Well completion is the process of making a well ready for production (or injection) after drilling operations. This principally involves preparing the bottom of the hole to the required specifications, running in the production tubing and its associated down hole tools as well as perforating and stimulating as required. Sometimes, the process of running in and cementing the casing is also included. After a well has been drilled, should the drilling fluids be removed, the well would eventually close in upon itself. Casing ensures that this will not happen while also protecting the wellstream from outside incumbents, like water or sand. [1]

Contents

Perforated shoe Perforated Shoe.JPG
Perforated shoe

Lower completion (downhole completion)

This refers to the portion of the well across the production or injection zone. The well designer has many tools and options available to design the lower completion (downhole completion) according to the conditions of the reservoir. Typically, the lower completion is set across the productive zone using a liner hanger system, which anchors the lower completion to the production casing string. The broad categories of lower completion are listed below.

Barefoot completion

This type is the most basic, but can be a good choice for hard rock, multi-laterals and underbalance drilling. It involves leaving the productive reservoir section without any tubulars. This effectively removes control of flow of fluids from the formation; it is not suitable for weaker formations which might require sand control, nor for formations requiring selective isolation of oil, gas and water intervals. However, advances in interventions such as coiled tubing and tractors means that barefoot wells can be successfully produced.

Open hole

The production casing is set above the zone of interest before drilling the zone. The zone is open to the well bore. In this case little expense is generated with perforations. Log interpretation is not critical. The well can be deepened easily and it is easily converted to screen and liner. However, excessive gas and water production is difficult to control, and may require frequent clean outs. Also the interval cannot be selectively stimulated.

Open hole completion

This designation refers to a range of completions where no casing or liner is cemented in place across the production zone. In competent formations, the zone might be left entirely bare, but some sort of sand-control and/or flow-control means are usually incorporated.

Openhole completions have seen significant uptake in recent years, and there are many configurations, often developed to address specific reservoir challenges. There have been many recent developments that have boosted the success of openhole completions, and they also tend to be popular in horizontal wells, where cemented installations are more expensive and technically more difficult. The common options for openhole completions are:

Pre-holed liner

Also often called pre-drilled liner. The liner is prepared with multiple small drilled holes, then set across the production zone to provide wellbore stability and an intervention conduit. Pre-holed liner is often combined with openhole packers, such as swelling elastomers, mechanical packers or external casing packers, to provide zonal segregation and isolation. It is now quite common to see a combination of pre-holed liner, solid liner and swelling elastomer packers to provide an initial isolation of unwanted water or gas zones. Multiple sliding sleeves can also be used in conjunction with openhole packers to provide considerable flexibility in zonal flow control for the life of the wellbore.

This type of completion is also being adopted in some water injection wells, although these require a much greater performance envelope for openhole packers, due to the considerable pressure and temperature changes that occur in water injectors.

Openhole completions (in comparison with cemented pipe) require better understanding of formation damage, wellbore clean-up and fluid loss control. A key difference is that perforating penetrates through the first 6-18 inches (15–45 cm) of formation around the wellbore, whilst openhole completions require the reservoir fluids to flow through all of the filtrate-invaded zone around the wellbore and lift-off of the mud filter cake.

Many openhole completions will incorporate fluid loss valves at the top of the liner to provide well control whilst the upper completion is run.

There are an increasing number of ideas coming into the market place to extend the options for openhole completions; for example, electronics can be used to actuate a self-opening or self-closing liner valve. This might be used in an openhole completion to improve clean-up, by bringing the well onto production from the toe-end for 100 days, then self-opening the heel-end. Inflow control devices and intelligent completions are also installed as openhole completions.

Pre-holed liner may provide some basic control of solids production, where the wellbore is thought to fail in aggregated chunks of rubble, but it is not typically regarded as a sand control completion.

Slotted liner

Slotted liners can be selected as an alternative to pre-holed liner, sometimes as a personal preference or from established practice on a field. It can also be selected to provide a low cost control of sand/solids production. The slotted liner is machined with multiple longitudinal slots, for example 2 mm × 50 mm, spread across the length and circumference of each joint. Recent advances in laser cutting means that slotting can now be done much cheaper to much smaller slot widths and in some situation slotted liner is now used for the same functionality as sand control screens.

