Mars Climate Orbiter

Last updated

Mars Climate Orbiter
Mars Climate Orbiter 2.jpg
Artist's conception of the Mars Climate Orbiter
NamesMars Surveyor '98 Orbiter
Mission type Mars orbiter
Operator NASA/JPL
COSPAR ID 1998-073A OOjs UI icon edit-ltr-progressive.svg
SATCAT no. 25571
Website science.nasa.gov
Mission duration286 days
Mission failure
Spacecraft properties
Manufacturer Lockheed Martin
Launch mass638 kilograms (1407 lb) [1]
Power500 watts
Start of mission
Launch dateDecember 11, 1998, 18:45:51 (1998-12-11UTC18:45:51Z) UTC
Rocket Delta II 7425
D-264
Launch site CCAFS SLC-17A
Contractor Boeing
End of mission
DisposalDestroyed
Last contact23 September 1999 09:06:00 (1999-09-23UTC09:07Z) UTC
Unintentionally deorbited
Orbital parameters
Reference system Areocentric
Epoch Planned
M98patch.png
Mars Surveyor 98 mission logo
MPL  

The Mars Climate Orbiter (formerly the Mars Surveyor '98 Orbiter) was a robotic space probe launched by NASA on December 11, 1998, to study the Martian climate, Martian atmosphere, and surface changes and to act as the communications relay in the Mars Surveyor '98 program for Mars Polar Lander. However, on September 23, 1999, communication with the spacecraft was permanently lost as it went into orbital insertion. The spacecraft encountered Mars on a trajectory that brought it too close to the planet, and it was either destroyed in the atmosphere or escaped the planet's vicinity and entered an orbit around the Sun. [2] An investigation attributed the failure to a measurement mismatch between two measurement systems: SI units (metric) by NASA and US customary units by spacecraft builder Lockheed Martin. [3]

Contents

Mission background

History

After the loss of Mars Observer and the onset of the rising costs associated with the future International Space Station, NASA began seeking less expensive, smaller probes for scientific interplanetary missions. In 1994, the Panel on Small Spacecraft Technology was established to set guidelines for future miniature spacecraft. The panel determined that the new line of miniature spacecraft should be under 1000 kg (2200 pounds) with highly focused instrumentation. [4] In 1995, a new Mars Surveyor program began as a set of missions designed with limited objectives, low costs, and frequent launches. The first mission in the new program was Mars Global Surveyor, launched in 1996 to map Mars and provide geologic data using instruments intended for Mars Observer. [5] Following Mars Global Surveyor, Mars Climate Orbiter carried two instruments, one originally intended for Mars Observer, to study the climate and weather of Mars.

The primary science objectives of the mission included: [6]

Spacecraft design

The Mars Climate Orbiter bus measured 2.1 meters (6 feet 11 inches) tall, 1.6 meters (5 feet 3 inches) wide and 2 meters (6 feet 7 inches) deep. The internal structure was largely constructed with graphite composite/aluminum honeycomb supports, a design found in many commercial airplanes. With the exception of the scientific instruments, battery and main engine, the spacecraft included dual redundancy on the most important systems. [6] [7] The spacecraft weighed 638-kilogram (1,407 lb). [1]

The spacecraft was 3-axis stabilized and included eight hydrazine monopropellant thrusters: four 22 N (4.9 lbf) thrusters to perform trajectory corrections and four 0.9 N (3.2 ozf) thrusters to control attitude. Orientation of the spacecraft was determined by a star tracker, two Sun sensors and two inertial measurement units. Orientation was controlled by firing the thrusters or using three reaction wheels. To perform the Mars orbital insertion maneuver, the spacecraft also included a LEROS 1B main engine rocket, [8] providing 640 N (140 lbf) of thrust by burning hydrazine fuel with nitrogen tetroxide (NTO) oxidizer. [6] [7]

The spacecraft included a 1.3-meter (4-foot-3-inch) high-gain antenna to transceive data with the Deep Space Network over the x band. The radio transponder designed for the Cassini–Huygens mission was used as a cost-saving measure. It also included a two-way UHF radio frequency system to relay communications with Mars Polar Lander upon an expected landing on December 3, 1999. [6] [7] [9]

