Rice Solar Energy Project

Last updated
Rice Solar Energy Project
Rice Solar Energy Project
CountryUnited States
Location Riverside County, California
Coordinates 34°4′0″N114°48′30″W / 34.06667°N 114.80833°W / 34.06667; -114.80833 Coordinates: 34°4′0″N114°48′30″W / 34.06667°N 114.80833°W / 34.06667; -114.80833
StatusProposed
Construction cost$750 million
Solar farm
Type CSP
CSP technology Solar power tower
Site resource2,598 kWh/m2/yr
Power generation
Nameplate capacity 150 MW
Capacity factor 34%
Annual net output 450 GW·h [1]
External links
Website www.ricesolarenergy.com

The Rice Solar Energy Project was a 150 MW concentrating solar power facility project proposed for Rice Valley in the southern Mojave Desert, within Riverside County in southern California. [2] It was put on indefinite hold in 2014. [3]

Contents

Description

Proposed by Rice Solar, a subsidiary of SolarReserve, the thermal power tower facility would have been located on 1,410 acres (570 ha) of private land on the site of the former Rice Army Airfield, near the former settlement of Rice. [2]

The project's innovative molten salt storage system was to capture solar energy and deliver power to the grid even after the sun goes down. The facility was "expected to power 68,000 homes, create up to 450 construction jobs, and generate more than $48 million in state and local tax revenue over the first 10 years of operation." [4]

Details

The project was developed by Rice Solar Energy, LLC, a subsidiary of SolarReserve, LLC. The facility would have consisted of about 17,000 heliostats [5] focused onto a central receiver tower with an overall height of 653 feet (199 m), [6] and an integrated thermal storage system, which uses molten salt, a mixture of sodium nitrate and potassium nitrate, as heat carrier. [1] [7] The power plant would have been located on 1,410 acres (570 ha) of private land, with previously disturbed and natural habitat sections. [4]

The project had undergone extensive environmental review and had proposed mitigations for environmental impacts from its construction and operation. SolarReserve was to fund the acquisition and enhancement of 1,522 acres (616 ha) to compensate for impacts to desert tortoise habitat on private and public land. [4]

In December 2011, Secretary of the Interior Ken Salazar approved a transmission line, access road and substation on public lands that will connect the Rice project to the power grid in California. [4]

In January 2013, the California Public Utilities Commission (CPUC) approved SolarReserve's amended 25-year power purchase agreement (PPA) with Pacific Gas and Electric (PG&E). [8]

Indefinite hold

As of October 2014, SolarReserve put the Rice Solar Project on "indefinite hold". The reason was the investment tax credit for renewable energy slated to drop from 30 percent to 10 percent at the end of 2016, and only available for projects that are fully online by then." [9]

See also

Related Research Articles

Solar thermal energy Technology using sunlight for heat

Solar thermal energy (STE) is a form of energy and a technology for harnessing solar energy to generate thermal energy for use in industry, and in the residential and commercial sectors.

The Solar Project

The SOLAR Project consists of the Solar One, Solar Two and Solar Tres solar thermal power plants based in the Mojave Desert, United States and Andalucía, Spain. The US Department of Energy (DOE) and a consortium of US utilities built the country's first two large-scale, demonstration solar power towers in the desert near Barstow, California.

Nevada Solar One

Nevada Solar One is a concentrated solar power plant, with a nominal capacity of 64 MW and maximum steam turbine power output up to 72 MW net (75 MW gross), spread over an area of 400 acres (160 ha). The projected CO2 emissions avoided is equivalent to taking approximately 20,000 cars off the road. The project required an investment of $266 million USD, and the project officially went into operation in June 2007. Electricity production is estimated to be 134 GWh (gigawatt hours) per year.

Gemasolar Thermosolar Plant

Gemasolar is a concentrated solar power plant with a molten salt heat storage system. It is located within the city limits of Fuentes de Andalucía in the province of Seville, Spain.

Solar power plants in the Mojave Desert Supplies power to the electricity grid using excellent solar radiation

There are several solar power plants in the Mojave Desert which supply power to the electricity grid. Insolation in the Mojave Desert is among the best available in the United States, and some significant population centers are located in the area. These plants can generally be built in a few years because solar plants are built almost entirely with modular, readily available materials. Solar Energy Generating Systems (SEGS) is the name given to nine solar power plants in the Mojave Desert which were built in the 1980s, the first commercial solar plant. These plants have a combined capacity of 354 megawatts (MW) which made them the largest solar power installation in the world, until Ivanpah Solar Power Facility was finished in 2014.

Concentrated solar power Use of mirror or lens assemblies to heat a working fluid for electricity generation

Concentrated solar power systems generate solar power by using mirrors or lenses to concentrate a large area of sunlight onto a receiver. Electricity is generated when the concentrated light is converted to heat, which drives a heat engine connected to an electrical power generator or powers a thermochemical reaction.

BrightSource Energy

BrightSource Energy, Inc. is an Oakland, California based, corporation that designs, builds, finances, and operates utility-scale solar power plants.

Solar power tower Structure containing the furnace, the focal point for concentrated sunlight, and plumbing

A solar power tower, also known as 'central tower' power plant or 'heliostat' power plant, is a type of solar furnace using a tower to receive focused sunlight. It uses an array of flat, movable mirrors to focus the sun's rays upon a collector tower. Concentrating Solar Power (CSP) systems are seen as one viable solution for renewable, pollution-free energy.

