Penn Station Access (PSA) is a public works project underway by the Metropolitan Transportation Authority in New York City. The goal of the project is to allow Metro-North Railroad commuter trains to access Penn Station on Manhattan's West Side, using existing trackage owned by Amtrak. Metro-North trains currently terminate exclusively at Grand Central in Midtown Manhattan.
The project is scheduled to complement Grand Central Madison, which opened as part of East Side Access in 2023, and will commence in two separate phases. The first phase, which is under construction, will add four new stations along the Hell Gate Line (part of the Northeast Corridor) in the Bronx and route some New Haven Line trains to Penn Station. The second phase, which is unfunded, would add two more stations along the Empire Connection/West Side Line on Manhattan's West Side; this would be served by the Hudson Line. An agreement for the first phase was reached in early 2019, and a groundbreaking ceremony took place in December 2022. New Haven Line trains are tentatively expected to run into Penn Station in 2027. The opening of East Side Access will allow the expanded services to operate at Moynihan Train Hall, an expansion of Penn Station.
A 1969 proposal by the North Bronx Transportation Project considered running trains via the Hell Gate Bridge to Penn Station, with travel times estimated to be 25 minutes. Some plans for the Second Avenue Subway included integration with the upper portion of the line, providing express service from the East Side of Manhattan to Co-op City and Parkchester. This line was also considered for through-running with the Northeast Corridor in New Jersey, easing travel for residents of Westchester and Connecticut trying to get to New Jersey. [1] : 104, 128, 130
While not proposed officially, in June 1973, two Congressmen and the Mayor of Yonkers proposed having trains run from Stamford, Connecticut, to Penn Station, making stops at Pelham Manor, Co-op City, and Parkchester/Van Nest. They proposed that the line be operated by the MTA pending completion of the Second Avenue Subway, which was under construction at the time and slated to be completed in 1980. Sixty percent of Co-op City residents that responded to a survey said that they would have used the proposed rail service. [2]
The Penn Station Access project was initiated on September 2, 1999, when the Federal Transit Administration (FTA), in conjunction with Metro-North Railroad, issued a Notice of Intent (NOI) to prepare a Major Investment Study/Environmental Impact Statement (EIS). The EIS was intended to consider possible additions to Metro-North using existing rail lines, with the intention of providing flexibility and increased regional access. [3] Rail alternatives originally considered included Hudson and New Haven service, via the Empire Connection and Hell Gate Line, respectively, and a Harlem Line option via wyes at Mott Haven and Spuyten Duyvil. [4] : A-3 [5]
In November 2000, the Final Scoping Document for Penn Station Access was completed, showing 18 alternatives, including a no-build option, a Transportation Systems Management option, various commuter rail options, and alternatives using other modes. Various alternatives considered various ways to run service to Penn Station from the New Haven Line, the Hudson Line, and the Harlem Line, either during all times, or only operating during off-peak hours and weekends. Existing Metro-North riders would have the choice of arriving at either Penn Station or Grand Central on the New Haven Line and the Hudson Line. [6] Service from the New Haven Line would diverge at New Rochelle, using Amtrak's Hell Gate Line to access Penn Station, while service from the Hudson Line would split off at Spuyten Duyvil station via Amtrak's Empire Connection. The alternatives via the Harlem Line would have required the construction of wye tracks. One option would have branched off of the Harlem Line at Mott Haven, using a wye track to go north via the Hudson Line. Using a newly constructed wye track at Spuyten Duyvil, service would turn south via the Empire Connection before reaching Penn Station. Another option considered would have constructed a wye track at Woodlawn, allowing Harlem trains to go east and head down the Hell Gate Line to Penn Station. The final option would have required the reconstruction of the Port Morris Branch and the Hell Gate Line. An additional option would have extended service from Grand Central to Penn Station through the construction of a new tunnel. [7] : 14–16 [8]
In September 2002, a second screening took place narrowing five alternatives to four, and narrowing 20 potential station locations in the Bronx, Queens and Manhattan to five locations. The remaining alternatives considered would have used either the Hudson or New Haven Lines. The Harlem Line options were removed from consideration. The five remaining stations under consideration were at West 125th Street and West 59th Street under the Hudson alternative, and at Co-Op City, Parkchester and Hunts Point under the New Haven alternative. [3] The preferred alternatives would have used 3 miles (4.8 km) of trackage, and would have involved the construction of six new Metro-North stations in the Bronx and Manhattan, allowing riders in these areas to easily access Penn Station, Westchester, Dutchess, and Putnam counties upstate as well as Fairfield and New Haven counties in Connecticut. [9] [10] Existing Metro-North riders would have the choice of arriving at either Penn Station or Grand Central on the New Haven Line and the Hudson Line. [6]
