Avenal Solar Facility

Last updated • a couple of secsFrom Wikipedia, The Free Encyclopedia
Avenal Solar Facility
Avenal Solar Facility
CountryUnited States
Location Kings County
Coordinates 35°59′N120°06′W / 35.983°N 120.100°W / 35.983; -120.100 Coordinates: 35°59′N120°06′W / 35.983°N 120.100°W / 35.983; -120.100
StatusOperational
Construction beganSeptember 2010 [1]
Commission date August 5, 2011
Owner(s) NRG Solar and Eurus Energy America
Solar farm
Type Flat-panel PV
Site area500 acres (200 ha)
Power generation
Units operational450,900
Sharp Electronics (128W thin film) [2]
Nameplate capacity 57.7 MW or 45 MWAC
Annual net output 58 GWh [3]

The Avenal Solar Facility is a 57.7  megawatt (MW) photovoltaic power station in Kings County, California, constructed using 450,900 SHARP-128W thin-film modules. At its completion, it was California's largest photovoltaic facility. [4]

Contents

The power generated is sold to Pacific Gas & Electric, using three separate 20-year power purchase agreements (PPA).

Units

Production

Generation (MW·h) of Avenal Park [6]
YearJanFebMarAprMayJunJulAugSepOctNovDecTotal
20112,1441,4801,1834203985,625
2012383779251,3381,8391,9881,7191,3551,26899751037212,726
20132414958428889991,2741,2021,6171,5721,3921,3851,44613,353
20144655319351,1061,2711,4091,3041,4111,3771,2431,03370512,789
20156097681,1251,2621,2691,3071,3531,3701,13095288272612,753
Total57,246
Generation (MW·h) of Sun City Project LLC [7]
YearJanFebMarAprMayJunJulAugSepOctNovDecTotal
20117,4975,1744,1361,4691,39319,668
20121281,2753,1254,5216,2156,7175,8094,5774,2863,3681,7231,25943,003
20138011,6412,7942,9463,3164,2253,9865,3655,2154,6174,5964,79644,298
20141,5611,7813,1353,7104,2624,7274,3744,7334,6184,1703,4652,36342,897
20152,0392,5703,7664,2264,2484,3774,5304,5853,7843,1882,9532,43142,695
Total192,561
Generation (MW·h) of Sand Drag LLC [8]
YearJanFebMarAprMayJunJulAugSepOctNovDecTotal
20116,8294,7133,7681,3381,26917,917
20121201,1962,9334,2435,8326,3045,4514,2964,0223,1611,6171,18140,357
20137651,5672,6692,8143,1674,0373,8085,1254,9824,4114,3914,58242,320
20141,4821,6912,9763,5224,0464,4884,1534,4944,3843,9593,2902,24440,729
20151,9392,4433,5814,0194,0394,1624,3074,3603,5983,0312,8082,31140,597
Total181,920

See also

Related Research Articles

<span class="mw-page-title-main">Solar Energy Generating Systems</span> Concentrated solar thermal power station in the Mojave Desert of California

Solar Energy Generating Systems (SEGS) is a concentrated solar power plant in California, United States. With the combined capacity from three separate locations at 354 megawatt (MW), it was once the world's second largest solar thermal energy generating facility, until the commissioning of the even larger Ivanpah facility in 2014. It consisted of nine solar power plants in California's Mojave Desert, where insolation is among the best available in the United States.

<span class="mw-page-title-main">Solar power in California</span> Overview of solar power in the U.S. state of California

Solar power in California includes utility-scale solar power plants as well as local distributed generation, mostly from rooftop photovoltaics. It has been growing rapidly because of high insolation, community support, declining solar costs, and a Renewable Portfolio Standard which requires that 33% of California's electricity come from renewable resources by 2020, and 60% by 2030. Much of this is expected to come from solar power via photovoltaic facilities or concentrated solar power facilities.

<span class="mw-page-title-main">Sierra SunTower</span>

Sierra SunTower was a 5 MW commercial concentrating solar power (CSP) plant built and operated by eSolar. The plant is located in Lancaster, California. As of mid-September, 2022, the two towers that were the center of the facility are no longer standing. The rest of the plant, however, is still present.

