Ball Square | |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
General information | |||||||||||||
Location | Broadway at Boston Avenue Somerville, Massachusetts | ||||||||||||
Coordinates | 42°23′59.94″N71°6′39.97″W / 42.3999833°N 71.1111028°W | ||||||||||||
Line(s) | Medford Branch | ||||||||||||
Platforms | 1 island platform (Green Line) | ||||||||||||
Tracks | 2 (Green Line) 2 (Lowell Line) | ||||||||||||
Connections | MBTA bus: 80, 89 | ||||||||||||
Construction | |||||||||||||
Bicycle facilities | 50-space "Pedal and Park" bicycle cage | ||||||||||||
Accessible | Yes | ||||||||||||
History | |||||||||||||
Opened | December 12, 2022 | ||||||||||||
Passengers | |||||||||||||
2030 (projected) | 1,890 daily boardings [1] : 49 | ||||||||||||
Services | |||||||||||||
| |||||||||||||
| |||||||||||||
Location | |||||||||||||
Ball Square station is a light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line located at Ball Square in Somerville and Medford, Massachusetts. The accessible station has a single island platform serving the two tracks of the Medford Branch. It opened on December 12, 2022, as part of the Green Line Extension (GLX), which added two northern branches to the Green Line, and is served by the E branch.
The location was previously served by railroad stations. The Boston and Lowell Railroad (B&L) opened Willow Bridge station at Cambridge Road (now Broadway) by 1850. It was renamed North Somerville around 1878, and a new station building was constructed in the 1880s. The station was served by the Boston and Maine Railroad, successor to the B&L, until 1958. Extensions to the Green Line were proposed throughout the 20th century, most with North Somerville as one of the intermediate stations. A Ball Square station near the former station site was officially chosen for the GLX in 2008. Cost increases triggered a wholesale reevaluation of the GLX project in 2015, and a scaled-down station design was released in 2016. A design and construction contract was issued in 2017. Construction of Magoun Square station began in early 2020 and was largely completed by late 2021.
Ball Square station is located off Broadway near Boston Avenue at Ball Square on the border of Somerville and Medford. (Both entrances are in Somerville, but the platform is in Medford.) The Lowell Line runs roughly northwest–southeast through the station area, with the two-track Medford Branch of the Green Line on the south side of the Lowell Line tracks. The station has a single island platform, 225 feet (69 m) long and 22.5 feet (6.9 m) wide, between the Green Line tracks northwest of Broadway. A canopy covers the full length of the platform. [2]
The platform is 8 inches (200 mm) high for accessible boarding on current light rail vehicles (LRVs), and can be raised to 14 inches (360 mm) for future level boarding with Type 9 and Type 10 LRVs; it is also provisioned for future extension to 300-foot (91 m) length. [3] : 12.1-5 The tracks and platform are located level with Boston Avenue; the Broadway bridge arcs over the tracks. [2] The main entrance is from the Broadway bridge, with a small footbridge to a headhouse structure; stairs plus an elevator for accessibility connect the headhouse to the southeast end of the platform. A secondary accessible entrance from Boston Avenue also connects to the southeast end, with a grade crossing of the inbound Green Line track. [2]
A 50-space "Pedal and Park" bike cage is located along the entrance from Boston Avenue. The Ball Square Traction Power Substation is located next to the northwest end of the station along Boston Avenue. The remaining station frontage along Boston Avenue is reserved for future transit oriented development. [2] Public art at the station includes Tour Jeté Series by Christine Vaillancourt – colored geometric glass forms located on the elevator tower – as well as historic images and views of Vaillancourt's artwork on panels on the station signs. [4] [5] MBTA bus routes 80 and 89 stop on Broadway just west of Boston Avenue. [6] [2]
The Boston and Lowell Railroad opened through Somerville and Medford in 1835, although local passenger stops were not added until several years later. Willow Bridge station was open by 1850 at Cambridge Road (now Broadway) on the border between the municipalities. [7] [8] It was named for the willow trees that lined nearby Winter Brook. [9] The station was briefly renamed Cambridge Road in the early 1850s, but reverted to Willow Bridge by 1858. [10] [11] [12] The station became an unloading point for cattle bound for the Brighton Abattoir; the railroad built a cattle station in 1859. [13] The wooden bridge was replaced in 1868 with an iron bridge, which was in turn replaced in 1893. [14] [15]
By 1874, the station was located on the west side of the tracks just north of Broadway. [16] It was renamed North Somerville around 1878. [17] [18] The original station building was replaced with a small Queen Anne style station in the 1880s. [19] In 1887, the B&L was leased by the Boston and Maine Railroad (B&M) as its Southern Division. [10] A southbound freight train derailed at the station on June 25, 1916, blocking the line for over 24 hours and attracting 10,000 onlookers. [20] [21]
