HSR Next | |
---|---|
Overview | |
Locale | Hamilton, Ontario, Canada |
Transit type | Light rail / bus rapid transit |
Number of lines | 6 |
Website | (Re)envision the HSR |
Operation | |
Operator(s) | Hamilton Street Railway (buses), TBD (LRT) |
Technical | |
Track gauge | 1,435 mm (4 ft 8+1⁄2 in) standard gauge |
HSR Next is a proposal for a frequent rapid transit system operated by the Hamilton Street Railway in the city of Hamilton, Ontario, Canada. The plans include an overhaul of the existing bus network, converting it from a hub-and-spoke network to a point-to-point network. Also included are six rapid routes, with one light rail transit (LRT) line, and five bus rapid transit (BRT) lines, alongside changes to local routes and additional on-demand transit zones. As of July 6,2025 [update] , the system is awaiting approval from Hamilton City Council and is planned for implementation beginning September 2026.
In 1981, during Bill Davis's Progressive Conservative administration, the Province of Ontario offered to finance the construction of a light metro in Hamilton from Lloyd D. Jackson Square to the Lime Ridge Mall. The line would have employed the ICTS platform used in the Scarborough RT in Toronto and the Expo Line in Vancouver. The plan, however, faced significant local opposition, and Hamilton-Wentworth Council rejected the proposal. The plan called for an elevated track –one of the elements that triggered opposition, with residents suggesting commuters would be invading their privacy by looking down on their backyards and in their second-floor windows. [1]
The BLAST network was a former iteration of Hamilton's transit network planning. It was initially proposed as part of the city's 2007 transportation master plan, with three lines which would become the BLAST A-, B-, and T-Lines. Other corridors, including the BLAST S-Line, were also identified for future expansion.
These corridors were later incorporated by Metrolinx as part of its regional transportation plan, The Big Move, approved in September 2008. [2] [3] The L-Line would not be conceived until an October 2008 report from city staff, at which point the network was given the BLAST name. [4]
In February 2013, the City of Hamilton would release a transportation plan entitled Rapid Ready. [5] [6] Initially intended as a five year plan prior to the B-Line LRT delays, this report set out three main objectives to ensure effective usage of the LRT:
The B-Line LRT and A-Line were among The Big Move's prioritized transit expansion projects and were funded by the Government of Ontario in May 2015. [7] Originally, the A-Line was planned to be a 2-kilometre (1.2 mi) light rail transit (LRT) spur from King Street to West Harbour GO Station, and potentially extending to Hamilton Harbour; however, this was reassessed and cut due to budget concerns and reported community desire for greater route coverage. [8] The A-Line was henceforth planned as a bus rapid transit service from the waterfront to Hamilton Airport. [9] [10] Upon Metrolinx's 2041 Regional Transportation Plan being published in March 2018, the waterfront portion was dropped. The agency would recommend dedicated BRT from West Harbour GO to Rymal Road, and priority bus service from Rymal Road to the airport. [11]
In January 2019, the City of Hamilton launched a project entitled (Re)envision the HSR to solicit feedback from the community on an improved system network. [12] [13] This was justified by the Rapid Ready plan's objectives of multi-modality and an LRT-supportive bus network.
Through 2019, Hamilton and Metrolinx were preparing to build the B-Line LRT. [14] Land acquisition and building demolition for a 14-kilometre (8.7 mi) line from McMaster University to Eastgate Square had started. [15]
On December 16, 2019, the Government of Ontario announced it was cancelling its funding for the LRT due to cost overruns. [16] The provincial Ministry of Infrastructure noted that provincial funds originally planned for the Hamilton LRT project would be redistributed to other transportation infrastructure projects, with consultation with a newly formed Hamilton Transportation Task Force and Hamilton's city council. [17]
On April 9, 2020, the Hamilton Transportation Task Force released the report, suggested that the city need a "higher order transit project", and it could be either LRT on B-Line or BRT on both A-Line and B-Line. [18]
On February 9, 2021, the province reversed its decision and reinstated the project as the Hamilton LRT. [19] Though the LRT is no longer referred to as the B-Line, the bus service that runs along the equivalent route retains the name.
In July 2021, the city received $370 million from the provincial and federal governments to be used for the transportation network, alongside a $134 million contribution from the city. [20] [21] This included provisions for:
By 2023, planning work on the (Re)envision the HSR project began to show fruits. According to a city report from April 2023, the BLAST network was insufficient due to incomplete links between high-use transit areas, poor connections, and poor access to rapid transit across Hamilton communities. [22] The city claims the redesigned network will place approximately 309,000 residents will be within 800 metres (2,600 ft) of rapid transit, a 23% increase over the original BLAST network concept. [23]
The project was an evolution of the BLAST network with the following changes:
The BLAST network branding would no longer be used in public-facing material but would continue to be used for internal planning leading up to HSR Next's announcement.