The space probe was powered with a 3-panel solar array, providing an average of 500 W (0.67 hp) at Mars. Deployed, the solar array measured 5.5 meters (18 ft 1 in) in length. Power was stored in 12-cell, 16-amp-hour nickel-hydrogen batteries. The batteries were intended to be recharged when the solar array received sunlight and power the spacecraft as it passed into the shadow of Mars. When entering into orbit around Mars, the solar array was to be utilized in the aerobraking maneuver, to slow the spacecraft until a circular orbit was achieved. The design was largely adapted from guidelines from the Small Spacecraft Technology Initiative outlined in the book, Technology for Small Spacecraft. [6] [7] [4]

In an effort to simplify previous implementations of computers on spacecraft, Mars Climate Orbiter featured a single computer using an IBM RAD6000 processor utilizing a POWER1 ISA capable of 5, 10 or 20 MHz operation. Data storage was to be maintained on 128 MB of random-access memory (RAM) and 18 MB of flash memory. The flash memory was intended to be used for highly important data, including triplicate copies of the flight system software. [6]

Scientific instruments

Pressure Modulated Infrared Radiometer (PMIRR)
PMIRR diagram Mars Observer - PMIRR Diagram.png
PMIRR diagram

The Pressure Modulated Infrared Radiometer (PMIRR) uses narrow-band radiometric channels and two pressure modulation cells to measure atmospheric and surface emissions in the thermal infrared and a visible channel to measure dust particles and condensates in the atmosphere and on the surface at varying longitudes and seasons. [10] Its principal investigator was Daniel McCleese at JPL/CALTECH. Similar objectives were later achieved with Mars Climate Sounder on board Mars Reconnaissance Orbiter . Its objectives: [11]

Mars Color Imager (MARCI)
MARCI camera Mars Climate Orbiter - mco marci.jpg
MARCI camera

The Mars Color Imager (MARCI) is a two-camera (medium-angle/wide-angle) imaging system designed to obtain pictures of the Martian surface and atmosphere. Under proper conditions, resolutions up to 1 kilometer (3300 ft) are possible. [12] [13] The principal investigator on this project was Michael Malin at Malin Space Science Systems and the project was reincorporated on Mars Reconnaissance Orbiter .

Its objectives: [12]

Mission profile

Timeline of travel
DateTime
(UTC)
Event
Dec 11
1998
18:45:51Spacecraft launched
Sep 23
1999
08:41:00Insertion begins. Orbiter stows solar array.
08:50:00Orbiter turns to correct orientation to begin main engine burn.
08:56:00Orbiter fires pyrotechnic devices which open valves to begin pressurizing the fuel and oxidizer tanks.
09:00:46Main engine burn starts; expected to fire for 16 minutes 23 seconds.
09:04:52Communication with spacecraft lost
09:06:00Orbiter expected to enter Mars occultation, out of radio contact with Earth. [n 1]
09:27:00Expected to exit Mars occultation. [n 1]
Sep 25
1999
Mission declared a loss. Reason for loss known. No further attempts to contact.

Launch and trajectory

The Mars Climate Orbiter probe was launched on December 11, 1998, at 18:45:51 UTC by NASA from Space Launch Complex 17A at the Cape Canaveral Air Station in Florida, aboard a Delta II 7425 launch vehicle. The complete burn sequence lasted 42 minutes bringing the spacecraft into a Hohmann transfer orbit, sending the probe into a 9.5-month, 669 million km (416 million mi) trajectory. [6] [9] At launch, Mars Climate Orbiter weighed 638 kg (1407 lb) including propellant. [1]

Encounter with Mars

Mars Climate Orbiter began the planned orbital insertion maneuver on September 23, 1999, at 09:00:46 UTC. Mars Climate Orbiter went out of radio contact when the spacecraft passed behind Mars at 09:04:52 UTC, 49 seconds earlier than expected, and communication was never reestablished. Due to complications arising from human error, the spacecraft encountered Mars at a lower-than-anticipated altitude and it was either destroyed in the atmosphere or re-entered heliocentric space after leaving Mars' atmosphere. [2] Mars Reconnaissance Orbiter has since completed most of the intended objectives for this mission.

