Nuclear decommissioning is the process leading to the irreversible complete or partial closure of a nuclear facility, usually a nuclear reactor, with the ultimate aim at termination of the operating licence. The process usually runs according to a decommissioning plan, including the whole or partial dismantling and decontamination of the facility, ideally resulting in restoration of the environment up to greenfield status. The decommissioning plan is fulfilled when the approved end state of the facility has been reached.
The process typically takes about 15 to 30 years, or many decades more when an interim safe storage period is applied for radioactive decay. Radioactive waste that remains after the decommissioning is either moved to an on-site storage facility where it is still under control of the owner, or moved to a dry cask storage or disposal facility at another location. The final disposal of nuclear waste from past and future decommissioning is a growing still unsolved problem.
Decommissioning is an administrative and technical process. The facility is dismantled to the point that it no longer requires measures for radiation protection. It includes clean-up of radioactive materials. Once a facility is fully decommissioned, no radiological danger should persist. The license will be terminated and the site released from regulatory control. The plant licensee is then no longer responsible for the nuclear safety.
The costs of decommissioning are to be covered by funds that are provided for in a decommissioning plan, which is part of the facility's initial authorization. They may be saved in a decommissioning fund, such as a trust fund.
There are worldwide also hundreds of thousands small nuclear devices and facilities, for medical, industrial and research purposes, that will have to be decommissioned at some point. [1]
Nuclear decommissioning is the administrative and technical process leading to the irreversible closure of a nuclear facility such as a nuclear power plant (NPP), a research reactor, an isotope production plant, a particle accelerator, or uranium mine. It refers to the administrative and technical actions taken to remove all or some of the regulatory controls from the facility to bring about that its site can be reused. Decommissioning includes planning, decontamination, dismantling and materials management. [2]
Decommissioning is the final step in the lifecycle of a nuclear installation. It involves activities from shutdown and removal of nuclear material to the environmental restoration of the site. [3] The term decommissioning covers all measures carried out after a nuclear installation has been granted a decommissioning licence until nuclear regulatory supervision is no longer necessary. The aim is ideally to restore the natural initial state that existed before the construction of the nuclear power plant, the so-called greenfield status. [4]
Decommissioning includes all steps as described in the decommissioning plan, leading to the release of a nuclear facility from regulatory control. The decommissioning plan is fulfilled when the approved end state of the facility has been reached. Disposal facilities for radioactive waste are closed rather than decommissioned. The use of the term decommissioning implies that no further use of the facility (or part thereof) for its existing purpose is foreseen. Though decommissioning typically includes dismantling of the facility, it is not necessarily part of it as far as existing structures are reused after decommissioning and decontamination. [5] ,p. 49-50
From the owner's perspective, the ultimate aim of decommissioning is termination of the operating license, once he has given certainty that the radiation at the site is below the legal limits, which in the US is an annual exposure of 25 millirem in case of releasing of the site to the public for unrestricted use. [6] The site will be dismantled to the point that it no longer requires measures for radiation protection. Once a facility is decommissioned no radioactive danger persists and it can be released from regulatory control.
The complete process usually takes about 20 to 30 years. [3] In the US, the decommissioning must be completed within 60 years of the plant ceasing operations, unless a longer time is necessary to protect public health and safety; [6] up to 50 years are for radioactive decay and 10 years to dismantle the facility. [7]
The decommissioning process encompasses:
Under supervision of the IAEA, a member state first develops a decommissioning plan to demonstrate the feasibility of decommissioning and assure that the associated costs are covered. At the final shutdown, a final decommissioning plan describes in detail how the decommissioning will take place, how the facility will be safely dismantled, ensuring radiation protection of the workers and the public, addressing environmental impacts, managing radioactive and non-radioactive materials, and termination of the regulatory authorization. [2] In the EU, decommissioning operations are overseen by Euratom. Member states are assisted by the European Commission. [3]
The progressive demolition of buildings and removal of radioactive material is potentially occupationally hazardous, expensive, time-intensive, and presents environmental risks that must be addressed to ensure radioactive materials are either transported elsewhere for storage or stored on-site in a safe manner.
Radioactive waste that remains after the decommissioning is either moved to an on-site storage facility where it still is under control of the plant owner, or moved to a dry cask storage or disposal facility at another location. [9] The problem of long-term disposal of nuclear waste is still unsolved. Pending the availability of geologic repository sites for long-term disposal, interim storage is necessary. As the planned Yucca Mountain nuclear waste repository – like elsewhere in the world – is controversial, on- or off-site storage in the US usually takes place in Independent Spent Fuel Storage Facilities (ISFSI's). [10]
In the UK, all eleven Magnox reactors are in decommissioning under responsibility of the NDA. The spent fuel was removed and transferred to the Sellafield site in Cumbria for reprocessing. [11] Facilities for "temporary" storage of nuclear waste – mainly 'Intermediate Level Waste' (ILW) – are in the UK called Interim Storage Facilities (ISF's). [12]
The decommission of a nuclear reactor can only take place after the appropriate licence has been granted pursuant to the relevant legislation. As part of the licensing procedure, various documents, reports and expert opinions have to be written and delivered to the competent authority, e.g. safety report, technical documents and an environmental impact assessment (EIA). In the European Union these documents are a precondition for granting such a licence is an opinion by the European Commission according to Article 37 of the Euratom Treaty. [13] On the basis of these general data, the Commission must be in a position to assess the exposure of reference groups of the population in the nearest neighbouring states.