Openhole sand control

This is selected where the liner is required to mechanically hold back the movement of formation sand. There are many variants of openhole sand control, the three popular choices being stand-alone screens, openhole gravel packs (also known as external gravel packs, where a sized sand 'gravel' is placed as an annulus around the sand control screen) and expandable screens. Screen designs are mainly wire-wrap or premium; wire-wrap screens use spiral-welded corrosion-resistant wire wrapped around a drilled basepipe to provide a consistent small helical gap (such as 0.012-inch (0.30 mm), termed 12 gauge). Premium screens use a woven metal cloth wrapped around a basepipe. Expandable screens are run to depth before being mechanically swaged to a larger diameter. Ideally, expandable screens will be swaged until they contact the wellbore wall.

Horizontal open hole completions

This is the most common open hole completion used today. It is basically the same described on the vertical open hole completion but on a horizontal well it enlarges significantly the contact with the reservoir, increasing the production or injection rates of your well. Sand control on a horizontal well is completely different from a vertical well. We can no longer rely on the gravity for the gravel placement. Most service companies uses an alpha and beta wave design to cover the total length of the horizontal well with gravel. It's known that very long wells (around 6000 ft) were successfully gravel packed in many occasions, including deepwater reservoirs in Brazil.

Liner completions

In this case the casing is set above the primary zone. An un-cemented screen and liner assembly is installed across the pay section. This technique minimizes formation damage and gives the ability to control sand. It also makes cleanout easy. Perforating expense is also low to non-existent. However gas and water build up is difficult to control and selective stimulation not possible the well can't be easily deepened and additional rig time may be needed.

Perforated liner

Casing is set above the producing zone, the zone is drilled and the liner casing is cemented in place. The liner is then perforated for production. This time additional expense in perforating the casing is incurred, also log interpretation is critical and it may be difficult to obtain good quality cement jobs.

Perforated casing

Production casing is cemented through the zone and the pay section is selectively perforated. Gas and water are easily controlled as is sand. The formation can be selectively stimulated and the well can be deepened. This selection is adaptable to other completion configurations and logs are available to assist casing decisions. Much better primary casing. It can however cause damage to zones and needs good log interpretation. The perforating cost can be very high.

Cased hole completion

This involves running casing and a liner down through the production zone, and cementing it in place. Connection between the well bore and the formation is made by perforating. Because perforation intervals can be precisely positioned, this type of completion affords good control of fluid flow, although it relies on the quality of the cement to prevent fluid flow behind the liner. As such it is the most common form of completion...

Conventional completions

Completion components

The upper completion refers to all components from the bottom of the production tubing upwards. Proper design of this "completion string" is essential to ensure the well can flow properly given the reservoir conditions and to permit any operations as are deemed necessary for enhancing production and safety.

Wellhead with situation control

This is the pressure containing equipment at the surface of the well where casing strings are suspended and the blowout preventer or Christmas tree is connected.

Christmas tree

This is the main assembly of valves that controls flow from the well to the process plant (or the other way round for injection wells) and allows access for chemical squeezes[ clarification needed (definition)] and well interventions.

Tubing hanger

This component sits in the upper portion of the wellhead, within the tubing head flange and serves as the main support for the production tubing.

The tubing hanger may be manufactured with rubber or polymer sealing rings to isolate the tubing from the annulus.

The tubing hanger is secured within the tubing head flange with lag bolts. These lag bolts apply a downward pressure on the tubing hanger to compress the sealing gaskets and to prevent the tubing from being hydrostatically or mechanically ejected from the annulus. [2]

Production tubing

Production tubing is the main conduit for transporting hydrocarbons from the reservoir to surface (or injection material the other way). It runs from the tubing hanger at the top of the wellhead down to a point generally just above the top of the production zone.

Production tubing is available in various diameters, typically ranging from 2 inches to 4.5 inches.

Production tubing may be manufactured using various grades of alloys to achieve specific hardness, corrosion resistance or tensile strength requirements.

Tubing may be internally coated with various rubber or plastic coatings to enhance corrosion and/or erosion resistance.