Afterwards, in coordination with the current rail operators at Penn Station (Amtrak, LIRR, and New Jersey Transit) it was determined that there were several operational limitations with the Hudson Line service alternative, mainly because the Empire Line's connection into Penn Station consists of only one track. The connection only leads to tracks 1–8 at Penn, which are used primarily by NJ Transit, with some usage by Amtrak. Since the implementation of Penn Station Access via the Hudson Line would have required substantial service reductions to those Penn Station tracks by NJ Transit and Amtrak or a new connection between the Empire Line and the LIRR tracks at Penn, progress did not continue on this alternative. Even though the Hell Gate Line alternative was chosen, this alternative is still being considered by Metro-North as capacity improvements at Penn Stations are underway, such as the Gateway tunnels. [11] Penn Station Access would also provide system resiliency to protect service in the event of natural or other disasters. [12]
By 2011, Metro-North had initiated a federal environmental study for Penn Station Access, to be completed by 2013. The cost of the project was estimated at $350 million with the state of Connecticut funding $100 million and the state of New York funding the remaining $250 million. [13] [14]
Penn Station Access - Phase One | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
The first piece of Penn Station Access would route some New Haven Line trains down Amtrak's Northeast Corridor to Penn Station. The New Haven Line to Grand Central splits off from the Northeast Corridor near New Rochelle. The Northeast Corridor (also known here as the Hell Gate Line) continues south crossing the Pelham Bay Bridge into the Bronx, the Hell Gate Bridge into Queens, and entering Manhattan through the East River Tunnels also used by the Long Island Rail Road. This phase includes the construction of four new Metro-North stations in the Bronx to be served by the New Haven Line, located in Co-op City, Morris Park, Parkchester/Van Nest, and Hunts Point. [10] The stations would provide fast, direct rides to West Midtown and facilitate reverse-commuting trips to Westchester County and Connecticut. [12] The new stations would provide transit access to the transit-deficient East Bronx. [15]
Previously, a station was also considered to be built in Astoria, Queens; however, analysis showed that there would not be enough riders to justify the high cost of constructing a station. [16] [17] The construction of a station was projected to cost over $20 million, and the station would only be able to be four cars long. The station would only have a projected annual ridership of 310,367. [17] Since 2014, local residents have pushed to have a Metro-North station built in Queens, either between 41st and 44th Streets in Astoria, or at Northern Boulevard and Broadway in Woodside. [18] [16] [19]
On January 8, 2014, then-New York Governor Andrew Cuomo voiced support for the project in his 2014 State of the State address. [12] With his support for the project, $695 million was budgeted for the project in the MTA's 2015–2019 Capital Program. [20] In order to accommodate more trains, power and signal systems, and yards at Penn Station and New Rochelle [21] will be upgraded and three railroad bridges will be rehabilitated or replaced. [15] In addition, a third track will be installed between the Parkchester/Van Nest station and north of the Co-Op City station, and additional switches will be added. Metro-North service to Penn Station will begin after the completion of the East Side Access project, which has diverted some Long island Rail Road trains to Grand Central, therefore opening up slots at Penn Station for Metro-North service. [20] During peak hours there will be between six and ten trains to Penn Station. There will be four trains per hour to Connecticut in the reverse peak direction, and there will be two trains per hour to and from Penn Station during off-peak and weekends. [22]
The project would add redundancy to the regional transportation network in case of service interruption. Regional connectivity will be increased with accessible transfers to Amtrak, the Long Island Rail Road and New Jersey Transit at Penn Station. Through-running between the New Haven Line and NJ Transit would be possible, linking business centers in Connecticut and New Jersey while providing access to Newark Liberty Airport. [22] The draft Environmental Assessment was to be made available for public review in late 2018. [11] In September 2017, the proposed alignment for the project only had three tracks through Hunts Point. [23]