There are several options for decommissioning:
Immediate dismantling (DECON in the United States; )
Shortly after the permanent shutdown, the dismantling and/or decontamination of the facility begins. Equipment, structures, systems and components that contain radioactive material are removed and/or decontaminated to a level that permits the ending of regulatory control of the facility and its release, either for unrestricted use or with restrictions on its future use. [5] ,p. 50 The operating license is terminated. [6]
Deferred dismantling (SAFSTOR in the United States; "care and maintenance" (C&M) in the UK)
The final decommissioning is postponed for a longer period, usually 30 to 50 years. Often the non-nuclear part of the facility is dismantled and the fuel removed immediately. The radioactive part is maintained and monitored in a condition that allows the radioactivity to decay. Afterwards, the plant is dismantled and the property decontaminated to levels that permit release for unrestricted or restrict use. [5] In the US, the decommissioning must be completed within 60 years. [6] With deferred dismantling, costs are shifted to the future, but this entails the risk of rising expenditures for decades to come and changing rules. [14] Moreover, the site cannot be re-used until the decommissioning is finished, while there are no longer revenues from production.
Partial entombment
The US has introduced the so-called In Situ Decommissioning (ISD) closures. All aboveground structures are dismantled; all remaining belowground structures are entombed by grouting all spaces. Advantages are lower decommissioning costs and safer execution. Disadvantages are main components remaining undismantled and definitively inaccessible. The site has to be monitored indefinitely.
This method was implemented at the Savannah River Site in South Carolina for the closure of the P and R Reactors. With this method, the cost of decommissioning for each reactor was about $73 million. In comparison, the decommissioning of each reactor using traditional methods would have been an estimated $250 million. This resulted in a 71% decrease in cost. [15] Other examples are the Hallam nuclear reactor and the Experimental Breeder Reactor II.
Complete entombment
The facility will not be dismantled. Instead it is entombed and maintained indefinitely, and surveillance is continued until the entombed radioactive waste is decayed to a level permitting termination of the license and unrestricted release of the property. The licensee maintains the license previously issued. [16] This option is likely the only possible one in case of a nuclear disaster where the reactor is destroyed and dismantling is impossible or too dangerous. An example of full entombment is the Chernobyl reactor.
In IAEA terms, entombment is not considered an acceptable strategy for decommissioning a facility following a planned permanent shutdown, except under exceptional circumstances, such as a nuclear disaster. In that case, the structure has to be maintained and surveillance continued until the radioactive material is decayed to a level permitting termination of the licence and unrestricted release of the structure. [5] ,p. 50
The calculation of the total cost of decommissioning is challenging, as there are large differences between countries regarding inclusion of certain costs, such as on-site storage of fuel and radioactive waste from decommissioning, dismanting of non-radioactive buildings and structures, and transport and (final) disposal of radioactive waste. [17] ,p. 61
Moreover, estimates of future costs of deferred decommissioning are virtually impossible, due to the long periode, where inflation and rising costs are unpredictable. Nuclear decommissioning projects are characterized by high and highly variable costs, long schedule and a range of risks. Compared with non-nuclear decommissioning, additional costs are usually related with radiological hazards and safety & security requirements, but also with higher wages for required higher qualified personnel. Benchmarking, comparing projects in different countries, may be useful in estimating the cost of decommissioning. While, for instance, costs for spent fuel and high-level-waste management significantly impacts the budget and schedule of decommissioning projects, it is necessary to clarify which is the starting and the ending point of the decommissioning process. [18]
The effective decommissioning activities begin after all nuclear fuel has been removed from the plant areas that will be decommissioned and these activities form a critical component of pre-decommissioning operations, thus should be factored into the decommissioning plan. The chosen option – immediate or deferred decommissioning – impacts the overall costs. Many other factors also influence the cost. A 2018 KPMG article about decommissioning costs observes that many entities do not include the cost of managing spent nuclear fuel, removed from the plant areas that will be decommissioned (in the US routinely stored in ISFSIs). [19]
In 2004, in a meeting in Vienna, the International Atomic Energy Agency estimated the total cost for the decommissioning of all nuclear facilities. Decommissioning of all nuclear power reactors in the world would require US$187 billion; US$71 billion for fuel cycle facilities; less than US$7 billion for all research reactors; and US$640 billion for dismantling all military reactors for the production of weapons-grade plutonium, research fuel facilities, nuclear reprocessing chemical separation facilities, etc. The total cost to decommission the nuclear fission industry in the World (from 2001 to 2050) was estimated at US$1 trillion. [20] Market Watch estimated (2019) the global decommissioning costs in the nuclear sector in the range of US$1 billion to US$1.5 billion per 1,000-megawatt plant. [21]
The huge costs of research and development for (geological) longterm disposal of nuclear waste are collectively defrayed by the taxpayers in different countries, not by the companies.
