Vietnam is considering developing nuclear power for peaceful purposes based on modern, verified technology since 1995, [1] and firm proposals surfaced in 2006. [2] In November 2016 Vietnam suspended its nuclear power plans. [3] [4] In 2022 industry and trade minister Nguyen Hong Dien announced that developing nuclear power is an “inevitable trend” for Vietnam, and will help the country to become carbon neutral by 2050. [5]
The race to diversify beyond its primarily hydropower and coal energy mix, is driven largely by the country's growing energy demand, which was expected to increase annually by 16%, e.g. from 16 GW (2010) to 30 GW (2015). [1] Another factor is the challenges it faces in identifying new suitable hydro power project sites. [2]
Its first ever nuclear power projects were planned be implemented in two major sites in Ninh Thuận Province. The 4 X 1000 MW Ninh Thuận 1 site [6] at Phuoc Dinh, will be built in collaboration with Russian State company - Atomstroyexport, and will set the stage for the foundation of Vietnam's first ever nuclear power plant unit (estimated completion - 2020). The Japanese consortium - JINED will construct the second site - 4 X 1000 MW Ninh Thuận 2 at Ninh Hải district. [7]
In March 2012, [8] an intergovernmental pact was signed between Vietnam and South Korea, to start a one-year feasibility study for the construction of four Korean-developed APR-1400 [9] nuclear reactors, additional to the NPPs signed with Russia and Japan. It practically clinched the South Korean consortium as the preferred bidder; however, an official deal will only be signed after approval from the Vietnamese parliament. [9]
The 1 GW reactor unit no. 1 at Ninh Thuận 1, will be commissioned and connected to the national grid by 2020, which at that time will represent 1.5% [10] of the projected total output of 52 GW. In June 2010, Vietnam announced that it plans to build 14 nuclear reactors at eight sites in five provinces by 2030, to satisfy at least 15 GW nuclear power (i.e. 10% share) [11] of the estimated total demand of 112 GW. An ambitious strategy to increase the nuclear share to 20-25% by 2050 has also been outlined.
The nuclear power plant sites in Vietnam would have been operated by the state electricity utility company - EVN.
Vietnam's aspiration to harness nuclear energy for electricity generation and uses in areas such as medicine and agriculture, dates back to 1958, [12] when South Vietnam - one of the first nations under the Atoms for Peace program, ordered a small research reactor, the General Atomics-built TRIGA-Mark II.
In 1963, the Dalat Nuclear Research Institute, which houses Vietnam's nuclear research reactor, began operating with US assistance. [13] The Second Indochina War interrupted Vietnam's development plans and during that war, the United States dismantled the U.S.-supplied Triga reactor.
Immediately after the war, the reunified nation began to rebuild its infrastructure and governmental agencies, establishing the Vietnam Atomic Energy Commission (VAEC) [12] (now the Vietnam Atomic Energy Institute, VAEI) [2] in 1976, under the management of the Ministry of Science and Technology (MOST).
The VAEC was tasked with pursuing a national programme for application of Nuclear Energy to Socio-Economy Sectors of Vietnam. In 1982 the Dalat research reactor reconstruction and expansion project began under the management of the VAEC with assistance from the Soviet Union and IAEA support. On March 20, 1984 the reactor was officially put into operation with a nominal power of 500 kW, twice that of the previous TRIGA reactor. [14]
In the early 1980s, two preliminary nuclear power studies were undertaken, followed by another which stated in 1995 that: "Around the year 2015, when electricity demand reaches more than 100 billion kWh, nuclear power should be introduced for satisfying the continuous growth in the country's electricity demand in that time and beyond". [1]
The race to diversify beyond its primarily hydropower and coal energy mix intensified, when the country's energy demand projections were estimated to increase annually by 16% from 16 GW (2010) to 30 GW (2015). [1] The challenges it faced in identifying new suitable hydro power project sites and inefficient running of the current hydropower facilities due to unfavorable weather conditions, furthered its cause to harness nuclear energy for power generation. [2]
In 2006, firm proposals surfaced and the Vietnamese government announced that a 2000 MWe nuclear power plant should be on line by 2020. [15] This general target was confirmed in a nuclear power development plan approved by the government in August 2007, with the target being raised to a total of 8000 MWe nuclear by 2025. A general law on nuclear energy was passed in mid 2008, and plans for developing a comprehensive legal and regulatory framework envisaged.
