Queensferry Crossing

Last updated

Queensferry Crossing
Queensferry Crossing - geograph.org.uk - 5539383.jpg
The Queensferry Crossing, 2017
Coordinates 56°00′17″N3°24′45″W / 56.0046°N 3.4124°W / 56.0046; -3.4124
CarriesUK-Motorway-M90.svg M90
Crosses Firth of Forth
Locale Edinburgh and Fife, Scotland
Characteristics
Design Cable-stayed bridge
Total length2,700 metres (8,858 ft)
Longest span650 metres (2,133 ft)
No. of lanes Dual two-lane carriageway with hard shoulders [1]
History
Constructed byForth Crossing Bridge Constructors (FCBC)
Construction startSeptember 2011
Construction end27 August 2017
Construction cost£1.35 billion
Opened30 August 2017 (2017-08-30)
Inaugurated4 September 2017 (2017-09-04)
Location
Queensferry Crossing

The Queensferry Crossing (formerly the Forth Replacement Crossing) is a road bridge in Scotland. It was built alongside the existing Forth Road Bridge and the Forth Bridge. It carries the M90 motorway across the Firth of Forth between Edinburgh, at South Queensferry, and Fife, at North Queensferry.

Contents

Forth Crossing Act 2011
Act of the Scottish Parliament
Coat of Arms of the United Kingdom in Scotland (Variant 1).svg
Long title An Act of the Scottish Parliament to give the Scottish Ministers power to construct a new bridge over the Firth of Forth and to construct and improve associated roads and structures; to authorise the acquisition, or temporary possession and use, of land for construction and improvement works; and for connected purposes.
Citation 2011 asp 2
Dates
Royal assent 20 January 2011
Status: Current legislation
Text of the Forth Crossing Act 2011 as in force today (including any amendments) within the United Kingdom, from legislation.gov.uk.

Proposals for a second Forth Road crossing, to meet unexpected demand, were first put forward in the 1990s, but no action was taken until structural issues were discovered in the Forth Road Bridge in 2004. In 2006–07 Transport Scotland carried out a study, and in December 2007 decided to proceed with a replacement bridge. The following year it was announced that the existing bridge would be retained as a public transport link. The Forth Crossing Act received royal assent in January 2011. [2] In April 2011, the Forth Crossing Bridge Constructors consortium was awarded the contract, and construction began in late summer/autumn of 2011. [3]

The Queensferry Crossing is a three-tower cable-stayed bridge, with an overall length of 1.7 miles (2.7 kilometres). [4] Around 2.5 miles (4 kilometres) of new connecting roads were built, [5] including new and upgraded junctions at Ferrytoll in Fife, South Queensferry and Junction 1A on the M9.

The bridge was first due to be completed by December 2016, but this deadline was extended to August 2017 after several delays. [6] It is the third bridge across the Forth at Queensferry, alongside the Forth Road Bridge completed in 1964, and the Forth Rail Bridge completed in 1890. Following a public vote, it was formally named on 26 June 2013 and opened to traffic on 30 August 2017. The bridge was formally opened on 4 September 2017 by Queen Elizabeth II, fifty-three years to the day after she opened the adjacent Forth Road Bridge. [7]

Background

A crossing route over the Forth had existed at the site since the eleventh century, when the queen of Scotland, Margaret, founded a free ferry to take pilgrims north to St Andrews. [8] The site of the ferry crossing became the location of the Forth Road Bridge, which opened in 1964. Proposals for an additional road crossing at Queensferry were drawn up in the early 1990s, as part of the "Setting Forth" consultation document prepared by the Scottish Office. [9] The plans met stiff opposition from environmentalists and from the City of Edinburgh Council on the grounds of increased traffic. Following the Labour victory in the 1997 general election, the proposals were shelved. [10]

An inspection of the integrity of the cables under way on the Forth Road Bridge Forth Road Bridge cable inspection.jpg
An inspection of the integrity of the cables under way on the Forth Road Bridge

