Union Square | |||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
General information | |||||||||||||||||||||||||||
Location | Prospect Street south of Union Square Somerville, Massachusetts | ||||||||||||||||||||||||||
Coordinates | 42°22′37.72″N71°5′39.45″W / 42.3771444°N 71.0942917°W | ||||||||||||||||||||||||||
Line(s) | Union Square Branch | ||||||||||||||||||||||||||
Platforms | 1 island platform (Green Line) | ||||||||||||||||||||||||||
Tracks | 2 (Green Line) 2 (Fitchburg Line) | ||||||||||||||||||||||||||
Connections | MBTA bus: 85, 86, 87, 91, CT2 | ||||||||||||||||||||||||||
Construction | |||||||||||||||||||||||||||
Bicycle facilities | 120 spaces [1] | ||||||||||||||||||||||||||
Accessible | Yes | ||||||||||||||||||||||||||
History | |||||||||||||||||||||||||||
Opened | March 21, 2022 | ||||||||||||||||||||||||||
Passengers | |||||||||||||||||||||||||||
3,645 boardings (projected) [2] : 6 | |||||||||||||||||||||||||||
Services | |||||||||||||||||||||||||||
| |||||||||||||||||||||||||||
| |||||||||||||||||||||||||||
Location | |||||||||||||||||||||||||||
Union Square station is a light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line located in the Union Square neighborhood of southeastern Somerville, Massachusetts. The accessible terminal station has a single island platform serving the two tracks of the Union Square Branch, which parallels the Fitchburg Line. It opened on March 21, 2022, as part of the Green Line Extension (GLX), which added two northern branches to the Green Line.
The Fitchburg Railroad opened a station at Prospect Street in the 1840s; it was renamed to Union Square around 1875. The station was closed in 1938 and demolished around that time. Extensions to the Green Line were proposed throughout the 20th century, but a Union Square spur was not considered until the early 21st century. Several station sites and alignments were considered, with the Prospect Street location and the route along the Fitchburg Line chosen in 2009. The MBTA agreed in 2012 to open the station by 2017, and a construction contract was awarded in 2013.
Cost increases triggered a wholesale reevaluation of the GLX project in 2015. A scaled-down station design was released in 2016, with a design and construction contract issued in 2017. Construction of Union Square station began in early 2020 and was largely completed by late 2021. The station was initially served by the Green Line E branch, but is now served by the Green Line D branch. A major development project is under construction near the station.
Union Square station is located on the east side of the Prospect Street bridge, about 900 feet (270 m) south of the Union Square intersection. The Fitchburg Line runs roughly northwest–southeast through the station area, with the two-track Union Square Branch of the Green Line on the north side of the Fitchburg Line tracks. The station has a single island platform, 225 feet (69 m) long and 20 feet (6.1 m) wide, located about 250 feet (76 m) east of Prospect Street between the Green Line tracks. A canopy covers the full length of the platform. [1]
The platform is 8 inches (200 mm) high for accessible boarding on current light rail vehicles (LRVs), and can be raised to 14 inches (360 mm) for future level boarding with Type 9 and Type 10 LRVs. It is also provisioned for future extension to 300-foot (91 m) length. [3] : 12.1-5 A starter booth is located at the east end of the platform, with an at-grade emergency exit walkway leading to Allen Street. [1] : 9
The station entrance plaza is located on the east side of the Prospect Street bridge, next to a small utility building. A walkway connects the plaza and platform, with fare vending machines located in a wider section of the walkway at its west end. Tail tracks are located on each side of the walkway. [1] The tail tracks are designed not to preclude further extension to Porter station in the future. [4] Bike racks with space for 34 bikes are located in the entrance plaza. [1] Public artwork at the station includes Passage by Matthew Trimble – a sculptural archway over the walkway to the platform – as well as murals on station sign panels. [5]
The main entrance to the station will be a walkway from Prospect Street to the north. To the north of the entrance plaza will be "Station Plaza", built by the developer of an adjacent building. An elevator and stairs will connect to the Prospect Street bridge. [6] A covered shelter will have racks for 86 bikes. [1] The elevator opened in April 2022, but Station Plaza will not be completed until 2023. [6] [7] Five MBTA bus routes – 85 , 86 , 87 , 91 , and CT2 – stop in Union Square near the station. [8]