Streetcars consolidated under the Boston Elevated Railway, then automobiles, cut sharply into local railroad traffic. All stops south of North Somerville were closed by the late 1940s. On April 18, 1958, the Public Utilities Commission approved a vast set of cuts to B&M commuter service, including the closure of North Somerville, Tufts College, and Medford Hillside stations. [22] The three stations were closed on May 18, 1958, amid the first of a series of cuts. [23] [24] The station building, modified for other uses, remained standing until the 1990s. [25] [19]
The Boston Elevated Railway (BERy) opened Lechmere station in 1922 as a terminal for streetcar service in the Tremont Street subway. [26] That year, with the downtown subway network and several radial lines in service, the BERy indicated plans to build three additional radial subways: one paralleling the Midland Branch through Dorchester, a second branching from the Boylston Street subway to run under Huntington Avenue, and a third extending from Lechmere Square northwest through Somerville. [27]
The Report on Improved Transportation Facilities, published by the Boston Division of Metropolitan Planning in 1926, proposed extension from Lechmere to North Cambridge via the Southern Division and the 1870-built cutoff. Consideration was also given to extension past North Cambridge over the Lexington Branch, and to a branch following the Southern Division from Somerville Junction to Woburn. [28] [29]
In 1945, a preliminary report from the state Coolidge Commission recommended nine suburban rapid transit extensions – most similar to the 1926 plan – along existing railroad lines. These included an extension from Lechmere to Woburn over the Southern Division, rather than using the Fitchburg Cutoff. North Somerville was to be among the intermediate stations. [30] : 16 [31] [32] The 1962 North Terminal Area Study recommended that the elevated Lechmere–North Station segment be abandoned. The Main Line (now the Orange Line) was to be relocated along the B&M Western Route; it would have a branch following the Southern Division to Arlington or Woburn. [33]
The Massachusetts Bay Transportation Authority (MBTA) was formed in 1964 as an expansion of the Metropolitan Transit Authority to subsidize suburban commuter rail service, as well as to construct rapid transit extensions to replace some commuter rail lines. [23] : 15 In 1965, as part of systemwide rebranding, the Tremont Street subway and its connecting lines became the Green Line. [34] The 1966 Program for Mass Transportation, the MBTA's first long-range plan, listed a short extension from Lechmere to Washington Street as an immediate priority, with a second phase reaching to Mystic Valley Parkway (Route 16) or West Medford. [35] [28]
The 1972 final report of the Boston Transportation Planning Review listed a Green Line extension from Lechmere to Ball Square as a lower priority, as did several subsequent planning documents. [28] [36] In 1980, the MBTA began a study of the "Green Line Northwest Corridor" (from Haymarket to Medford), with extension past Lechmere one of its three topic areas. Extensions to Tufts University or Union Square were considered. [37] : 308 [38]
A 1991 agreement between the state and the Conservation Law Foundation, which settled a lawsuit over auto emissions from the Big Dig, committed to the construction of a "Green Line Extension To Ball Square/Tufts University". [39] No progress was made until an updated agreement was signed in 2005. [40] The Beyond Lechmere Northwest Corridor Study, a Major Investment Study/alternatives analysis, was published in 2005. The analysis studied a variety of light rail, bus rapid transit, and commuter rail extensions, most of which included a Ball Square station near the former North Somerville station site. The highest-rated alternatives all included an extension to West Medford with Ball Square as one of the intermediate stations. [41]
The Massachusetts Executive Office of Transportation and Public Works submitted an Expanded Environmental Notification Form (EENF) to the Massachusetts Executive Office of Environmental Affairs in October 2006. The EENF identified a Green Line extension with Medford and Union Square branches as the preferred alternative. [42] Planned station sites for the Green Line Extension (GLX) were announced in May 2008. Locations at both Broadway and Harvard Street were considered for Ball Square station. The Broadway site was chosen due to its proximity to Ball Square, more public support, and better station spacing. [43] [44] [45] An alternative with a tunnel from Ball Square to Alewife via Powderhouse Square and Clarendon Hill was analyzed later in 2008. It was found to be technically feasible but not cost-effective. [46]
The Draft Environmental Impact Report (DEIR), released in October 2009, concurred with the Broadway site, noting also the connections available to the route 80 and 89 buses. [47] Preliminary plans in the DEIR called for the station to have a single island platform northwest of Broadway. A two-level headhouse with stairs, two escalators, and four elevators would have entrances from a plaza on Boston Avenue and from the Broadway bridge. [1] : 49 [48] A Ball Square commuter rail station – either in addition to a Green Line station or in lieu of it – was listed as a possibility in 2012 as an interim air quality mitigation measure in response to delays in building the Green Line Extension. However, such a station would have been costly to build and could not have been completed by the 2015 deadline, and was thus not supported by MassDOT. [49]
