Grand Street station (IND Sixth Avenue Line)

Last updated

 Grand Street
  NYCS-bull-trans-B-Std.svg NYCS-bull-trans-D-Std.svg
MTA NYC logo.svg New York City Subway station (rapid transit)
IND Sixth Grand Street Northbound Platform.jpg
Northbound platform
Station statistics
AddressGrand Street and Chrystie Street
New York, New York
Borough Manhattan
Locale Chinatown, Lower East Side
Coordinates 40°43′05″N73°59′38″W / 40.718119°N 73.993864°W / 40.718119; -73.993864
Division B (IND) [1]
Line     IND Sixth Avenue Line
Services    B   NYCS-SSI-weekdaysonly.svg (weekdays during the day)
   D   NYCS-SSI-alltimes.svg (all times)
TransitAiga bus trans.svg NYCT Bus: M15, M15 SBS (on Allen Street)
M103 (on Bowery)
StructureUnderground
Platforms2 side platforms
Tracks2
Other information
OpenedNovember 26, 1967;56 years ago (1967-11-26)
AccessibilitySame-platform wheelchair transfer available
Opposite-
direction
transfer
Yes
Traffic
20235,821,650 [2] Increase2.svg 18.3%
Rank37 out of 423 [2]
Services
Preceding station MTA NYC logo.svg New York City Subway Following station
Broadway–Lafayette Street
B   NYCS-SSI-weekdaysonly.svg D   NYCS-SSI-alltimes.svg
NYCS-bull-trans-D-Std.svg
Express
Atlantic Avenue–Barclays Center
D   NYCS-SSI-allexceptnights.svg
NYCS-bull-trans-B-Std.svg
Local
DeKalb Avenue
B   NYCS-SSI-weekdaysonly.svg D   NYCS-SSI-nightsonly.svg
Location
NYCS map blank.svg
Map pointer.svg
USA New York City location map.svg
Map pointer.svg
USA New York location map.svg
Map pointer.svg
Track layout

Contents

BSicon MFADEg.svg
BSicon uvSTR.svg
BSicon uvSTRfg.svg
BSicon numN345.svg
BSicon cPLT.svg
BSicon uvSTR.svg
BSicon cPLT.svg
BSicon cPLT.svg
BSicon uvSTR.svg
BSicon cPLT.svg
BSicon cPLT.svg
BSicon uvSTR.svg
BSicon cPLT.svg
BSicon cPLT.svg
BSicon uvSTR.svg
BSicon cPLT.svg
BSicon uvSTRfg.svg
BSicon MFADEf.svg
BSicon uvSTR.svg
Street map

Grand Street station (IND Sixth Avenue Line)

Station service legend
SymbolDescription
NYCS-SSI-allexceptnights.svg Stops all times except late nights
NYCS-SSI-alltimes.svg Stops all times
NYCS-SSI-nightsonly.svg Stops late nights only
NYCS-SSI-weekdaysonly.svg Stops weekdays during the day

The Grand Street station is an express station on the IND Sixth Avenue Line of the New York City Subway. Located at the intersection of Grand Street and Chrystie Street at the border of Chinatown and the Lower East Side, it is served by the D train at all times and the B train on weekdays.

Opened on November 26, 1967, this station was one of two added as part of the Chrystie Street Connection. The station has two tracks and two narrow side platforms, located approximately 30 feet (9.1 m) below ground. In the original plan for the station, this would have been a four-track, two-island platform station, with a transfer to the Second Avenue Subway. The fourth phase of the Second Avenue Subway, if built, would include new platform(s) with connections to the existing platforms.

History

Construction

The station was built as part of the Chrystie Street Connection between the Sixth Avenue Line and the Manhattan and Williamsburg Bridges. The Chrystie Street Connection was first proposed in 1947 as the southern end of the Second Avenue Subway (SAS), which would feed into the two bridges, allowing Sixth Avenue Line trains to access the Jamaica, Fourth Avenue, and Brighton lines in Brooklyn. [3] The New York City Board of Estimate voted in September 1951 to construct the Second Avenue Subway and several related lines for $500 million. [4] [5] The next year, the New York City Board of Transportation (BOT) indicated that it would award contracts for the construction of an 890-foot-long (270 m) section of tunnel between Hester and Delancey Streets, including a station at Grand Street, as part of the SAS project. [6] Work had been expected to begin in mid-1952 but was delayed because of engineering difficulties. [7] By 1954, the BOT's successor, the New York City Transit Authority, had asked the city for $37.3 million to begin constructing the Chrystie Street Connection. [8]

