Ngatapa Branch

Last updated

Contents

Ngatapa Branch
Map

The Ngatapa Branch was a secondary branch line railway 18.5 kilometres (11.5 mi) long that for a short time formed part of the national rail network in Poverty Bay in the North Island of New Zealand. The Ngatapa branch diverged from the Moutohora branch line about 6 kilometres (3.7 mi) from Gisborne and ran a further 12.5 kilometres (7.8 mi) across the coastal flat to a terminus at Ngatapa. It was sometimes referred to as the Ngapata branch. [1] [2]

Built to the New Zealand standard 3 ft 6 in (1,067 mm) gauge the branch was originally authorised as part of the proposed inland route for the Wairoa to Gisborne section of the Palmerston North – Gisborne Line. However, in 1924, an engineer's report recommended that the then-new isolated section between Wairoa and Waikokopu in Hawke's Bay be incorporated as the southernmost portion of a new coastal route from Wairoa to Gisborne. The Public Works Department (PWD) accordingly stopped work on the inland Ngatapa route, which was officially opened as a branch line on 15 December 1924, and began work on the coastal route. [3] The Ngatapa branch became a dead end, and it was closed on 1 April 1931. [4]

Construction

Lord Islington turning the first sod near King's Road in 1912 Lord Islington turning the sod for the Gisborne-Napier Railway.jpg
Lord Islington turning the first sod near King's Road in 1912

Construction started in 1911. [5] The first sod was turned by the Governor, Lord Islington, on Saturday 10 February 1912, just north of King's Road, where the branch was intended to join the line towards Rotorua. [6] In July 1912 it was decided that the junction should instead be near Mākaraka. [7] There was much criticism of slow progress; the 1912 Reform government cut spending on many branches and were slow to mechanise work. [8] In 1914 there were also complaints that a change from cooperative contracts to contracts with small contractors wasn't working. Due to the slips the route near Ngātapa was changed and contracts postponed. [9] The Minister of Public Works, William Fraser, said £45,000 was budgeted for the line in 1914-15 and £45,968 had been spent. [10] The rails reached Ngātapa on 7 July 1914. [11] The only substantial structure was the bridge over the Waipaoa River. It had 3 spans of 25 ft (7.6 m) and 2 of 106 ft (32 m). [12] A temporary bridge was built over the river in 1913, [13] but swept away in 1914. [14] The line was completed to Ngatapa by December 1915, although it was not formally handed over to the New Zealand Railways Department (NZR) until 15 December 1924. [5] In 1915 earthworks and a short tunnel were being built in the 3 miles beyond Ngātapa. [15] Between 1918 and 1920, work started at Wairoa on the section to Frasertown, which was to have been linked through to Ngatapa, and on the Waikura section beyond Ngatapa, but all work was stopped in 1920 after the Waikura section was found to be unstable. [16]

Construction of the line presented few problems as far as Ngatapa. The course of the line beyond this point was a different matter and would have required heavy earthworks and extensive tunnelling [17] the longest being about 1.25 mi (2 km). [18] The Gisborne-Wairoa distance as built was 96.05 km (59.68 mi). [19] In 1929 the route via Ngātapa had been surveyed as 72 mi 19 ch (116.3 km) and the coastal route via Waikokopu as 68 mi 12 ch (109.7 km). The surveyed Ngātapa line would have been - Gisborne-Mākaraka 3 mi 5 ch (4.9 km), -Ngātapa 11 mi 51 ch (18.7 km), -Wharekōpae 4 mi 69 ch (7.8 km), -Waikura 5 mi 40 ch (8.9 km), -Waterfall 6 mi 66 ch (11.0 km), -Hangaroa 4m, [20] -Te Reinga 17 mi 11 ch (27.6 km), -Marumaru 9 mi 40 ch (15.3 km), -Wairoa 10 mi (16 km). [21] In his 1919-20 report the Minister said banks had been widened, ballast-crushing intermittently carried on at Repongaere quarry, including 614 tons of lime supplied to farmers [22] (in 1922 it supplied 400 tons of lime), [23] and 2 mi (3.2 km) beyond Ngātapa was repegged, levelled, cross-sectioned and had earthworks started. Work also started on the Wairoa to Frasertown section in September 1919. The Minister said progress had been hindered by the shortage of cement and scarcity and quality of labour, [22] which was possibly due to low pay. [24] Beyond Ngatapa, some formation work was undertaken for about 8 km, including the excavation of a short tunnel; [25] including a large cutting, [26] 3 mi (4.8 km) was partly formed and rails were laid for 1 mi 50 ch (2.6 km). [27] [28] Today, earthworks such as embankments and cuttings can still be found, but no actual tunnels can be located, possibly due to collapse in the slip prone ground. [16] [29] [30]