Cause of failure

The problem here was not the error; it was the failure of NASA's systems engineering, and the checks and balances in our processes, to detect the error. That's why we lost the spacecraft.

—Edward Weiler, NASA associate administrator for space science [14]

On November 10, 1999, the Mars Climate Orbiter Mishap Investigation Board released a Phase I report, detailing the suspected issues encountered with the loss of the spacecraft.

Previously, on September 8, 1999, Trajectory Correction Maneuver-4 (TCM-4) was computed, and was then executed on September 15, 1999. It was intended to place the spacecraft at an optimal position for an orbital insertion maneuver that would bring the spacecraft around Mars at an altitude of 226 km (140 miles) on September 23, 1999.

However, during the week between TCM-4 and the orbital insertion maneuver, the navigation team reported that it appeared the insertion altitude could be much lower than planned, at about 150 to 170 km (93 to 106 miles). Twenty-four hours prior to orbital insertion, calculations placed the orbiter at an altitude of 110 km (68 miles). 80 km (50 miles) was the minimum altitude that Mars Climate Orbiter was thought to be capable of surviving during this maneuver.

During insertion, the orbiter was intended to skim through Mars' upper atmosphere, gradually aerobraking for weeks, but post-failure calculations showed that the spacecraft's trajectory would have taken it within 57 km (35 miles) of the surface. At this altitude, the spacecraft would likely have skipped violently off the denser-than-expected atmosphere,[ citation needed ] and it was either destroyed in the atmosphere, or re-entered heliocentric space. [2]

The primary cause of this discrepancy was that one piece of ground software supplied by Lockheed Martin produced results in a United States customary unit, contrary to its Software Interface Specification (SIS), while a second system, supplied by NASA, expected those results to be in SI units, in accordance with the SIS. Specifically, software that calculated the total impulse produced by thruster firings produced results in pound-force seconds. The trajectory calculation software then used these results – expected to be in newton-seconds (incorrect by a factor of 4.45) [2] – to update the predicted position of the spacecraft. [2]

Still, NASA does not place the responsibility on Lockheed for the mission loss; instead, various officials at NASA have stated that NASA itself was at fault for failing to make the appropriate checks and tests that would have caught the discrepancy. [14]

The discrepancy between calculated and measured position, resulting in the discrepancy between desired and actual orbit insertion altitude, had been noticed earlier by at least two navigators, whose concerns were dismissed because they "did not follow the rules about filling out [the] form to document their concerns". A meeting of trajectory software engineers, trajectory software operators (navigators), propulsion engineers, and managers was convened to consider the possibility of executing Trajectory Correction Maneuver-5, which was in the schedule. Attendees of the meeting recall an agreement to conduct TCM-5, but it was ultimately not done. [14]

Project costs

According to NASA, the cost of the mission was $327.6 million ($571.41 million in 2023) [15] total for the orbiter and lander, comprising $193.1 million ($336.81 million in 2023) [15] for spacecraft development, $91.7 million ($159.95 million in 2023) [15] for launching it, and $42.8 million ($74.65 million in 2023) [15] for mission operations. [7]

See also

Notes

  1. 1 2 Planned but unaccounted for event.

Related Research Articles

<i>Mars Observer</i> Failed NASA orbiter mission to Mars (1992–1993)

The Mars Observer spacecraft, also known as the Mars Geoscience/Climatology Orbiter, was a robotic space probe launched by NASA on September 25, 1992, to study the Martian surface, atmosphere, climate and magnetic field. On August 21, 1993, during the interplanetary cruise phase, communication with the spacecraft was lost, three days prior to the probe's orbital insertion. Attempts to re-establish communications with the spacecraft were unsuccessful.