In mid-1957, the New York City government solicited bids from contractors to construct the various parts of the connection. [9] [10] One of the contracts was for the construction of a station at Grand and Chrystie Streets, serving trains to and from the Manhattan Bridge. [9] Because there was a large number of senior citizens living near that intersection, the station was originally planned to contain many ramps and "a minimum of steps". [11] That October, the Board of Estimate approved an initial $10.2 million for the connection. [12] [13] A groundbreaking ceremony for the connection took place on November 25, 1957. [14] [11] The connection was projected to cost $100 million and provide capacity for 52,000 more riders an hour between Brooklyn and Manhattan. [15] In 1960, New York City Transit allocated $23 million for the installation of new signals in the Chrystie Street tunnels and six other locations in the subway system. [16]

Construction of the station started in 1962, and the entire seven-block length of Chrystie Street was closed until 1964. [17] By March 1964, the new connection was expected to be completed within the next year. [18] Later that year, the tracks in the new connection were laid. [19] In contrast to subway tracks on existing lines, which contained wooden cross ties, the new tracks were installed on rubber pads attached to the concrete track bed, thereby dampening noise from trains. [18] Lighting, power and signal equipment for the Chrystie Street tunnel had been installed by January 1965. At that time, the project was projected to be completed in 1967, with the portion involving the opening of the Grand Street station to be finished in 1966. [15]

Opening and use

The first part of the connection, including the Grand Street station, opened on November 26, 1967, when the link between the Sixth Avenue Line and the Manhattan Bridge north tracks opened. [3] [20] The connection was fully opened on July 1, 1968, with the opening of the 57th Street station and the opening of the connection between the Sixth Avenue Line and the Williamsburg Bridge. [3]

With the connection completed, the most significant service changes ever carried out in the subway's history were introduced. [21] [22] Upon this station's opening the routes of the B and D were rerouted via the new connection. BB trains were relabeled the B, and began to run to Coney Island via the Chrystie Street Connection, the Manhattan Bridge north tracks, Fourth Avenue Line express tracks, and the West End Line. D trains were rerouted from the Culver Line to run to Coney Island via the new Sixth Avenue express tracks, the Chrystie Street Connection, the Manhattan Bridge north tracks, and the Brighton Line. [3] [20] [23] [22]

Manhattan Bridge closures

The north Manhattan Bridge tracks were closed for repairs from April 1986 [24] to December 1988. [25] During this time, this station was served by the Grand Street Shuttle to the Sixth Avenue Line, and there was no subway service from the station to Brooklyn. [26] The Grand Street Shuttle also operated when the north tracks were closed again from April to November 1995; [27] the closure caused nearby vendors' business to decline. [28] A third entrance was added in 1999 to accommodate the station's growing ridership, which in turn was spurred by the growth of the Chinese population in New York City. [29] At the time, the Grand Street station was one of two subway stations in Manhattan's Chinatown, with subway service running directly to the Chinatowns in Brooklyn. [30]

The MTA proposed closing the Manhattan Bridge's northern tracks again in 2000, running a shuttle between Broadway–Lafayette Street and Grand Street. [31] [32] Many Chinese New Yorkers expressed opposition to the plans, as there would no longer be direct subway service between Grand Street and Brooklyn. The New York Times wrote that many of the station's 27,000 daily riders were "Chinese- Americans who live in Brooklyn, come for fresh fish and produce, herbal medicines and household supplies", and that community members feared a decline in business when the Manhattan Bridge's north tracks closed. [30] The Grand Street Shuttle began operating again when the north tracks were closed in July 2001. [33] [34] The MTA also agreed to operate a shuttle bus to the Canal Street station when the bridge's northern tracks were closed in 2001. [35] Regular service was restored in February 2004. [36]

Station layout

GroundStreet levelExit/entrance
MezzanineFare control, station agent
Platform level Side platform
Northbound NYCS-bull-trans-B-Std.svg weekdays toward Bedford Park Boulevard or 145th Street (Broadway–Lafayette Street)
NYCS-bull-trans-D-Std.svg toward Norwood–205th Street (Broadway–Lafayette Street)
Southbound NYCS-bull-trans-B-Std.svg weekdays toward Brighton Beach (DeKalb Avenue)
NYCS-bull-trans-D-Std.svg toward Coney Island–Stillwell Avenue (DeKalb Avenue late nights, Atlantic Avenue–Barclays Center other times)
Side platform