The costs of decommissioning are to be covered by funds that are provided for in a decommissioning plan, which is part of the facility's initial authorization, before the start of the operations. In this way, it is ensured that there will be sufficient money to pay for the eventual decommissioning of the facility. This may for example be through saving in a trust fund or a guarantee from the parent company [22]
Switzerland has a central fund for decommissioning its five nuclear power reactors, and another one for disposal the nuclear waste. [23] Germany has also a state-owned fund for decommissioning of the plants and managing radioactive waste, for which the reactor owners have to pay. The UK Government (the taxpayers) will pay most of the costs for both nuclear decommissioning and existing waste. [24] The decommissioning of all Magnox reactors is entirely funded by the state. [25]
Since 2010, owners of new nuclear plants in the Netherlands are obliged to set up a decommissioning fund before construction is started. [26]
The economic costs of decommissioning will increase as more assets reach the end of their life, but few operators have put aside sufficient funds. [21]
In 2016 the European Commission assessed that European Union's nuclear decommissioning liabilities were seriously underfunded by about 118 billion euros, with only 150 billion euros of earmarked assets to cover 268 billion euros of expected decommissioning costs covering both dismantling of nuclear plants and storage of radioactive parts and waste. [27]
In Feb 2017, a committee of the French parliament warned that the state-controlled EDF has underestimated the costs for decommissioning. France had set aside only €23 billion for decommissioning and waste storage of its 58 reactors, which was less than a third of 74 billion in expected costs, [27] while the UK's NDA estimated that clean-up of UK's 17 nuclear sites will cost between €109-€250 billion. EDF estimated the total cost at €54 billion. According to the parliamentary commission, the clean-up of French reactors will take longer, be more challenging and cost much more than EDF anticipates. It said that EDF showed "excessive optimism" concerning the decommissioning. [24] EDF values some €350 million per reactor, whereas European operators count with between 900 million and 1.3 billion euros per reactor. The EDF's estimate was primarily based on the single historic example of the already dismantled Chooz A reactor. The committee argued that costs like restoration of the site, removal of spent fuel, taxes and insurance and social costs should be included. [28]
Similar concerns about underfunding exist in the United States, where the U.S. Nuclear Regulatory Commission has located apparent decommissioning funding assurance shortfalls and requested 18 power plants to address that issue. [29] The decommissioning cost of Small modular reactors is expected to be twice as much respect to Large Reactors. [30]
In France, decommissioning of Brennilis Nuclear Power Plant, a fairly small 70 MW power plant, already cost €480 million (20x the estimate costs) and is still pending after 20 years. Despite the huge investments in securing the dismantlement, radioactive elements such as plutonium, caesium-137 and cobalt-60 leaked out into the surrounding lake. [32] [33]
In the UK, the decommissioning of civil nuclear assets were estimated to be £99 to £232 billion (2020), earlier in 2005 under-estimated to be £20-40 billion. The Sellafield site (Calder Hall, Windscale and the reprocessing facility) alone accounts for most of the decommissioning cost and increase in cost; [21] as of 2015, the costs were estimated £53.2 billion. [25] In 2019, the estimate was even much higher: £97 billion. [34] A 2013 estimate by the United Kingdom's Nuclear Decommissioning Authority predicted costs of at least £100 billion to decommission the 19 existing United Kingdom nuclear sites. [35]
In Germany, decommissioning of Niederaichbach nuclear power plant, a 100 MW power plant, amounted to more than €143 million.[ citation needed ]
Lithuania has increased the prognosis of decommissioning costs from €2019 million in 2010 to €3376 million in 2015. [21]
The decommissioning can only be completed after the on-site storage of nuclear waste has been ended. Under the 1982 Nuclear Waste Policy Act, a "Nuclear Waste Fund", funded by tax on electricity was established to build a geologic repository. On May 16, 2014, collection of the fee was suspended [36] after a complaint by owners and operators of nuclear power plants. By 2021, the Fund had a balance of more than $44 billion, including interest. Later, the Fund has been put back into the general fund and is being used for other purposes. As the plan for the Yucca Mountain nuclear waste repository has been canceled, DOE announced in 2021 the establishing of an interim repository for nuclear waste. [37]
Because the government has failed to establish a central repository, the federal government pays about half-a-billion dollars a year to the utilities as penalty, to compensate the cost of storage at more than 80 ISFSI sites in 35 states as of 2021. [38] As of 2021, the government had paid $9 billion to utility companies for their interim storage costs, which may grow to $31 billion or more. [37]
Nuclear waste costed the American taxpayers through the Department of Energy (DOE) budget as of 2018 about $30 billion per year, $18 billion for nuclear power and $12 billion for waste from nuclear weapons programs. [38]
KPMG estimated the total cost of decommissioning the US nuclear fleet as of 2018 to be greater than US$150 billion. About two-thirds can be attributed to costs for termination of the NRC operating licence; 25% to management of spent fuel; and 10% to site restoration. [19] The decommissioning of only the three uranium enrichment facilities would have an estimated cost (2004) of US$18.7 to 62 billion, with an additional US$2 to 6 billion for the dismantling of a large inventory of depleted uranium hexafluoride. A 2004 GAO report indicated the "costs will have exceeded revenues by $3.5 billion to $5.7 billion (in 2004 dollars)" for the 3 enrichment facilities slated for decommissioning. [39]
Organizations that promote the international sharing of information, knowledge, and experiences related to nuclear decommissioning include the International Atomic Energy Agency, the Organization for Economic Co-operation and Development's Nuclear Energy Agency and the European Atomic Energy Community. [40] In addition, an online system called the Deactivation and Decommissioning Knowledge Management Information Tool was developed under the United States Department of Energy and made available to the international community to support the exchange of ideas and information. The goals of international collaboration in nuclear decommissioning are to reduce decommissioning costs and improve worker safety. [40]
Many warships and a few civil ships have used nuclear reactors for propulsion. Former Soviet and American warships have been taken out of service and their power plants removed or scuttled. Dismantling of Russian submarines and ships and American submarines and ships is ongoing. Russia has a fleet of nuclear-powered vessels in decommissioning, dumped in the Barents Sea. Estimated cost for the decommissioning of the two K-27 and K-159 submarines alone was €300 million (2019), [41] or $330 million. [42] Marine power plants are generally smaller than land-based electrical generating stations.
