Loharinag Pala Hydropower Project

Last updated

Loharinag Pala Hydropower Project
Bhagirathi River at Gangotri.JPG
The Bhagirathi river, the source stream of the Ganges River, in Gangotri, Uttarakhand, India
India Uttarakhand relief map.svg
Red pog.svg
Location of Loharinag Pala Hydropower Project in Uttarakhand
Location Uttarkashi Dt, Uttarakhand state, India
(near Uttarkashi 18.7 km (11.6 mi) ExNE)
Coordinates 30°49′6″N78°37′5″E / 30.81833°N 78.61806°E / 30.81833; 78.61806
StatusDiscontinued
Construction began19 February 2004 [1]
Opening dateOctober 2011 est.
Construction costRs 28,951 million (US$ 658 million).
Dam and spillways
Type of dam Weir
Impounds Bhagirathi River
Height15 m (49.2 ft)
Length115 m (377.3 ft)
Spillway type4 gates @ 13 m (43 ft) wide and 8.5 m (28 ft) high
Reservoir
Total capacity190,320 cubic metres (6,721,000 cu ft)
Catchment area 3,316 km2 (1,280 sq mi)
Surface area3 ha (0.0 km2)
Maximum water depth8.5 m (27.9 ft)
Normal elevation2,147.5 m (7,046 ft)
Power Station
Operator(s) National Thermal Power Corporation
Commission dateOctober 2011 est.
Hydraulic head 475.67 metres (1,560.6 ft)
Turbines four Pelton Turbines
@ 150 MW
Installed capacity 600 MW
Annual generation 2,353.37 Gigawatt hours per year
Website
III. LOHARINAG–PALA HYDROELECTRIC PROJECT 16
Designer: Voith Hydro (E&M Package)

Loharinag Pala Hydropower Project is a run-of-the-river hydroelectricity generating project planned by the National Thermal Power Corporation (NTPC) Ltd to have an output capacity of 600 MW (150 MW x 4 Units). The project is located on the river Bhagirathi, the headstream of the Ganges River at Loharinag Pala, below the confluence of the Songad River, next to NH 34 in Uttarkashi District of Uttarakhand state, India. This is about 100 kilometres (62 mi) upstream of the Tehri Dam. [2]

Contents

The main project construction contracts were awarded and construction started in 2006, [3] however, work was stopped in 2009 after Professor G. D. Agrawal, one of India's eminent scientists, [4] came close to dying on the 38th day of his fast in protest of the blocking the headwaters of the sacred River Ganges. [5] [6] Tarun Bharat Sangh, headed by Magsaysay award-winner, Rajendra Singh also played a pivotal role in stopping the project. [7] The project was officially scrapped in 2010.[ citation needed ]

The Loharinag-Pala project was one of several hundred dams and barrages planned or now being constructed by India, in the southern foothills of the Himalayas. Together they are expected to provide 150,000 MW of electricity for areas in which power cuts are frequent and demand is growing fast. [5]

Description

The Hydroelectricity project had been envisaged for installation of 4 generating Units of 150 MW utilizing a hydraulic head of 476.5 metres (1,563 ft) to have a maximum capacity of 600 MW. The facilities would include 4 vertical shaft Pelton wheel turbines. The generators would be of synchronous vertical shaft type. The generators would have capacity at a lagging power factor of 0.90, 3 phase, 250 rpm, and rated voltage of 11 to 18 kV. The generator transformer would be 4 nos oil forced air forced (OFAF) type with step-up voltage capacity of 400 kV. The estimate of Greenhouse gases (GHG) abatement in tonnes CO2 equivalent is 5,268,027 t (Starting from 2010). Host Country Approval Status was Approved. [8]

The Project Owner/Proponent was Mr. Piyush Pradhan, CDM Representative, Engineering Division, Project Engineering (Mech-CDM) (NTPC) Limited, NTPC Bhawan, Core-7; Scope Complex, 7-Institutional Area, Lodhi Road NTPC Bhawan, Scope Complex, New Delhi – 110003. The baseline methodology used for the project evaluation was ACM 0002: Consolidated methodology for grid-connected electricity generation from renewable sources – version 6; The latest version of the tool for demonstration and assessment of additionality (the additionality tool). The expected date for commissioning of the project was in the year 2010. Duration of the project activity is 21 years. [8]

Project land

For 16.455 hectares (41 acres) of private land, The District Magistrate (DM), Uttarkashi was instructed by The Government of Uttarakhand state to issue award in line to land acquisition (LA) Act. The Village Development Advisory Committee (VDAC) meeting was held on 08-05-2006 at Uttarkashi. f Award by the Special Land Acquisition Officer (SLAO) had been declared.