The existing bridge had a planned design life of 120 years, [11] but by the early years of the 21st century the planned theoretical capacity for the bridge was being routinely exceeded. It was designed for up to 11 million vehicles per year, but this had risen steadily to 23 million vehicles in 2006. [12] Between 2003 and 2005, an inspection programme found that the main suspension cables had suffered an estimated 8–10% loss of strength as a result of corrosion. Projections highlighted the likelihood of an accelerating loss of strength, with traffic restrictions to limit loading required in 2014 in the worst-case scenario. [13] In 2006-2007 Transport Scotland carried out a study to examine the options and in December 2007, the decision was made to proceed with a replacement bridge. [14]

The strategic transport importance of the road bridge, and the threat of closure by 2019 if major structural work was not successful, led to fears of serious economic consequences, especially as work on a new crossing was estimated to take up to 11 years. [15] Scottish Transport Minister Nicol Stephen commissioned a new study, which priced a second Forth Road Bridge at £300 million, in 2003. [10] The Forth Estuary Transport Authority voiced support for a new bridge in 2005, [16] and in 2006 the UK Transport Secretary, Alistair Darling, spoke in favour of the idea. [17]

Planning

In 2007, the Forth Replacement Crossing Study was commissioned by Transport Scotland to examine various options for new bridges or tunnels across the Forth. [18] The report recommended adoption of a cable-stayed bridge, located to the west of the Forth Road Bridge, as the preferred solution. The study concluded that this option was significantly cheaper than a tunnel, would take less time to construct, and would represent better value for money, though it was noted that a tunnel would have fewer environmental impacts. [19] In December 2007 finance secretary John Swinney announced that a new cable-stayed bridge would be constructed, with an estimated cost of between £3.25 billion and £4.22 billion. He claimed it would be "the largest construction project in a generation in Scotland". [20]

There was opposition to the project on environmental, traffic and cost grounds. The ForthRight Alliance, an umbrella group including Friends of the Earth, the Scottish Green Party, the RSPB, sustainable transport groups and other local organisations, opposed the scheme since 1994, [21] and presented arguments that the Forth Road crossing could be repaired and maintained. [22] [23] Another group, Forth Tunnel Action Group, campaigned for a tunnel as the solution with lowest costs and fewest long-term environmental impacts. [24]

It was initially suggested that the new bridge would be funded via the Scottish Futures Trust, an alternative to public-private partnership funding for major public-sector schemes. However, the Scottish Government announced in December 2008 that public funding would be used. [25] As part of the Scottish Government's Strategic Transport Projects Review, the new Forth crossing was priced at between £1.72 billion and £2.34 billion. [26] Under the revised scheme, the existing bridge will be retained for public transport, cyclists and pedestrians, and the new bridge was to be operational by 2016. [25]

A joint venture between consultancies Arup and Jacobs was appointed as project manager, and in February 2008 environmental and technical studies were begun, continuing through 2009. Public consultations were held, and some changes to the scheme were made in response to the comments received. [27] An environmental statement was published in November 2009, [28] coinciding with the introduction of the Forth Crossing Bill into the Scottish Parliament by John Swinney. A majority of MSPs voted in favour of the new legislation on 16 December 2010, [29] and the Forth Crossing Act received royal assent in January 2011. [30]

Bidding process

The Queensferry Crossing (left) in relation to the Forth Road Bridge (centre) and the Forth Bridge (right) Forth Replacement Crossing map.png
The Queensferry Crossing (left) in relation to the Forth Road Bridge (centre) and the Forth Bridge (right)

In 2009, Transport Scotland solicited for tenders to construct the proposed bridge. [31] Although Transport Scotland received 39 expressions of interest, concerns over the risks associated with the fixed-price contract resulted in only two consortia of large construction companies bidding. [32] Due to the bidders' concerns that the bidding process itself would prove to be an expensive proposition, the Scottish Government allocated £10 million to defray the bidders' costs during the full bidding process, should the project be abandoned. [32]