The biggest American military nuclear facility for the production of weapons-grade plutonium was Hanford site (in the State of Washington), now defueled, but in a slow and problematic process of decontamination, decommissioning, and demolition. There is "the canyon", a large structure for the chemical extraction of plutonium with the PUREX process. There are also many big containers and underground tanks with a solution of water, hydrocarbons and uranium-plutonium-neptunium-cesium-strontium (all highly radioactive). With all reactors now defueled, some were put in SAFSTOR (with their cooling towers demolished). Several reactors have been declared National Historic Landmarks.
A wide range of nuclear facilities have been decommissioned so far. The number of decommissioned nuclear reactors out of the List of nuclear reactors is small. As May 2022, about 700 nuclear reactors have been retired from operation in several early and intermediate stages (cold shut-down, defueling, SAFSTOR, internal demolition), but only about 25 have been taken to fully "greenfield status". [43] Many of these sites still host spent nuclear fuel in the form of dry casks embedded in concrete filled steel drums. [44]
As of 2017, most nuclear plants operating in the United States were designed for a life of about 30–40 years [45] and are licensed to operate for 40 years by the US Nuclear Regulatory Commission. [46] [47] As of 2020, the average age of these reactors was about 39 years. [47] Many plants are coming to the end of their licensing period and if their licenses are not renewed, they must go through a decontamination and decommissioning process. [45] [48] [43]
Generally are not included the costs of storage of nuclear waste, including spent fuel, and maintenance of the storage facility, pending the realization of repository sites for long-term disposal [17] ,p. 246 (in the US Independent Spent Fuel Storage Installations (ISFSI's). [9] Thus many entities do not include the cost of managing spent nuclear fuel, removed from the plant areas that will be decommissioned. [19] There are, however, large differences between countries regarding inclusion of certain costs, such as on-site storage of fuel and radioactive waste from decommissioning, dismanting of non-radioactive buildings and structures, and transport and (final) disposal of radioactive waste. [17] ,p. 61
The year of costs may refer to the value corrected for exchange rates and inflation until that year (e.g. 2020-dollars).
The stated power in the list is preferably given in design net capacity (reference unit power) in MWe, similar to the List of commercial nuclear reactors.
Country | Location | Reactor type | Operative life | Decommissioning | Decommissioning costs |
---|---|---|---|---|---|
Austria | Zwentendorf | BWR 723 MWe | Never activated due to referendum in 1978 [51] | Now a technics museum | |
Belgium | SCK•CEN – BR3, located at Mol, Belgium | PWR (BR-3) | 1962–1987 (25 years) | 2002- [52] | Still unknown |
Bulgaria | Kozloduy Units 1, 2, 3, 4 [53] | PWR VVER-440 (4 x 408 MWe) | Reactors 1,2 closed in 2003, reactors 3,4 closed in 2006 | Ongoing | Still unknown |
Canada | Gentilly Unit 1 (Québec) | CANDU-BWR 250 MWe | 180 days (between 1966 and 1973) | Ongoing | Still unknown stage two:[ clarification needed ] |
Canada | Gentilly-2(Québec) | CANDU-BWR 675 MWe | October 1, 1983 to December 28, 2012 | Ongoing | $1.8 billion (estimated) [57] |
Canada | Pickering NGS Units A2, A3 (Ontario) | CANDU-PWR 8 x 542 MWe | 30 years (from 1974 to 2004) | Ongoing Two units currently in "cold standby" | Still unknown calculated:[ clarification needed ] $270–430/kWe[ citation needed ] |
China [60] | Beijing (CIAE) | HWWR 10 MWe (multipurpose Heavy Water Experimental Reactor for the production of plutonium and tritium) | 49 years (1958–2007) | SAFSTOR until 2027 | Still unknown proposed: $6 million for dismantling |
France [61] | Brennilis | HWGCR 70 MWe | 12 years (1967–1979) | Ongoing Phase 3 | Still unknown already spent €480 million |
France | Bugey Unit 1 | UNGG Gas cooled, graphite moderator | 1972–1994 | Ongoing postponed | Still unknown |
France | Chinon Units 1, 2, 3 | Gas-graphite | (1973–1990) | Ongoing postponed | Still unknown |
France | Chooz-A | PWR 300 MW | 24 years (1967–1991) | 2007- Ongoing Deferred dismantling; [65] | Still unknown |
France | Saint-Laurent | Gas-graphite | 1969–1992 | Ongoing Postponed | Still unknown |
France | Rapsodie at Cadarache | Experimental Fast breeder nuclear reactor (sodium-cooled) 40 MWe | 15 years (1967–1983) | 1983- Ongoing dismantling planned by 2005; general decontamination planned by 2020 [66] | Still unknown |
France | Phénix at Marcoule | Experimental Fast breeder nuclear reactor (sodium-cooled) 233 MWe | 36 years (1973–2009) [67] | 2005- Ongoing | Still unknown |
France | Superphénix at Creys-Malville | Fast breeder nuclear reactor (sodium-cooled) | 11 years (1985–1996) [69] | Ongoing 1) Defuelled | Still unknown |