Operations and closure

From 13 December 1915 the Public Works Department (PWD) was operating goods and passenger trains on the branch, [31] though ballasting wasn't completed until 1916, most of it being dragged from the Waipaoa River bed by scoop on an aerial cableway. Traffic was described as very light in 1916. [32] Responsibility for the line was transferred from PWD to NZR on 15 December 1924. [33] The NZR service ran from Gisborne, rather than Mākaraka. [34] The line carried only about 12,000 tonnes of freight per annum, almost all road metal. [35] By 1930 a Railways Commission noted that with the abandonment of the originally proposed inland route the need for the line had disappeared, and the twice-daily Monday to Saturday NZR service attracted an average of only 20 passengers a day. The commission recommended the branch should either close or be taken over by its users, the PWD, or the Gisborne City Council. There were no takers, and the line was closed on 1 April 1931. [35] By 1931 stone from the quarry was almost the only traffic and said not to justify keeping the branch open. [36]

Stations

Stations on the branch were -

NameDistance from Gisborne [37] Opened [2] Closed [2] Elevation Notes [37]
Mākaraka3 mi 12 ch (5.1 km)26 June 1902

31 March 1979 renamed as Gisborne Industrial Line

29 January 1945 to passengers

15 March 1959 to freight

5 m (16 ft)
Makaraka in 1942, showing the Ngatapa branch diverging west from the Moutohora branch Makaraka in 1942.jpg
Mākaraka in 1942, showing the Ngātapa branch diverging west from the Moutohora branch
The station serving the suburb of Mākaraka opened on the Moutohora branch on 26 June 1902. [2] In July 1912 it was decided that the Ngātapa branch junction would be about half a kilometre north of the station. [38] [39]

In 1916 a platelayer's cottage was built [40] and by 1926 there was a station building, platform, cart approach, 30 ft (9.1 m) x 20 ft (6.1 m) goods shed (with a corrugated iron roof, stringers of rimu, studs, plates and purlins of matai and weatherboard walls), cattle and sheep yards, urinals and a passing loop for 62 wagons.

Feilding Sash & Door Co had a private siding until 1937. In 1947 the goods shed verandah was removed. In 1957 regular traffic included cream from Moutohora and Puha and stone for the Ministry of Works. After closure of the Moutohora Branch on 15 March 1959 the track was lifted in 1960 to 35 ch (700 m) north of Mākaraka, just south of bridge No 3. By 1962 the siding was rarely used and the station building in a dilapidated condition. In 1963 the station building was sold to the Chief Stationmaster at Gisborne for removal for £5. The goods shed remained, but the station site was sold in September 1994. [37] A single track remains, [41] behind the East Coast Museum of Technology station, which was moved from nearby Matawhero. [42]

In 1916 there was also a request for a siding at Bushmere, near the Waipaoa River, [43] but it was rejected as being too close to Mākaraka. [44]

