Alstom Metropolis C851E (Circle Line)

Last updated

Alstom Metropolis C851E (Circle Line)
C851E CCL interior.jpg
Stock typeElectric multiple unit
In service13 April 2026;6 months ago (2026-04-13) – Present
Manufacturer Alstom
Built at Barcelona, Spain
Family name Metropolis
Constructed2021 – 2025
Entered service13 April 2026;6 months ago (2026-04-13)
Number built69 Vehicles (23 Sets)
Number in service69 Vehicles (23 Sets)
Formation3 cars per trainset (Mc1–T–Mc2)
Fleet numbers865 – 887
Capacity931 passengers (148 seats)
Operator SMRT Trains Ltd (SMRT Corporation)
Depot Kim Chuan
Line served Circle Line CCL symbol.svg Circle Line
Specifications
Car body constructionWelded aluminium
Train length70.1 m (229 ft 11+7⁄8 in)
Car length
- 23.65 m (77 ft 7+1⁄8 in) (Mc)

- 22.8 m (74 ft 9+5⁄8 in) (T)

Width3.2 m (10 ft 6 in)
Height3.7 m (12 ft 1+5⁄8 in)
Doors1,450 mm (57+1⁄8 in), 8 per car, 4 per side
Maximum speed
- 90 km/h (56 mph) (design)

- 78 km/h (48 mph) (service)

Traction systemAlstom OPTONIX IGBT–VVVF [1]
Acceleration 0.95 m/s2 (3.1 ft/s2)
Deceleration 1.3 m/s2 (4.3 ft/s2) (Emergency)
Electric systems 750 V DC   third rail
Current collection Collector shoe
UIC classification Bo′Bo′+2′2′+Bo′Bo′
Braking systems Regenerative and pneumatic
Safety systems Alstom URBALIS 300 moving block CBTC ATC under ATO GoA 4 (UTO), with subsystems of ATP, Iconis ATS and Smartlock CBI [2] [3]
Coupling system Scharfenberg
Track gauge 1,435 mm (4 ft 8+1⁄2 in) standard gauge

The Alstom Metropolis C851E (Circle Line) is the third generation electric multiple unit rolling stock introduced on the Circle Line of Singapore's Mass Rapid Transit (MRT) system, manufactured by Alstom under Contract 851E. It consists of 23 three-car trains built alongside six six-car trains for the North East Line. The trains were manufactured and assembled in Alstom's manufacturing facility in Barcelona, Spain and progressively shipped to Singapore from 2022. [4] The contract, valued at around S$250 million, was awarded by the Land Transport Authority (LTA) during a ceremony held at Sengkang Depot. [5] Alstom was the sole bidder for this contract. [6]

Contents

Tender

The tender for trains under the contract C851E was closed on 2 October 2017 with Alstom being the sole bidder for this contract. [6] The LTA shortlisted and published the tender results.

S/NName of tendererAmount (S$) Offer 1 [7] Amount (S$) Offer 2 [7] Remarks
1 Alstom Transport S.A. / Alstom Transport (S) Pte Ltd Consortium279,782,872.00293,489,289.00Offer 1 in mixed currencies; S$410,100,934.00 (Alternative in mixed currencies)

Contract 851E was awarded to the sole bidder, Alstom, at a cost of S$250 million on 30 April 2018. [6] [5]

Overview

The 23 trains supplement the existing C830 and C830C trains on the Circle Line, coinciding with the 4.3-kilometre (2.7 mi) long extension from HarbourFront to Marina Bay via Keppel, Cantonment and Prince Edward Road, which all three opened on 12 July 2026. The first train set arrived in Singapore on 11 March 2022. [8] The first of these trains entered passenger service on 13 April 2026. [9]

Features

To enable a more robust maintenance regime, all the new trains are equipped with condition monitoring systems to gather data from equipment on the trains. This enables continuous monitoring of the health of the equipment and allows the operator to carry out predictive maintenance for the trains. Contact shoe sensors on the new Circle Line trains enable the operator to react promptly and take necessary measures if any dislodgement is detected [10] .