East Germany | Greifswald Units 1, 2, 3, 4, 5, 6 | VVER-440 5 x 408 MWe | Reactors 1–5 closed in 1989/1990, reactor 6: finished but never operated | Ongoing Immediate | Still unknown |
East Germany | Rheinsberg Unit 1 | VVER-210 70–80 MWe | 24 years (1966–1990) | Ongoing In dismantling | Still unknown |
East Germany | Stendal Units 1, 2, 3, 4 | VVER-1000 (4 x 1000 MWe) | Never activated (1st reactor 85% completed) | Not radioactive (Cooling towers demolished; Structure in exhibition inside an industrial park) | Still unknown |
West Germany | Gundremmingen-A | BWR 250 MWe | 11 years | Ongoing Immediate | Still unknown |
India [73] | Rajasthan Atomic Power Station Unit 1 (Rajasthan) | PHWR 100 MWe (similar to CANDU) | 44 years (1970–2014) | Ongoing | Still unknown |
Italy [74] | Caorso | BWR 840 MWe [75] [76] | 3 years[ citation needed ] (1978 – Closed in 1987 after referendum in 1986) | SAFSTOR: 30 years (internal demolition) | €450 million (dismantling) + €300 million (fuel reprocessing) [77] [78] [79] [80] |
Italy | Garigliano (Caserta) | BWR 150 MWe [81] | Closed on March 1, 1982 | Ongoing | Still unknown |
Italy | Latina (Foce Verde) | Magnox 210 MWe Gas-graphite [82] | 24 years (1962 – Closed in 1986 after referendum) | SAFSTOR: 30 years (internal demolition) | Still unknown |
Italy | Trino Vercellese | PWR Westinghouse, 270 MWe [83] | (Closed in 1986 after referendum) | SAFSTOR: 30 years (internal demolition) | Still unknown |
Japan | Fukushima Dai-ichi Unit 1 | BWR 439 MWe | November 17, 1970 – March 11, 2011 | Ongoing Since 2011 Tōhoku earthquake and tsunami of March 11 | Estimated at ¥10 trillion (US$100 billion) for decontaminating Fukushima and dismantling all reactors in Japan and considering long time damage to environment and economy, including agriculture, cattle breeding, fishery, water potabilization, tourism, loss of reputation in the world (without considering further health care spending and reduction of life expectancy). [89] |
Japan | Fukushima Dai-ichi Unit 2 | BWR 760 MWe | December 24, 1973 – March 11, 2011 | Ongoing | Still unknown |
Japan | Fukushima Dai-ichi Unit 3 | BWR 760 MWe | October 26, 1974 – March 11, 2011 | Ongoing | Still unknown |
Japan | Fukushima Dai-ichi Unit 4 | BWR 760 MWe | February 24, 1978 – March 11, 2011 | Ongoing Since March 11, 2011 Reactor defueled when tsunami hit | Still unknown |
Japan | Fukushima Dai-ichi Unit 5 | BWR 760 MWe | September 22, 1977 – March 11, 2011 | Planned decommissioning Cold shutdown since March 11, 2011 | Still unknown |
Japan | Fukushima Dai-ichi Unit 6 | BWR 1067 MWe | May 4, 1979 – March 11, 2011 | Planned decommissioning Cold shutdown since March 11, 2011 | Still unknown |
Japan | Fukushima Daini Unit 1 [90] | BWR 1067 MWe | July 31, 1981 – 11 March 2011 | Planned decommissioning Cold shutdown since March 11, 2011 [91] | Still unknown |
Japan | Fugen [92] | Advanced thermal reactor (MOX fuel core, heavy water-BWR) 165 MWe | 1979–2003 | Ongoing | Still unknown |
Japan | Tokai Unit 1 | Magnox (GCR) 160 MWe | 1966–1998 | deferred dismantling: 10 years [96] [97] then decon until 2018 | ¥93 billion [98] (€660 million of 2003) |
North Korea | Yongbyon | Magnox-type (reactor for the production of nuclear weapons through PUREX treatment) | 1985–2005 (20 years) Deactivated after a treaty [99] | deferred dismantling; cooling tower dismantled | Still unknown |
Netherlands | Dodewaard | BWR Westinghouse 55 MWe | 1968–1997 (28 years) | 2002-2100+ safe-storage; start dismantling in 2045; separate interim storage of high-level waste at COVRA for 100 years or longer [100] [17] ,p. 171 | estimated cost €134 million (1999); [26] €180 million (2016) [17] ,p. 174 |
Russia | Mayak [101] (Chelyabinsk-65) | PUREX plant for uranium enrichment | 1946–1956 (10 years) | Ongoing | Still unknown |
Russia | Seversk [102] (Tomsk-7) | Three plutonium reactors Plant for uranium enrichment | Two fast-breeder reactors closed (of three), after disarmaments agreements with USA in 2003. [103] | Ongoing | Still unknown |
Slovakia | Jaslovské Bohunice Units 1, 2 [104] [105] | VVER 440/230 2 X 440 MWe | (1978–2006) (1980–2008) | Ongoing | Still unknown |
Spain [106] | José Cabrera | PWR 1 x 160 MWe (Westinghouse) | 38 years (1968–2006) | 2010-2023 [107] [108] [109] | Still unknown Estimation increased from €135 mln in 2003 to €217.8 mln in 2014 [110] |
Spain | Santa María de Garoña (Burgos) | BWR/3 1 x 466 MWe (by Dutch RDM) | 1966–2013 | Ongoing Defueled | Still unknown |
Spain | Vandellós Unit 1 | UNGG 480 MWe (gas-graphite) | 18 years Incident: fire in a turbogenerator (1989) | SAFSTOR: 30 years (internal demolition) | Still unknown Phases 1 and 2: €93 million |
Sweden | Barsebäck Units 1, 2 | BWR 2 x 615 MW | Reactor 1: 24 years 1975–1999 Reactor 2: 28 years 1977 – 2005 | SAFSTOR: demolition will begin in 2020 | The Swedish Radiation Safety Authority has assessed that the costs for decommissioning and final disposal for the Swedish nuclear power industry may be underestimated by SKB by at least 11 billion Swedish kronor ($1.63 billion) [111] |