Pātūtahi8 mi (13 km)13 December 1915 PWD

15 December 1924 NZR

1 April 193139 ft (12 m)
Patutahi in 1942 Patutahi in 1942. The railway station was between Patutahi and Bilham Roads.jpg
Pātūtahi in 1942
Also sometimes called Putatahi, [2] or Patuahi, the station served the small village of Pātūtahi. A plan for the flag station was made in 1913. By 1921 some buildings needed repair and two 16 ft (4.9 m) gates were painted. By 1924 there was a shelter shed, platform, 30 ft (9.1 m) x 20 ft (6.1 m) goods shed, loading bank, cattle and sheep yards and a passing loop for 58 wagons. By 1926 urinals had been added.
Repongaere10 mi 54 ch (17.2 km)13 December 1915 PWD

15 December 1924 NZR

18 May 193127 m (89 ft)
Repongaere station (top right) and quarry (bottom left) in 1942 Repongaere station and quarry in 1942.jpg
Repongaere station (top right) and quarry (bottom left) in 1942
Repongaere, [2] or Repongarere, was also a flag station, mainly serving the quarry.

In 1915 the new quarry near Repongaere had a temporary line into it. [45] 4 railway houses were built in 1916 [40] and more in 1924.

By 1926 Repongaere had a station building, platform, cart approach, loading bank and a passing loop for 41 wagons.

Ngātapa14 mi 45 ch (23.4 km)13 December 1915 PWD

15 December 1924 NZR

1 April 1931231 ft (70 m) [46]
Auckland Weekly News photo of the railway at Ngatapa in 1916 Ngatapa railway.jpg
Auckland Weekly News photo of the railway at Ngātapa in 1916
Planning for the station to serve Ngātapa began in 1912, with cottages built in 1913 [37] and, in March 1914, a tender for the station was accepted. [47] By 1919 a platform and goods shed had been built, but the yard was still to be ballasted and the station building built. In 1921 a verandah was added to the goods shed and the yard, platform and loading bank were raised to avoid flooding. [37] 4 railway houses were built in 1916 [40] and more in 1924, by which time Ngātapa had a shelter shed, ladies waiting room, platform, 30 ft (9.1 m) x 20 ft (6.1 m) goods shed, loading bank, cattle and sheep yards. [37]

Remains

Not much remains of the branch formation or other works on the coastal plain. [35] Apart from the bridge piers of the Waipaoa River crossing between Makaraka and Patutahi, the most significant remains are those past the original terminus at Ngatapa, over which trains never ran but which illustrate the problems that would have faced the constructors if the line had continued into the hills. Beyond the terminus at Ngatapa the formation works take the proposed line through a 180-degree climbing turn [28] before following a winding path across the face of the hills until disappearing into the bush. [35]

See also

Related Research Articles

<span class="mw-page-title-main">Waipawa</span> Town in Hawkes Bay, New Zealand

Waipawa is the second-largest town in Central Hawke's Bay in the east of the North Island of New Zealand. It has a population of 2,400.

The Tokanui Branch, also known as the Seaward Bush Branch, was a branch line railway located in Southland, New Zealand. It diverged from the Bluff Branch south of the main railway station in Invercargill and ran for 54 kilometres in a southeasterly direction. Construction began in 1883 and it operated until 1966.

<span class="mw-page-title-main">Raetihi Branch</span> Branch line railway

The Raetihi Branch was a branch line railway in the central North Island of New Zealand. It formed part of New Zealand's national rail network and operated from 1917 until 1968.

<span class="mw-page-title-main">Stillwater–Ngākawau Line</span> Railway line in New Zealand

The Stillwater Ngākawau Line (SNL), formerly the Stillwater–Westport Line (SWL) and the Ngakawau Branch, is a secondary main line, part of New Zealand's national rail network. It runs between Stillwater and Ngakawau via Westport on the West Coast of the South Island. It was one of the longest construction projects in New Zealand's history, with its first section, at the south end, opened in 1889, and the beginnings of the Ngākawau Branch, at its Westport end, in 1875. The full line was completed in 1942. The only slower railway projects were Palmerston North to Gisborne, 1872 to 1942, and the Main North Line to Picton, 1872 to 1945.