Downhole safety valve (DHSV)

This component is intended as a last-resort method of protecting the surface from the uncontrolled release of hydrocarbons. It is a cylindrical valve with either a ball or flapper closing mechanism. It is installed in the production tubing and is held in the open position by a high-pressure hydraulic line from surface contained in a 6.35 mm (1/4") control line that is attached to the DHSV's hydraulic chamber and terminated at surface to a hydraulic actuator. The high pressure is needed to overcome the production pressure in the tubing upstream of the choke on the tree. The valve will operate if the umbilical HP line is cut or the wellhead/tree is destroyed.

This valve allows fluids to pass up or be pumped down the production tubing. When closed the DHSV forms a barrier in the direction of hydrocarbon flow, but fluids can still be pumped down for well kill operations. It is placed as far below the surface as is deemed safe from any possible surface disturbance including cratering caused by the wipeout of the platform. Where hydrates are likely to form (most production is at risk of this), the depth of the SCSSV (surface-controlled, sub-surface safety valve) below the seabed may be as much as 1 km: this will allow for the geothermal temperature to be high enough to prevent hydrates from blocking the valve.

Annular safety valve

On wells with gas lift capability, many operators consider it prudent to install a valve, which will isolate the A annulus for the same reasons a DHSV may be needed to isolate the production tubing in order to prevent the inventory of natural gas downhole from becoming a hazard as it became on Piper Alpha.

Side pocket mandrel

This is a welded/machined product which contains a "side pocket" alongside the main tubular conduit. The side pocket, typically 1" or 1½" diameter is designed to contain gas lift valve, which allows flow of High pressure gas into the tubing there by reducing the tubing pressure and allowing the hydrocarbons to move upwards.

Electrical submersible pump

This device is used for artificial lift to help provide energy to drive hydrocarbons to surface if reservoir pressure is insufficient.

Electrical Submersible Pumps, or ESPs, are installed at the bottom of the production tubing or inside the production tubing (Through Tubing ESP).

Being electrically powered, ESPs require an electrical communications conduit to be run from surface, through a specialized wellhead and tubing hanger, to provide the required power to function.

During installation, the power cable is spliced into the ESP then attached to the outside of the tubing by corrosion resistant metal bands as it is run in the hole.

Specialized guards, called cannon guards, may be installed over each tubing collar to prevent the cable from rubbing on the casing walls which can cause premature cable failure.

Installation and workover processes require careful consideration to prevent any damage to the power cable.

Like many other artificial lift methods, the ESP reduces the bottom hole pressure at the tubing bottom to allow hydrocarbons to flow into the tubing.

Landing nipple

A completion component fabricated as a short section of heavy wall tubular with a machined internal surface that provides a seal area and a locking profile. Landing nipples are included in most completions at predetermined intervals to enable the installation of flow-control devices, such as plugs and chokes. Three basic types of landing nipple are commonly used: no-go nipples, selective-landing nipples and ported or safety-valve nipples.

Sliding sleeve

The sliding sleeve is hydraulically or mechanically actuated to allow communication between the tubing and the 'A' annulus. They are often used in multiple reservoir wells to regulate flow to and from the zones.

Production packer

The packer isolates the annulus between the tubing and the inner casing and the foot of the well. This is to stop reservoir fluids from flowing up the full length of the casing and damaging it. It is generally placed close to the foot of the tubing, shortly above the production zone.

Downhole gauges

This is an electronic or fiberoptic sensor to provide continuous monitoring of downhole pressure and temperature. Gauges either use a 1/4" control line clamped onto the outside of the tubing string to provide an electrical or fiberoptic communication to surface, or transmit measured data to surface by acoustic signal in the tubing wall. The information obtained from these monitoring devices can be used to model reservoirs or predict the life or problems in a specific wellbore.

Perforated joint

This is a length of tubing with holes punched into it. If used, it will normally be positioned below the packer and will offer an alternative entry path for reservoir fluids into the tubing in case the shoe becomes blocked, for example, by a stuck perforation gun.

Formation isolation valve

This component, placed towards the foot of the completion string, is used to provide two way isolation from the formation for completion operations without the need for kill weight fluids. Their use is sporadic as they do not enjoy the best reputation for reliability when it comes to opening them at the end of the completion process.

Centralizer

In highly deviated wells, this component may be included towards the foot of the completion. It consists of a large collar, which keeps the completion string centralised within the hole while cementing.