At the MTA's Metro-North Railroad Committee meeting on January 22, 2019, it was announced that Amtrak and the MTA had reached an agreement regarding track usage rights, and $35 million was approved for initial engineering design work. [24] In addition, HNTB New York Engineering and Architecture received a $35 million contract to consult on the planning of the four new stations. [25] [26] [27] In exchange for being allowed to use the Hell Gate Line and build the four stations, the MTA agreed to replace the Pelham Bay Bridge across the Hutchinson River, as well as pay access fees for using the Hell Gate Bridge. Amtrak and the MTA also agreed to conduct a joint study on the feasibility of extending Amtrak service to Long Island via the tracks used by the LIRR. [28] [29] As part of the project, three track interlockings would be built, one existing interlocking would be rehabilitated, and the line would be widened from three to four tracks between the Hell Gate and Pelham Bay Bridges. [30] : 50 The expanded services will operate at Moynihan Train Hall, an expansion of Penn Station into the neighboring James A. Farley Building. [31]
Design for the project began in February 2019, and construction was expected to begin in late 2020, with an expected opening by 2023. [30] : 53 By February 2020, the MTA had identified three firms that were qualified to bid on the design–build contracts for Penn Station Access. At that point, the project's opening date was announced as 2024. [32] [33] Shortly afterward, work was placed on hold due to the COVID-19 pandemic in the United States. [34] The FTA published a draft EIS in May 2021, and the state government commenced a request for proposals for the project's development. [35] The project's completion was then announced for 2025. [36] On September 28, 2021, the FTA issued a Finding of No Significant Impact (FONSI) for the project, allowing the project to move forward. [37] The FRA issued a FONSI for the project on November 16, 2021. In December 2021, it was announced that completion of the line would be delayed until 2027. [38]
On December 13, 2021, it was announced that Senate Majority Leader Chuck Schumer had helped broker a deal with the MTA and Amtrak to fund $500 million for the PSA project and $432 million for the rehabilitation of the East River Tunnels using money available due to the passage of the Infrastructure Investment and Jobs Act. [39] On December 15, the MTA Board approved the award of a 63-month design-build contract for the project to a joint venture of Halmar International and RailWork Transit for $1,850,643,000, of which $133,580,000 was for an option to complete improvements in New Rochelle Yard. The MTA Board also approved a cost sharing agreement with Amtrak that set the conditions for the completion of the project on Amtrak's right-of-way. Amtrak agreed to fund $500 million of the project costs as it derived some benefits from the project. [40]
On the same date, the MTA Board approved the awarding of an 86-month contract to WSP USA and Atlas ATC Engineering for project management. The contract was awarded for $116,572,815, with an option for $17,035,237. [41] Furthermore, the MTA Board approved an amendment to the 2020–2024 Capital Program to increase the entire cost of the project to $2.867 billion, and defer $460 million of the project costs, including the option for improvements in New Rochelle Yard and some contingencies and support costs, to a future date. The amendment would increase funding in the 2020–2024 program from $1.131 billion to $2.052 billion, or $920.8 million; $452 million for the project was in the 2015–2019 program. The entire budget for the project went up from $1.561 billion to $2.482 billion. The cost increase was due to bids that were received, increases in the price of construction materials and labor, additional scope required by Amtrak, including expanded power and communication upgrades and a fourth track, and limitations on labor support committed by Amtrak and track outages. Funding for the budget increase would be made using the $500 million in Amtrak funding, and the reallocation of funding from other projects in the Capital Program. [42]
A groundbreaking ceremony for Penn Station Access took place in the Bronx on December 9, 2022, [43] [44] marking the official start of construction. [45] Although the project was initially supposed to be completed by March 2027, [46] MTA officials indicated in January 2023 that the first phase of Penn Station Access could be postponed by six to nine months. [47] [48] According to MTA Construction and Development president Jamie Torres-Springer, the Hell Gate Line had to be partially closed to allow work on Penn Station Access to proceed, but Amtrak had refused to approve a plan that would have closed the line at night and during the weekend. Torres-Springer said the MTA had proposed closing the line for up to eight months beginning in March 2023 but that Amtrak had not yet approved the proposal. [48] Without a temporary closure of the Hell Gate Line, the project would not be complete until at least October 2027. [46] The federal government provided $1.6 billion for the project in late 2023. [49] [50]
