Martin Next Generation Solar Energy Center | |
---|---|
Country | United States |
Location | Martin County, Florida |
Coordinates | 27°03′11″N80°33′00″W / 27.053°N 80.550°W Coordinates: 27°03′11″N80°33′00″W / 27.053°N 80.550°W |
Status | Operational |
Construction began | December 2008 |
Commission date | December 2010 |
Construction cost | $141 million |
Owner(s) | FPL |
Solar farm | |
Type | CSP |
CSP technology | Parabolic trough |
Collectors | 6,864 (192,192 mirrors) |
Total collector area | 464,908 square metres (5,004,230 sq ft) |
Site area | 500 acres (202 ha) |
Power generation | |
Nameplate capacity | 75 MW |
Capacity factor | 24% |
Annual net output | 124 GW·h (planned) |
External links | |
Website | www |
Martin Next Generation Solar Energy Center is the solar parabolic-trough component of an integrated solar combined cycle (ISCC) 1150 MW plant, in western Martin County, Florida, United States, just north of Indiantown. The project was built by Florida Power & Light Company (FPL). Lauren Engineers & Constructors (Abilene, TX) was the EPC contractor for the project. [1] Its construction began in 2008 [2] and was completed by the end of 2010. [3]
The ISCC plant is part of the Martin Plant site which consists of 5 units. Unit 1 & Unit 2 are 800 MW steam electric generating units that use natural gas and low-sulfur residual oil. Unit 3 & Unit 4 are 500 MW natural gas-fired combined cycle units.
Unit 8 is a natural gas fired 4-on-1 combined cycle unit with a nominal capacity of 1150 MW. Light oil is used as backup. Unit 8, placed into commercial operation in 2005, is integrated with the solar plant. Unit 8 features four 170 MW gas turbines, one 470 MW steam turbine, and a single condenser and cooling tower [4] [5] The single solar field circuit heats 4 steam generators, after each gas turbine. The Martin solar thermal facility is designed to provide steam for FPL's existing Martin Unit 8 combined cycle unit, thus reducing FPL's use of natural gas. No additional capacity (MW) will result from the operation of the solar thermal facility.
The Solar Energy Center has an array of approximately 190,000-mirror parabolic troughs on about 500 acres (202 ha) of the Martin County plant. [6] The solar collectors feed heat to the existing steam plant, displacing gas generated electricity at an estimated rate of 155,000 MWh per year. [7] The 2012 solar-derived production was about 89,000 MWh of power, according to records filed with the state’s Public Service Commission, which was 42% less than projected when the plant got approval. [8]
The solar component can generate electrical energy only if the four gas turbines are in operation, otherwise the 470 MW steam turbine will not move. When gas turbines are stopped, the solar heat is used to keep the steam turbine in temperature, in order to facilitate a more rapid start-up.
FPL expects the $476 million [9] solar plant to reduce the combined-cycle power plant's natural gas consumption by 1.3 billion cubic feet (37 million m³) per year. [9] Over the 30-year life of the project, this is expected to save $178 million in fuel cost [10] and reduce carbon emissions by 2.75 million tons. [9]
Excess pressure and a release of operating fluid led to the plant being shut down for four months in 2011 for cleanup and testing. [11]
As of 2022, no additional concentrated solar plants are planned for Florida, although in 2007 FPL had planned on building a 300 MW Fresnel solar thermal plant. [12]
Year | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec | Total |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2011 | 2,868 | 4,641 | 9,249 | 2,891 | 3,357 | 114 | -120 | -120 | 3,640 | -118 | 2,668 | 0 | 29,067 |
2012 | 5,017 | 2,921 | 9,915 | 12,018 | 9,555 | 9,100 | 11,001 | 7,541 | 6,169 | 7,146 | 3,956 | 3,999 | 88,338 |
2013 | 4,388 | 7,288 | 8,883 | 7,254 | 12,784 | 14,352 | 12,872 | 10,675 | 8,227 | 9,372 | 2,522 | 3,264 | 101,881 |
2014 | 4,632 | 8,055 | 10,500 | 11,950 | 13,344 | 9,944 | 11,009 | 12,322 | 11,236 | 16,884 | 5,971 | 8,629 | 124,476 |
2015 | 4,730 | 437 | 8,791 | 9,877 | 15,155 | 15,571 | 17,349 | 14,827 | 7,468 | 6,139 | 3,809 | 1,950 | 106,103 |
2016 | 2,222 | 5,510 | 5,728 | 11,479 | 13,962 | 9,534 | 5,404 | 6,522 | 5,344 | 2,638 | 4,344 | 6,635 | 79,322 |
Total | 529,187 |
Electricity generation is the process of generating electric power from sources of primary energy. For utilities in the electric power industry, it is the stage prior to its delivery to end users or its storage.
A power station, also referred to as a power plant and sometimes generating station or generating plant, is an industrial facility for the generation of electric power. Power stations are generally connected to an electrical grid.
A combined cycle power plant is an assembly of heat engines that work in tandem from the same source of heat, converting it into mechanical energy. On land, when used to make electricity the most common type is called a combined cycle gas turbine (CCGT) plant. The same principle is also used for marine propulsion, where it is called a combined gas and steam (COGAS) plant. Combining two or more thermodynamic cycles improves overall efficiency, which reduces fuel costs.
Cogeneration or combined heat and power (CHP) is the use of a heat engine or power station to generate electricity and useful heat at the same time.
Florida Power & Light Company (FPL), the principal subsidiary of NextEra Energy Inc., is the largest power utility in Florida. It is a Juno Beach, Florida-based power utility company serving roughly 5,145,225 customers and 11 million people in Florida. It is a rate-regulated electric utility that generates, transmits, distributes and sells electric energy.