Sweden | Oskarshamn Units 1, 2 | BWR 1 x 473 MW BWR 1 x 638 MW | Reactor 1: 45 years 1972–2017 Reactor 2: 41 years 1975 – 2016 | Ongoing | Still unknown |
Sweden | Ringhals Units 1, 2 | BWR 1 x 881 MW PWR 1 x 904 MW | Reactor 1: 44 years 1976–2020 Reactor 2: 44 years 1975 – 2019 | Ongoing | Still unknown |
Switzerland [112] | DIORIT | MWe CO2-Gas-heavy water (experimental) | Decommissioned [113] | Still unknown | |
Switzerland | LUCENS | 8,3 MWe CO22-Gas-heavy water (experimental) | (1962–1969) Incident: fire in 1969 | Decommissioned [114] | Still unknown |
Switzerland | SAPHIR | 0,01–0,1 MWe (Light water pool) | 39 years (1955–1994) (Experimental demonstrator) | Decommissioned [114] | Still unknown |
Ukraine | Chernobyl-4 (110 km from Kyiv) | RBMK-1000 1000 MWe | hydrogen explosion, then graphite fire (1986) (INES 7) | Ongoing ENTOMBMENT | Still unknown Future: riding sarcophagus in steel [115] |
Location | Reactor type | Operative life | Decommissioning | Decommissioning costs |
---|---|---|---|---|
Berkeley | Magnox (2 x 138 MWe) | 1962–1989 (27 years) | save storage | Still unknown |
Bradwell | Magnox 2 x 121 MWe | 1962–2002 (40 years) | 2002-2083 or later save storage [116] | Still unknown |
Calderhall Sellafield | Magnox 4 x 60 MWe | 1956-2003 (44–46 years) [117] [118] | save storage [119] | Still unknown |
Chapelcross | Magnox 4 x 60 MWe ("sister reactor" to Calderhall) | 1959–2004 (45 years) | save storage | Still unknown |
Dounreay: DMTR (Research facility of UKAEA) | Fast-neutron reactor | 1958–1969 | Ongoing Demolition contract awarded December 2018 [120] | Still unknown |
Dounreay: DFR (Research facility of UKAEA) | Loop-type fast breeder. 14 MWe. [121] | 1959–1977 | Ongoing [122] | Still unknown |
Dounreay: PFR (Research facility of UKAEA) | Pool-type fast breeder cooled by liquid sodium, fueled with MOX.250 MWe. [123] | 1974–1994 (with average 26.9% load) [124] Delays and reliability problems before reaching full power. [125] | Remotely operated robot 'Reactorsaurus' will be sent in to decontaminate equipment as too dangerous a task for a human. [126] Control panel has been earmarked for an exhibition at London Science Museum (2016). [127] | Still unknown |
Winfrith Dorset | SGHWR 92 MWe | 1968 to 1990 (22 years) | 1995- dismantled; off-site storage of waste [128] | Still unknown |
Location | Reactor type | Operative life | Decommissioning | Decommissioning costs |
---|---|---|---|---|
Connecticut Yankee Connecticut | PWR 619 MWe | 1968–1996 (28 years) | 1998-2007 DECON; on-site ISFSI waste storage [131] | 931 mln; [132] additional $575.5 mln in court awarded from DOE for waste storage at 3 plants [133] |
Crystal River 3 Florida | PWR 825 MWe | 1977–2009 (32 years) | 2013-2037 (estimated) DECON; on-site ISFSI waste storage [134] | In 2013 estimated ~$1,2 bln [135] |
Dresden Unit 1 (Illinois) | BWR 207 MWe | 1960–1978 (18 years) | Defueled in safety in 1998 now in SAFSTOR [136] Fuel in on-site dry-casks. [137] | Still unknown |
Fort St. Vrain (Colorado) | HTGR (helium-graphite) 330 MWe | 1979–1989 (10 years) [138] | 1989-1992 (3 years) dismantled; off-site ISFSI waste storage; replaced by conventional station [139] | $283 million [132] |
Pacific Gas & Electric – Humboldt Bay Unit 3 | BWR 63 MWe | 1963–1976 (13 years) [140] | 1988-2021 (33 years) License terminated in Oct 2021; site released for unrestricted use; New license for on-site storage facility for the spent fuel. [141] | Unknown Fund for $53.3 million required for decommissioning of storage alone. [141] |
Maine Yankee | PWR 860 MWe | 24 years (closed in 1996) | DECON; on-site ISFSI waste storage [142] [143] | $635 million [144] |
Piqua NGS (Ohio) | OCM (Organically Cooled/Moderated) reactor 46 MWe [145] | 2 years (closed in 1966) | ENTOMB (coolant design inadequate for neutron flux) | Still unknown |
Rancho Seco NGS [146] (California) | PWR 913 MWe | 12 years (Closed after a referendum in 1989) | SAFSTOR: 5–10 years completed in 2009 [147] Fuel in insite long-term dry-cask storage | $538.1 million [148] |
San Onofre NGS Unit 1 (California) | PWR 436 MWe Westinghouse Electric Corporation | 1967–1992 (25 years) [149] | 1993-2032 (estimated) dismantled; on-site ISFSI waste storage for whole plant [150] | Still unknown |
San Onofre NGS Units 2, 3 (California) [151] | PWR 1070 MWe 1080 MWe | Unit 2: 1983–2013 Unit 3: 1984–2013 In 2011, Edison finished replacing the steam generators in both reactors with improved Mitsubishi ones, but the new design had several problems, cracked, causing leaks and vibrations. [152] | in defueling.Permanent shutdown – DECON soon defueling [153] | Still unknown 2014 cost forecast: |
Shippingport (Pennsylvania) | BWR 60 MWe | 25 years (closed in 1989) | Decon completed dismantled in 5 years (first small experimental reactor) | $98.4 million [156] |