<span class="mw-page-title-main">East Coast Main Trunk</span> Railway in New Zealand running between Hamilton and Kawerau

The East Coast Main Trunk (ECMT) is a railway line in the North Island of New Zealand, originally running between Hamilton and Taneatua via Tauranga, connecting the Waikato with the Bay of Plenty. The ECMT now runs between Hamilton and Kawerau, with a branch line to Taneatua from the junction at Hawkens. The line is built to narrow gauge of 1,067 mm, the uniform gauge in New Zealand. It was known as the East Coast Main Trunk Railway until 2011, when the word "Railway" was dropped.

<span class="mw-page-title-main">Stratford–Okahukura Line</span> Railway line in New Zealand

The Stratford–Okahukura Line (SOL) is a secondary railway line in the North Island of New Zealand, between the Marton - New Plymouth Line (MNPL) and the North Island Main Trunk (NIMT) Railway, with 15 intermediate stations. It is 144 km (89 mi) long through difficult country, with 24 tunnels, 91 bridges and a number of sections of 1 in 50 grade. Near Okahukura there is an unusual combined road-rail bridge over the Ongarue River, with the one-lane road carriageway below the single rail track. The line is not currently in service for rail traffic and is under a 30-year lease for a tourist venture. In July 2019 KiwiRail's CEO stated that reopening the line was a priority. Minister of Transport Michael Wood announced the government's 10-year plan for rail investment on 6 May 2021, which specifically stated that plans could include re-opening the Stratford to Okahukura line.

The Palmerston North–Gisborne Line (PNGL) is a secondary main line railway in the North Island of New Zealand. It branches from the North Island Main Trunk at Palmerston North and runs east through the Manawatū Gorge to Woodville, where it meets the Wairarapa Line, and then proceeds to Hastings and Napier in Hawke's Bay before following the coast north to Gisborne. Construction began in 1872, but the entire line was not completed until 1942. The line crosses the runway of Gisborne Airport, one of the world's only railways to do so since Pakistan's Khyber Pass Railway closed.

Makaraka is an outer suburb of Gisborne, in New Zealand's North Island, located in the west of the city. The suburb features Gisborne's horse-racing circuit, Makaraka Racecourse. It is part of the statistical area of Makaraka-Awapuni, which is covered at Awapuni.

<span class="mw-page-title-main">Rotorua Branch</span> Mothballed railway line in New Zealand

The Rotorua Branch is a railway line from Putāruru to Rotorua, in the Waikato and Bay of Plenty regions of the North Island of New Zealand. Construction of the line was commenced by the Thames Valley and Rotorua Railway Company and finished by the Public Works Department (PWD). The complete line, 50.5 kilometres (31.4 mi) in length, opened in two sections; on 24 November 1893 to Tārukenga and the final 8 mi 43 ch (13.7 km) to Rotorua on 8 December 1894.

<span class="mw-page-title-main">Thames Branch</span>

The Thames Branch railway line connected Thames, New Zealand, with Hamilton and was originally part of the East Coast Main Trunk railway. Part of the line between Morrinsville and Waitoa remains open and is in use as the Waitoa Branch line, connecting to the Fonterra Dairy Factory at Waitoa.

<span class="mw-page-title-main">Mangapōike River</span> River in New Zealand

The Mangapōike River is a river beginning in the Gisborne Region of New Zealand's North Island. It flows generally southwest from sources south of Waingake, reaching the Wairoa River in Hawke's Bay 10 kilometres (6 mi) northeast of Frasertown. Mangapōike River was Gazetted as an official name on 28 November 2022.

<span class="mw-page-title-main">Cape Foulwind Railway</span>

The Cape Foulwind Railway was a branch railway line west of Westport to Cape Foulwind. In 1886 the Westport Harbour Board built the line to their quarry to transport rocks to their breakwaters in the Buller River. In 1888 it was linked to Westport by a road-rail bridge over the Buller River. The iron bridge was planked with kauri forming a 12 ft (3.7 m) wide road. The bridge cost £13,794 and was 1,040 ft (320 m) long. By 1888 it was said to be carrying a considerable passenger traffic, using two coaches. In 1914 a new section of line including a tunnel was built to a new quarry south of the Cape.