The station has two tracks and two narrow side platforms, located approximately 30 feet (9.1 m) below ground. [37] They are column-less, except at staircases, and have a blue trim line with "GRAND ST" in white sans-serif font on it at regular intervals. [38] [39] In the original plan for the station, this would have been a four-track, two-island platform station; the Second Avenue Subway would have served the outer tracks while the Sixth Avenue Line served the inner tracks, providing a cross-platform interchange between these two lines. [38] [39] [40] [23] :216–217 [41] Although the connection only served Sixth Avenue Line trains, it was essentially the first part of the Second Avenue line that had been constructed. [40] [23] There is a sole mezzanine at the center of the station which has two staircases to each platform, a turnstile bank, token booth, and access to the street exits. [42]

Musicians playing huqin for passengers in the station; behind them is the Trains of Thought frieze Grand Street art vc.jpg
Musicians playing huqin for passengers in the station; behind them is the Trains of Thought frieze

On the Brooklyn-bound side, there is a small sign reading "Change Radio Channel to B1", indicating that train operators must change the channel on the route destination box from B2 (IND) to B1 (BMT) before crossing the Manhattan Bridge. Southbound trains leaving this station cross over the north side of the bridge and arrive at DeKalb Avenue or Atlantic Avenue–Barclays Center (via the DeKalb Avenue bypass tracks). [43] As the tracks curve onto the bridge, trackways from Canal Street on the Manhattan Bridge branch of the BMT Broadway Line are visible. [44] The north side of the bridge originally led to that station before the current alignment was completed in 1967. [38]

Artwork

A painted frieze called Trains of Thought by Andrea Gardner and Sally Heller was installed at the mezzanine and platforms in the late 1990s as the "Creative Stations" program sponsored by the Lower Manhattan Cultural Council. It features red clay models of R62s and R62As mounted on wood. [45]

Exits

1960s-era entrance at the northeast corner of Chrystie Street and Grand Street Grand Street Stair.JPG
1960s-era entrance at the northeast corner of Chrystie Street and Grand Street

There are three staircase exits: two going up to the northeastern corner of the intersection of Grand and Chrystie Streets, and one going up to the northwestern corner. [42] The station originally only had the two street stairs to the northeastern corner of the intersection, but due to growing ridership over the years—mainly by commuters from various Brooklyn neighborhoods to Manhattan's Chinatown—the third staircase to the northwestern corner was added in 1999. [29]

Second Avenue Subway plans

In addition to connecting the BMT Nassau Street and IND Sixth Avenue Lines, as well as the Sixth Avenue Line to the Manhattan Bridge, the Chrystie Street Connection is one of the few completed sections of the SAS. The Grand Street station was built to serve as a transfer point between the Sixth Avenue and Second Avenue lines. [38] The connection was built this way because the original 1960s plans for the SAS had Second Avenue and Sixth Avenue Line trains sharing two island platforms in a four-track layout, with connections from the Second Avenue Line to the Sixth Avenue Line and the Manhattan Bridge. [38] Because Second Avenue Subway construction was halted in 1975, this station has only served Sixth Avenue Line trains since its opening. As part of the contemporary construction of the Second Avenue Subway, a new station is planned for construction below the current station during the fourth and final phase of the project; [46] Phase 1 of the project on the Upper East Side opened on January 1, 2017, [47] [48] with Phase 2 in planning [49] [50] and two other phases with no funding commitments. [51]

An abandoned segment of the Second Avenue Subway located just south of Grand Street Second Avenue Line provision vc.jpg
An abandoned segment of the Second Avenue Subway located just south of Grand Street

During modern planning, it was considered to utilize the cross-platform provision, known as the "Shallow Chrystie Option", or to place the tracks under Forsyth Street one block east (the Forsyth Option), both of which could tie into an existing tunnel near the Chatham Square station site south of Canal Street. This tunnel, known as the Confucius Plaza Tunnel, was built in the 1970s along with several sections in Upper Manhattan used for Phases 1 and 2 of the SAS. [38] [52] [53] [54] [55] Both these options would require extensive usage of cut-and-cover construction methods, creating large amounts of disturbances to the local community, environmental issues, and possibly requiring the demolition of existing structures. [52] [56]