They are fully automated (GoA4) and do not require an attendant on board. [11]

On the Circle Line, the trains draw 750 V DC power from a bottom-contact third rail. Each 3-car train (Formation: Mc1–Tc–Mc2) comprises two Motor Cars (Mc1 and Mc2) at each end, and an unpowered Trailer Car (Tc) in the middle. The interior of the Circle Line C851E remains largely consistent with its predecessor, the C830C, save for a few subtle differences such as the colour scheme of the seats, enhanced cabin lighting, as well as the LED text displays being identical to the trains on the North East Line. [12]

Automatic Track Inspection (ATI)

Two of the Circle Line C851E trains are each fitted with an Automatic Track Inspection (ATI) System, which enables monitoring of the running rails, track equipment, and sleepers while the trains are in operation. [4] The ATI system uses a network of cameras, lasers, and sensors installed on train bogies to detect defects like rail cracks or missing fasteners. [13] The CCL trains fitted with ATI are sets 867 and 868. [8]

Train formation

The coupling configuration of a CCL C851E in revenue service is Mc1–T–Mc2. [14]

Cars of C851E (Circle Line)
Car typeQuantity Driver cab Motor Collector shoe Car lengthWheelchair bay
mft in
Mc2✓23.6577 ft 7.1 in✗
T1✗✓22.874 ft 9.6 in✓

The car numbers of the trains range from 8065x to 8087x, where x depends on the carriage type. Individual cars are assigned a five-digit serial number by the rail operator SMRT Trains. A complete three-car trainset consists of one trailer (T) and two driving motor (Mc) cars permanently coupled together. For example, set 865 consists of carriages 80651, 80652, and 80653.

See also

References

  1. ↑ "Alstom to supply 34 Metropolis trains and signalling upgrade to Singapore metro". French Chamber Singapore. Archived from the original on 24 September 2015. Retrieved 9 August 2015.
  2. ↑ "Singapore Northeast Line: will soon be the largest, fully automatic metro system in the world" (PDF). pp. 4 to 8. Archived (PDF) from the original on 15 June 2020. Retrieved 16 June 2020.
  3. ↑ "URBALIS Evolution: Controlling the Performance" (PDF). p. 4. Archived (PDF) from the original on 15 June 2020. Retrieved 16 June 2020.
  4. 1 2 "Alstom to Supply 17 New Trains for North East Line Extension and Circle Line 6". Land Transport Authority . 30 April 2018. Archived from the original on 10 July 2021. Retrieved 23 November 2019.
  5. 1 2 Lim, Adrian (30 April 2018). "Alstom to supply 17 new MRT trains for North East Line and Circle Line". The Straits Times. Archived from the original on 16 November 2021. Retrieved 30 April 2018.
  6. 1 2 3 "Tender information". www.lta.gov.sg. Archived from the original on 26 July 2018. Retrieved 2 May 2018.
  7. 1 2 "851E Schedule" (PDF). www.lta.gov.sg. Archived (PDF) from the original on 15 September 2018. Retrieved 15 September 2018.
  8. 1 2 "New train for Circle Line MRT arrives in Singapore; first of 23 to be shipped here". The Straits Times. 11 March 2022. Archived from the original on 14 March 2022. Retrieved 16 March 2022.
  9. ↑ Chia, Laura (11 April 2026). "'For the record, it's orange, not yellow': LTA unveils new Circle Line trains in signature colour". The Straits Times . Retrieved 11 April 2026.
  10. ↑ "LTA | Circle Line 6". www.lta.gov.sg. Retrieved 9 November 2026.
  11. ↑ "Circle Line | Land Transport Guru". 28 February 2016. Retrieved 9 November 2026.
  12. ↑ Closing, Doors Are (30 April 2018). "Alstom Metropolis C851E (Circle Line) | Land Transport Guru" . Retrieved 9 November 2026.
  13. ↑ "Factsheet: Technology for Depots and Trains to Improve Rail Reliability". Land Transport Authority. Archived from the original on 17 February 2020. Retrieved 17 February 2020.
  14. ↑ "Alstom Metropolis C851E (Circle Line)". SGTrains. Retrieved 9 November 2026.