The two consortia were Forthspan, which included Morgan Sindall, BAM Nuttall and Balfour Beatty; and Forth Crossing Bridge Constructors (FCBC), which consists of Dragados, Hochtief, American Bridge, and Morrison Construction. [33] Bids for the main contract, priced at between £900 million and £1.2 billion, and including design and construction of the bridge and approach roads, [33] were submitted in January 2011. [31] In March 2011 the Scottish Government announced FCBC as preferred bidder, with a bid of £790 million. [34] [35] Ramboll is leading the Design Joint Venture which includes Sweco and Leonhardt Andra and Partners. [36]

In addition to the main contract, two smaller contracts form part of the scheme. The contract to implement the Intelligent Transport System (ITS) traffic management system in Fife was awarded to John Graham (Dromore) Ltd, with a tender of £12.9 million, while the upgrade of M9 Junction 1a was awarded to a joint venture between John Sisk and Roadbridge, with a tender of £25.6 million. As with the main contract, the tenders received were below the original estimated budgets. [37] [38] Naeem Hussain, Global Bridge Design Practice Leader at Arup, was the lead design engineer for the project. [39]

Construction

Queensferry Crossing under construction in August 2016 Queensferry Crossing Aug 2016.jpg
Queensferry Crossing under construction in August 2016

Preparatory works for the new bridge began in September 2011 with works beginning at the southern end of the M90 to build the northern approach roads. 149 segments of bridge deck, each of which is 12 metres (39 ft) long and 40 metres (130 ft) wide, were constructed in China and Spain, then delivered by sea in October 2013. [40] The approach steel bridge sections were manufactured by Cleveland Bridge & Engineering Company in Darlington. [41]

The towers reached 160 metres (525 ft) in height in August 2015, making it the UK's tallest bridge. [42] The completed towers stand at 207 metres (679 ft). [42]

On 28 April 2016, one construction worker was killed and another injured in an accident involving a crane. Work on the bridge was halted to allow an investigation to take place. [43] [44]

The bridge was due to be completed by December 2016, but that date was put back to May 2017 due to weather delays slowing construction, [45] with 25 days lost due to high winds during April and May 2016. [46] An additional delay was announced in March 2017 as a result of high winds, making work on the structure difficult and unsafe for workers. [47] The opening of the bridge was pushed back to the summer of 2017 as a result of "adverse weather conditions" delaying work on the bridge. [48]

The bridge opened on 30 August 2017 and was formally opened by Queen Elizabeth II on 4 September 2017. [49]

The bridge

The Beamer Rock, prior to removal of the lighthouse to make way for the bridge Beamer Rock - geograph.org.uk - 1320903.jpg
The Beamer Rock, prior to removal of the lighthouse to make way for the bridge

The bridge is a cable-stayed structure, with three towers each 207 metres (679 ft) high. [40] Including approaches, the overall length of the bridge is 1.7 miles (2.7 kilometres); at opening, it was the longest triple tower cable-stayed bridge in the world. [50] The bridge carries motorcycles, cars and heavy goods vehicles, while public transport, cyclists and pedestrians use the Forth Road Bridge. Wind shielding has been built into the design, to enable use of the bridge in high winds, which often led to restrictions on the old bridge. [1] [51] The bridge was closed for the first time on 11 February 2020, 30 months after opening, due to accumulations of ice on the towers. [52] Some of the ice then fell onto the carriageway, which damaged eight vehicles and prompted the closure. [52]

The bridge is the third crossing of the Forth at Queensferry, alongside the Forth Road Bridge, completed in 1964, and the Forth Bridge, a railway bridge completed in 1890. It is sited west of the road bridge, with the northern landfall at St Margaret's Hope, between Rosyth Dockyard and North Queensferry and the southern landfall just west of Port Edgar in South Queensferry. The central tower was constructed on the Beamer Rock, a small islet in the Forth. [53]

The project was known as the Forth Replacement Crossing, and a name for the new bridge was selected in a public vote in 2013 after a panel of independent advisers provided a shortlist of possible names. [54] [55] Five names were shortlisted: Caledonia Bridge, Firth of Forth Crossing, Queensferry Crossing, Saltire Crossing and St Margaret's Crossing. A public vote was held up until 7 June 2013 and the name Queensferry Crossing received the most votes: 12,039 out of 37,000 (32%). [56]