In August 2024, the New York City Council voted to rezone 46 city blocks in Parkchester, Van Nest, and Morris Park, around the Metro-North Railroad's Parkchester/Van Nest and Morris Park stations, as part of the Penn Station Access project. The city government also promised to spend $500 million on infrastructure upgrades around these stations. The rezoning was intended to encourage development around these stations. [51] [52] As a result, up to 7,000 housing units could be constructed in the three neighborhoods. [53] [54]
New Haven Line service to Penn Station already existed in a very limited fashion, the Train to the Game, which ran between New Haven and NJ Transit's Secaucus Junction. Connecting service to Meadowlands station brought riders to Sunday 1 PM NFL games played by the New York Jets and New York Giants. This special service, operated using NJ Transit equipment, stopped at Penn Station, but that was only a secondary benefit of the operation. [55]
Penn Station Access - Phase Two | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
The second part of the project would bring Hudson Line trains into Penn Station using Amtrak's Empire Connection, which runs on Manhattan's West Side via the West Side Line. The Empire Connection branches off from the Hudson Line near Spuyten Duyvil station, just north of the eponymous bridge across Spuyten Duyvil Creek, and is currently used by Amtrak's Empire Corridor trains traveling from Upstate New York, Canada, and other destinations. The majority of the Empire Connection is not electrified, so the M3A and M7A electric railcars in use on the Hudson Line would be unable to travel to Penn Station unless the line is electrified. The former New York Central Railroad lines, including the Hudson Line, use under-running third rail. Tracks in Penn Station and on the LIRR use over-running third rail. Any Metro-North cars traveling from the Hudson Line to Penn Station would have to be specially equipped to operate with both current collection systems. This phase includes a proposal for two new Metro-North stations to be served by the Hudson Line. Both stations would be located in Manhattan along the Empire Connection: one at West 125th Street in Manhattanville and the other near 62nd Street on the Upper West Side. [56]
Penn Station Access will add new tracks along the Hell Gate Line right-of-way, relocate, reconfigure, and add new interlockings, realign and install new catenaries, construct four new stations, replace and repair undergrade bridges, upgrade existing AC substations, and construct new AC substations. Since M8 rolling stock cannot operate under Amtrak's 25 Hz traction power system between Gate Interlocking and just east of Harold Interlocking, the project will also install 3 miles (4.8 km) of third rail and two new DC substations at Gate and Woodside. The MTA had considered relocating the existing AC phase break from Gate to Harold. The project would also upgrade New Rochelle Yard and replace the existing wayside signaling with a higher-density signaling system to accommodate the increased level of service on the line. C Yard in Penn Station will be modified minimally with the reenergizing of the third rail on Track 3 in the yard, which had been used to store Long Island Rail Road maintenance-of-way trucks. These changes would allow three train sets to be stored in the yard. [57]
The MTA had the design consultant study the feasibility of building a tunnel connecting the Hunts Point station on PSA with the Hunts Point Avenue station on the IRT Pelham Line. It also had them study whether it made sense to reuse the historic Westchester Avenue station headhouse for the Hunts Point station. [57] : 22
It has been proposed to have Harlem Line access to Penn Station as well by reactivating the abandoned Port Morris Branch in the South Bronx. The reactivated railroad branch would connect the Harlem Line to the Hell Gate Line. [19] However, these plans have been complicated due to the private ownership of the land next to the right-of-way, [58] as well as a new housing development directly on the right-of-way at 156th Street. [59]
The Long Island Rail Road, often abbreviated as the LIRR and verbalized "L-I-Double-R", is a railroad in the southeastern part of the U.S. state of New York, stretching from Manhattan to the eastern tip of Suffolk County on Long Island. The railroad currently operates a public commuter rail service, with its freight operations contracted to the New York and Atlantic Railway. With an average weekday ridership of 354,800 passengers in 2016, it is the busiest commuter railroad in North America. It is also one of the world's few commuter systems that runs 24/7 year-round. It is publicly owned by the Metropolitan Transportation Authority, which refers to it as MTA Long Island Rail Road. In 2023, the system had a ridership of 75,186,900, or about 276,800 per weekday as of the first quarter of 2024.