In October 2008, two major locations in Ninh Thuận Province, namely Phuoc Dinh and Vinh Hai, were confirmed by the Vietnamese government as the sites to implement its first ever nuclear power projects, with 2 X 1000 MW reactors units on each site, totalling nearly 4 GW of power output
In June 2010, Vietnam announced that it plans to build 14 nuclear reactors at eight sites in five provinces by 2030, to satisfy at least 15 GW nuclear power (i.e. 10% share) [10] of the estimated total demand of 112 GW. Four more units were added to the first two sites in Ninh Thuận, then six more at six sites, namely Binh Tien (Ninh Thuận Province), Xuan Phuong (Phú Yên Province), Hoai My (Bình Định Province), Duc Thang (Quảng Ngãi Province), Duc Chanh (Quảng Ngãi Province), and Ky Xuan (Hà Tĩnh Province). [16]
In October 2010, Vietnam signed an inter-governmental agreement with Russia for the construction of the country's first nuclear power plant - Ninh Thuận 1 at Phuoc Dinh, using two VVER-1000 or 1200 reactors (increased later by two more units). The 4 X 1000 MW Ninh Thuận 1 site, [6] will be built by Atomstroyexport, a subsidiary of Rosatom. The construction is due to start by 2014 and the first unit to be commissioned and connected to the national grid by 2020. [17] Russia's Ministry of Finance will finance Vietnam, at least 85% of the first plant and in November 2011, an agreement for a $8 billion loan was signed with the Russian government's state export credit bureau. [18] An intergovernmental agreement was also signed to establish a nuclear science and technology center in Vietnam.
On the same day in October 2010, an intergovernmental agreement with Japan was signed for construction of a second nuclear power plant – Ninh Thuận 2 at Vinh Hai in Ninh Thuận Province, with its two reactors to come on line in 2024–25. The Japanese consortium - International Nuclear Energy Development of Japan Co. Ltd. (JINED) will construct the 4 X 1000 MW Ninh Thuận 2 site. The Japanese Ministry of Economy, Trade and Industry (METI), confirmed the financing and insurance of up to 85% of the total cost. [7]
Aside from the currently involved Atomstroyexport (Russia) and JINED (Japan), Westinghouse (Japan/US), GE (US), EDF (France), KEPCO (South Korea), and CGNPC (China), have all expressed strong interest in constructing the future nuclear power projects outlined, as part of an ambitious strategy to increase the nuclear share to 20-25% by 2050. [16] [19]
In March 2012, [8] it was announced that South Korea and Vietnam will start a one-year feasibility study for the construction of four Korean-developed APR-1400 [9] nuclear reactors, additional to the NPP's signed with Russia and Japan. The intergovernmental pact signed between Vietnamese Prime Minister Nguyen Tan Dung and South Korean President Lee Myung-bak, practically clinched the South Korean consortium as the preferred bidder. However, an official deal will only be signed after approval from the Vietnamese parliament. [20]
Vietnam is planning to send 2,000 workers and engineers to the Russian Federation and Japan for 2–3 years training in nuclear power construction, starting in 2013. [21]
However, in January 2014 it was reported that Vietnam had decided to delay construction by six years, to permit improved safety and efficiency in the plants. [22]
In November 2016 Vietnam decided to abandon nuclear power plans as they were considered "not economically viable because of other cheaper sources of power", by the Vietnamese government. [3] [4] [23] The Ninh Thuận price had risen from 4 to 8 US cents per kWh, [24] reflecting a project cost of VND400 trillion (US$18 billion) or higher. [25] With a public debt at around 65% of gross domestic product, Vietnam would struggle to finance the plants. [25]
In a meeting with the Director General of Russia’s Rosatom State Atomiс Energy Corporation, in June of 2024, Vietnam’s Prime Minister said the country would consider nuclear energy as a means of meeting its net-zero by 2050 commitment. [26] Shortly thereafter, Russia’s Rosatom State Nuclear Energy Corporation and Vietnam’s Ministry of Science and Technology went on signed a memorandum of understanding with respect to jointly establishing a Nuclear Science and Technology Center in Vietnam with a Russian nuclear reactor in Vietnam. [27]
This article needs to be updated.(June 2022) |
The nuclear power plants planned would have been operated by the state electricity utility company - EVN.