SolarReserve was a developer of utility-scale solar power projects which include Concentrated Solar Power (CSP) and Photovoltaic (PV) technology. The company has commercialized solar thermal energy storage technology that enables solar power tower CSP plants to deliver electricity day and night. In this technology, a molten salt is used to capture the energy from the sun and store it. When electricity is needed, the stored liquid salt is used to turn water into steam to turn a turbine and generate electricity.

eSolar

eSolar is a privately held company that develops concentrating solar power (CSP) plant technology. The company was founded by the Pasadena-based business incubator Idealab in 2007 as a developer of CSP plant technology. The company aims to develop a low cost alternative to fossil fuels through a combination of small heliostats, modular architecture, and a high-precision sun-tracking system. In October 2017, an article in GreenTech Media suggested that eSolar ceased business in late 2016.

Solar power in California Overview of solar power in the U.S. state of California

Solar power in California includes utility-scale solar power plants as well as local distributed generation, mostly from rooftop photovoltaics. It has been growing rapidly because of high insolation, community support, declining solar costs, and a Renewable Portfolio Standard which requires that 33% of California's electricity come from renewable resources by 2020, and 60% by 2030. Much of this is expected to come from solar power via photovoltaic facilities or concentrated solar power facilities.

Ivanpah Solar Power Facility Concentrated solar thermal power station in the Mojave Desert of California

The Ivanpah Solar Electric Generating System is a concentrated solar thermal plant in the Mojave Desert. It is located at the base of Clark Mountain in California, across the state line from Primm, Nevada. The plant has a gross capacity of 392 megawatts (MW). It deploys 173,500 heliostats, each with two mirrors focusing solar energy on boilers located on three 459 ft tall solar power towers. The first unit of the system was connected to the electrical grid in September 2013 for an initial synchronisation test. The facility formally opened on February 13, 2014. In 2014, it was the world's largest solar thermal power station.

Sierra SunTower

Sierra SunTower was a 5 MW commercial concentrating solar power (CSP) plant built and operated by eSolar. The plant is located in Lancaster, California. As of mid-August, 2018, the two towers that were the center of the facility are no longer standing. The plant, however, is still present.

Crescent Dunes Solar Energy Project Solar power station in Nevada, United States

The Crescent Dunes Solar Energy Project is a solar thermal power project with an installed capacity of 110 megawatt (MW) and 1.1 gigawatt-hours of energy storage located near Tonopah, about 190 miles (310 km) northwest of Las Vegas. Crescent Dunes is the first commercial concentrated solar power (CSP) plant with a central receiver tower and advanced molten salt energy storage technology, following the experimental Solar Two.

Mojave Solar Project

The Mojave Solar Project (MSP) is a concentrated solar power (CSP) facility in the Mojave Desert in California, about 20 miles (32 km) northwest of Barstow. Surrounding the hamlet of Lockhart, Mojave Solar is adjacent to Harper Lake and the SEGS VIII–IX solar plant.

The McCoy Solar Energy Project is a 250 megawatt (MWAC) photovoltaic power plant near the city of Blythe in Riverside County, California. It occupies about 2,300 acres of mostly public land in the Mojave Desert. The construction uses CdTe thin film panels from First Solar, and the output is being sold to Southern California Edison under a power purchase agreement.

Genesis Solar Energy Project

The Genesis Solar Energy Project is a concentrated solar power station located in the Mojave Desert on 1,920 acres (780 ha) of Bureau of Land Management land, in eastern Riverside County, California. The plant is owned/managed by Genesis Solar, LLC, a subsidiary of NextEra Energy Resources, LLC. The Genesis Solar Energy Project is located about 25 miles (40 km) west of Blythe, in the Lower Colorado River Valley. The plant was built in the Colorado Desert along an ancient trade route that native people had traveled for thousands of years. The route traversed the Sonoran Desert and enabled trade between the Colorado River and the coast.

The Copiapó Solar Project is a 390 megawatt (MW) net solar thermal power project to be located near Copiapó, about 65 kilometers east of the coastal town of Caldera. The project is being developed by SolarReserve, and is scheduled to reach commercial operation in 2019.

The Sandstone Solar Energy Project was an up to 1,600 megawatt (MW) solar thermal power project with 16 gigawatt-hours of energy storage, planned just to the east of Tonopah, about 170 miles (270 km) northwest of Las Vegas. The project was about up to eight 200 MW solar towers with integrated molten salt energy storage technology. The project, developed by SolarReserve and owned by Sandstone Solar Energy, LLC. was anticipated to cost about $5 billion. Planned energy output is 5,600 GW·h per year.

References

  1. 1 2 "Rice Solar Energy Project - Power Plant Licensing Case". California Energy Commission . Retrieved 2011-12-12.
  2. 1 2 "Rice Solar Energy Project: Notice of Proposed Power Plant" (PDF). California Energy Commission. Archived from the original (PDF) on 2011-07-08. Retrieved 2010-12-26.
  3. The Desert Sun: "Developer puts Rice large-scale solar project on indefinite hold", by Sammy Roth, 3 October 2014 . (accessed 12 June 2016).
  4. 1 2 3 4 States News Service (12 September 2011). "Secretary Salazar approves transmission for solar thermal power tower project". Power Engineering.
  5. "Rice Solar Energy Project". Concentrating Solar Power Projects. National Renewable Energy Laboratory (NREL), U.S. Department of Energy (DOE). December 3, 2010. Retrieved 12 December 2011.
  6. "Frequently Asked Questions". Rice Solar. Retrieved 12 December 2011.
  7. Liggett, Brit (2010-12-16). "California's First Molten Salt Solar Energy Project Gets Green Light". Inhabitat.com. Retrieved 2010-12-26.
  8. "SolarReserve Project Receives Unanimous Approval From California Public Utilities" (Press release). SolarReserve. January 28, 2013. Retrieved 31 January 2013.
  9. Rice large-scale solar project near Blythe all but dead, The Desert Sun, October 3, 2014, retrieved 17 January 2016