Pennsylvania Station is the main intercity railroad station in New York City and the busiest transportation facility in the Western Hemisphere, serving more than 600,000 passengers per weekday as of 2019. The station is located beneath Madison Square Garden in the block bounded by Seventh and Eighth Avenues and 31st and 33rd Streets and in the James A. Farley Building, with additional exits to nearby streets, in Midtown Manhattan. It is close to several popular Manhattan locations, including Herald Square, the Empire State Building, Koreatown, and Macy's Herald Square.
Metro-North Railroad, trading as MTA Metro-North Railroad, is a suburban commuter rail service operated by the Metropolitan Transportation Authority (MTA), a public authority of the U.S. state of New York. Metro-North serves the New York Metropolitan Area, running service between New York City and its northern suburbs in New York and Connecticut, including Port Jervis, Spring Valley, Poughkeepsie, Yonkers, New Rochelle, Mount Vernon, White Plains, Southeast and Wassaic in New York and Stamford, New Canaan, Danbury, Bridgeport, Waterbury, and New Haven in Connecticut. Service in Connecticut is operated under contract with the Connecticut Department of Transportation. Metro-North also provides local rail service within the New York City boroughs of Manhattan and the Bronx.
The Northeast Corridor (NEC) is an electrified railroad line in the Northeast megalopolis of the United States. Owned primarily by Amtrak, it runs from Boston in the north to Washington, D.C. in the south, with major stops in Providence, New Haven, Stamford, New York City, Newark, Trenton, Philadelphia, Wilmington, and Baltimore. The NEC closely parallels Interstate 95 for most of its length. Carrying more than 2,200 trains a day, it is the busiest passenger rail line in the United States by ridership and service frequency.
Beacon station is a commuter rail station on the Metro-North Railroad Hudson Line located in Beacon, New York. The station has three tracks, with one island platform and one side platform.
Harlem–125th Street station is a commuter rail stop serving the Metro-North Railroad's Hudson, Harlem, and New Haven Lines. It is located at East 125th Street and Park Avenue in East Harlem, Manhattan, New York City. The station also serves as an important transfer point between the Metro-North trains and the New York City Subway's IRT Lexington Avenue Line for access to the Upper East Side of Manhattan. It is the only station besides Grand Central Terminal that serves all three lines east of the Hudson River. Trains leave for Grand Central Terminal, as well as to the Bronx and the northern suburbs, regularly.
Fordham station, also known as Fordham–East 190th Street station, is a commuter rail stop on the Metro-North Railroad's Harlem and New Haven Lines, serving Fordham Plaza in the Fordham neighborhood of the Bronx, New York City. The platforms are situated just below street level and feature two expanded side platforms that serve eight cars each, on the outer tracks. The station building sits above the tracks on the Fordham Road overpass, and still bears the name New York Central Railroad on its facade. The station is among the busiest rail stations in the Bronx.
The Harlem Line is an 82-mile (132 km) commuter rail line owned and operated by the Metro-North Railroad in the U.S. state of New York. It runs north from New York City to Wassaic, in eastern Dutchess County. The lower 53 miles (85 km) from Grand Central Terminal to Southeast, in Putnam County, is electrified with a third rail and has at least two tracks. The section north of Southeast is a non-electrified single-track line served by diesel locomotives. Before the renaming of the line in 1983, it eventually became the Harlem Division of the New York Central Railroad. The diesel trains usually run as a shuttle on the northern end of the line, except for rush-hour express trains in the peak direction.