Current plans, however, have the Second Avenue platform to be built below the current one, though a free transfer will still be provided. [38] [57] [53] The "Deep Chrystie Option", as the selected proposal is called, would instead place the Second Avenue Subway platform below the Sixth Avenue Line tracks, to create the least amount of community disturbance by utilizing tunnel boring machines. Cut-and-cover methods would be utilized only at the station site. [52] [58] [38] The current platforms would be widened to create space for staircases to a new intermediate mezzanine between the two levels. This new mezzanine level will also include a new fare control area with staircases, escalators and elevators leading to two new station entrances/exits, with one on either side of Grand Street between Chrystie and Forsyth Streets. [58] [59] [52] The Second Avenue Subway platform and the new entrances/exits would be ADA accessible. [59] To the north of the station, the Second Avenue Subway tunnels would curve to travel under Sara D. Roosevelt Park rather than directly below the Sixth Avenue Line tunnels under Chrystie Street, to avoid steel piles and other obstructions dating from the construction of the Chrystie Street Connection. To the south, the unused tunnel between Pell and Canal Streets could be used as an ancillary facility with the new passenger-service tunnels located beneath and slightly to the west. [53]

Related Research Articles

<span class="mw-page-title-main">Brooklyn–Manhattan Transit Corporation</span> Defunct transit operator in New York City

The Brooklyn–Manhattan Transit Corporation (BMT) was an urban transit holding company, based in Brooklyn, New York City, United States, and incorporated in 1923. The system was sold to the city in 1940. Today, together with the IND subway system, it forms the B Division of the modern New York City Subway.

<span class="mw-page-title-main">Independent Subway System</span> Defunct subway operator in New York City

The Independent Subway System was a rapid transit rail system in New York City that is now part of the New York City Subway. It was first constructed as the Eighth Avenue Line in Manhattan in 1932. It was originally also known as the Independent City-Owned Subway System (ICOSS) or the Independent City-Owned Rapid Transit Railroad (ICORTR).

<span class="mw-page-title-main">Proposed expansion of the New York City Subway</span>

Since the opening of the original New York City Subway line in 1904, and throughout the subway's history, various official and planning agencies have proposed numerous extensions to the subway system. The first major expansion of the subway system was the Dual Contracts, a set of agreements between the City of New York and the IRT and the BRT. The system was expanded into the outer reaches of the Bronx, Brooklyn, and Queens, and it provided for the construction of important lines in Manhattan. This one expansion of the system provided for a majority of today's system.

<span class="mw-page-title-main">Chrystie Street Connection</span> New York City Subway track connections

The Chrystie Street Connection is a set of New York City Subway tunnels running the length of Chrystie Street on the Lower East Side of Manhattan. It is one of the few track connections between lines of the former Brooklyn–Manhattan Transit Corporation (BMT) and Independent Subway System (IND) divisions, which together constitute the system's B Division. A major branch of the IND Sixth Avenue Line, it connects the Sixth Avenue Line to the BMT Brighton Line and BMT Fourth Avenue Line via the north side of the Manhattan Bridge and to the BMT Jamaica Line over the Williamsburg Bridge. The project, opened in 1967 and 1968, also includes the Sixth Avenue Line's Grand Street and 57th Street stations, the latter of which is not part of the connection itself.

The BMT Broadway Line is a rapid transit line of the B Division of the New York City Subway in Manhattan. As of November 2016, it is served by four services, all colored yellow: the N and ​Q trains on the express tracks and the R and ​W trains on the local tracks during weekdays. The line is often referred to as the "N and R", since those were the only services on the line from 1988 to 2001, when the Manhattan Bridge's southern tracks were closed for rebuilding. The Broadway Line was built to give the Brooklyn Rapid Transit Company access to Midtown Manhattan.

The IND Sixth Avenue Line is a rapid transit line of the B Division of the New York City Subway in the United States. It runs mainly under Sixth Avenue in Manhattan, and continues south to Brooklyn. The B, D, F, and M trains, which use the Sixth Avenue Line through Midtown Manhattan, are colored orange. The B and D trains use the express tracks, while the F, <F> and M trains use the local tracks.

The BMT Nassau Street Line is a rapid transit line of the B Division of the New York City Subway system in Manhattan. At its northern end, the line is a westward continuation of the BMT Jamaica Line in Brooklyn after the Jamaica Line crosses the Williamsburg Bridge into Manhattan. The Nassau Street Line continues south to a junction with the BMT Broadway Line just before the Montague Street Tunnel, after which the line reenters Brooklyn. Although the tracks merge into the Broadway Line south of Broad Street, there has been no regular service south of the Broad Street station since June 25, 2010. While the line is officially recognized as the Nassau Street Line, it only serves one station on Nassau Street: Fulton Street.