Connecting roads

The Queensferry Crossing in 2024 Queensferry Crossing (Nouveau pont du Forth).jpg
The Queensferry Crossing in 2024

Several new and upgraded roads connect the bridge into the existing road network with around 2.5 miles (4 kilometres) of new roads constructed. These new roads join the M9 and M90 motorways together for the first time, with the Queensferry Crossing being built to motorway standard in order to carry the M90 across the Forth. The M90 motorway previously terminated at Admiralty Junction, around 1.9 miles (3 kilometres) north of the current Forth Road Bridge, with the road continuing as all-purpose dual carriageway across the existing bridge and joining the M9 via the M9 Spur. [57] [58]

Admiralty

Admiralty Junction, previously Junction 1 of the M90 motorway remains unaltered, with the exception of a bus lane added on the southbound carriageway. The junction was renumbered to Junction 1C of the M90 when the Queensferry Crossing opened. [58]

Ferrytoll Junction

Ferrytoll Junction was redesigned to give access to the new crossing and to maintain public transport access to the Forth Road Bridge. The design of the new junction required the realignment of the B981 road to North Queensferry. [59] Ferrytoll Junction was numbered Junction 1B of the M90 following completion of the Queensferry Crossing. [58]

South Queensferry Junction

The Southern Approach to the M90 towards the Queensferry Crossing M90 - Southern Approach to the Queensferry Crossing - geograph.org.uk - 5539369.jpg
The Southern Approach to the M90 towards the Queensferry Crossing

The M90 was extended west from the existing bridge access at Ferry Muir, wrapping around South Queensferry to the southern landfall of the new crossing. A grade-separated junction was built on the A904 just west of Echline, at the south-west edge. The existing access from the Forth Road Bridge to the A90 remains open to public transport. [60] South Queensferry Junction became Junction 1A of the M90 when the Queensferry Crossing opened. [58]

M9 Junction 1a

Junction 1a provides access from the M9 to the Forth Road Bridge and Queensferry Crossing via the M9 Spur, which was renumbered as M90 upon completion of the Queensferry Crossing. Originally, only east-facing connections were provided to the M9, forcing traffic heading west from the bridge onto the A904 through the village of Newton in West Lothian. The upgrade of the junction included new west-facing slip roads, enabling direct access onto the M9 from the Forth Road Bridge and the new crossing, as well as the widening of the existing connections to assist the flow of traffic at peak times. [61] The improvements were completed in February 2013 at a cost of £25.6m. [62] The junction connecting the A90 / M90 at the southern end of the bridges with the A90 towards Edinburgh city centre and the M90 extension is named the Scotstoun Junction and is numbered as Junction 1 of the M90. [58]

Intelligent Transport System

An "Intelligent transportation system" (ITS) was installed between Halbeath on the M90, and the M9, covering the whole scheme. The ITS is an active traffic management, enabling variable speed restrictions and lane closures to be displayed on overhead gantries. [58]

Archaeological finds

During routine archaeological excavations by Headland Archaeology in advance of work on the new bridge, archaeological deposits from the Mesolithic were found on both sides of the Forth. [63]

On the northern side two post-built structures and their surrounding pits were found, and dated to the mid to late Mesolithic period.

On the south bank in a field at Echline the remnants of a sunken floor structure with in situ floor deposits were found. The structure, based around an oval pit approximately 7 metres (23 ft) in length, contained the remains of a hearth, stone tools, and bone from a variety of animals. Radiocarbon analysis gave a date of c.8300, about 1000 years older than the northern site, making it the earliest known dwelling in Scotland. Additionally three isolated Neolithic pits and a Bronze Age pit group and pit alignment were identified. [64] [65]

See also

Related Research Articles

<span class="mw-page-title-main">Forth Road Bridge</span> Suspension bridge spanning the Firth of Forth in east-central Scotland

The Forth Road Bridge is a suspension bridge in east central Scotland. The bridge opened in 1964 and at the time was the longest suspension bridge in the world outside the United States. The bridge spans the Firth of Forth, connecting Edinburgh, at South Queensferry, to Fife, at North Queensferry. It replaced a centuries-old ferry service to carry vehicular traffic, cyclists and pedestrians across the Forth; railway crossings are made by the nearby Forth Bridge, opened in 1890.