For reserve forest Civil Soyam land (total 139.029 hectares (344 acres)), the draft CAT Plan was submitted by District Forest Officer, Uttarkashi on 20-02-2006. Approval of the Catchment Area Treatment (CAT) Plan by GoUA was done.

For Forest Clearance, The Certificate for "Non Availability of Non-Forest Land for afforestation" was obtained by UPCL from Chief Secretary (UA). Certificate was submitted to Nodal Officer on 01-05-2006. Proposal has been cleared by Nodal Officer.

For township Land at Matli, private land needed was 11.383 hectares (28 acres) and government land needed was 1.835 ha. The revised proposal for Section IV was submitted in DM Office on 23-03-06. The Proposal was sent by DM, Uttarkashi to GoUA.now with discontinuation of the project by orders of India government the land acquisition is not being done.

For township land at Central Industrial Security Force (CISF) Colony at Kyark, private land needed was 9.979 hectares (25 acres) and government land needed was 1.436 hectares (4 acres). The proposal for Section IV was submitted in DM Office on 17-03-2006. The Proposal was sent to GoUA by DM, Uttarkashi but now not required as project has been discontinued by India government.

The project site starts from confluence of the Songad river on the Bhagirathi River in the Garhwal Himalaya to 18 kilometres (11 mi) down stream at Thirang gad confluence with Bhagirathi river. The barrage site is next to NH 108 at Loharinag Temple. The Project has a mountainous catchment area of 3,316 square kilometres (1,280 sq mi), of which 1,849 square kilometres (714 sq mi) (56%) is covered in snow or glacier. The source of the Bhagirathi is about 82 kilometres (51 mi) above the barrage. [9]

Construction of approach roads

For construction of approach road to Dabrani Adit (750 metres (2,460 ft) long ) private, forest and government land was needed. The LOA No. was LOA-54 dated 07-04-05 and the Deposit Work Agency was PWD, UA. Completion period was 6 months. The Date PWD Awarded the Work was 18-06-2005, Date of Start of Work was 01-08-2005 and the scheduled completion date was 31-01-2006. The formation width required was 10 m .

For construction of approach road to Gunaga Adit (4,000 metres (13,000 ft) long )Private, Forest and Govt land was needed. The LOA No. was LOA-32 dated 20-12-04 and Deposit Work Agency was PWD, UA. The completion period was 10 months and date PWD awarded the work was 28-02-2005. The date of start of Work was 16-07-2005, scheduled completion date was 16-05-2006, formation width Required was 10m.

For construction of approach road to Helgu Adit (6,000 metres (20,000 ft) long) private, forest and Govt land was needed. The LOA No. LOA-53 was dated 07-04-05. Deposit Work, Agency was PWD, UA. The completion period was 20 months, date PWD awarded the work was 18-06-2005, date of start of work was 19-01-2006, scheduled completion date was 18-09-2007. The formation[ clarification needed ] required was 10 metres (33 ft). This road could not be completed due to geotechnical reason and alignment was require change but due to suspension of work forest land needed was not transferred. The formation[ clarification needed ] width was 10 m.

For construction of approach road to surge shaft, a 6,810 metres (22,340 ft) long Bhukki -Kujjan road was to be constructed. LOA No. was LOA-09 dated 29-03-2004. The Deposit Work Agency was BRO[ clarification needed ]. Completion period was 24 Months, date of start of work was 01-07-2005 and scheduled completion date was 30-06-2007. Formation width was 10 m. Private land/forest land was acquired to start the work.

Construction of dam and powerhouse

For construction of three units, there were audits of 18-01-05 account, 17-03-05 account and 29-07-05 account, 13 months were awarded. For the Head Race Tunnel Package, on 18-04-05 account, 15-09-05 account and June 2006 account, there were 38 months. Evaluation was in progress. For underground power house and Penstock Package on 25-10-05 account, May 2006 account and Sept 2006, there was a schedule for 45 months. Bids were invited. For the electro-mechanical package April 2006 account, 09-06-06 and schedule Oct ’06, there was a schedule for 44 months. Bids were invited. For the hydro-mechanical package, Jan ’06, Account 31-05-06 Schedule Sep ’06, Schedule 40 months bids were invited. For construction of barrage and de-silting chamber 16-08-05, account 16-12-05. account June ’06 and anticipated 40 months, the evaluation was in progress.