The IND 63rd Street Line and BMT 63rd Street Line, also referred to as the 63rd Street Crosstown, Crosstown Route, or Route 131-A, are two rapid transit lines of the B Division of the New York City Subway system. The two lines run under 63rd Street in the Upper East Side of Manhattan, with a cross-platform interchange at the Lexington Avenue–63rd Street station.

<span class="mw-page-title-main">D (New York City Subway service)</span> New York City Subway service

The D Sixth Avenue Express is a rapid transit service in the B Division of the New York City Subway. Its route emblem, or "bullet", is colored orange, since it uses the IND Sixth Avenue Line in Manhattan.

<span class="mw-page-title-main">M (New York City Subway service)</span> New York City Subway service

The M Queens Boulevard/Sixth Avenue Local is a rapid transit service in the B Division of the New York City Subway. Its route emblem, or "bullet", is colored orange since it is a part of the IND Sixth Avenue Line in Manhattan.

<span class="mw-page-title-main">DeKalb Avenue station (BMT lines)</span> New York City Subway station in Brooklyn

The DeKalb Avenue station is an interchange station on the BMT Brighton Line and BMT Fourth Avenue Line of the New York City Subway, located at the intersection of DeKalb and Flatbush Avenues in Downtown Brooklyn. It is served by the Q and R trains at all times, the B train on weekdays, and the D and N trains during late nights. During rush hours only, a few W train trips also serve this station.

The BMT Astoria Line is a rapid transit line in the B Division of the New York City Subway, serving the Queens neighborhood of Astoria. It runs south from Ditmars Boulevard in Astoria to 39th Avenue in Long Island City above 31st Street. It then turns west and serves Queensboro Plaza over Queens Plaza.

<span class="mw-page-title-main">34th Street–Herald Square station</span> New York City Subway station in Manhattan

The 34th Street–Herald Square station is an underground station complex on the BMT Broadway Line and the IND Sixth Avenue Line of the New York City Subway. It is located at Herald Square in Midtown Manhattan where 34th Street, Broadway and Sixth Avenue intersect, and is served by the D, F, N, and Q trains at all times; the R train at all times except late nights; the B, M, and W trains on weekdays; and the <F> train during rush hours in the peak direction.

<span class="mw-page-title-main">Carroll Street station</span> New York City Subway station in Brooklyn

The Carroll Street station is a local station on the IND Culver Line of the New York City Subway, located in the neighborhood of Carroll Gardens, Brooklyn, at Carroll and Smith Streets. It is served by the F and G trains at all times.

<span class="mw-page-title-main">Second Avenue station</span> New York City Subway station in Manhattan

The Second Avenue station is a station on the IND Sixth Avenue Line of the New York City Subway, located at the intersection of Second Avenue and Houston Street on the border between the East Village and the Lower East Side, in Manhattan. It is served by the F train at all times and the <F> train during rush hours in the peak direction.

<span class="mw-page-title-main">West Fourth Street–Washington Square station</span> New York City Subway station in Manhattan

The West Fourth Street–Washington Square station is an express station and transfer stop on the IND Sixth Avenue and IND Eighth Avenue Lines of the New York City Subway, located at the intersection of West Fourth Street and Sixth Avenue in Greenwich Village, Manhattan. It is served by the A, D, E, and F trains at all times; the B and M trains on weekdays; the C train at all times except late nights; and the <F> train during rush hours in the peak direction.

<span class="mw-page-title-main">Fort Hamilton Parkway station (IND Culver Line)</span> New York City Subway station in Brooklyn

The Fort Hamilton Parkway station is a local station on the IND Culver Line of the New York City Subway. It is served by the F and G trains at all times.

<span class="mw-page-title-main">York Street station (IND Sixth Avenue Line)</span> New York City Subway station in Brooklyn

The York Street station is a station on the IND Sixth Avenue Line of the New York City Subway. It is served by the F train at all times and the <F> train during rush hours in the peak direction. It is located at York Street and Jay Street in Dumbo.

<span class="mw-page-title-main">Lexington Avenue–63rd Street station</span> New York City Subway station in Manhattan

The Lexington Avenue–63rd Street station is a New York City Subway station in Lenox Hill, Manhattan, shared by the IND and BMT 63rd Street Lines. Located at the intersection of Lexington Avenue and 63rd Street, it is served by the F and Q trains at all times; <F> trains during rush hours in the peak direction; limited rush hour N trains; and one A.M. rush hour R train in the northbound direction only.