<span class="mw-page-title-main">A9 road (Scotland)</span> Major road in Scotland

The A9 is a major road in Scotland running from the Falkirk council area in central Scotland to Scrabster Harbour, Thurso in the far north, via Stirling, Bridge of Allan, Perth and Inverness. At 273 miles (439 km), it is the longest road in Scotland and the fifth-longest A-road in the United Kingdom. Historically it was the main road between Edinburgh and John o' Groats, and has been called the spine of Scotland. It is one of the three major north–south trunk routes linking the Central Belt to the Highlands – the others being the A82 and the A90.

<span class="mw-page-title-main">M8 motorway (Scotland)</span> Busiest motorway in Scotland

The M8 is the busiest motorway in Scotland. It connects the country's two largest cities, Glasgow and Edinburgh, and serves other large communities including Airdrie, Coatbridge, Greenock, Livingston and Paisley. The motorway is 60 miles (97 km) long. A major construction project to build the final section between Newhouse and Baillieston was completed on 30 April 2017. The motorway has one service station, Heart of Scotland Services, previously named Harthill due to its proximity to the village.

<span class="mw-page-title-main">A90 road</span> Road in Scotland between Edinburgh and Fraserburgh via Dundee and Aberdeen

The A90 road is a major north-to-south road in eastern Scotland, running from Edinburgh to Fraserburgh, through Dundee and Aberdeen. Along with the A9 and the A82 it is one of the three major north–south trunk roads connecting the Central Belt to northern destinations. The A90 is not continuous, separated between Dalmeny and Perth by the M90.

<span class="mw-page-title-main">M9 motorway (Scotland)</span> Motorway in Scotland

The M9 is a major motorway in Scotland. It runs from the outskirts of Edinburgh, bypassing the towns of Linlithgow, Falkirk, Grangemouth and Stirling to end at Dunblane.

<span class="mw-page-title-main">River Forth</span> River in central Scotland

The River Forth is a major river in central Scotland, 47 km (29 mi) long, which drains into the North Sea on the east coast of the country. Its drainage basin covers much of Stirlingshire in Scotland's Central Belt. The Gaelic name for the upper reach of the river, above Stirling, is Abhainn Dubh, meaning "black river". The name for the river below the tidal reach is Uisge For.

<span class="mw-page-title-main">M90 motorway</span> Motorway in Scotland

The M90 is a motorway in Scotland. It runs from Junction 1A of the M9 motorway, south of the Queensferry Crossing, to Perth. It is the northernmost motorway in the United Kingdom. The northern point goes to the western suburbs of Perth at Broxden. A small part of the M90 was originally numbered as the M85 motorway.

<span class="mw-page-title-main">Rosyth</span> Port town in Scotland

Rosyth is a town and Garden City in Fife, Scotland, on the coast of the Firth of Forth.

<span class="mw-page-title-main">M80 motorway</span> Motorway in Scotland

The M80 is a motorway in Scotland's central belt, running between Glasgow and Stirling via Cumbernauld and Denny and linking the M8, M73 and M9 motorways. Following completion in 2011, the motorway is 25 miles (40 km) long. Despite being only a two lane motorway, parts of the M80 Stepps Bypass are used by around 60,000 vehicles per day.

<span class="mw-page-title-main">Edinburgh City Bypass</span> Road in Scotland

The Edinburgh City Bypass, designated as A720, is one of the most important trunk roads in Scotland. Circling around the south of Edinburgh, as the equivalent of a ring road for the coastal city, it links together the A1 towards north-east England, the A702 towards north-west England, the M8 through the Central Belt towards Glasgow, the A7 through south-east Scotland and north-west England as well as the A8 leading to the M9 for Stirling and the Queensferry Crossing.

<span class="mw-page-title-main">Stagecoach East Scotland</span> Bus operator in East Scotland

Stagecoach East Scotland is a bus operator providing services in eastern Scotland, with its regional base in Dunfermline, Fife. The company is a subsidiary of the Stagecoach Group.