<span class="mw-page-title-main">Blythe Mesa Solar Power Project</span> Linux solar power

The Blythe Mesa Solar Power Project, also known as the Blythe Solar Energy Center, is a 485 megawatt (MWAC) photovoltaic power plant near the city of Blythe in Riverside County, California. It occupies about 2,000 acres of public land managed by the Bureau of Land Management in the Mojave Desert. The construction uses CdTe thin film panels from the U.S. firm First Solar, and the majority of the output is being sold to Kaiser Permanente and Southern California Edison under 20-year power purchase agreements.

The 21 megawatt Blythe Photovoltaic Power Plant is a photovoltaic (PV) solar project in California. It is located in Blythe, California, in Riverside County about 200 miles (320 km) east of Los Angeles. Commercial operation began in December 2009. Electricity generated by the power plant is being sold to Southern California Edison under a 20-year power purchase agreement. Another 20 MW plant called NRG Solar Blythe II came online in April 2017.

<span class="mw-page-title-main">Copper Mountain Solar Facility</span> Solar power plant in Nevada, United States

The Copper Mountain Solar Facility is a 802 megawatt (MWAC) solar photovoltaic power plant in Boulder City, Nevada, United States. The plant was developed by Sempra Generation. When the first unit of the facility entered service on December 1, 2010, it was the largest photovoltaic plant in the U.S. at 58 MW. With the opening of Copper Mountain V in March 2021, it again became the largest in the United States. It is co-located with the 64 MW Nevada Solar One, 150 MW Boulder Solar, and 300 MW Techren Solar projects in the Eldorado Valley, thus forming a more than 1 gigawatt (GW) solar generating complex. By comparison, generating capacity at the nearby Hoover Dam is about 2 GW.

<span class="mw-page-title-main">Space Coast Next Generation Solar Energy Center</span> Photovoltaic power plant located in Clark County, Nevada,

The Space Coast Next Generation Solar Energy Center is a 10 megawatt (MW) solar photovoltaic (PV) facility at the Kennedy Space Center, Florida. Commissioned in April 2010, the center is the result of a partnership between NASA and Florida Power & Light. The facility has approximately 35,000 solar photovoltaic panels from SunPower covering an area of 60 acres. The facility provides slightly less than one percent of the power needed to keep Kennedy Space Center up and running.

<span class="mw-page-title-main">Desert Sunlight Solar Farm</span> Photovoltaic power station in California

The Desert Sunlight Solar Farm is a 550 megawatt (MWAC) photovoltaic power station approximately six miles north of Desert Center, California, United States, in the Mojave Desert. It uses approximately 8.8 million cadmium telluride modules made by the US thin-film manufacturer First Solar. As of Fall 2015, the Solar Farm has the same 550 MW installed capacity as the Topaz Solar Farm in the Carrizo Plain region of Central California, making both of them tied for the second largest completed solar plants by installed capacity.

The Antelope Valley Solar Ranch 1 (AVSR1) is a 230 megawatt (MWAC) photovoltaic power plant near Lancaster within Antelope Valley, in the western Mojave Desert, Southern California. It uses cadmium telluride modules made by the US thin-film manufacturer First Solar. The project was developed by First Solar and later bought by Exelon Corporation in 2011. The solar facility was fully commissioned in April 2014.

The Hatch Solar Energy Center is a 5.88 MWp (5.0 MWAC) photovoltaic power station. It was built by Blattner Energy using 84 dual-axis trackers and Amonix 7700 concentrator photovoltaics (CPV) panels, each of which contains 7,560 fresnel lens to concentrate sunlight 500 times onto multijunction photovoltaic cells. It was the largest CPV facility in North America when it was completed in 2011. The facility was subsequently repowered with SunPower panels that use high-efficiency monocrystalline silicon cells without concentration. The output is being sold to El Paso Electric, under a 25 year power purchase agreement (PPA). Annual electricity production is expected to be about 11,000 MW·h/year.

The Tenaska Imperial Solar Energy Center South is a 130 megawatt (MW) photovoltaic power plant built in Imperial County, California. Construction began in December 2011 and full commercial operation was achieved in November 2013. Power is sold to San Diego Gas & Electric on a 25-year agreement.

Campo Verde Solar Project is a 139-megawatt (MWAC) solar photovoltaic power station in Imperial County, California. The project was approved in December 2012. Construction began in early 2013 and was completed the same year. Designed and constructed by U.S. thin-film manufacturer First Solar, the plant uses nearly 2.3 million CdTe-PV modules. Campo Verde Solar was acquired in April 2013 by Southern Power and Turner Renewable Energy. First Solar acquired the project in 2012 from US Solar Holdings LLC, which had developed the project and negotiated the 139 MW PPA with SDG&E.