<span class="mw-page-title-main">Unbuilt plans for the Second Avenue Subway</span> History of a New York City Subway line

The Second Avenue Subway, a New York City Subway line that runs under Second Avenue on the East Side of Manhattan, has been proposed since 1920; the first phase of the line did not open until 2017. Up until the 1960s, many distinct plans for the Second Avenue subway line were never carried out, though small segments were built in the 1970s. The complex reasons for these delays are why the line has been called "the line that time forgot".

References

  1. "Glossary". Second Avenue Subway Supplemental Draft Environmental Impact Statement (SDEIS) (PDF). Vol. 1. Metropolitan Transportation Authority. March 4, 2003. pp. 1–2. Archived from the original (PDF) on February 26, 2021. Retrieved January 1, 2021.
  2. 1 2 "Annual Subway Ridership (2018–2023)". Metropolitan Transportation Authority. 2023. Retrieved April 20, 2024.
  3. 1 2 3 4 Perlmutter, Emanuel (November 16, 1967). "SUBWAY CHANGES TO SPEED SERVICE: Major Alterations in Maps, Routes and Signs Will Take Effect Nov. 26" (PDF). The New York Times . Archived from the original on October 30, 2021. Retrieved July 7, 2015.
  4. Crowell, Paul (September 14, 1951). "$500,000,000 Voted for 2d Ave. Subway by Estimate Board; Program Including Connections to Existing Lines Depends on Public's Exemption of Bonds". The New York Times. ISSN   0362-4331 . Retrieved June 12, 2023.
  5. "Estimate Board Approves 2d Av. Subway Project: Votes $500,000,000 Plan Subject to Exemption at Election in November". New York Herald Tribune. September 14, 1951. p. 1. ISSN   1941-0646. ProQuest   1318307124.
  6. Ingalls, Leonard (April 23, 1952). "City to Begin 2d Ave. Subway This Summer in Chrystie St". New York Herald Tribune. p. 1. ISSN   1941-0646. ProQuest   1319901942.
  7. Ingalls, Leonard (July 12, 1952). "Transit Board Moves to Start 2d Av. Subway: Gives First Authorization; Forecasts Deficit for 7 Years After It Is Built". New York Herald Tribune. p. 7. ISSN   1941-0646. ProQuest   1323041074.
  8. Ingalls, Leonard (July 10, 1954). "Transit Body Asks $172,062,000 Of City for Capital Improvements". The New York Times. ISSN   0362-4331 . Retrieved June 12, 2023.
  9. 1 2 Katz, Ralph (July 3, 1957). "Project, to Be Completed in 3 Years, Will Link BMT From Brooklyn and Queens With IND at 2d Ave. Station". The New York Times. ISSN   0362-4331 . Retrieved May 30, 2022.
  10. "T. A. Approves E. Side Tunnels to Link IND, BMT". New York Herald Tribune. July 3, 1957. p. 4. ISSN   1941-0646. ProQuest   1327111380.
  11. 1 2 "Ground Is Broken for the Chrystie Street Subway Link". The New York Times. November 26, 1957. ISSN   0362-4331 . Retrieved May 30, 2022.
  12. "Chrystie St. Subway Fund Voted: Line Will Link BMT and IND". New York Herald Tribune. October 25, 1957. p. 11. ISSN   1941-0646. ProQuest   1325602834.
  13. Crowell, Paul (October 25, 1957). "Chrystie St. Link for BMT is Voted; $10,227,400 Authorized to Begin East Side Project". The New York Times. ISSN   0362-4331 . Retrieved June 12, 2023.
  14. "Start Chrystie St. Subway Today". New York Herald Tribune. November 25, 1957. p. 12. ProQuest   1325667117.
  15. 1 2 Annual Report 1964–1965. New York City Transit Authority. 1965.
  16. "New York City Transit to Spend $23 Million for Signals". Railway Signaling and Communications. Vol. 53, no. 10. October 1, 1960. p. 53. ProQuest   865426639.
  17. "Barriers on Chrystie St. Removed Alter 6 Years". The New York Times . January 24, 1964. Retrieved August 23, 2015.
  18. 1 2 "New BMT Tunnel Opens Next Year; Lower East Side Project to Tie In With the IND". The New York Times. March 1, 1964. ISSN   0362-4331 . Retrieved May 30, 2022.
  19. "A big city's subway grows bigger: New York has spent $800 million in the past 10 years on its rapid transit system. Ahead: more big spending for a new Queens tunnel, additional lines". Railway Age. Vol. 157, no. 5. August 3, 1964. p. 21. ProQuest   882955046.