The Charlestown Branch Railroad was extended through Somerville in 1841, opening on January 5, 1842. It was absorbed into the Fitchburg Railroad in 1846. [9] Prospect Street station – which was located off Medford Street (now Webster Avenue), slightly west of Prospect Street – was opened within several years to serve the Sand Pit Square area. [10] [11] [12] Like Somerville station and other local stops, Prospect Street was primarily served by Lexington Branch trains in the mid-19th century. [13] The nearby square became Union Square in the 1860s, but the station was not renamed Union Square until around 1875. [14]
Prospect Street was placed on a bridge over the railroad by 1849, but Webster Street crossed the railroad at grade. [10] [15] [16] Planning to eliminate the eleven remaining grade crossings in Somerville, five of which were on the Fitchburg Route mainline, began in 1900. [17] In 1906, the city engineer proposed to raise 1.8 miles (2.9 km) of the line between Beacon Street and Somerville Avenue to eliminate the five level crossings, but that scheme was not adopted. [18]
After the Somerville Avenue grade crossing was eliminated in 1908–09, work began in April 1911 to raise Webster Street above the tracks. [19] [20] Webster Street and several adjacent buildings were raised about 20 feet (6.1 m), while the tracks were slightly lowered. A special bridge on the east side of the road bridge was built for a 4-foot (1.2 m)-diameter water main that weighed 700 pounds per foot (1,000 kg/m). As part of the project, the 67-year-old station building was replaced by a larger building on the south side of the tracks. [12] Work was completed in December 1911. [21]
Horsecar and later electric streetcar service cut ridership at urban stations; by 1917, Union Square and Somerville stations were served by four to five daily Watertown Branch trains plus several off-peak mainline local trains. [22] As passengers volumes dwindled, the station building was reused for manufacturing by 1924. [23] By 1929, the only service to Union Square and Somerville was one outbound and two inbound Watertown Branch trains. [24] Service to the two stations ended on July 9, 1938, along with the end of passenger service on the Watertown Branch. [25] [26] [27] The station building was demolished sometime between 1936 and 1940. [28] [29]
Adding an MBTA Commuter Rail Fitchburg Line station at Union Square has been considered; by 2003, a stop was expected to open within five years. [30] The 2004 state Program for Mass Transportation estimated such a station would attract 390 daily riders. [25] A Union Square commuter rail station – either in addition to a Green Line station or in lieu of it – was listed as a possibility in 2012 as an interim air quality mitigation measure in response to delays in building the Green Line Extension. However, such a station would have been costly to build and could not have been completed by the 2015 deadline, and was therefore not supported by MassDOT. [31]
Rapid transit extension northwest from Lechmere was first proposed in 1922. [32] Various 20th-century proposals called for rapid transit along the B&M Southern Division (now the Lowell Line) to West Medford or beyond; the nearest station to Union Square was to be about 0.4 miles (0.6 km) to the east. [33] [34] A 1980s corridor plan considered a direct extension to Union Square as a possible alternative. [35] : 308 [36] The 1991 agreement between the state and the Conservation Law Foundation specified a "Green Line Extension To Ball Square/Tufts University". [37] The 2003 Program for Mass Transportation considered both Green Line and Blue Line extensions to West Medford, including alignments that would deviate from the Lowell Line right-of-way to directly serve Union Square. [38]
An updated agreement, announced in May 2005, added a Union Square branch to the Green Line Extension. [39] The Beyond Lechmere Northwest Corridor Study, a Major Investment Study/alternatives analysis, was published in 2005. The analysis studied a variety of light rail and bus rapid transit extensions, including a branch to Union Square. [40] The Massachusetts Executive Office of Transportation and Public Works submitted an Expanded Environmental Notification Form (EENF) to the Massachusetts Executive Office of Environmental Affairs in October 2006. The EENF identified a Green Line extension with Medford and Union Square branches as the preferred alternative; the Union Square Branch was to follow the Fitchburg Line right-of-way. [41] That December, the Secretary of Environmental Affairs issued a certificate that required analysis of a Somerville Avenue alignment for the Union Square Branch in the draft environmental impact report (DEIR) for the Green Line Extension (GLX). [42]