<span class="mw-page-title-main">Aerobraking</span> Spaceflight maneuver

Aerobraking is a spaceflight maneuver that reduces the high point of an elliptical orbit (apoapsis) by flying the vehicle through the atmosphere at the low point of the orbit (periapsis). The resulting drag slows the spacecraft. Aerobraking is used when a spacecraft requires a low orbit after arriving at a body with an atmosphere, as it requires less fuel than using propulsion to slow down.

<i>Mars Global Surveyor</i> NASA orbiter mission to Mars (1996–2006)

Mars Global Surveyor (MGS) was an American robotic space probe developed by NASA's Jet Propulsion Laboratory and launched November 1996. MGS was a global mapping mission that examined the entire planet, from the ionosphere down through the atmosphere to the surface. As part of the larger Mars Exploration Program, Mars Global Surveyor performed atmospheric monitoring for sister orbiters during aerobraking, and helped Mars rovers and lander missions by identifying potential landing sites and relaying surface telemetry.

<i>Magellan</i> (spacecraft) NASA orbiter mission to Venus (1989–1994)

The Magellan spacecraft was a 1,035-kilogram (2,282 lb) robotic space probe launched by NASA on May 4, 1989. Its mission objectives were to map the surface of Venus by using synthetic-aperture radar and to measure the planetary gravitational field.

<span class="mw-page-title-main">Mars Polar Lander</span> Failed NASA Mars lander (1999)

The Mars Polar Lander, also known as the Mars Surveyor '98 Lander, was a 290-kilogram robotic spacecraft lander launched by NASA on January 3, 1999, to study the soil and climate of Planum Australe, a region near the south pole on Mars. It formed part of the Mars Surveyor '98 mission. On December 3, 1999, however, after the descent phase was expected to be complete, the lander failed to reestablish communication with Earth. A post-mortem analysis determined the most likely cause of the mishap was premature termination of the engine firing prior to the lander touching the surface, causing it to strike the planet at a high velocity.

<span class="mw-page-title-main">Mars Surveyor '98</span> Canceled NASA spaceflight mission in the Mars Exploration Program

Mars Surveyor '98 was a mission in NASA's Mars Exploration Program that launched the Mars Climate Orbiter and the Mars Polar Lander to the planet Mars. The mission was to study the Martian weather, climate, water and carbon dioxide (CO2) budget, to understand the reservoirs, behavior, and atmospheric role of volatiles and to search for evidence of long-term and episodic climate changes. The Mars Polar Lander also carried two surface-penetrator probes for the New Millennium Program's Deep Space 2 mission. Both spacecraft were launched in 1998 and both were lost.

<span class="mw-page-title-main">Exploration of Mars</span>

The planet Mars has been explored remotely by spacecraft. Probes sent from Earth, beginning in the late 20th century, have yielded a large increase in knowledge about the Martian system, focused primarily on understanding its geology and habitability potential. Engineering interplanetary journeys is complicated and the exploration of Mars has experienced a high failure rate, especially the early attempts. Roughly sixty percent of all spacecraft destined for Mars failed before completing their missions, with some failing before their observations could begin. Some missions have been met with unexpected success, such as the twin Mars Exploration Rovers, Spirit and Opportunity, which operated for years beyond their specification.

<i>Nozomi</i> (spacecraft) Failed Japanese orbiter mission to Mars (1998–2003)

Nozomi was a Japanese Mars orbiter that failed to reach Mars due to electrical failure. It was constructed by the Institute of Space and Astronautical Science, University of Tokyo and launched on July 4, 1998, at 03:12 JST with an on-orbit dry mass of 258 kg and 282 kg of propellant. The Nozomi mission was terminated on December 31, 2003.

<span class="mw-page-title-main">Mars 96</span> Failed Mars mission

Mars 96 was a failed Mars mission launched in 1996 to investigate Mars by the Russian Space Forces and not directly related to the Soviet Mars probe program of the same name. After failure of the second fourth-stage burn, the probe assembly re-entered the Earth's atmosphere, breaking up over a 320 km (200 mi) long portion of the Pacific Ocean, Chile, and Bolivia. The Mars 96 spacecraft was based on the Phobos probes launched to Mars in 1988. They were of a new design at the time and both ultimately failed. For the Mars 96 mission the designers believed they had corrected the flaws of the Phobos probes, but the value of their improvements was never demonstrated due to the destruction of the probe during the launch phase.