  20. 1 2 Perlmutter, Emanuel (November 27, 1967). "BMT-IND CHANGES BEWILDER MANY; Transit Authority Swamped With Calls From Riders as New System Starts". The New York Times . Archived from the original on December 11, 2021. Retrieved August 23, 2015.
  21. Brian J. Cudahy (January 1995). Under the Sidewalks of New York: The Story of the Greatest Subway System in the World . Fordham University Press. p.  132. ISBN   978-0-8232-1618-5.
  22. 1 2 Gershowitz, Mike (November 24, 1967). "Subway Land Turned Upsidedown". Greenpoint Weekly Star. p. 4. Archived from the original on May 6, 2022. Retrieved August 14, 2016 via fultonhistory.com.
  23. 1 2 3 Raskin, Joseph B. (2013). The Routes Not Taken: A Trip Through New York City's Unbuilt Subway System. New York, New York: Fordham University Press. doi:10.5422/fordham/9780823253692.001.0001. ISBN   978-0-82325-369-2.
  24. "Repairs to Close Part Of Manhattan Bridge". The New York Times. April 14, 1986. ISSN   0362-4331 . Retrieved May 16, 2023.
  25. Lyall, Sarah (December 12, 1988). "All Aboard. . .Somewhere. . .for Subway Changes!". The New York Times. ISSN   0362-4331 . Retrieved May 16, 2023.
  26. "1987 system map". nycsubway.org. 1987. Archived from the original on November 11, 2020. Retrieved August 12, 2009.
  27. Belluck, Pam (November 13, 1995). "For Riders, A Bright Spot Amid Tumult". The New York Times. ISSN   0362-4331 . Retrieved March 29, 2019.
  28. Jacobs, Andrew (January 28, 1996). "Neighborhood Report: Chinatown/downtown; Experiment Fails As Peddlers Vote With Their Feet". The New York Times . Archived from the original on September 30, 2015. Retrieved August 6, 2015.
  29. 1 2 Lee, Denny (February 18, 2001). "NEIGHBORHOOD REPORT: CHINATOWN; Will a Shuttered Subway Lead to Shuttered Stops?". The New York Times . Archived from the original on May 27, 2015. Retrieved August 6, 2015.
  30. 1 2 Wolfson, John (March 18, 2001). "Neighborhood Report: Chinatown; Divided by Tradition, United by a Subway Closing". The New York Times. ISSN   0362-4331 . Retrieved May 26, 2023.
  31. Saulny, Susan (December 5, 2000). "In Subway Changes, W Follows V, but for Riders It's Not So Simple". The New York Times. ISSN   0362-4331 . Retrieved May 26, 2023.
  32. Donohue, Pete (December 4, 2000). "Subway Branching Out New W Line Part of Reconfiguring". New York Daily News. p. 7. ISSN   2692-1251. ProQuest   305607979.
  33. Lemire, Jonathan; Donohue, Pete (July 25, 2001). "Big Crush at Subway Station With Reroutings". New York Daily News. p. 3. ISSN   2692-1251. ProQuest   305613525.
  34. Dewan, Shaila K. (July 23, 2001). "For Riders, Many Riddles, Written in Q's, D's and W's". The New York Times. ISSN   0362-4331 . Retrieved May 16, 2023.
  35. Blood, Michael R.; Donohue, Pete (March 20, 2001). "Rudy: MTA Plan Not Grand Rips Brass for 3-yr. Bypass of Chinatown Subway Stop". New York Daily News. p. 5. ISSN   2692-1251. ProQuest   305639325.
  36. Luo, Michael (February 20, 2004). "A Subway Map Remade, in Hopes of Matching Routes and Riders". The New York Times. ISSN   0362-4331 . Retrieved November 5, 2016.
  37. "Second Avenue Subway Supplemental Draft Environmental Impact Statement (SDEIS): Chapter 2: Project Alternatives" (PDF). Metropolitan Transportation Authority. Archived (PDF) from the original on December 5, 2019. Retrieved August 9, 2019.
  38. 1 2 3 4 5 6 7 8 "Second Avenue Subway Final Environmental Impact Statement (FEIS): Appendix B: Development of Alternatives" (PDF). Metropolitan Transportation Authority. Archived (PDF) from the original on November 22, 2016. Retrieved August 5, 2015.
  39. 1 2 "The Subway Compromise". The New York Times . July 28, 1969. Archived from the original on July 11, 2015. Retrieved July 9, 2015.
  40. 1 2 "2nd Avenue Subway – Tentative track plan, Manhattan portion". nycsubway.org. Archived from the original on May 25, 2012. Retrieved August 13, 2016.