By early 2008, three alignments were under consideration: a surface route along the Fitchburg Line, with a station east of Prospect Street; a surface route on Somerville Avenue, with a station west of Prospect Street; and a single-track loop combining both routes, with an underground station under Prospect Street south of Somerville Avenue. [43] Union Square was among the planned station sites officially announced in May 2008. [44] [45] [46] Several additional potential tunnel alternatives for an underground station at Union Square, with a short tunnel near Prospect Street or a longer tunnel under Somerville Avenue, were analyzed in 2008 and found not to be cost-effective. [47]
The DEIR, released in October 2009, selected the Fitchburg Line routing on the basis of lower cost, higher reliability due to grade separation, and less property acquisition required than the other alternatives. [48] : 39 Preliminary plans in the DEIR called for a curved station platform with faregates at the west end. A two-story station building would connect to the Prospect Street bridge, with an additional connection directly to platform level from the north. [48] : 50 [49]
Updated plans shown in May 2011 moved the platform eastwards and added moved the kiss-and-ride area from the bridge to north of the headhouse. [50] Plans presented in February 2012 enlarged the upper level of the headhouse to have it become the primary entrance. This would have allowed the lower entrance to be closed to accommodate the outbound track, were a proposed further extension to Porter to be built. [51] [52] A further update in June 2013 removed a mechanical penthouse, modified the lobby designs, and added bicycle racks near the upper entrance. [53] [54]
In August 2012, the City of Somerville, MassDOT, and the MBTA reached a memorandum of agreement about the station. Through the Somerville Redevelopment Authority, the City would acquire $8 million worth of land for the station and grant the MBTA a permanent easement, while retaining the rights for transit-oriented development overhead. In return, the MBTA and MassDOT would pay for cleanup costs at the site, begin construction by the spring of 2014, and open the station no later than "late 2016-early 2017". [55] [56]
In October 2012, the Somerville Board of Aldermen approved the Union Square Redevelopment Plan and authorized an $8 million bond, including $6 million to purchase the land and $2 million for cleanup and station planning. [57] The North Prospect block – a mostly industrial area bordered by the railroad tracks, Prospect Street, Somerville Avenue, and the rear of residential properties on Allen Street – was acquired by the city via eminent domain for $4.5 million in June 2013. The properties were to be vacated by August. The city also received a $1 million EPA grant to clean up one of the properties. [58]
In September 2013, MassDOT awarded a $393 million (equivalent to $507 million in 2023), 51-month contract for the construction of Phase 2/2A – Lechmere station, the Union Square Branch, and the first segment of the Medford Branch to Washington Street – with the stations to open in early 2017. [59] [60] Site cleanup began in September 2014. [61] Design of the station was completed in late 2014. [62]
In August 2015, the MBTA disclosed that project costs had increased substantially, with Phase 2A rising from $387 million to $898 million. [63] This triggered a wholesale re-evaluation of the GLX project. In December 2015, the MBTA ended its contracts with four firms. Construction work in progress continued, but no new contracts were awarded. [64] At that time, cancellation of the project was considered possible, as were elimination of the Union Square Branch and other cost reduction measures. [65] [66]
In May 2016, the MassDOT and MBTA boards approved a modified project that had undergone value engineering to reduce its cost. Stations were simplified to resemble D branch surface stations rather than full rapid transit stations, with canopies, faregates, escalators, and some elevators removed. The new design for Union Square removed the direct access from the Prospect Street overpass, with entrance to be only from the plaza on the north side of the station. [2] [67] Several elements of the reduced-cost project design were criticized by community advocates and local politicians. E. Denise Simmons criticized the scaled-down station designs at Union Square and East Somerville for having long ramps rather than elevators, saying they were not sufficient for accessibility. [68] In December 2016, the MBTA announced a new planned opening date of 2021 for the extension. [69]
A design-build contract for the GLX was awarded in November 2017. [70] The winning proposal included six additive options – elements removed during value engineering – including full-length canopies at all stations. [71] [72] [73] Station design advanced from 0% in March 2018 to 24% that December and to 100% in October 2019. [74] [1] The 100% design relocated a utility building between the tracks so as to not preclude future extension. [75]