<span class="mw-page-title-main">Friarton Bridge</span> Bridge in Perth, Scotland

The Friarton Bridge is a steel box girder bridge with a concrete deck, across the River Tay on the southeastern outskirts of Perth, Scotland. It is located approximately 20 miles (32 km) upstream of the Tay Road Bridge.

The Forth Estuary Transport Authority (FETA) was the authority responsible for the maintenance of the Forth Road Bridge over the Firth of Forth in eastern central Scotland. FETA was created in 2001 by the Transport (Scotland) Act 2001 - to replace the Forth Road Bridge Joint Board.

<span class="mw-page-title-main">Transport in Edinburgh</span> Overview of the transport system in Edinburgh

Edinburgh is a major transport hub in east central Scotland and is at the centre of a multi-modal transport network with road, rail and air communications connecting the city with the rest of Scotland and internationally.

<span class="mw-page-title-main">A494 road</span> Road in Great Britain

The A494 is a trunk road in Wales and England. The route, which is officially known as the Dolgellau to South of Birkenhead Trunk Road, runs between the terminus of the M56 motorway between Mollington and Capenhurst and the A470 at Dolgellau, Gwynedd. Its northern sections remain among the busiest roads in Wales.

The B800 is a short road in eastern Scotland, connecting the Forth Road Bridge to Kirkliston. It is a two-way single carriageway road.

<span class="mw-page-title-main">Aberdeen Western Peripheral Route</span> Road in Scotland

The Aberdeen Western Peripheral Route (AWPR), unofficially also the City of Aberdeen Bypass, is a major road that wraps around the city of Aberdeen, Scotland. The road stretches north from Stonehaven through Kincardineshire and crosses both the River Dee and River Don before terminating at Blackdog. The main stretch of the AWPR is 22 miles (35 km) in length.

<span class="mw-page-title-main">Newton, West Lothian</span> Human settlement in Scotland

Newton or is a small village in the county of West Lothian, Scotland. It lies on the A904 trunk road 2.6 miles (4.2 km) west of South Queensferry and the Forth Road Bridge and 6 miles (9.7 km) east of Linlithgow.

<span class="mw-page-title-main">Smart motorway</span> Designation of roads in the United Kingdom

A smart motorway, also known in Scotland as an intelligent transport system, is a section of motorway in the United Kingdom that employs active traffic management (ATM) techniques to increase capacity through the use of MIDAS technology including variable speed limits and occasionally hard shoulder running and ramp metering at busy times. They were developed at the turn of the 21st century as a cost-effective alternative to traditional carriageway widening, with intended benefits ranging from more reliable journey times to lower vehicle emissions. However, despite the risk of a collision occurring between two moving vehicles being found to be decreased, there has been an acknowledged rise in the incidence of collisions involving vehicles where at least one was stationary in the first few years following the widespread removal of the hard shoulder on the country's busiest sections of motorway. Smart motorways garnered intense criticism from politicians, police representatives and motoring organisations, particularly from 2020 onwards, after a surge in near miss incidents and dozens of fatalities were revealed, and as of April 2023, no new smart motorways will be built.

<span class="mw-page-title-main">Forth Bridge</span> Railway bridge over the Firth of Forth in Scotland

The Forth Bridge is a cantilever railway bridge across the Firth of Forth in the east of Scotland, 9 miles west of central Edinburgh. Completed in 1890, it is considered a symbol of Scotland, and is a UNESCO World Heritage Site. It was designed by English engineers Sir John Fowler and Sir Benjamin Baker. It is sometimes referred to as the Forth Rail Bridge, although this is not its official name.