Mount Signal Solar, also known as Imperial Valley Solar Project, is a 794 MWp (614 MWAC) photovoltaic power station west of Calexico, California, United States, in the southern Imperial Valley, near the Mexican border. The facility is being developed and constructed by 8minutenergy Renewables in three phases, with two completed as of 2018. At full build-out, it will be one of the world's largest PV solar farms with a capacity of about 800 MWp (600 MWAC). The project has been supported by several environmental groups, as the power station was built on low productivity farmland.

Solar Star is a 579-megawatt (MWAC) photovoltaic power station near Rosamond, California, United States, that is operated and maintained by SunPower Services. When completed in June 2015, it was the world's largest solar farm in terms of installed capacity, using 1.7 million solar panels, made by SunPower and spread over 13 square kilometers.

The Springbok Solar Farm is a 443 MWp (350 MWAC) photovoltaic power station in the northwestern Mojave Desert, near California City in eastern Kern County, California. The facility was developed and constructed by 8minutenergy Renewables in three phases. It is among the country's largest PV solar farms with a capacity of about 440 MWp (350 MWAC).

The Tenaska Imperial Solar Energy Center West is a 150 megawatt (MW) photovoltaic power plant built in Imperial County, California. Construction began in 2014 and full commercial operation was achieved in September 2016. Power is sold to San Diego Gas & Electric on a 25-year agreement.

The Beacon Solar Project is a photovoltaic power station in the northwestern Mojave Desert, near California City in eastern Kern County, California. Split into five phases, the combined Beacon solar facilities generate 250 MW of renewable energy for the Los Angeles Department of Water and Power (LADWP). The five phases of the project, fully completed in December 2017, include a total of 903,434 individual solar photovoltaic modules, mounted onto Nextracker single-axis tracking systems.

The Victor Valley College Solar Farm is a 1.26 MWp (1.02 MWAC) concentrator photovoltaics (CPV) power station in Victorville, California. Upon completion in May 2010 it was the largest CPV project installed in North America. It was built by Sachs Electric using 122 dual-axis SF-1100S systems, each of which contains 28 SF-1100 modules. Each module contains reflective optics to concentrate sunlight 650 times onto multi-junction solar cells, allowing a greater efficiency than other photovoltaic power plants. The farm was constructed under California Solar Initiative (CSI) incentives and the projected annual output of 2.3 GW·h partially satisfies electricity consumption at the college.

The Escalante Solar Project is a 240 MWAC (315 MWp) photovoltaic power station located about 5 miles north of the town of Milford in Beaver County, Utah. The project was developed by SunEdison, built by Mortenson Construction, and commissioned in September 2016. The power is being sold under three separate 20-year power purchase agreements to Rocky Mountain Power which serves customers in Utah, Idaho, and Wyoming. At 1900 acres (3.0 sq miles), it is the largest grouping of photovoltaic generators in the state of Utah.

<span class="mw-page-title-main">Bison Solar Plant</span> Power plant in Colorado, USA

The Bison Solar Plant, also known as the Rawhide Flats Solar Plant, is a 30 megawatt (MWAC) photovoltaic power station in Larimer County, Colorado located about 10 miles (16 km) north of the town of Wellington. The plant is notable for being one of the first in the U.S. built to a 1500 Volt system specification. The electricity is being sold to the Platte River Power Authority (PRPA) under a 25-year power purchase agreement.

References

  1. Sharp Signs Contract for 58 MW (DC) Photovoltaic Solar Power Project
  2. "Avenal Park". Archived from the original on 2012-04-09. Retrieved 2012-04-06.
  3. Sharp Electronics provides PV modules for Avenal Solar Generating Facility Archived April 8, 2012, at the Wayback Machine
  4. Avenal Solar Facility Starts Generating Power
  5. Solar projects
  6. "Avenal Park, Monthly". Electricity Data Browser. Energy Information Administration . Retrieved March 8, 2017.
  7. "Sun City Project LLC, Monthly". Electricity Data Browser. Energy Information Administration . Retrieved March 8, 2017.
  8. "Sand Drag LLC, Monthly". Electricity Data Browser. Energy Information Administration . Retrieved March 8, 2017.