Commissioning

Old schedule

Commissioning dates scheduled were: UNIT #1 February ’2011, UNIT #2 March ’2011, UNIT #3 April ’2011 and UNIT #4 - May ’2011. At present the schedule has slipped to end the project somewhere in second quarter of 2013 [10]

Update

Work on the Loharinag Pala Hydropower Project was stopped after one of India's eminent scientists came close to dying on the 38th day of his fast in protest of the harnessing of the river Bhagirathi, a source stream of the Ganges River.

Professor G. D. Agrawal (b. 1932), former dean of the Indian Institute of Technology Kanpur, in the first week of March 2009 called off his second fast in a year against Himalayan dam projects, after the Indian government agreed to speed up its inquiry into how electricity could be generated without the flow of the Ganges being impeded. The free-running of the river is a crucial element of its sacred status.

Before his fast began in January, Agrawal said,: "The water ...(of the Ganges) is not ordinary water to a Hindu. It is a matter of the life and death of Hindu faith". [5]

In August 2010, the Group of Ministers discontinued the project. [11]

Impact

Addition of 2,353.37 GWh of electricity generation to the Northern region grid would be the main measurable benefit of the Project. The average unit cost of electricity generated by the plant would be about Rs2.00 (US$0.0455) per kWh. The project appears to be economically viable under normal operating conditions. This table power supply is crucial for increased employment balanced growth in the area. The unit power cost from plants like the Loharinag–Pala HEP is less than the cost of private on site generation of electricity due to less-efficient technology and high fuel cost used of private off-grid generation. [12]

The Environmental impact statement (EIS) prepared by the NTPC indicates the main adverse environmental impacts of the project will be changes in river hydrology, a decline in the quality of aquatic ecosystems, loss of agricultural and forest land, and resettlement. Impacts on the rivers will be mitigated by the release of a 0.85–1.1 m3/s minimum environmentally acceptable dry season flow from the Loharinag–Pala dam, the release of monsoon season flushing flows, and yearly restocking of rivers above and below the barrage sites with common snowtrout. [13]

The loss of private agricultural and forest land has been or will be mitigated by the acquisition of private land at an above-market rate. The social impact of the projects will be mitigated by NTPC's resettlement and rehabilitation procedures, with fair compensation being paid by NTPC. [14]

Also the owner of the project is not been fair on their contractual part as of not clearing the situation of uncertainty prevailing from so long duration to their contractors causing high stakes and risks at contractors end.

Related Research Articles

<span class="mw-page-title-main">Tehri Dam</span> Dam in Uttarakhand, India

The Tehri Dam is a multi-purpose rock and earth-fill embankment dam on the Bhagirathi River in New Tehri, Tehri Garhwal district in Uttarakhand, India. With a height of 260.5 m (855 ft), it is the tallest dam in India and the 13th-tallest dam in the world. It is the primary dam of THDC India Ltd. and the Tehri hydroelectric complex. The dam begun construction in 1978 and was completed in 2006. It withholds a reservoir for irrigation, municipal water supply and the generation of 1,000 megawatts (1,300,000 hp) of hydroelectricity. The dam's 1,400 MW variable-speed pumped-storage scheme is currently under construction, with the commissioning of the first two units was expected to be completed in 2023, which got finished in March 2024, and the rest to be done by 2025.

<span class="mw-page-title-main">Alaknanda River</span> River in India

The Alaknanda is a turbulent Himalayan river in the Indian state of Uttarakhand and one of the two headstreams of the Ganges, the major river of Northern India and a river considered holy in Hinduism. In hydrology, the Alaknanda is considered the source stream of the Ganges on account of its greater length and discharge; while, in Hindu tradition and culture, the other headstream, the Bhagirathi, is considered the source stream.

<span class="mw-page-title-main">Nam Theun 2 Dam</span> Dam in Bolikhamsai and Khammouane Provinces, Laos

The Nam Theun 2 Hydropower Project, or simply NT2, is a hydroelectric dam on the Nam Theun River in Laos. Commercial operation of the plant began in April 2010. The scheme diverts water from the Nam Theun, a tributary of the Mekong River, to the Xe Bang Fai River, enabling a generation capacity of 1,075 MW, from a 350 m (1,148 ft) difference in elevation between the reservoir and the power station.