<i>MESSENGER</i> NASA mission to Mercury

MESSENGER was a NASA robotic space probe that orbited the planet Mercury between 2011 and 2015, studying Mercury's chemical composition, geology, and magnetic field. The name is a backronym for "Mercury Surface, Space Environment, Geochemistry, and Ranging", and a reference to the messenger god Mercury from Roman mythology.

<i>Mars Reconnaissance Orbiter</i> NASA spacecraft active since 2005

The Mars Reconnaissance Orbiter (MRO) is a spacecraft designed to search for the existence of water on Mars and provide support for missions to Mars, as part of NASA's Mars Exploration Program. It was launched from Cape Canaveral on August 12, 2005, at 11:43 UTC and reached Mars on March 10, 2006, at 21:24 UTC. In November 2006, after six months of aerobraking, it entered its final science orbit and began its primary science phase.

<i>Venus Express</i> European orbiter mission to Venus (2005–2015)

Venus Express (VEX) was the first Venus exploration mission of the European Space Agency (ESA). Launched in November 2005, it arrived at Venus in April 2006 and began continuously sending back science data from its polar orbit around Venus. Equipped with seven scientific instruments, the main objective of the mission was the long term observation of the Venusian atmosphere. The observation over such long periods of time had never been done in previous missions to Venus, and was key to a better understanding of the atmospheric dynamics. ESA concluded the mission in December 2014.

<span class="mw-page-title-main">Aerocapture</span> Orbital transfer maneuver

Aerocapture is an orbital transfer maneuver in which a spacecraft uses aerodynamic drag force from a single pass through a planetary atmosphere to decelerate and achieve orbit insertion.

In spaceflight an orbit insertion is an orbital maneuver which adjusts a spacecraft’s trajectory, allowing entry into an orbit around a planet, moon, or other celestial body. An orbit insertion maneuver involves either deceleration from a speed in excess of the respective body's escape velocity, or acceleration to it from a lower speed.

<span class="mw-page-title-main">Timeline of Mars Reconnaissance Orbiter</span>

Timeline for the Mars Reconnaissance Orbiter (MRO) lists the significant events of the launch, aerobraking, and transition phases as well as subsequent significant operational mission events; by date and brief description.

<span class="mw-page-title-main">Trace Gas Orbiter</span> Mars orbiter, part of ExoMars programme

The ExoMars Trace Gas Orbiter is a collaborative project between the European Space Agency (ESA) and the Russian Roscosmos agency that sent an atmospheric research orbiter and the Schiaparelli demonstration lander to Mars in 2016 as part of the European-led ExoMars programme.

<span class="mw-page-title-main">Mars Orbiter Mission</span> Indian orbiter mission to Mars (2013–2022)

The Mars Orbiter Mission (MOM), unofficially known as Mangalyaan, was a space probe orbiting Mars since 24 September 2014. It was launched on 5 November 2013 by the Indian Space Research Organisation (ISRO). It was India's first interplanetary mission and it made ISRO the fourth space agency to achieve Mars orbit, after Soviet space program, NASA, and the European Space Agency. It made India the first Asian nation to reach Martian orbit and the second national space agency in the world to do so on its maiden attempt after the European Space Agency did in 2003. It also made India the fourth nation to orbit another planet after the United States, the Soviet Union, and ESA member states.

<i>Schiaparelli</i> EDM Mars landing demonstration system

Schiaparelli EDM was a failed Entry, Descent, and Landing Demonstrator Module (EDM) of the ExoMars programme—a joint mission of the European Space Agency (ESA) and the Russian Space Agency Roscosmos. It was built in Italy and was intended to test technology for future soft landings on the surface of Mars. It also had a limited but focused science payload that would have measured atmospheric electricity on Mars and local meteorological conditions.

<span class="mw-page-title-main">Emirates Mars Mission</span> Space exploration probe mission to Mars

The Emirates Mars Mission is a United Arab Emirates Space Agency uncrewed space exploration mission to Mars. The Hope probe was launched on 20 July 2020, and went into orbit around Mars on 9 February 2021.