Updated plans shown in June 2011 changed the headhouse exterior and modified the emergency exit from the northwest end of the platform. [50] Plans presented in February 2012 added a bike cage, a traction power substation, and a drop-off area for The Ride at the lower plaza. [51] [52] By late 2012, the portion of the Medford Branch from Gilman Square station to College Avenue was expected to be completed by June 2019. [53] A further update in June 2013 moved the headhouse back 60 feet (18 m) from Broadway to avoid a buried NStar power distribution line that had not been previously known. The substation was set back from Boston Avenue to leave room for future transit oriented development, while part of the plaza became sloped terraces. [54] [55] Design was then paused while Phase 2/2A stations (Lechmere, Union Square, and East Somerville) were prioritized, as they were scheduled to open sooner than the rest of the GLX. Design resumed in fall 2014 and reached 90% by May 2015. [56]
In August 2015, the MBTA disclosed that project costs had increased substantially, triggering a wholesale re-evaluation of the GLX project. [57] In December 2015, the MBTA ended its contracts with four firms. Construction work in progress continued, but no new contracts were awarded. [58] At that time, cancellation of the project was considered possible, as were elimination of the Union Square Branch and other cost reduction measures. [59] [60] In May 2016, the MassDOT and MBTA boards approved a modified project that had undergone value engineering to reduce its cost. Stations were simplified to resemble D branch surface stations rather than full rapid transit stations, with canopies, faregates, escalators, and some elevators removed. Ball Square station was reduced to a single entrance from Boston Avenue with an at-grade crossing of the inbound track; there would be no elevators and no access from the Broadway bridge. [61] [62]
In December 2016, the MBTA announced a new planned opening date of 2021 for the extension. [63] A design-build contract for the GLX was awarded in November 2017. [64] The winning proposal included six additive options – elements removed during value engineering – including full-length canopies at all stations, as well as an entrance from the Broadway bridge with a single elevator and stairs. [65] [66] [67] Station design advanced from 0% in March 2018 to 45% that December and to 95% in October 2019. [68] [2]
The Broadway bridge adjacent to the station required replacement with a longer bridge to accommodate the Green Line tracks. A temporary utility bridge was constructed in the first half of 2015. [69] Replacement of the road bridge required a lengthy closure of Broadway — one of the primary east–west arterials in Somerville. Several options to shorten the detour for pedestrians, including retrofitting the utility bridge to serve as a footbridge, were found to be infeasible. [70] The bridge closed on March 22, 2019, with bus routes 80 and 89 detoured. [71] [72] Demolition of the old bridge began the next day. [73] The new bridge partially opened (with one lane per direction and one sidewalk) on June 6, 2020, and was fully opened by November. [74] [75] [76]
Several older buildings, including a bowling alley, were demolished in April 2019 to make way for the station and the traction power substation. [77] [78] Work on the substation was underway by February 2020. [79] Construction of the platform foundation began by August 2020; it was completed by November, with the platform poured by the end of the year. [80] [81] [82] The canopy was completed in April 2021, with the elevator shaft and headhouse frame erected in May. [83] [84] [85] In July 2021, the MBTA indicated that planning for adjacent transit-oriented development would not take place until after the station opened. [86]
Original plans called for the D branch to be extended to Medford/Tufts. [87] [88] However, in April 2021, the MBTA indicated that the Medford branch would instead be served by the E branch. [89] By March 2021, the station was expected to open in December 2021. [90] In June 2021, the MBTA indicated an additional delay, under which the station was expected to open in May 2022. [91] In February 2022, the MBTA announced that the Medford Branch would open in "late summer". [92] Train testing on the Medford Branch began in May 2022. [93] In August 2022, the planned opening was delayed to November 2022. [94] The Medford Branch, including Ball Square station, opened on December 12, 2022. [95]
The Green Line is a semi-metro system run by the Massachusetts Bay Transportation Authority (MBTA) in the Boston, Massachusetts, metropolitan area. It is the oldest MBTA subway line, and with tunnel sections dating from 1897, the oldest subway in North America. It runs underground through downtown Boston, and on the surface into inner suburbs via six branches on radial boulevards and grade-separated alignments. With an average daily weekday ridership of 137,700 in 2019, it is the third most heavily used light rail system in the country. The line was assigned the green color in 1967 during a systemwide rebranding because several branches pass through sections of the Emerald Necklace of Boston.