The Moutohora Branch was a branch line railway that formed part of New Zealand's national rail network in Poverty Bay in the North Island of New Zealand. The branch ran for 78 km approximately North-West from Gisborne into the rugged and steep Raukumara Range to the terminus at Moutohora. Construction started in 1900, and the line was opened to Moutohora on 26 November 1917.

<span class="mw-page-title-main">Mohaka Viaduct</span> Bridge in North Island, New Zealand

The Mohaka Viaduct is a railway viaduct spanning the Mohaka River in northern Hawke’s Bay, on the East Coast of the North Island of New Zealand, near the small settlement of Raupunga. It was built between 1930 and 1937 by the Public Works Department (PWD) for the New Zealand Railways Department (NZR). It is 276.8 metres (908 ft) in length, and at 95 metres (312 ft), is the tallest viaduct in Australasia.

<span class="mw-page-title-main">Palmerston North railway station</span> Railway station in New Zealand

Palmerston North railway station is a main station on the North Island Main Trunk serving the city of Palmerston North in the Manawatū-Whanganui region of New Zealand.

The Paeroa-Pokeno railway line or deviation in the upper North Island of New Zealand between Paeroa on the East Coast Main Trunk (ECMT) and Pokeno on the North Island Main Trunk (NIMT) was a proposed route with construction started but abandoned. The proposal has been revived in recent years as part of a more direct route between Auckland and Tauranga.

<span class="mw-page-title-main">Onehunga Wharf railway station</span> Defunct railway station in New Zealand

Onehunga Wharf railway station on the Onehunga Branch section of the Onehunga Line was the terminal station for the line to Auckland from 28 November 1878 to 1927. A petition in 1870 objected to the extension from Onehunga, on the grounds that it would take business away from the town.

<span class="mw-page-title-main">Ormondville</span> Settlement in Manawatū-Whanganui Region, New Zealand

Ormondville is a locality in the Manawatū-Whanganui region of New Zealand's North Island. It is located inland, south of Waipukurau and west of Flemington, Hawke's Bay.

<span class="mw-page-title-main">Te Aute railway station</span> Railway station in New Zealand

Opapa railway station is a preserved station, probably dating from 1896, on the Palmerston North–Gisborne Line in Hastings District of Hawke's Bay, 23.56 km (14.64 mi) south of Hastings in New Zealand's North Island. Although it closed in 1981 and is now in a meshblock with a 2018 population of only 222, Te Aute is unusual in 3 respects:

<span class="mw-page-title-main">Kopua railway station</span> Railway station in New Zealand

Kopua in New Zealand is now a sparsely populated area, immediately south of the border of the Manawatū-Whanganui and Hawke's Bay regions, with 150 people scattered over a 40 km2 (15 sq mi) meshblock. For two years it briefly flourished as a village, centred on a railway station on the Palmerston North–Gisborne line, opened on 25 January 1878, when it became the southern terminus of the line from Napier and Spit. Building to the south was delayed by the need to erect 3 large viaducts over the Manawatū River and its tributaries, so the extension to Makotuku didn't open until 9 August 1880. Kopua then declined until the station closed on 8 May 1977. Only a single line now passes through the station site and there are remnants of cattle yards.