  41. "Full text of "Metropolitan transportation, a program for action. Report to Nelson A. Rockefeller, Governor of New York."". Metropolitan Commuter Transportation Authority. November 7, 1967. Retrieved October 1, 2015 via Internet Archive.
  42. 1 2 "MTA Neighborhood Maps: Lower East Side" (PDF). Metropolitan Transportation Authority. 2015. Archived (PDF) from the original on July 24, 2015. Retrieved August 6, 2015.
  43. Dougherty, Peter (2006) [2002]. Tracks of the New York City Subway 2006 (3rd ed.). Dougherty. OCLC   49777633 via Google Books.
  44. "Grand Street". nycsubway.org. Archived from the original on July 9, 2016. Retrieved July 7, 2016.
  45. "Artwork: Trains of Thought (Andrea Gardner and Sally Heller)". nycsubway.org. Archived from the original on August 12, 2017. Retrieved July 7, 2016.
  46. "Second Avenue Subway Final Environmental Impact Statement (FEIS): Proposed Phase 4" (PDF). Metropolitan Transportation Authority. Archived (PDF) from the original on March 4, 2016. Retrieved August 5, 2015.
  47. Siff, Andrew (December 19, 2016). "2nd Avenue Subway Service to Begin New Year's Day: Gov. Cuomo". NBC New York. NBC Universal Media. Archived from the original on December 20, 2016. Retrieved December 19, 2016.
  48. Rivoli, Dan; Sandoval, Edgar; Greene, Leonard (December 18, 2016). "Cuomo promises Second Ave. subway will open Jan. 1". NY Daily News. Archived from the original on March 9, 2021. Retrieved December 19, 2016.
  49. Donohue, Pete (August 7, 2014). "MTA chairman outlines future plans for Phase 2 of Second Ave. subway construction, expansion projects". New York Daily News. Archived from the original on January 6, 2017. Retrieved December 14, 2016.
  50. Fitzsimmons, Emma G. (October 29, 2015). "Anger in East Harlem Over New Delays in 2nd Ave. Subway Plans". The New York Times. Archived from the original on November 3, 2015. Retrieved November 3, 2015.
  51. Donohue, Pete (January 20, 2013). "Second Ave. subway on track to open in 2016: MTA". New York Daily News. Archived from the original on February 3, 2013. Retrieved March 25, 2013.
  52. 1 2 3 4 "Second Avenue Subway Final Environmental Impact Statement (FEIS): Chapter 2: Project Alternatives" (PDF). Metropolitan Transportation Authority. Archived (PDF) from the original on October 5, 2018. Retrieved August 5, 2015.
  53. 1 2 3 "Second Avenue Subway Final Environmental Impact Statement (FEIS): Deep Chrystie Option" (PDF). Metropolitan Transportation Authority. Archived (PDF) from the original on July 10, 2015. Retrieved July 9, 2015.
  54. Donohue, Pete (June 24, 2013). "Underground subway party could put organizers in hot water: MTA: Gothamist website printed pictures of the bash. MTA says it'll turn over case to NYPD". New York Daily News . Archived from the original on March 10, 2016. Retrieved August 5, 2015.
  55. Kabak, Benjamin (June 25, 2015). "Abandoned SAS segment party prompts NYPD inquiry". secondavenuesagas.com. Archived from the original on July 15, 2015. Retrieved August 5, 2015.
  56. "Second Avenue Subway Final Environmental Impact Statement (FEIS): Chapter 3: Description of Construction Methods and Activities" (PDF). Metropolitan Transportation Authority. Archived (PDF) from the original on April 19, 2020. Retrieved August 5, 2015.
  57. "Second Avenue Subway Final Environmental Impact Statement (FEIS): Track Diagram, South of 57th Street" (PDF). Metropolitan Transportation Authority. Archived (PDF) from the original on July 10, 2015. Retrieved July 9, 2015.
  58. 1 2 "Second Avenue Subway: Tunnel Construction Techniques" (PDF). Metropolitan Transportation Authority. August 2002. Archived (PDF) from the original on August 19, 2014. Retrieved August 5, 2015.
  59. 1 2 "Second Avenue Subway Station Entrances: Community Board 3" (PDF). mta.info . Metropolitan Transportation Authority, DMJM HARRIS, ARUP. May 20, 2003. Archived (PDF) from the original on March 4, 2016. Retrieved August 5, 2015.