Wireline entry guide

This component is often installed at the end of the tubing, or "the shoe". It is intended to make pulling out wireline tools easier by offering a guiding surface for the toolstring to re-enter the tubing without getting caught on the side of the shoe.

Perforating and stimulating

In cased hole completions (the majority of wells), once the completion string is in place, the final stage is to make a connection between the wellbore and the formation. This is done by running perforation guns to blast holes in the casing or liner to make a connection. Modern perforations are made using shaped explosive charges, similar to the armor-penetrating charge used on antitank rockets (bazookas).

Sometimes once the well is fully completed, further stimulation is necessary to achieve the planned productivity. There are a number of stimulation techniques.

Acidizing

This involves the injection of chemicals to eat away at any skin damage, "cleaning up" the formation, thereby improving the flow of reservoir fluids. A strong acid (usually hydrochloric acid) is used to dissolve rock formations, but this acid does not react with the Hydrocarbons. As a result, the Hydrocarbons are more accessible. Acid can also be used to clean the wellbore of some scales that form from mineral laden produced water.

Fracturing

This means creating and extending fractures from the perforation tunnels deeper into the formation, increasing the surface area for formation fluids to flow into the well, as well as extending past any possible damage near the wellbore. This may be done by injecting fluids at high pressure (hydraulic fracturing), injecting fluids laced with round granular material (proppant fracturing), or using explosives to generate a high pressure and high speed gas flow (TNT or PETN up to 1,900,000 psi (13,000,000 kPa) ) and (propellant stimulation up to 4,000 psi (28,000 kPa) ).

Acidizing and fracturing (combined method)

This involves use of explosives and injection of chemicals to increase acid-rock contact.

Nitrogen circulation

Sometimes, productivity may be hampered due to the residue of completion fluids, heavy brines, in the wellbore. This is particularly a problem in gas wells. In these cases, coiled tubing may be used to pump nitrogen at high pressure into the bottom of the borehole to circulate out the brine.

See also

Related Research Articles

<span class="mw-page-title-main">Oil well</span> Well drilled to extract crude oil and/or gas

An oil well is a drillhole boring in Earth that is designed to bring petroleum oil hydrocarbons to the surface. Usually some natural gas is released as associated petroleum gas along with the oil. A well that is designed to produce only gas may be termed a gas well. Wells are created by drilling down into an oil or gas reserve that is then mounted with an extraction device such as a pumpjack which allows extraction from the reserve. Creating the wells can be an expensive process, costing at least hundreds of thousands of dollars, and costing much more when in hard to reach areas, e.g., when creating offshore oil platforms. The process of modern drilling for wells first started in the 19th century, but was made more efficient with advances to oil drilling rigs during the 20th century.

<span class="mw-page-title-main">Wireline (cabling)</span> Technology used in oil and gas wells

In the oil and gas industry, the term wireline usually refers to the use of multi-conductor, single conductor or slickline cable, or "wireline", as a conveyance for the acquisition of subsurface petrophysical and geophysical data and the delivery of well construction services such as pipe recovery, perforating, plug setting and well cleaning and fishing. The subsurface geophysical and petrophysical information results in the description and analysis of subsurface geology, reservoir properties and production characteristics.

<span class="mw-page-title-main">Pumpjack</span> Drive for a reciprocating piston pump in an oil well

A pumpjack is the overground drive for a reciprocating piston pump in an oil well.

Well control is the technique used in oil and gas operations such as drilling, well workover and well completion for maintaining the hydrostatic pressure and formation pressure to prevent the influx of formation fluids into the wellbore. This technique involves the estimation of formation fluid pressures, the strength of the subsurface formations and the use of casing and mud density to offset those pressures in a predictable fashion. Understanding pressure and pressure relationships is important in well control.

<span class="mw-page-title-main">Casing (borehole)</span>

Casing is a large diameter pipe that is assembled and inserted into a recently drilled section of a borehole. Similar to the bones of a spine protecting the spinal cord, casing is set inside the drilled borehole to protect and support the wellstream. The lower portion is typically held in place with cement. Deeper strings usually are not cemented all the way to the surface, so the weight of the pipe must be partially supported by a casing hanger in the wellhead.