Peaking power plants, also known as peaker plants, and occasionally just "peakers", are power plants that generally run only when there is a high demand, known as peak demand, for electricity. Because they supply power only occasionally, the power supplied commands a much higher price per kilowatt hour than base load power. Peak load power plants are dispatched in combination with base load power plants, which supply a dependable and consistent amount of electricity, to meet the minimum demand.
The Moss Landing Power Plant is a natural gas powered electricity generation plant located in Moss Landing, California, United States, at the midpoint of Monterey Bay. Its large stacks are landmarks, visible throughout the Monterey Bay Area. The plant is owned and operated by Houston-based Dynegy and currently has a generation capacity of 1020 MW (net) from its two combined cycle generation units. It was once the largest power plant in the state of California, with a generation capacity of 2560 MW, before its two large supercritical steam units were retired in 2016.
An integrated gasification combined cycle (IGCC) is a technology using a high pressure gasifier to turn coal and other carbon based fuels into pressurized gas—synthesis gas (syngas). It can then remove impurities from the syngas prior to the electricity generation cycle. Some of these pollutants, such as sulfur, can be turned into re-usable byproducts through the Claus process. This results in lower emissions of sulfur dioxide, particulates, mercury, and in some cases carbon dioxide. With additional process equipment, a water-gas shift reaction can increase gasification efficiency and reduce carbon monoxide emissions by converting it to carbon dioxide. The resulting carbon dioxide from the shift reaction can be separated, compressed, and stored through sequestration. Excess heat from the primary combustion and syngas fired generation is then passed to a steam cycle, similar to a combined cycle gas turbine. This process results in improved thermodynamic efficiency compared to conventional pulverized coal combustion.
There are several solar power plants in the Mojave Desert which supply power to the electricity grid. Insolation in the Mojave Desert is among the best available in the United States, and some significant population centers are located in the area. These plants can generally be built in a few years because solar plants are built almost entirely with modular, readily available materials. Solar Energy Generating Systems (SEGS) is the name given to nine solar power plants in the Mojave Desert which were built in the 1980s, the first commercial solar plant. These plants have a combined capacity of 354 megawatts (MW) which made them the largest solar power installation in the world, until Ivanpah Solar Power Facility was finished in 2014.
The Hassi R'Mel integrated solar combined cycle power station is an integrated solar combined cycle (ISCC) power station near Hassi R'Mel in Algeria. The plant combines a 25 MW parabolic trough concentrating solar power array, covering an area of over 180,000 m2, in conjunction with a 130 MW combined cycle gas turbine plant, so cutting carbon emissions compared to a traditional power station. The output from the solar array is used in the steam turbine.
Concentrated solar power systems generate solar power by using mirrors or lenses to concentrate a large area of sunlight onto a receiver. Electricity is generated when the concentrated light is converted to heat, which drives a heat engine connected to an electrical power generator or powers a thermochemical reaction.
Archimede combined cycle power plant is an integrated solar combined cycle (ISCC) power generation plant at Priolo Gargallo near Syracuse in Sicily, Italy. The combine cycle section was inaugurated in 2003, and the solar field on 14 July 2010. The solar field is the first to use molten salt for heat transfer and storage which is integrated with the combined-cycle gas facility. It uses technology developed by ENEA and Archimede Solar Energy, a joint venture between Angelantoni Industrie and Siemens Energy. Archimede is owned and operated by Enel.
SolarReserve was a developer of utility-scale solar power projects which include Concentrated Solar Power (CSP) and Photovoltaic (PV) technology. The company has commercialized solar thermal energy storage technology that enables solar power tower CSP plants to deliver electricity day and night. In this technology, a molten salt is used to capture the energy from the sun and store it. When electricity is needed, the stored liquid salt is used to turn water into steam to turn a turbine and generate electricity.
The Ivanpah Solar Electric Generating System is a concentrated solar thermal plant in the Mojave Desert. It is located at the base of Clark Mountain in California, across the state line from Primm, Nevada. The plant has a gross capacity of 392 megawatts (MW). It deploys 173,500 heliostats, each with two mirrors focusing solar energy on boilers located on three 459 ft tall solar power towers. The first unit of the system was connected to the electrical grid in September 2013 for an initial synchronisation test. The facility formally opened on February 13, 2014. In 2014, it was the world's largest solar thermal power station.
The Yazd Solar Power Station is an integrated solar combined cycle (ISCC) power station situated near Yazd, Iran which became operational in 2009, and in 2011 as a solar integrated plant. The plant has a capacity of 467 MW and uses solar energy to augment its steam generation by concentrating solar power technology.
Solar power in Florida has been increasing, as the cost of solar power systems using photovoltaics (PV) has decreased in recent years. Florida has low electricity costs compared with other states, which makes individual solar investment less attractive. Florida ranks ninth nationally in solar resource strength according to the National Renewable Energy Laboratory and tenth in solar generation by the Solar Energy Industries Association.
The Dorad power station is a power station in Ashkelon, Israel. It is a combined cycle power station powered by natural gas.
The Ain Beni Mathar Integrated Thermo Solar Combined Cycle Power Plant is an integrated solar combined cycle power generation plant in northeastern Morocco. It is located in the commune of Ain Bni Mathar within Jerada Province, in the Oriental Region.
Termosolar Borges is a hybrid biomass-parabolic trough solar thermal power plant which provides electricity to Spain's transmission system. It is located about 100 kilometres (62 mi) west of Barcelona, about 10 kilometres (6.2 mi) south-east of Lleida, near Les Borges Blanques, Catalonia, Spain.