The list of planned NPPs were as follows: [1] [6] [7]
Power plant-Unit | Site Location | Province | Type | Total capacity (MW) | Start construction | First criticality | Commercial operation | Reactor supplier | Construction | Fuel |
---|---|---|---|---|---|---|---|---|---|---|
Ninh Thuận 1-1 | Phuoc Dinh | Ninh Thuận | VVER | 1000 | 2014 | - | 2020 | - | Atomstroyexport | - |
Ninh Thuận 1-2 | Phuoc Dinh | Ninh Thuận | VVER | 1000 | - | - | 2021 | - | Atomstroyexport | - |
Ninh Thuận 1-3 | Phuoc Dinh | Ninh Thuận | VVER | 1000 | - | - | 2023 | - | - | - |
Ninh Thuận 1-4 | Phuoc Dinh | Ninh Thuận | VVER | 1000 | - | - | 2024 | - | - | - |
Ninh Thuận 2-1 | Vinh Hai | Ninh Thuận | Japanese Gen III | 1000 | 2015 | - | 2021 | - | JINED | - |
Ninh Thuận 2-2 | Vinh Hai | Ninh Thuận | Japanese Gen III | 1000 | - | - | 2022 | - | JINED | - |
Ninh Thuận 2-3 | Vinh Hai | Ninh Thuận | Japanese Gen III | 1000 | - | - | 2024 | - | - | - |
Ninh Thuận 2-4 | Vinh Hai | Ninh Thuận | Japanese Gen III | 1000 | - | - | 2025 | - | - | - |
Total | 8000 |
Russia is one of the world's largest producers of nuclear energy. In 2020 total electricity generated in nuclear power plants in Russia was 215.746 TWh, 20.28% of all power generation. The installed gross capacity of Russian nuclear reactors is 29.4 GW in December 2020.
The Belene Nuclear Power Plant is an abandoned nuclear power plant 3 km from Belene and 11 km from Svishtov in Pleven Province, northern Bulgaria, near the Danube River. It was intended to substitute four VVER-440 V230 reactors of the Kozloduy Nuclear Power Plant that were decommissioned as a prerequisite for Bulgaria to join the European Union.
In Pakistan, nuclear power is provided by six commercial nuclear power plants with a net capacity of 3,262 megawatts (3.262 GW) from pressurized water reactors. In 2020, Pakistan's nuclear power plants produced a total of 133 terawatt-hours of electricity, which accounted for roughly 10% of the nation's total electric energy generation.
The Armenian Nuclear Power Plant (ANPP), also known as the Metsamor Nuclear Power Plant, is the only nuclear power plant in the South Caucasus, located 36 kilometers west of Yerevan in Armenia.
The program for nuclear power in Indonesia includes plans to build nuclear reactors in the country for peaceful purposes. Indonesia prohibited development of nuclear weapon or any offensive uses due to signing the Treaty on the Non-Proliferation of Nuclear Weapons on 2 March 1970 and ratified it as Law No. 8/1978 on 18 December 1978.
Kudankulam Nuclear Power Plant is the largest nuclear power station in India, situated in Kudankulam in the Tirunelveli district of the southern Indian state of Tamil Nadu. Construction on the plant began on 31 March 2002, but faced several delays due to opposition from local fishermen. KKNPP is scheduled to have six VVER-1000 reactors built in collaboration with Atomstroyexport, the Russian state company and Nuclear Power Corporation of India Limited (NPCIL), with an installed capacity of 6,000 MW of electricity.
Nuclear power is a major power source in South Korea, providing 29% of the country's electricity. The total electrical generation capacity of the nuclear power plants of South Korea is 20.5 GWe from 23 reactors, equivalent to 22% of South Korea's total electrical generation capacity.
The Japan Atomic Power Company is a company initially formed to jump start the commercial use of nuclear power in Japan, and currently operates two different sites. According to the official web site, JAPC is "the only power company in Japan solely engaged in nuclear energy".