The New Haven Line is a 72.7 mi (117.0 km) commuter rail line operated by the Metro-North Railroad in the U.S. states of New York and Connecticut. Running from New Haven, Connecticut, to New York City, the New Haven Line joins the Harlem Line in Mount Vernon, New York, and continues south to Grand Central Terminal in Manhattan. The New Haven Line carries 125,000 passengers every weekday and 39 million passengers a year. The busiest intermediate station is Stamford, with 8.4 million passengers, or 21% of the line's ridership.
The Hudson Line is a commuter rail line owned and operated by the Metro-North Railroad in the U.S. state of New York. It runs north from New York City along the east shore of the Hudson River, terminating at Poughkeepsie. The line was originally the Hudson River Railroad, and eventually became the Hudson Division of the New York Central Railroad. It runs along what was the far southern leg of the Central's famed "Water Level Route" to Chicago.
Woodlawn station is a commuter rail stop on the Metro-North Railroad's Harlem Line, serving the Woodlawn section of the Bronx, New York City. It is located on East 233rd Street near Webster Avenue. Just north of the station is Woodlawn Junction, where the New Haven Line splits from the Harlem Line to join the Northeast Corridor.
East Side Access (ESA) is a public works project in New York City that extended the Long Island Rail Road (LIRR) two miles from its Main Line in Queens to the new Grand Central Madison station under Grand Central Terminal on Manhattan's East Side. The Metropolitan Transportation Authority (MTA) project was originally scheduled to open in 2009 but was delayed by more than a decade. The new station and tunnels opened with limited service to Jamaica station in Queens on January 25, 2023, before full service began on February 27, 2023. The estimated cost of the project rose over threefold from US$3.5 billion to US$11.1 billion as of April 2018, making it one of the world's most expensive underground rail-construction projects.
Yankees–East 153rd Street station is a commuter rail stop on the Metro-North Railroad's Hudson Line, serving Yankee Stadium and the Concourse neighborhood in the Bronx, New York City. It opened on May 23, 2009, and provides daily local service on the Hudson Line.
The Pelham Bay Bridge, also known as the Amtrak Hutchinson River Bridge, is a two-track movable railroad bridge that carries the Northeast Corridor (NEC) over the Hutchinson River in the Bronx, New York, upstream from the vehicular/pedestrian Pelham Bridge. It is owned by Amtrak, which provides passenger service, and is used by CSX Transportation and the Providence & Worcester Railroad for freight traffic.
Harold Interlocking is a large railroad junction located in New York City. It is the busiest rail junction in the United States. It serves trains on Amtrak's Northeast Corridor and the Long Island Rail Road's Main Line and Port Washington Branch, which diverge at the junction.
The Hell Gate Line is the portion of Amtrak's high-speed Northeast Corridor between Harold Interlocking in Sunnyside, Queens, and Shell Interlocking in New Rochelle, New York, within the New York metropolitan area.
Co-op City station is a planned passenger rail station on the Metro-North Railroad's New Haven Line, to be located in the Co-op City neighborhood of the Bronx in New York City. The station is planned to open in 2027 as part of the Penn Station Access project. The station will be located under Interstate 95 along the southern edge of Co-op City, with two entrances on the north side of the tracks.
Morris Park station is a planned passenger rail station on the Metro-North Railroad's New Haven Line, to be located in the Morris Park neighborhood of the Bronx in New York City. The station is planned to open in 2027 as part of the Penn Station Access project. It will be located at Morris Park Avenue adjacent to the Albert Einstein College of Medicine, with entrances from both sides of the tracks. Groundbreaking took place in December 2022.
Parkchester/Van Nest station is a planned passenger rail station on the Metro-North Railroad's New Haven Line, to be located within Bronx Community Board 11 in Van Nest and just north of the Parkchester neighborhood of the Bronx in New York City. The station is planned to open in 2027 as part of the Penn Station Access project, which will add four stations in the Bronx. It will be located east of Unionport Road, with entrance from East Tremont Avenue.
Hunts Point station is a planned passenger rail station on Metro-North Railroad's New Haven Line, to be located in the Hunts Point neighborhood of the Bronx in New York City. The station is planned to open in 2027 as part of the Penn Station Access project, which will add four stations in the Bronx. The station will be located north of Hunts Point Avenue, behind the former New York, New Haven and Hartford Railroad station, which was designed by Cass Gilbert.