Alewife station is a Massachusetts Bay Transportation Authority (MBTA) intermodal transit station in the North Cambridge neighborhood of Cambridge, Massachusetts. It is the northwest terminal of the rapid transit Red Line and a hub for several MBTA bus routes. The station is at the confluence of the Minuteman Bikeway, Alewife Linear Park, Fitchburg Cutoff Path, and Alewife Greenway off Alewife Brook Parkway adjacent to Massachusetts Route 2, with a five-story parking garage for park and ride use. The station has three bike cages. Alewife station is named after nearby Alewife Brook Parkway and Alewife Brook, themselves named after the alewife fish.
Porter station is a Massachusetts Bay Transportation Authority (MBTA) transit station in Cambridge, Massachusetts. It serves the Red Line rapid transit line, the MBTA Commuter Rail Fitchburg Line, and several MBTA bus lines. Located at Porter Square at the intersection of Massachusetts and Somerville Avenues, the station provides rapid transit access to northern Cambridge and the western portions of Somerville. Porter is 14 minutes from Park Street on the Red Line, and about 10 minutes from North Station on commuter rail trains. Several local MBTA bus routes also stop at the station.
Government Center station is an MBTA subway station in Boston, Massachusetts. It is located at the intersection of Tremont, Court and Cambridge Streets in the Government Center area. It is a transfer point between the light rail Green Line and the rapid transit Blue Line. With the Green Line platform having opened in 1898, the station is the third-oldest operating subway station in the MBTA system; only Park Street and Boylston are older. The station previously served Scollay Square before its demolition for the creation of Boston City Hall Plaza.
The Somerville Community Path is a paved rail trail in Somerville, Massachusetts, running 3.2 miles (5.1 km) from Massachusetts Avenue to East Cambridge via Davis Square. The first portion opened in 1985 along part of the former Fitchburg Cutoff rail line. Extensions opened in 1994 and 2015. A further 1.9-mile (3.1 km) extension to East Cambridge opened in June 2023 as part of the Green Line Extension project. It is a section of the partially completed Mass Central Rail Trail.
Science Park station is an elevated light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line in Boston, Massachusetts, United States. The station is located at the Boston end of the Charles River Dam Bridge at Leverett Circle. It is at the southeast end of the Lechmere Viaduct, which carries the Green Line over the Charles River. The station is named for the nearby Boston Museum of Science. With 873 daily boardings by a FY 2019 count, Science Park is the least-used fare-controlled station on the Green Line, and the second-lowest on the MBTA subway system after Suffolk Downs.
Lechmere station is a Massachusetts Bay Transportation Authority (MBTA) Green Line light rail station in Lechmere Square in East Cambridge, Massachusetts. It is located on the east side of Monsignor O'Brien Highway near First Street, adjacent to the NorthPoint development. The accessible elevated station has a single island platform, with headhouses at both ends. It opened on March 21, 2022, as part of the Green Line Extension (GLX). Lechmere station is served by Green Line D branch and E branch service.
The E branch is a light rail line in Boston, Cambridge, Medford, and Somerville, Massachusetts, operating as part of the Massachusetts Bay Transportation Authority (MBTA) Green Line. The line runs in mixed traffic on South Huntington Avenue and Huntington Avenue between Heath Street and Brigham Circle, in the median of Huntington Avenue to Northeastern University, then into the Huntington Avenue subway. The line merges into the Boylston Street subway just west of Copley, running to North Station via the Tremont Street subway. It then follows the Lechmere Viaduct to Lechmere, then the Medford Branch to Medford/Tufts. As of February 2023, service operates on eight-minute headways at weekday peak hours and eight to nine-minute headways at other times, using 13 to 17 trains.