References

  1. "GISBORNE-NGATAPA LINE. Poverty Bay Herald". paperspast.natlib.govt.nz. 13 December 1924. Retrieved 26 March 2023.
  2. 1 2 3 4 5 6 Scoble, Juliet (April 2010). "Names & Opening & Closing Dates of Railway Stations in New Zealand 1863 to 2010" (PDF). Rail Heritage Trust of New Zealand.
  3. Churchman & Hurst 2001, p. 145.
  4. Hermann, Bruce J; North Island Branch Lines p 59 (2007, New Zealand Railway & Locomotive Society, Wellington) ISBN   978-0-908573-83-7
  5. 1 2 Leitch D. & Scott B., 1995, ‘Exploring New Zealand’s Ghost Railways’, Grantham House Publishing, Wellington, New Zealand, ISBN   1-86934-048-5
  6. "THE RAILWAY CEREMONY. Poverty Bay Herald". paperspast.natlib.govt.nz. 10 February 1912. Retrieved 25 March 2023.
  7. "Gisborne Times". paperspast.natlib.govt.nz. 1 July 1912. Retrieved 26 March 2023.
  8. Noonan, Rosslyn J. (1975). By Design: A brief history of the Public Works Department Ministry of Works 1870-1970. Wellington: Ministry of Works (Crown Copyright). p. 100.
  9. "MARKING TIME. Poverty Bay Herald". paperspast.natlib.govt.nz. 20 November 1914. Retrieved 25 March 2023.
  10. Parliament, New Zealand (1915). Parliamentary Debates: House of Representatives.
  11. "RAILS REACH NGATAPA. Poverty Bay Herald". paperspast.natlib.govt.nz. 7 July 1914. Retrieved 25 March 2023.
  12. "GISBORNE LINES. Poverty Bay Herald". paperspast.natlib.govt.nz. 1 April 1914. Retrieved 26 March 2023.
  13. "Local and General. Gisborne Times". paperspast.natlib.govt.nz. 17 November 1913. Retrieved 26 March 2023.
  14. "EAST COAST DELUGED. Auckland Star". paperspast.natlib.govt.nz. 25 March 1914. Retrieved 26 March 2023.
  15. "PUBLIC WORKS STATEMENT, BY THE HON. WILLIAM FRASER, MINISTER OF PUBLIC WORKS". paperspast.natlib.govt.nz. 1915. Retrieved 25 March 2023.
  16. 1 2 Historic Poverty Bay and the East Coast, N.I., N.Z.. J A Mackay, Gisborne, 1949
  17. Bromby, R., 2003, ‘Rails That Built a Nation – An Encyclopedia of New Zealand Railways’, Grantham House Publishing, Wellington, New Zealand, ISBN   1-86934-080-9
  18. "Poverty Bay Herald". paperspast.natlib.govt.nz. 28 March 1918. Retrieved 25 March 2023.
  19. "KiwiRail Network Map". kiwirail.maps.arcgis.com. November 2018. Retrieved 25 March 2023.
  20. "PUBLIC WORKS STATEMENT (BY THE HON. E. A. RANSOM, MINISTER OF PUBLIC WORKS)". paperspast.natlib.govt.nz. 1929. Retrieved 25 March 2023.
  21. "PUBLIC WORKS STATEMENT (BY THE HON. E. A. RANSOM, MINISTER OF PUBLIC WORKS)". paperspast.natlib.govt.nz. 1929. Retrieved 25 March 2023.
  22. 1 2 "PUBLIC WORKS STATEMENT. BY THE HON. J. G. COATES, MINISTER OF PUBLIC WORKS". paperspast.natlib.govt.nz. 31 March 1920. Retrieved 25 March 2023.
  23. "RAILWAY WORKS. Poverty Bay Herald". paperspast.natlib.govt.nz. 28 January 1922. Retrieved 25 March 2023.
  24. "Local and General. Gisborne Times". paperspast.natlib.govt.nz. 22 November 1919. Retrieved 25 March 2023.
  25. Bromby, R., 2003, ‘Rails That Built a Nation – An Encyclopedia of New Zealand Railways’, Grantham House Publishing, Wellington, New Zealand, ISBN   1-86934-080-9