The coming of the station provided an opportunity for the city to redevelop Union Square and surrounding areas. A 2009 rezoning designated commercial corridors and transit-oriented development sites; a 2012 revitalization plan led to the selection of a master developer for the area. As with the GLX as a whole, the Union Square redevelopment has been criticized by local advocates for its potential to cause gentrification and community displacement. [76] [77] A 2014 study found that the areas around Union Square and East Somerville stations were expected to have the highest rent increases – up to 67% in some instances. [76]
The USQ mixed-use development in Union Square, which is primarily replacing light industrial buildings, is intended as an anti-gentrification measure by increasing housing supply and subsidizing nearby households and businesses at risk of displacement. [78] Still, by late 2014, both residential and commercial rents were rising more than typical in Union Square. [79] In November 2019, the USQ developer, US2, agreed to fund an elevator connecting the station to the Prospect Street bridge. [80] The first new buildings adjacent to the station broke ground in 2021 and are expected to be completed in 2022–23. [81]
A groundbreaking ceremony was held on June 25, 2018. [82] With the design complete, work on the station foundation began in January 2020. [83] The station platform was poured by early August 2020, with the canopy constructed that September. [84] [85] Tracks were installed at the station in October 2020. [86] A signal hut at the station was in place by April 2021, with overhead lines added in May. [87] [88] In May 2021, the MBTA indicated that the elevator to the Prospect Street bridge might not be complete by the time the station opened, but that the normal accessible pedestrian route from Prospect Street would be available. [89] Electrical work began in mid-2021; canopy lighting was functional and next-train countdown signs were in place by that November. [90] [91]
Original plans called for the E Branch to be extended to Union Square. [92] [93] In April 2021, the MBTA indicated that Union Square would instead be served by the D Branch. [94] However, the Union Square Branch will be initially served by the E Branch rather than the D Branch from its opening until Medford Branch testing begins. [95] By March 2021, the station was expected to open in October 2021. [96] This was delayed in June 2021 to a December 2021 opening due to supply chain issues, and in October 2021 to a March 2022 opening due to issues with a substation. [97] [98] Train testing on the Union Square Branch began in December 2021. [99] Pre-revenue service, where trains on the branch were operated on a revenue schedule but without passengers aboard, began on January 16, 2022. [100]
The Union Square Branch opened on March 21, 2022. [101] The elevator opened in late April 2022. [7] From August 6 to 21, 2022, Union Square was served by C and D branch trains, as the E branch was closed for maintenance work. [102] The Union Square Branch was closed from August 22 to September 18, 2022; the closure allowed for final integration of the Medford Branch, elimination of a speed restriction on the Lechmere Viaduct, and other work. [103] After that closure, Union Square was served by a mixture of D and E branch trains until November 1, when E branch trains began operating pre-revenue service on the Medford Branch. [102]
The original temporary ramp to Prospect Street was closed on April 20, 2023, for construction of the permanent path. [104] The Union Square Branch was closed from September 18 to October 10, 2023, during repairs to Squires Bridge, which carries the McGrath Highway over the tracks. [105] [106] The closure was originally planned for July 18 to August 28, but was delayed and shortened due to public criticism. [107] [108] [109]
A further extension to Porter has been proposed by local officials. In February 2022, the Cambridge City Council signed a resolution requesting work around Union Square station not to interfere with such an extension. [110]
The Green Line is a semi-metro system run by the Massachusetts Bay Transportation Authority (MBTA) in the Boston, Massachusetts, metropolitan area. It is the oldest MBTA subway line, and with tunnel sections dating from 1897, the oldest subway in North America. It runs underground through downtown Boston, and on the surface into inner suburbs via six branches on radial boulevards and grade-separated alignments. With an average daily weekday ridership of 137,700 in 2019, it is the third most heavily used light rail system in the country. The line was assigned the green color in 1967 during a systemwide rebranding because several branches pass through sections of the Emerald Necklace of Boston.