The Green Line D branch is a light rail line in Boston, Brookline, Cambridge, Newton, and Somerville, Massachusetts, operating as part of the Massachusetts Bay Transportation Authority (MBTA) Green Line. The line runs on a grade separated surface right-of-way for 9 miles (14 km) from Riverside station to Fenway station. The line merges into the C branch tunnel west of Kenmore, then follows the Boylston Street subway and Tremont Street subway to North Station. It is the longest and busiest of the four Green Line branches. As of February 2023, service operates on 8 to 9-minute headways at weekday peak hours and 8 to 11-minute headways at other times, using 13 to 19 trains.
The Urban Ring was a proposed project of the Massachusetts Bay Transportation Authority and the Massachusetts Department of Transportation, to develop new public transportation routes that would provide improved circumferential connections among many existing transit lines that project radially from downtown Boston. The Urban Ring Corridor is located roughly one to two miles from downtown Boston, passing through the Massachusetts cities of Boston, Chelsea, Everett, Medford, Somerville, Cambridge, and Brookline. The project was expected to convert 41,500 car trips to transit trips daily.
The Lechmere Viaduct is a concrete arch bridge connecting the West End neighborhood of Boston to East Cambridge, Massachusetts. Opened in 1912, the viaduct carries the MBTA's Green Line over the Charles River. It is adjacent to the Charles River Dam Bridge, but structurally separate.
The Green Line Extension (GLX) was a construction project to extend the Massachusetts Bay Transportation Authority (MBTA) Green Line light rail system northwest into Somerville and Medford, two inner suburbs of Boston, Massachusetts. The project opened in two phases in 2022 at a total cost of $2.28 billion. Total ridership on the 4.3-mile (6.9 km) extension is estimated to reach 45,000 one-way trips per day in 2030.
Assembly station is a rapid transit station in Somerville, Massachusetts. It serves the MBTA's Orange Line. It is an infill station, located on a section of the Orange Line that has been active since 1975. The station, which opened on September 2, 2014, was the first new rail station on the MBTA subway system since 1987. Assembly station is meant to provide convenient access to Assembly Square - a major retail and residential development located on the site of a former Ford assembly plant - and the adjacent Assembly Square Marketplace.
Medford/Tufts station is a light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line located off Boston Avenue near College Avenue in Medford, Massachusetts, adjacent to Tufts University. The accessible station has a single island platform serving the two tracks of the Medford Branch. It opened on December 12, 2022, as part of the Green Line Extension (GLX), which added two northern branches to the Green Line, and is the northern terminus of the E branch.
Magoun Square station is a light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line located at Lowell Street south of Magoun Square in Somerville, Massachusetts. The accessible station has a single island platform serving the two tracks of the Medford Branch. It opened on December 12, 2022, as part of the Green Line Extension (GLX), which added two northern branches to the Green Line, and is served by the E branch.
Gilman Square station is a light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line located at Gilman Square in Somerville, Massachusetts. The accessible station has a single island platform serving the two tracks of the Medford Branch. It opened on December 12, 2022, as part of the Green Line Extension (GLX), which added two northern branches to the Green Line, and is served by the E branch.
East Somerville station is a light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line located in southeastern Somerville, Massachusetts. The accessible station has a single island platform serving the two tracks of the Medford Branch. It opened on December 12, 2022, as part of the Green Line Extension (GLX), which added two northern branches to the Green Line, and is served by the E branch.
Union Square station is a light rail station on the Massachusetts Bay Transportation Authority (MBTA) Green Line located in the Union Square neighborhood of southeastern Somerville, Massachusetts. The accessible terminal station has a single island platform serving the two tracks of the Union Square Branch, which parallels the Fitchburg Line. It opened on March 21, 2022, as part of the Green Line Extension (GLX), which added two northern branches to the Green Line.
The Massachusetts Bay Transportation Authority operates subway, bus, commuter rail, and ferry service in the Greater Boston region. Boston has some of the highest rates of non-motorized commuting in the United States, including high bicycle usage. The MBTA offers certain provisions for riders wishing to make part of their trips by bicycle. The agency allows bicycles to be carried on all fixed-route services except the Green Line and the Ashmont-Mattapan High Speed Line light rail lines, although they are restricted on the commuter rail and heavy rail subway services at peak hours. Bicycle storage areas are offered at many stations, with "Pedal and Park" locking bicycle cages at certain high-usage stations.
North Station is an underground MBTA subway station in Boston, Massachusetts. Served by the Massachusetts Bay Transportation Authority (MBTA) Green Line and Orange Line, it is connected to the North Station surface terminal used by MBTA Commuter Rail and Amtrak. The station is fully accessible.
Media related to Ball Square station at Wikimedia Commons