  26. "VISIT OF MR. COATES Gisborne Times". paperspast.natlib.govt.nz. 13 May 1921. Retrieved 25 March 2023.
  27. "PUBLIC WORKS STATEMENT (BY THE HON. E. A. RANSOM, MINISTER OF PUBLIC WORKS)". paperspast.natlib.govt.nz. 1929. Retrieved 25 March 2023.
  28. 1 2 Bromby, R., 2003, ‘Rails That Built a Nation – An Encyclopedia of New Zealand Railways’, Grantham House Publishing, Wellington, New Zealand, ISBN   1-86934-080-9
  29. "Of Stone, Steel And Skill", A L R Merrifield. Chapter from "Steel Roads of New Zealand" (p.111), G S Troup (ed.), Reed Books, 1973.
  30. The Ngatapa Branch Tunnels Mystery. P J R Dunford, 2010
  31. "BY RAIL TO NGATAPA. Poverty Bay Herald". paperspast.natlib.govt.nz. 13 December 1915. Retrieved 25 March 2023.
  32. "PUBLIC WORKS STATEMENT, BY THE HON. WILLIAM FRASER, MINISTER OF PUBLIC WORKS". paperspast.natlib.govt.nz. 1916. Retrieved 25 March 2023.
  33. Leitch D. & Scott B., 1995, ‘Exploring New Zealand’s Ghost Railways’, Grantham House Publishing, Wellington, New Zealand, ISBN   1-86934-048-5
  34. "GISBORNE-NGATAPA LINE. Poverty Bay Herald". paperspast.natlib.govt.nz. 13 December 1924. Retrieved 26 March 2023.
  35. 1 2 3 4 Leitch D. & Scott B., 1995, ‘Exploring New Zealand’s Ghost Railways’, Grantham House Publishing, Wellington, New Zealand, ISBN   1-86934-048-5
  36. "RAILWAYS STATEMENT BY THE MINISTER OF RAILWAYS, THE HON. W. A. VEITCH". paperspast.natlib.govt.nz. 1931. Retrieved 25 March 2023.
  37. 1 2 3 4 5 6 Scoble, Juliet. "Station Archive". Rail Heritage Trust of New Zealand.
  38. "Gisborne Times". paperspast.natlib.govt.nz. 1 July 1912. Retrieved 26 March 2023.
  39. "1:63360 map Sheet: N98 Gisborne". www.mapspast.org.nz. 1944. Retrieved 26 March 2023.
  40. 1 2 3 "PUBLIC WORKS STATEMENT, BY THE HON. WILLIAM FRASER, MINISTER OF PUBLIC WORKS". paperspast.natlib.govt.nz. 1916. Retrieved 25 March 2023.
  41. "KiwiRail Network Map". kiwirail.maps.arcgis.com. November 2018. Retrieved 25 March 2023.
  42. "Collections & Stories". E.C.M.o.T. 7 September 2016. Retrieved 26 March 2023.
  43. "Bushmere, Gisborne". NZ Topo Map. Retrieved 26 March 2023.
  44. "DISTRICTS NEEDS. Gisborne Times". paperspast.natlib.govt.nz. 4 October 1916. Retrieved 26 March 2023.
  45. "PUBLIC WORKS STATEMENT, BY THE HON. WILLIAM FRASER, MINISTER OF PUBLIC WORKS". paperspast.natlib.govt.nz. 1915. Retrieved 25 March 2023.
  46. New Zealand Railway and Tramway Atlas (First ed.). Quail Map Co. 1965. pp. 3 & 4.
  47. "Local and General. Gisborne Times". paperspast.natlib.govt.nz. 10 March 1914. Retrieved 25 March 2023.

Bibliography

  • Churchman, Geoffrey B; Hurst, Tony (2001) [1990, 1991]. The Railways of New Zealand: A Journey through History (Second ed.). Transpress New Zealand. ISBN   0-908876-20-3.
  • Leitch, David; Scott, Brian (1995). Exploring New Zealand's Ghost Railways (1998 ed.). Wellington: Grantham House. ISBN   1-86934-048-5.
  • Mulligan, Barbara (2000). New Zealand Rail Trails: A Guide to 42 Ghost Lines. Wellington: Grantham House Publishing. pp. 45, 46. ISBN   978-1-86934-126-8.