On November 6, 2024, Metrolinx released a request for qualifications for civil works and utilities along the LRT route, using an alliance delivery model. [24] In May 2025, Metrolinx announced that four consortia had been shortlisted for the civil works and utilities package. [25]
On June 24, 2025, Metrolinx hosted a virtual open house for the Hamilton LRT. [26] During the presentation, Nicholas Chaloux, HSR manager of transit strategic planning, unveiled the resulting network of the (Re)envision the HSR initiative, branded as HSR Next. The plan intends to shift away from the existing hub-and-spoke network to a point-to-point network, improving efficiency and cutting trip times. The myRide on-demand service was also planned to be expanded to parts of Dundas, Ancaster, Glanbrook, Stoney Creek, more areas of Waterdown, and in the southeast portion of Hamilton Mountain from Heritage Greene Shopping Centre to Elfrida Gateway.
As part of the new point-to-point network, West Harbour GO Station is intended to become a new primary lower city terminal. The proposed alignment map shows no routes passing through the current Frank A. Cooke Transit Terminal. [27] [28]
Travel from the Hamilton LRT to local GO Transit stations will require no more than one transfer. Due to the scope of the plan, route changes are to be phased in gradually. The BRT lines retain the B-L-A-S-T-E letters in their naming, but route maps now feature the route numbering instead.
Routes are not finalized and are subject to change. [27]
Line | Type | Corridor / main route | Termini | Opening target | Frequency target (peak) | Additional notes | |
---|---|---|---|---|---|---|---|
![]() | LRT | Main Street, King Street, Queenston Road | McMaster University | Eastgate Square | TBA | Every 6 minutes | Formerly the B-Line LRT. Owned by Metrolinx. Hamilton city council has recommended the line be operated privately (i.e. not by the HSR) for the first 10 years. Currently served by 10 B-Line Express. |
![]() | BRT or priority bus | Queenston Road, Barton Street, Fifty Road | Eastgate Square | Winona Crossing | No earlier than September 2026 | Every 20 minutes | Runs express service between Eastgate Square and Stoney Creek Gateway, local service to Winona Crossing. Previous discussions for the original B-Line have included BRT, however it is unclear what priority if any the new line will carry. Currently served by 55 Stoney Creek Central. |
![]() | BRT and priority bus | James Street, Upper James Street | Pier 8 Waterfront | Hamilton International Airport | Currently implemented as express/local bus | Every 10 minutes | Currently known as 20 A-Line Express, operating express service between Pier 8 and Mountain Transit Centre, local service to Hamilton International Airport. Improvements are funded between West Harbour GO Station and the airport. |
![]() | Priority bus | Queenston Road, Red Hill Valley Parkway, Upper Red Hill Valley Parkway, Rymal Road, Garner Road | Parkdale LRT Station | Ancaster Gateway | No earlier than September 2026 | Every 10 minutes | Express service between Parkdale LRT Station and Redeemer University, local service to Ancaster Gateway. Currently served by 11 Parkdale and 44 Rymal. |
![]() | Priority bus | Centennial Parkway, Upper Centennial Parkway, Rymal Road, Upper Red Hill Valley Parkway | Confederation GO Station | Heritage Greene | No earlier than September 2026 | Every 10 minutes | Express service between Confederation GO and Elfrida Gateway, and between Rymal / Upper RHVP and Heritage Greene. Local service along Rymal Road. Currently served by 44 Rymal. |
![]() | Priority bus | Cootes Drive, Main Street West, Golf Links Road, Mohawk Road, Limeridge Road | Downtown Dundas | Heritage Greene | No earlier than September 2026 | Every 10 minutes | Express service between McMaster University and Wilson Steet East/Rousseaux Road, as well as between Meadowlands and Heritage Greene. Local service between McMaster University and Downtown Dundas, as well as between Wilson Street East/Rousseaux Road and Meadowlands. Currently served by 5(A) Delaware, 41 Mohawk, 42 Mohawk East, and 21 Upper Kenilworth. |
![]() | Priority bus | Highway 6, York Boulevard, James Street, Upper James Street, Mohawk Road East, Upper Ottawa Street, Ottawa Street | The Centre on Barton | Waterdown Gateway | No earlier than September 2026 | Every 20 minutes | Express service. Currently served within Hamilton by 41 Mohawk, and partially served to Waterdown by 9 Rock Gardens and 18 Waterdown. |
![]() | James Street, Upper James Street, Mohawk Road East, Upper Ottawa Street, Ottawa Street | West Harbour GO Station | Every 10 minutes | Express service. Currently served by 41 Mohawk and 20 A-Line Express. |
Prior to the 2019 defunding, the A-Line and B-Line projects were originally targeted to be completed in 2024. A contract for the Hamilton LRT is expected to be issued in early 2026. [26] No timeline is currently provided for the beginning of construction or updated target date for opening.
While the original plans formed a solid foundation for the expansion of rapid transit in Hamilton, the BLAST plan had a few gaps. BLAST lacked a connection between Ancaster and McMaster University, lacked maximized connections between all high transit use areas (hubs) to one another, lacked direct connections between all rapid routes, and did not provide access to rapid transit in all communities. (Re)envision offered an opportunity to enhance the BLAST network within the proposed Rail Ready network.