Alewife station is a Massachusetts Bay Transportation Authority (MBTA) intermodal transit station in the North Cambridge neighborhood of Cambridge, Massachusetts. It is the northwest terminal of the rapid transit Red Line and a hub for several MBTA bus routes. The station is at the confluence of the Minuteman Bikeway, Alewife Linear Park, Fitchburg Cutoff Path, and Alewife Greenway off Alewife Brook Parkway adjacent to Massachusetts Route 2, with a five-story parking garage for park and ride use. The station has three bike cages. Alewife station is named after nearby Alewife Brook Parkway and Alewife Brook, themselves named after the alewife fish.
Porter station is a Massachusetts Bay Transportation Authority (MBTA) transit station in Cambridge, Massachusetts. It serves the Red Line rapid transit line, the MBTA Commuter Rail Fitchburg Line, and several MBTA bus lines. Located at Porter Square at the intersection of Massachusetts and Somerville Avenues, the station provides rapid transit access to northern Cambridge and the western portions of Somerville. Porter is 14 minutes from Park Street on the Red Line, and about 10 minutes from North Station on commuter rail trains. Several local MBTA bus routes also stop at the station.
Davis station is an underground Massachusetts Bay Transportation Authority (MBTA) Red Line rapid transit station located at Davis Square in Somerville, Massachusetts. The accessible station has a single island platform for the Red Line, as well as a dedicated busway on the surface. It opened in 1984 as part of the Red Line Northwest Extension project.
The Somerville Community Path is a paved rail trail in Somerville, Massachusetts, running 3.2 miles (5.1 km) from Massachusetts Avenue to East Cambridge via Davis Square. The first portion opened in 1985 along part of the former Fitchburg Cutoff rail line. Extensions opened in 1994 and 2015. A further 1.9-mile (3.1 km) extension to East Cambridge opened in June 2023 as part of the Green Line Extension project. It is a section of the partially completed Mass Central Rail Trail.
Science Park station is an elevated light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line in Boston, Massachusetts, United States. The station is located at the Boston end of the Charles River Dam Bridge at Leverett Circle. It is at the southeast end of the Lechmere Viaduct, which carries the Green Line over the Charles River. The station is named for the nearby Boston Museum of Science. With 873 daily boardings by a FY 2019 count, Science Park is the least-used fare-controlled station on the Green Line, and the second-lowest on the MBTA subway system after Suffolk Downs.
Lechmere station is a Massachusetts Bay Transportation Authority (MBTA) Green Line light rail station in Lechmere Square in East Cambridge, Massachusetts. It is located on the east side of Monsignor O'Brien Highway near First Street, adjacent to the NorthPoint development. The accessible elevated station has a single island platform, with headhouses at both ends. It opened on March 21, 2022, as part of the Green Line Extension (GLX). Lechmere station is served by Green Line D branch and E branch service.
The E branch is a light rail line in Boston, Cambridge, Medford, and Somerville, Massachusetts, operating as part of the Massachusetts Bay Transportation Authority (MBTA) Green Line. The line runs in mixed traffic on South Huntington Avenue and Huntington Avenue between Heath Street and Brigham Circle, in the median of Huntington Avenue to Northeastern University, then into the Huntington Avenue subway. The line merges into the Boylston Street subway just west of Copley, running to North Station via the Tremont Street subway. It then follows the Lechmere Viaduct to Lechmere, then the Medford Branch to Medford/Tufts. As of February 2023, service operates on eight-minute headways at weekday peak hours and eight to nine-minute headways at other times, using 13 to 17 trains.
The Green Line D branch is a light rail line in Boston, Brookline, Cambridge, Newton, and Somerville, Massachusetts, operating as part of the Massachusetts Bay Transportation Authority (MBTA) Green Line. The line runs on a grade separated surface right-of-way for 9 miles (14 km) from Riverside station to Fenway station. The line merges into the C branch tunnel west of Kenmore, then follows the Boylston Street subway and Tremont Street subway to North Station. It is the longest and busiest of the four Green Line branches. As of February 2023, service operates on 8 to 9-minute headways at weekday peak hours and 8 to 11-minute headways at other times, using 13 to 19 trains.