<span class="mw-page-title-main">Uttarkashi district</span> District in Uttarakhand, India

Uttarkashi District is a district of Garhwal division of the Uttarakhand state in northern India, and has its headquarters at Uttarkashi city. It has six Tehsils namely Barkot, Dunda, Bhatwadi, Chinyalisaur, Purola and Mori.

<span class="mw-page-title-main">Jangipur, Murshidabad</span> City in West Bengal, India

Jangipur is a city and a municipality in Murshidabad district in the state of West Bengal, India. It is the headquarters of the Jangipur subdivision. It is situated on the banks of the Bhagirathi. Jangipur is an old town having reference from the historical period of Moghul emperor Jahangir when an army camp was established here.

<span class="mw-page-title-main">Uttarkashi</span> Town in Uttarakhand, India

Uttarkashi, meaning Kashi of the north, is a town located in Uttarkashi district in Uttarakhand, India. Uttarkashi town is headquarters of the district. Uttarkashi is also known as Somya Kashi. Uttarkashi is a Hindu religious place for spiritual and adventurous tourism. Uttarkashi town is also called as Shivnagri. The town has number of temples and ashrams. Uttarkashi is known for its religious people, weather, education.

<span class="mw-page-title-main">Sharda River</span> River along the India–Nepal border

The Sharda River is the downstream of Kāli River that originates in the northern Uttarakhand state of India in the Great Himalayas on the eastern slopes of Nanda Devi massif, at an elevation of 3,600 m (11,800 ft) in the Pithoragarh district. It then flows between the Nepal and India border. Descending, it enters the Indo-Gangetic Plain at Brahmadev Mandi in Nepal, where it expands above the Sharda Barrage. From that point onward, it is known as the Sharda River. The river proceeds southeastward into India through northern Uttar Pradesh before merging with the Ghaghara River southwest of Bahraich, covering a distance of approximately 300 miles (480 km).

Rengali dam is a dam located in Odisha, India. It is constructed across the Brahmani River in Rengali village, located 70 km from Angul in Angul district.

<span class="mw-page-title-main">G. D. Agrawal</span> Indian environmentalist (1932–2018)

Guru das Agrawal, also known as Sant Swami Sanand and Sant Swami Gyan Swaroop Sanand, was an Indian environmentalist, engineer, religious leader, monk, and professor. He was the Patron of Ganga Mahasabha, founded by Madan Mohan Malviya in 1905.

<span class="mw-page-title-main">Chutak Hydroelectric Plant</span> Dam in Ladakh India

The Chutak Hydroelectric Plant is a run-of-the-river power project on the Suru River in Kargil district in the Indian union territory of Ladakh. The barrage of the project is at Sarze village and the powerhouse is located on the right bank of the Suru near Chutak village. The project construction began on 23 September 2006, and the first three generators were commissioned in November 2012. The fourth was commissioned in January 2013.

<span class="mw-page-title-main">NTPC Limited</span> This page is about Maharatna PSU in India

NTPC Limited, formerly known as National Thermal Power Corporation, is an Indian central Public Sector Undertaking (PSU) under the ownership of the Ministry of Power and the Government of India, who is engaged in the generation of electricity and other activities. The headquarters of the PSU are situated at New Delhi. NTPC's core function is the generation and distribution of electricity to State Electricity Boards in India. The body also undertakes consultancy and turnkey project contracts that involve engineering, project management, construction management, and operation and management of power plants.

Sagardighi is a town situated in the Sagardighi CD block in the Jangipur subdivision of Murshidabad district in the state of West Bengal, India.

The Dharasu Power Station is a run-of-the-river hydroelectric power station on the Bhagirathi River located at Dharasu in Uttarkashi district, Uttarakhand, India. The power station was commissioned in 2008 and has a 304 MW capacity.

The Maneri Dam is a concrete gravity dam on the Bhagirathi River located at Maneri, 8.5 kilometres (5.3 mi) east of Uttarkashi in Uttarkashi district, Uttarakhand, India. The primary purpose of the dam is to divert water into a tunnel which feeds the 90 megawatts (120,000 hp) run-of-the-river Tiloth Power Plant.