Three Mile Island Nuclear Generating Station Unit 2 (Pennsylvania) | PWR 913 MWe | 1978–1979 Core meltdown incident | Post-Defuelling Phase 2 (1979) | $805 million (estimated) [157] |
Trojan (Oregon) | PWR 1,180 MWe | 16 years (Closed in 1993 because of proximity to seismic fault) | SAFSTOR (cooling tower demolished in 2006) | [158] |
Vermont Yankee | BWR 620 MWe (General Electric) | 1972–2014 (42 years) | Ongoing 2015– | ~$1.24 billion |
Yankee Rowe (Massachusetts) | PWR 180 MWe | 1961–1991 (30 years) Construction cost was $45 million | completed in 2007 [159] on-site ISFSI waste storage | $608 million (See main article) |
Zion Units 1, 2 (Illinois) | 2 x PWR 1040 MWe (Westinghouse) | 1973/1974–1998 (25 years) | 1998-2020 [160] after SAFSTOR full dismantling; New on-site for spent fuel storage | Costs for SAFSTOR unknown; for dismantling & decontamination estimated in 2010 $1 billion + demolition city fees millions; [161] for remaining waste unknown |
Nuclear power is the use of nuclear reactions to produce electricity. Nuclear power can be obtained from nuclear fission, nuclear decay and nuclear fusion reactions. Presently, the vast majority of electricity from nuclear power is produced by nuclear fission of uranium and plutonium in nuclear power plants. Nuclear decay processes are used in niche applications such as radioisotope thermoelectric generators in some space probes such as Voyager 2. Reactors producing controlled fusion power have been operated since 1958, but have yet to generate net power and are not expected to be commercially available in the near future.
Dry cask storage is a method of storing high-level radioactive waste, such as spent nuclear fuel that has already been cooled in a spent fuel pool for at least one year and often as much as ten years. Casks are typically steel cylinders that are either welded or bolted closed. The fuel rods inside are surrounded by inert gas. Ideally, the steel cylinder provides leak-tight containment of the spent fuel. Each cylinder is surrounded by additional steel, concrete, or other material to provide radiation shielding to workers and members of the public.
Low-level waste (LLW) or low-level radioactive waste (LLRW) is a category of nuclear waste. The definition of low-level waste is set by the nuclear regulators of individual countries, though the International Atomic Energy Agency (IAEA) provides recommendations.
The San Onofre Nuclear Generating Station (SONGS) is a permanently closed nuclear power plant located south of San Clemente, California, on the Pacific coast, in Nuclear Regulatory Commission Region IV. The plant was shut down in 2013 after defects were found in replacement steam generators; it is currently in the process of being decommissioned. The 2.2 GW of electricity supply lost when the plant shut down was replaced with 1.8 GW from new natural-gas-fired power plants and 250 MW from energy-storage projects.
Zion Nuclear Power Station was the third dual-reactor nuclear power plant in the Commonwealth Edison (ComEd) network and served Chicago and the northern quarter of Illinois. The plant was built in 1973, and the first unit started producing power in December 1973. The second unit came online in September 1974. This power generating station is located on 257 acres (104 ha) of Lake Michigan shoreline, in the city of Zion, Lake County, Illinois. It is approximately 40 direct-line miles north of Chicago, Illinois and 42 miles (68 km) south of Milwaukee, Wisconsin.
The Kewaunee Power Station is a decommissioned nuclear power plant, located on a 900 acres (360 ha) plot in the town of Carlton, Wisconsin, 27 miles (43 km) southeast of Green Bay, Wisconsin in Kewaunee County, and south of the city of Kewaunee.
Nuclear power in Canada is provided by 19 commercial reactors with a net capacity of 13.5 gigawatt (GW), producing a total of 95.6 terawatt-hours (TWh) of electricity, which accounted for 16.6% of the country's total electric energy generation in 2015. All but one of these reactors are located in Ontario, where they produced 61% of the province's electricity in 2019. Seven smaller reactors are used for research and to produce radiopharmaceuticals for use in nuclear medicine.
A deep geological repository is a way of storing hazardous or radioactive waste within a stable geologic environment, typically 200–1,000 m below the surface of the earth. It entails a combination of waste form, waste package, engineered seals and geology that is suited to provide a high level of long-term isolation and containment without future maintenance. This is intended to prevent radioactive dangers. A number of mercury, cyanide and arsenic waste repositories are operating worldwide including Canada and Germany. Radioactive waste storage sites are under construction with the Onkalo in Finland being the most advanced.