References

  1. 1 2 "The new bridge". Transport Scotland. Archived from the original on 16 February 2013. Retrieved 14 May 2012.
  2. "Forth Crossing Bill". www.parliament.scot. Chamber Office. 12 August 2010. Retrieved 22 January 2018.{{cite web}}: CS1 maint: others (link)
  3. "Procurement and construction | The Forth Bridges". www.theforthbridges.org. Retrieved 22 January 2018.
  4. "Transport Scotland The Queensferry Crossing". Transport Scotland. 2014. Archived from the original on 16 April 2014. Retrieved 22 February 2014.
  5. "Transport Scotland The Queensferry Crossing". Transport Scotland. 2014. Archived from the original on 18 January 2014. Retrieved 22 February 2014.
  6. "Queensferry Crossing Opening Date Announced". Forth Bridges Forum - Queensferry Crossing News. Retrieved 21 June 2017.
  7. Johnson, Simon (4 September 2017). "Queen opens new Forth crossing 53 years to the day after she opened old road bridge". The Telegraph. ISSN   0307-1235 . Retrieved 22 January 2018.
  8. Michael Lynch (1992). Scotland: A New History. London: Pimlico, p. 94.
  9. "Setting Forth: a consultation document on the Firth of Forths transport links". TRID. 30 November 1991. Retrieved 3 May 2012.
  10. 1 2 "£300m price tag put on bridge to beat gridlock". scotsman.com. 6 June 2004.
  11. "FAQs". Forth Estuary Transport Authority. Archived from the original on 16 June 2012. Retrieved 3 May 2012.
  12. "Firms told time running out on Forth Road Bridge". The Scotsman. 7 October 2006.
  13. Barry R Colford & Charles P E Cocksedge (2006). "Forth Road Bridge – First internal inspection, strength evaluation, acoustic monitoring and dehumidification of the main cables" (PDF).[ permanent dead link ]
  14. "Origin and early development | The Forth Bridges". www.theforthbridges.org. Retrieved 22 January 2018.
  15. "Time running out for new bridge – News". scotsman.com. 26 January 2006.
  16. "Vote favours 'new Forth Bridge'". BBC News. 29 April 2005.
  17. "Minister defiant on bridge issues". BBC News. 26 January 2006.
  18. "Transport Scotland". www.transport.gov.scot. Retrieved 22 January 2018.
  19. Jacobs (June 2007). "Forth Replacement Crossing Study Report 5 : Final Report Non Technical Summary" (PDF). Transport Scotland. pp. 16–17. Archived from the original (PDF) on 16 November 2011.
  20. "Forth to get new iconic bridge – News". scotsman.com. 19 December 2007. Retrieved 15 January 2012.
  21. "Queensferry Crossing: Why are locals calling the new bridge '˜Kevin'?". Edinburgh Evening News . 1 September 2017. Retrieved 10 September 2024.
  22. Allan, Tom (17 March 2010). "Forth Road Bridge opponents at parliament". The Guardian . Retrieved 10 September 2024.
  23. "The ForthRight Alliance". ForthRight Alliance. Retrieved 3 May 2012.
  24. "Our Objectives". Forth Tunnel Action Group. Retrieved 3 May 2012.
  25. 1 2 "Cut-price Forth crossing outlined". BBC News. 10 December 2008.
  26. "Transport blueprint at-a-glance". BBC News. 10 December 2008.
  27. "Public helps shape Forth Replacement Bridge Project". Transport Scotland. 23 June 2009. Archived from the original on 3 December 2013.
  28. "Forth Replacement Crossing: Environmental Statement". Transport Scotland. 17 November 2009. Archived from the original on 21 March 2013.
  29. "BBC News – New Forth bridge plans approved by MSPs". BBC. 15 December 2010. Retrieved 15 January 2012.
  30. "Royal Assent granted for Forth Replacement Crossing". Transport Scotland. 21 January 2011. Archived from the original on 2 December 2013.
  31. 1 2 "Principal contract". Transport Scotland. Archived from the original on 16 March 2012. Retrieved 15 January 2012.
  32. 1 2 "Just two bidders to build new Forth bridge". Scotsman.com. 29 September 2009.
  33. 1 2 "Construction industry invited to bid for Forth Replacement Crossing contract" (Press release). Transport Scotland. 30 November 2009. Retrieved 1 December 2016.