<span class="mw-page-title-main">Koldam Dam</span> Dam in Bilaspur district

The Koldam Hydropower Station, commonly known as Koldam, is an embankment dam on the Sutlej River upstream of the Dehar Power House. It is 18 km from Bilaspur off the Chandigarh-Manali Highway (NH-21) near Barmana, Himachal Pradesh, India. The main purpose of the dam is hydroelectric power generation and it will support an 800 MW power station. The dam was constructed by NTPC Limited.

<span class="mw-page-title-main">Renewable energy in Nepal</span>

Renewable energy in Nepal is a sector that is rapidly developing in Nepal. While Nepal mainly relies on burning biomass for its energy needs, solar and wind power is being seen as an important supplement to solve its energy crisis. The most common form of renewable energy in Nepal is hydroelectricity.

Solapur Super Thermal Power Station is under construction located at Fatatewadi and Aherwadi village in Solapur district in Indian state of Maharashtra. The power plant is one of the coal based power plants of National Thermal Power Corporation Limited (NTPCL).

Lakhwar-Vyasi Dam project on Yamuna River, includes under-construction Lakhwar Dam and Power Station, Vyasi Dam, Hathiari Power Station and Katapathar Barrage, near the Lakhwar town in Kalsi block of Dehradun district of Uttarakhand in India, for the purpose of irrigation of 40,000 hectare land and total 927 MW hydroelectric power generation. "Lakhwar Dam" is a gravity dam near the Lohari village with 300MW power generation capacity. "Vyasi Dam" will be built 5 km downstream along with 120 MW "Hathiari Power Station" further 0.5 km downstream. "Katapathar Barrage", with the maximum ponding water level at 514.5m elevation, will be built further 2.75 km downstream of the Hathiari Power Station to supply the water to stakeholder states. Project will hold 580 million cubic metres water during monsoon and release into Yamuna during dry months.

The Tapovan Vishnugad Hydropower Plant is a 520 MW run-of-river hydroelectric project being constructed on Dhauliganga River in Chamoli District of Uttarakhand, India. The plant is expected to generate over 2.5 TWh of electricity annually.

References

  1. Staff Correspondent (20 February 2004). "Work at Loharinag power project begins". The Hindu . Archived from the original on 4 November 2004. Retrieved 6 March 2010.{{cite news}}: |last= has generic name (help)
  2. (ADB) p. 16
  3. Construction of the 600 MW Loharinag-Pala Hydropower Project on thel Bhagirathi River in Uttarakhand, India, 2008. Photo [ permanent dead link ]: Matu People's Organization
  4. Professor GD Agrawal's Fast unto death over Dam on Bhagirathi
  5. 1 2 3 John Vidal (13 March 2009). "Himalayas hydroelectric dam project stopped after scientist on hunger strike against the project almost dies". reprint by International Rivers. Guardian News and Media Limited. Archived from the original on 2 October 2011. Retrieved 1 March 2010.
  6. "NTPC suspends work at Loharinag-Pala project". Business Line. 21 February 2009.
  7. "'Waterman' becomes Ganga's saviour". The Times of India . 5 September 2010. Archived from the original on 1 July 2012.
  8. 1 2 "Loharinag Pala Hydroelectric Project (4 x 150 MW)". CDM Projects India. Clean Development Mechanism Projects. Archived from the original on 13 July 2011. Retrieved 1 March 2010.
  9. (ADB) p. 17
  10. Infrastructure and Project Monitoring Division (January–March 2008). PROJECT IMPLEMENTATION STATUS REPORT OF CENTRAL SECTOR PROJECTS Costing Rs.20 crore & above (PDF). Government of India, Ministry of Statistics and Programme Implementation. p. 134. Archived from the original (PDF) on 14 November 2009. Retrieved 5 March 2010.
  11. "GoM decides to scrap NTPC hydel project on Bhagirathi river". The Economic Times. 20 August 2010. Archived from the original on 5 May 2013. Retrieved 23 November 2011.
  12. (ADB) p. 24
  13. (ADB) p. 28
  14. (ADB) by NTPC Limited for the Asian Development Bank (August 2007). "III. LOHARINAG–PALA HYDROELECTRIC PROJECT". Summary Environmental Impact Assessment - Project Number: 41904 (PDF). India: NTPC Capacity Expansion Financing II (Tapovan–Vishnugad Hydroelectric Project and Loharinag–Pala Hydroelectric Project). Asian Development Bank. pp. 16–27. Archived from the original (PDF) on 7 June 2011.