In the United States, nuclear power is provided by 94 commercial reactors with a net capacity of 97 gigawatts (GW), with 63 pressurized water reactors and 31 boiling water reactors. In 2019, they produced a total of 809.41 terawatt-hours of electricity, and by 2024 nuclear energy accounted for 18.6% of the nation's total electric energy generation. In 2018, nuclear comprised nearly 50 percent of US emission-free energy generation.
The BN-350 was a sodium-cooled, fast reactor located at the Mangyshlak Nuclear Power Plant, located in Aktau, Kazakhstan, on the shore of the Caspian Sea.
Yankee Rowe Nuclear Power Station was a nuclear power plant in Rowe, Massachusetts, located on the Deerfield River in the town of Rowe in western Massachusetts. Its 180 MWe pressurized water reactor operated from 1961 to 1991. It produced electricity for New England consumers. The site is referred to as "Yankee-Rowe" or simply "Rowe", to avoid confusion with Vermont Yankee, another nuclear power station located in nearby Vernon, Vermont. The decommissioning of the site was completed in 2007.
La Crosse Boiling Water Reactor (LACBWR) was a boiling water reactor (BWR) nuclear power plant located near La Crosse, Wisconsin in the small village of Genoa, in Vernon County, approximately 17 miles south of La Crosse along the Mississippi River. It was located directly adjacent to the coal-fired Genoa Station #3. The site is owned and was operated by Dairyland Power Cooperative (Dairyland). Although the reactor has been demolished and decommissioned, spent nuclear fuel is still stored at the location.
Spain has five active nuclear power plants with seven reactors producing 20% of the country's electricity as of 2023.
Nuclear power has various environmental impacts, both positive and negative, including the construction and operation of the plant, the nuclear fuel cycle, and the effects of nuclear accidents. Nuclear power plants do not burn fossil fuels and so do not directly emit carbon dioxide. The carbon dioxide emitted during mining, enrichment, fabrication and transport of fuel is small when compared with the carbon dioxide emitted by fossil fuels of similar energy yield, however, these plants still produce other environmentally damaging wastes. Nuclear energy and renewable energy have reduced environmental costs by decreasing CO2 emissions resulting from energy consumption.
The Humboldt Bay Power Plant, Unit 3 was a 63 MWe nuclear boiling water reactor, owned by Pacific Gas and Electric Company that operated from August 1963 to July 1976 just south of Eureka, California, in an area referred to as King Salmon and Fields Landing.
Nuclear entombment is a method of nuclear decommissioning in which radioactive contaminants are encased in a structurally long-lived material, such as concrete. This prevents radioactive material and other contaminated substances from being exposed to human activity and the environment. Entombment is usually applied to nuclear reactors, but also some nuclear test sites. Nuclear entombment is the least used of three methods for decommissioning nuclear power plants, the others being dismantling and deferred dismantling. The use of nuclear entombment is more practical for larger nuclear power plants that are in need of both long and short term burials, as well as for power plants which seek to terminate their facility licenses. Entombment is used on a case-by-case basis because of its major commitment with years of surveillance and complexity until the radioactivity is no longer a major concern, permitting decommissioning and ultimate unrestricted release of the property. Considerations such as financial backing and the availability of technical know-how are also major factors.
The United Arab Emirates is installing nuclear-powered plants to meet their electricity demand, which is estimated to increase from 15 GWe to over 40 GWe in 2020. In December 2009, the US and UAE signed a Section 123 Agreement for peaceful nuclear cooperation. The UAE has also signed Nuclear Non-Proliferation Treaty (NPT), along with the additional protocol.
SAFSTOR is a nuclear decommissioning method in which a nuclear power plant or facility governed by the United States Nuclear Regulatory Commission, is "placed and maintained in a condition that allows the facility to be safely stored and subsequently decontaminated to levels that permit release for unrestricted use".
The nuclear energy policy of the United States began in 1954 and continued with the ongoing building of nuclear power plants, the enactment of numerous pieces of legislation such as the Energy Reorganization Act of 1974, and the implementation of countless policies which have guided the Nuclear Regulatory Commission and the Department of Energy in the regulation and growth of nuclear energy companies. This includes, but is not limited to, regulations of nuclear facilities, waste storage, decommissioning of weapons-grade materials, uranium mining, and funding for nuclear companies, along with an increase in power plant building. Both legislation and bureaucratic regulations of nuclear energy in the United States have been shaped by scientific research, private industries' wishes, and public opinion, which has shifted over time and as a result of different nuclear disasters.
SOGIN is an Italian state-owned enterprise responsible for nuclear decommissioning as well as management and disposal of radioactive waste produced by industrial, research and medical processes. Founded in 1999 following the 1987 Italian referendums on nuclear power, SOGIN was originally part of state owned ENEL but became independent, but still government owned, in 2000. The company initially took over the Caorso, Enrico Fermi, Garigliano and Latina nuclear power plants, later adding other sites including ENEA's EUREX. The company has commenced the decommissioning of all the plants and is predicted to complete the work in 2036. The company has been involved in environmental remediation, radioactive waste management and nuclear safety work in Armenia, Bulgaria, China, Czech Republic, France, Kazakhstan, Lithuania, Romania, Russia, Slovakia and Ukraine. SOGIN also undertakes other decontamination work and in 2005 started to help to decommission nuclear submarines of the Russian Navy.
{{cite journal}}
: Cite journal requires |journal=
(help){{cite journal}}
: Cite journal requires |journal=
(help)