  34. "Consortium to build new Forth bridge". BBC News. 21 March 2011.
  35. "Preferred bidder announced for Forth Replacement Crossing" (Press release). Forth Estuary Transport Authority. 21 March 2011. Archived from the original on 14 March 2012.
  36. "Queensferry Crossing" . Retrieved 23 February 2017.
  37. "Another major contract award for Forth Replacement Crossing scheme" (Press release). Transport Scotland. 10 June 2011.
  38. "More savings, more jobs announced on Forth Replacement Crossing" (Press release). Transport Scotland. 30 June 2011. Retrieved 1 December 2016.
  39. "Visionary bridge designer, Naeem Hussain, wins the Prince Philip Medal - Royal Academy of Engineering".
  40. 1 2 "Forth Bridge may be finished a year early (if Scottish weather allows)". The Scotsman. 17 March 2012.
  41. "No Scots Bids for Forth Bridge Contract". The National. 21 October 2015.
  42. 1 2 "Queensferry Crossing becomes UK's tallest bridge". BBC News. 13 August 2015.
  43. "Worker killed in incident on Queensferry Crossing". British Broadcasting Corporation. 29 April 2016. Retrieved 30 April 2016.
  44. "Tragedy occurs on Workers' Memorial Day". Union of Construction, Allied Trades, and Technicians (UCATT). 28 April 2016. Retrieved 30 April 2016.
  45. "New Queensferry Crossing opening delayed until May 2017". BBC News. 8 June 2016. Retrieved 8 June 2016.
  46. Morby, Aaron (9 June 2016). "Queensferry Crossing to open five months late". Construction Enquirer. Retrieved 9 June 2016.
  47. "Queensferry Crossing set for further delay due to adverse weather". BBC News. 28 March 2017. Retrieved 22 September 2024.
  48. "Opening of Queensferry Crossing delayed until summer". BBC News. 29 March 2017. Retrieved 30 August 2017.
  49. Carrell, Severin (30 August 2017). "Queensferry Crossing across the Firth of Forth opens to traffic". The Guardian.
  50. "The Queensferry Crossing shimmering its way across the Forth". EdinburghReporter. 16 November 2016.
  51. "Everything you need to know about the Queensferry Crossing". BBC News. 30 August 2017.
  52. 1 2 Brocklehurst, Steven (11 February 2020). "Queensferry Crossing: The bridge that should never close". BBC News. Retrieved 11 February 2020.
  53. "Queensferry Crossing". The Gazetteer for Scotland. 12 October 2017.
  54. "Transport Minister Announces Naming Process for New Forth Crossing". Transport Scotland. 6 March 2012. Archived from the original on 13 December 2013. Retrieved 14 May 2012.
  55. "Public to be involved in naming of new bridge". Transport Scotland. 22 March 2011. Archived from the original on 13 December 2013. Retrieved 6 June 2012.
  56. "New Forth bridge: Queensferry Crossing wins naming contest". BBC News. 26 June 2013.
  57. "Connecting road network". Transport Scotland. Archived from the original on 18 January 2014. Retrieved 14 May 2012.
  58. 1 2 3 4 5 6 Transport Scotland. "Intelligent Transport Systems - Transport Scotland". Scottish Government. Archived from the original on 8 May 2013. Retrieved 9 July 2013.
  59. "Ferrytoll Junction". Transport Scotland. Archived from the original on 19 March 2012. Retrieved 14 May 2012.
  60. "South Queensferry Junction". Transport Scotland. Archived from the original on 19 March 2012. Retrieved 14 May 2012.
  61. "M9 Junction 1a". Transport Scotland. Archived from the original on 19 March 2012. Retrieved 14 May 2012.
  62. "FRC junction opens early and under budget". Transport Scotland. Archived from the original on 7 June 2013. Retrieved 24 July 2013.
  63. "Headland Archaeology | Forth Replacement Crossing, Edinburgh". www.headlandarchaeology.com. Retrieved 22 January 2018.
  64. Robertson, Alistair; Lochrie, Julie; Timpany, Scott (2013). "Built to last: Mesolithic and Neolithic settlement at two sites beside the Forth estuary, Scotland". Proceedings of the Society of Antiquaries of Scotland. 143: 73–136. doi:10.9750/PSAS.143.73.136.
  65. "Dig finds '10,000-year-old home'". BBC News. 18 November 2012.