References

  1. 1 2 3 "1998 MARS CLIMATE ORBITER ARRIVES AT NASA'S KENNEDY SPACE CENTER FOR FINAL LAUNCH PREPARATIONS" (Press release). NASA. September 14, 1998. Archived from the original on October 8, 1999. Retrieved January 3, 2011.
  2. 1 2 3 4 5 Arthur G. Stephenson; Lia S. LaPiana; Daniel R. Mulville; Peter J. Rutledge; Frank H. Bauer; David Folta; Greg A. Dukeman; Robert Sackheim; Peter Norvig (November 10, 1999). Mars Climate Orbiter Mishap Investigation Board Phase I Report (PDF). NASA. Archived (PDF) from the original on January 23, 2020. Retrieved May 11, 2021.
  3. Robin Lloyd (September 30, 1999). "Metric mishap caused loss of NASA orbiter". CNN . Archived from the original on October 24, 2019. Retrieved March 21, 2016.
  4. 1 2 Panel on Small Spacecraft Technology, National Research Council (1994). Technology for Small Spacecraft. Washington D.C.: National Academy Press. pp. 6, 121–123. ISBN   0-309-05075-8. Archived from the original on June 29, 2024. Retrieved January 13, 2011.
  5. Committee on Planetary and Lunar Exploration, Commission on Physical Sciences, Mathematics, and Applications, National Research Council (1995). The Role of Small Missions in Planetary and Lunar Exploration. Washington D.C.: National Academies Press. doi:10.17226/12285. hdl:2060/19960002222. ISBN   978-0-309-12250-4. S2CID   219866579. Archived from the original on October 17, 2012. Retrieved January 13, 2011.{{cite book}}: CS1 maint: multiple names: authors list (link)
  6. 1 2 3 4 5 6 7 "Mars Climate Orbiter Arrival Press Kit" (PDF) (Press release). NASA. September 1999. Archived from the original (PDF) on March 12, 2011. Retrieved January 13, 2011.
  7. 1 2 3 4 5 "Mars Climate Orbiter". science.nasa.gov. NASA. Archived from the original on June 29, 2024. Retrieved August 3, 2020.
  8. "LEROS 1B". Archived from the original on September 3, 2011.
  9. 1 2 "1998 Mars Missions Press Kit" (PDF) (Press release). NASA. December 1998. Archived from the original (PDF) on April 30, 2020. Retrieved January 13, 2011.
  10. "Pressure Modulated Infrared Radiometer (PMIRR)". nssdc.gsfc.nasa.gov. NASA. Archived from the original on April 14, 2020. Retrieved February 19, 2011.
  11. Arden L. Albee (1988). "Workshop on Mars Sample Return Science". Mars Sample Return Science. Lunar and Planetary Institute: 25–29. Bibcode:1988msrs.work...25A.
  12. 1 2 M. C. Malin; J. F. Bell, III; W. M. Calvin; M. A. Caplinger; R. T. Clancy; R. M. Harberle; et al. (2001). "Mars Color Imager (MARCI) on the Mars Climate Orbiter" (PDF). Journal of Geophysical Research. 106 (E8): 17, 651–17, 672. Bibcode:2001JGR...10617651M. doi:10.1029/1999JE001145. Archived (PDF) from the original on January 23, 2020. Retrieved January 13, 2011.
  13. "Mars Color Imager (MARCI)". nssdc.gsfc.nasa.gov. NASA. Archived from the original on April 14, 2020. Retrieved February 19, 2011.
  14. 1 2 3 James Oberg (December 1, 1999). "Why the Mars Probe went off course". IEEE . Archived from the original on February 5, 2023. Retrieved July 13, 2016.
  15. 1 2 3 4 Johnston, Louis; Williamson, Samuel H. (2023). "What Was the U.S. GDP Then?". MeasuringWorth . Retrieved November 30, 2023. United States Gross Domestic Product deflator figures follow the MeasuringWorth series.