China is one of the world's largest producers of nuclear power. The country ranks third in the world both in total nuclear power capacity installed and electricity generated, accounting for around one tenth of global nuclear power generated. As of February 2023, China has 55 plants with 57GW in operation, 22 under construction with 24 GW and more than 70 planned with 88GW. About 5% of electricity in the country is due to nuclear energy. These plants generated 417 TWh of electricity in 2022 This is versus the September 2022 numbers of 53 nuclear reactors, with a total capacity of 55.6 gigawatt (GW). In 2019, nuclear power had contributed 4.9% of the total Chinese electricity production, with 348.1 TWh.
Nuclear power is the fifth-largest source of electricity in India after coal, gas, hydroelectricity and wind power. As of November 2020, India has 23 nuclear reactors in operation in 8 nuclear power plants, with a total installed capacity of 7,380 MW. Nuclear power produced a total of 43 TWh in 2020–21, contributing 3.11% of total power generation in India. 10 more reactors are under construction with a combined generation capacity of 8,000 MW.
Tianwan Nuclear Power Plant is a nuclear power plant (NPP) on the coast of the Yellow Sea, approximately 30 kilometers east of downtown Lianyungang, Jiangsu Province, China. The plant's owner is Jiangsu Nuclear Power Corporation, a joint venture with majority owner a subsidiary of China National Nuclear Corporation (CNNC).
The Bushehr Nuclear Power Plant is a nuclear power plant in Iran 1,200 kilometres (750 mi) south of Tehran, between the fishing villages of Halileh and Bandargeh along the Persian Gulf.
National nuclear energy policy is a national policy concerning some or all aspects of nuclear energy, such as mining for nuclear fuel, extraction and processing of nuclear fuel from the ore, generating electricity by nuclear power, enriching and storing spent nuclear fuel and nuclear fuel reprocessing. Nuclear energy policies often include the regulation of energy use and standards relating to the nuclear fuel cycle.
Currently, Turkey has no operating commercial nuclear reactors. However, four VVER-1200 reactors at the Akkuyu Nuclear Power Plant, are currently under construction and expected to come online in October 2024. The government is aiming for 20 GW of nuclear.
The Ninh Thuận 1 Nuclear Power Plant was a planned nuclear power plant at Phước Dinh in Thuận Nam District, Ninh Thuận Province, Vietnam. Plans for it were cancelled in 2016. It would have consisted of four 1,200 MWe VVER pressurised water reactors. The plant was to be built by Atomstroyexport, a subsidiary of Rosatom. It would have been owned and operated by state-owned electricity company Vietnam Electricity. Fuel will have been supplied and used fuel will be reprocessed by Rosatom. The feasibility study was to be carried out by E4 Group.
The Ninh Thuận 2 Nuclear Power Plant is a cancelled nuclear power plant at Vĩnh Hải, Ninh Hải District, Ninh Thuận Province, Vietnam. It was supposed to consist of four 1,000 MWe reactors.
The Xudabao Nuclear Power Plant, known also as Xudapu, is a nuclear power station under construction in Xudabao Village, Haibin County, Xingcheng, Huludao, on the coast of Liaoning Province, in northeast China. It was initially planned to have six 1000-MW AP1000 or CAP1000 light water reactors, but the first two to start construction were changed to VVER-1200s.
Vietnam utilizes four main sources of renewable energy: hydroelectricity, wind power, solar power and biomass. At the end of 2018, hydropower was the largest source of renewable energy, contributing about 40% to the total national electricity capacity. In 2020, wind and solar had a combined share of 10% of the country's electrical generation, already meeting the government's 2030 goal, suggesting future displacement of growth of coal capacity. By the end of 2020, the total installed capacity of solar and wind power had reached over 17 GW. Over 25% of total power capacity is from variable renewable energy sources. The commercial biomass electricity generation is currently slow and limited to valorizing bagasse only, but the stream of forest products, agricultural and municipal waste is increasing. The government is studying a renewable portfolio standard that could promote this energy source.
In November 2016 the National Assembly passed a resolution to cancel plans for the two nuclear power stations, "due to economic conditions in our country today," and lower demand projections.
cost has escalated from the original estimate of US$10 billion to US$27 billion (€9.5‒25.6 bn)