecticut and the only multi-unit nuclear plant in New England. It is located at a former quarry in Waterford. With a total capacity of over 2 GW, the station produces enough electricity to power about 2 million homes. The operation of the Millstone Power Station supports more than 3,900 jobs, and generates the equivalent of over half the electricity consumed in Connecticut.
The Crystal River Nuclear Plant also called the Crystal River 3 Nuclear Power Plant, or simply CR-3, is a closed nuclear power plant located in Crystal River, Florida. As of 2013 the facility is being decommissioned, a process expected to last 60 years. The power plant was completed and licensed to operate in December 1976, and operated safely for 33 years until shutdown in September 2009. It was the third plant built as part of the 4,700-acre (1,900 ha) Crystal River Energy Complex (CREC) which contains a single nuclear power plant, while sharing the site with four operational fossil fuel power plants.
Turkey Point Nuclear Generating Station is a nuclear and gas-fired power plant located on a 3,300-acre (1,300 ha) site two miles east of Homestead, Florida, United States, next to Biscayne National Park located about 25 miles (40 km) south of Miami, Florida near the southernmost edge of Miami-Dade County. The facility is owned by Florida Power & Light.
The Byron Nuclear Generating Station is a nuclear power plant located in Ogle County, Illinois, 2 miles (3.2 km) east of the Rock River. The reactor buildings were constructed by Commonwealth Edison and house two Westinghouse Four-Loop pressurized water reactors, Unit 1 and Unit 2, which began operation in September 1985 and August 1987 respectively. The plant is owned and operated by Constellation Energy.
The Sequoyah Nuclear Plant is a nuclear power plant located on 525 acres (212 ha) located 7 miles (11 km) east of Soddy-Daisy, Tennessee, and 20 miles (32 km) north of Chattanooga, abutting Chickamauga Lake on the Tennessee River. The facility is owned and operated by the Tennessee Valley Authority (TVA).
The Bellefonte Nuclear Generating Station (BLN) is an unfinished nuclear power plant in Hollywood, Alabama, United States.
The Monticello Nuclear Generating Plant is a nuclear power plant located in Monticello, Minnesota, along the Mississippi River. The site, which began operating in 1971, has a single nuclear reactor of the General Electric BWR-3 design generating 671 MWe. The plant is owned by Xcel Energy and operated by Northern States Power, its regional subsidiary.
Nine Mile Point Nuclear Station is a nuclear power plant with two nuclear reactors located in the town of Scriba, approximately five miles northeast of Oswego, New York, on the shore of Lake Ontario. The 900-acre (360 ha) site is also occupied by the James A. FitzPatrick Nuclear Power Plant.
Grand Gulf Nuclear Station is a nuclear power station with one operational GE BWR reactor. It lies on a 2,100 acres (850 ha) site near Port Gibson, Mississippi. The site is wooded and contains two lakes. The plant has a 520-foot natural draft cooling tower. As of January 2023, the plant employs 675 people.
The Rancho Seco Nuclear Generating Station is a decommissioned nuclear power plant built by the Sacramento Municipal Utility District (SMUD) in Herald, California.
The Economic Simplified Boiling Water Reactor (ESBWR) is a passively safe generation III+ reactor design derived from its predecessor, the Simplified Boiling Water Reactor (SBWR) and from the Advanced Boiling Water Reactor (ABWR). All are designs by GE Hitachi Nuclear Energy (GEH), and are based on previous Boiling Water Reactor designs.
Tarapur Atomic Power Station (T.A.P.S.) is located in Tarapur, Palghar, India. It was the first commercial nuclear power station built in India. It is one of the largest nuclear power plant in the country. It has 4 reactors, 2 BWR-1 of 160 MWe each and 2 IPHWRs Of 540 MWe each.
Comanche Peak Nuclear Power Plant is located in Somervell County, Texas. The nuclear power plant is located 40 miles (64 km) southwest of Ft. Worth and about 60 miles (97 km) southwest of Dallas. It relies on nearby Comanche Creek Reservoir for cooling water. The plant has about 1,300 employees and is operated by Luminant Generation, a subsidiary of Vistra Corp.
The Nuclear power station Oskarshamn is one of three active nuclear power stations in Sweden. The plant is about 30 kilometers (19 mi) north of Oskarshamn, directly at the Kalmarsund at the Baltic Sea coast and with one active reactor, producing about 10% of the electricity needs of Sweden. All reactors were built using BWR technology.
The Hartsville Nuclear Plant is a canceled nuclear power plant project located near Hartsville, Tennessee. To be built and operated by the Tennessee Valley Authority (TVA), it was to have four General Electric boiling water reactors.
Phipps Bend Nuclear Plant was a planned nuclear power generation facility that was to be constructed and operated by the Tennessee Valley Authority (TVA) in unincorporated Hawkins County, Tennessee. Proposed to house two reactor units, the power plant was estimated to cost $1.6 billion when it was first planned in late 1977, provide a generating capacity of 2,600,000 kilowatts. Following negative public reactions towards nuclear energy following the Three Mile Island accident and a decreasing demand for power due to regional economic decline, the TVA's board of directors voted to defer further construction of the power plant. By 1981, the plant was 40% complete and an estimated $1.5 billion in planning, engineering, and construction costs had accumulated. Construction never resumed, and the project was canceled overall in 1982 due to lower load growth than forecast. By the project's cancellation, the TVA had amassed over $2.6 billion in spending for the incomplete nuclear facility. After being auctioned off by the TVA in 1987, the land acquired for the plant would be under the ownership of Hawkins County's industrial development board, who converted most of the site into an industrial park. A 1 MW solar farm was built at the site in 2017.
The residual heat removal service water intake structure is a single structure serving all three units. The reinforced concrete chimney stands 600 feet high and varies in diameter from 62 feet at the base to 6 feet at the top
The fire burned for seven hours, damaging scores of cables that provide the control room staff their eyes and ears to the two 1.1 million kilowatt reactors. Core cooling systems, pumps, dials and switches were knocked out by the fire. But plant workers found a way to press the auxiliary pumps into service, which kept the reactor cooled and allowed for a safe shutdown of the reactors after about 15 hours.
All three units of the Browns Ferry plant were actually shut down in 1985, but they retained their NRC operating licences. Unit 2 came back on line in 1991, and Unit 3 in 1995 at a cost of US $1.8bn, which was also the estimated cost of restarting Unit 1.
Media related to Browns Ferry Nuclear Power Plant at Wikimedia Commons