Production tubing is a tube used in a wellbore through which production fluids are produced (travel).

<span class="mw-page-title-main">Drilling fluid</span> Aid for drilling boreholes into the ground

In geotechnical engineering, drilling fluid, also known as drilling mud, is used to aid the drilling of boreholes into the earth. Used while drilling oil and natural gas wells and on exploration drilling rigs, drilling fluids are also used for much simpler boreholes, such as water wells.

<span class="mw-page-title-main">Blowout preventer</span> Specialized valve

A blowout preventer (BOP) is a specialized valve or similar mechanical device, used to seal, control and monitor oil and gas wells to prevent blowouts, the uncontrolled release of crude oil or natural gas from a well. They are usually installed in stacks of other valves.

<span class="mw-page-title-main">Drill stem test</span>

A drill stem test (DST) is a procedure for isolating and testing the pressure, permeability and productive capacity of a geological formation during the drilling of a well. The test is an important measurement of pressure behaviour at the drill stem and is a valuable way of obtaining information on the formation fluid and establishing whether a well has found a commercial hydrocarbon reservoir.

In drilling technology, casing string is a long section of connected oilfield pipe that is lowered into a wellbore and cemented. The purpose of the casing pipe is as follows:

Artificial lift refers to the use of artificial means to increase the flow of liquids, such as crude oil or water, from a production well. Generally this is achieved by the use of a mechanical device inside the well or by decreasing the weight of the hydrostatic column by injecting gas into the liquid some distance down the well. A newer method called Continuous Belt Transportation (CBT) uses an oil absorbing belt to extract from marginal and idle wells. Artificial lift is needed in wells when there is insufficient pressure in the reservoir to lift the produced fluids to the surface, but often used in naturally flowing wells to increase the flow rate above what would flow naturally. The produced fluid can be oil, water or a mix of oil and water, typically mixed with some amount of gas.

A production packer is a standard component of the completion hardware of oil or gas wells used to provide a seal between the outside of the production tubing and the inside of the casing, liner, or wellbore wall.

Slickline refers to a single strand wire which is used to run a variety of tools down into the wellbore for several purposes. It is used during well drilling operations in the oil and gas industry. In general, it can also describe a niche of the industry that involves using a slickline truck or doing a slickline job. Slickline looks like a long, smooth, unbraided wire, often shiny, silver/chrome in appearance. It comes in varying lengths, according to the depth of wells in the area it is used up to 35,000 feet in length. It is used to lower and raise downhole tools used in oil and gas well maintenance to the appropriate depth of the drilled well.

A perforation in the context of oil wells refers to a hole punched in the casing or liner of an oil well to connect it to the reservoir. It creates a channel between the pay zone and the wellbore to cause oil and gas to flow to the wellbore easily. In cased hole completions, the well will be drilled down past the section of the formation desired for production and will have casing or a liner run in separating the formation from the well bore. The final stage of the completion will involve running in perforating guns, a string of shaped charges, down to the desired depth and firing them to perforate the casing or liner. A typical perforating gun can carry many dozens of explosive charges.

A well kill is the operation of placing a column of special fluids of the required density into a well bore in order to prevent the flow of reservoir fluids without the need for pressure control equipment at the surface. It works on the principle that the hydrostatic head of the "kill fluid" or "kill mud" will be enough to suppress the pressure of the formation fluids. Well kills may be planned in the case of advanced interventions such as workovers, or be contingency operations. The situation calling for a well kill will dictate the method taken.

<span class="mw-page-title-main">Well stimulation</span>

Well stimulation is a well intervention performed on an oil or gas well to increase production by improving the flow of hydrocarbons from the reservoir into the well bore. It may be done using a well stimulator structure or using off shore ships / drilling vessels, also known as "Well stimulation vessels".

Oilfield terminology refers to the jargon used by those working in fields within and related to the upstream segment of the petroleum industry. It includes words and phrases describing professions, equipment, and procedures specific to the industry. It may also include slang terms used by oilfield workers to describe the same.

Oil Well Cementing Equipment are essential for the Oil/Gas exploration or production wells and are a must used oilfield equipments while drilling a well.

Petroleum production engineering is a subset of petroleum engineering.