The Fitchburg Cutoff was a rail line running 2.8 miles (4.5 km) from Brighton Street in Belmont, Massachusetts, to Somerville Junction in Somerville, Massachusetts. It was constructed in two segments in 1870 and 1881 to connect the Lexington Branch and Central Massachusetts Railroad to the Boston and Lowell Railroad. Passenger service lasted until 1927. Freight service ended in 1979–80 to allow construction of the Red Line Northwest Extension; the line was abandoned in three sections in 1979, 1983, and 2007.
The Lechmere Viaduct is a concrete arch bridge connecting the West End neighborhood of Boston to East Cambridge, Massachusetts. Opened in 1912, the viaduct carries the MBTA's Green Line over the Charles River. It is adjacent to the Charles River Dam Bridge, but structurally separate.
The Green Line Extension (GLX) was a construction project to extend the Massachusetts Bay Transportation Authority (MBTA) Green Line light rail system northwest into Somerville and Medford, two inner suburbs of Boston, Massachusetts. The project opened in two phases in 2022 at a total cost of $2.28 billion. Total ridership on the 4.3-mile (6.9 km) extension is estimated to reach 45,000 one-way trips per day in 2030.
Medford/Tufts station is a light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line located off Boston Avenue near College Avenue in Medford, Massachusetts, adjacent to Tufts University. The accessible station has a single island platform serving the two tracks of the Medford Branch. It opened on December 12, 2022, as part of the Green Line Extension (GLX), which added two northern branches to the Green Line, and is the northern terminus of the E branch.
Ball Square station is a light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line located at Ball Square in Somerville and Medford, Massachusetts. The accessible station has a single island platform serving the two tracks of the Medford Branch. It opened on December 12, 2022, as part of the Green Line Extension (GLX), which added two northern branches to the Green Line, and is served by the E branch.
Magoun Square station is a light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line located at Lowell Street south of Magoun Square in Somerville, Massachusetts. The accessible station has a single island platform serving the two tracks of the Medford Branch. It opened on December 12, 2022, as part of the Green Line Extension (GLX), which added two northern branches to the Green Line, and is served by the E branch.
Gilman Square station is a light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line located at Gilman Square in Somerville, Massachusetts. The accessible station has a single island platform serving the two tracks of the Medford Branch. It opened on December 12, 2022, as part of the Green Line Extension (GLX), which added two northern branches to the Green Line, and is served by the E branch.
East Somerville station is a light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line located in southeastern Somerville, Massachusetts. The accessible station has a single island platform serving the two tracks of the Medford Branch. It opened on December 12, 2022, as part of the Green Line Extension (GLX), which added two northern branches to the Green Line, and is served by the E branch.
The MBTA Commuter Rail Maintenance Facility is the primary train maintenance repair facility for the MBTA Commuter Rail system. It is located in the Inner Belt area of Somerville, Massachusetts, near North Station in Boston. The present Commuter Rail Maintenance Facility was built from 1995 to 1998, replacing the Boston Engine Terminal which was built by the former Boston and Maine Railroad. The present facility opened on March 25, 1998.
The Massachusetts Bay Transportation Authority operates subway, bus, commuter rail, and ferry service in the Greater Boston region. Boston has some of the highest rates of non-motorized commuting in the United States, including high bicycle usage. The MBTA offers certain provisions for riders wishing to make part of their trips by bicycle. The agency allows bicycles to be carried on all fixed-route services except the Green Line and the Ashmont-Mattapan High Speed Line light rail lines, although they are restricted on the commuter rail and heavy rail subway services at peak hours. Bicycle storage areas are offered at many stations, with "Pedal and Park" locking bicycle cages at certain high-usage stations.
North Station is an underground MBTA subway station in Boston, Massachusetts. Served by the Massachusetts Bay Transportation Authority (MBTA) Green Line and Orange Line, it is connected to the North Station surface terminal used by MBTA Commuter Rail and Amtrak. The station is fully accessible.
Media related to Union Square station (Somerville) at Wikimedia Commons