Queensferry Crossing | |
---|---|
![]() The Queensferry Crossing photographed in November 2017 | |
Coordinates | 56°00′17″N3°24′45″W / 56.0046°N 3.4124°W Coordinates: 56°00′17″N3°24′45″W / 56.0046°N 3.4124°W |
Carries | ![]() |
Crosses | Firth of Forth |
Locale | Edinburgh and Fife, Scotland |
Characteristics | |
Design | Cable-stayed bridge |
Total length | 2,700 metres (8,858 ft) |
Longest span | 650 metres (2,133 ft) |
No. of lanes | Dual two-lane carriageway with hard shoulders [1] |
History | |
Constructed by | Forth Crossing Bridge Constructors (FCBC) |
Construction start | September 2011 |
Construction end | 27 August 2017 |
Construction cost | £1.35 billion |
Opened | 30 August 2017 |
Inaugurated | 4 September 2017 |
Location | |
![]() |
The Queensferry Crossing (formerly the Forth Replacement Crossing) is a road bridge in Scotland. It was built alongside the existing Forth Road Bridge and the Forth Bridge. It carries the M90 motorway across the Firth of Forth between Edinburgh, at South Queensferry, and Fife, at North Queensferry.
Forth Crossing Act 2011 | |
---|---|
Act of the Scottish Parliament | |
![]() | |
Long title | An Act of the Scottish Parliament to give the Scottish Ministers power to construct a new bridge over the Firth of Forth and to construct and improve associated roads and structures; to authorise the acquisition, or temporary possession and use, of land for construction and improvement works; and for connected purposes. |
Citation | 2011 asp 2 |
Dates | |
Royal assent | 20 January 2011 |
Status: Current legislation | |
Text of the Forth Crossing Act 2011 as in force today (including any amendments) within the United Kingdom, from legislation.gov.uk. |
Proposals for a second Forth Road crossing, to meet unexpected demand, were first put forward in the 1990s, but no action was taken until structural issues were discovered in the Forth Road Bridge in 2004. In 2006-2007 Transport Scotland carried out a study and in December 2007, took the decision to proceed with a replacement bridge. The following year it was announced that the existing bridge would be retained as a public transport link. The Forth Crossing Act received royal assent in January 2011. [2] In April 2011, the Forth Crossing Bridge Constructors Consortium were awarded the contract and construction began in late Summer/Autumn of 2011. [3]
The Queensferry Crossing is a three-tower cable-stayed bridge, with an overall length of 2.7 kilometres (1.7 miles). [4] Around 4 kilometres (2.5 miles) of new connecting roads were built, [5] including new and upgraded junctions at Ferrytoll in Fife, South Queensferry and Junction 1A on the M9.
The bridge was first due to be completed by December 2016, but this deadline was extended to August 2017 after several delays. [6] It is the third bridge across the Forth at Queensferry, alongside the Forth Road Bridge completed in 1964, and the Forth Rail Bridge completed in 1890. Following a public vote, it was formally named on 26 June 2013 and opened to traffic on 30 August 2017. The official opening was carried out on 4 September 2017 by Queen Elizabeth II, fifty-three years to the day after she opened the adjacent Forth Road Bridge. [7]
A crossing route over the Forth had existed at the site since the eleventh century, when the queen of Scotland, Margaret, founded a free ferry to take pilgrims north to St Andrews. [8] The site of the ferry crossing became the location of the Forth Road Bridge, which opened in 1964. Proposals for an additional road crossing at Queensferry were drawn up in the early 1990s, as part of the "Setting Forth" consultation document prepared by the Scottish Office. [9] The plans met stiff opposition from environmentalists and from the City of Edinburgh Council on the grounds of increased traffic. Following the Labour victory in the 1997 general election, the proposals were shelved. [10]
The existing bridge had a planned design life of 120 years, [11] but by the early years of the 21st century the planned theoretical capacity for the bridge was being routinely exceeded. It was designed for up to 11 million vehicles per year, but this had risen steadily to 23 million vehicles in 2006. [12] Between 2003 and 2005, an inspection programme found that the main suspension cables had suffered an estimated 8–10% loss of strength as a result of corrosion. Projections highlighted the likelihood of an accelerating loss of strength, with traffic restrictions to limit loading required in 2014 in the worst-case scenario. [13] In 2006-2007 Transport Scotland carried out a study to examine the options and in December 2007, the decision was made to proceed with a replacement bridge. [14]
The strategic transport importance of the road bridge, and the threat of closure by 2019 if major structural work was not successful, led to fears of serious economic consequences, especially as work on a new crossing was estimated to take up to 11 years. [15] Scottish Transport Minister Nicol Stephen commissioned a new study, which priced a second Forth Road Bridge at £300 million, in 2003. [10] The Forth Estuary Transport Authority voiced support for a new bridge in 2005, [16] and in 2006 the UK Transport Secretary, Alistair Darling, spoke in favour of the idea. [17]
In 2007, the Forth Replacement Crossing Study was commissioned by Transport Scotland to examine various options for new bridges or tunnels across the Forth. [18] The report recommended adoption of a cable-stayed bridge, located to the west of the Forth Road Bridge, as the preferred solution. The study concluded that this option was significantly cheaper than a tunnel, would take less time to construct, and would represent better value for money, though it was noted that a tunnel would have fewer environmental impacts. [19] In December 2007 finance secretary John Swinney announced that a new cable-stayed bridge would be constructed, with an estimated cost of between £3.25 billion and £4.22 billion. He claimed it would be "the largest construction project in a generation in Scotland". [20]
There was opposition to the project on environmental, traffic and cost grounds. The ForthRight Alliance, an umbrella group including Friends of the Earth, the Scottish Green Party, the RSPB, sustainable transport groups and other local organisations, opposed the scheme as being "both unwelcome and unnecessary". [21] Another group, Forth Tunnel Action Group, campaigned for a tunnel as the solution with lowest costs and fewest long-term environmental impacts. [22]
It was initially suggested that the new bridge would be funded via the Scottish Futures Trust, an alternative to public-private partnership funding for major public-sector schemes. However, the Scottish Government announced in December 2008 that public funding would be used. [23] As part of the Scottish Government's Strategic Transport Projects Review, the new Forth crossing was priced at between £1.72 billion and £2.34 billion. [24] Under the revised scheme, the existing bridge will be retained for public transport, cyclists and pedestrians, and the new bridge was to be operational by 2016. [23]
A joint venture between consultancies Arup and Jacobs was appointed as project manager, and in February 2008 environmental and technical studies were begun, continuing through 2009. Public consultations were held, and some changes to the scheme were made in response to the comments received. [25] An environmental statement was published in November 2009, [26] coinciding with the introduction of the Forth Crossing Bill into the Scottish Parliament by John Swinney. A majority of MSPs voted in favour of the new legislation on 16 December 2010, [27] and the Forth Crossing Act received royal assent in January 2011. [28]
In 2009, Transport Scotland solicited for tenders to construct the proposed bridge. [29] Although Transport Scotland received 39 expressions of interest, concerns over the risks associated with the fixed-price contract resulted in only two consortia of large construction companies bidding. [30] Due to the bidders' concerns that the bidding process itself would prove to be an expensive proposition, the Scottish Government allocated £10 million to defray the bidders' costs during the full bidding process, should the project be abandoned. [30]
The two consortia were Forthspan, which included Morgan Sindall, BAM Nuttall and Balfour Beatty; and Forth Crossing Bridge Constructors (FCBC), which consists of Dragados, Hochtief, American Bridge, and Morrison Construction. [31] Bids for the main contract, priced at between £900 million and £1.2 billion, and including design and construction of the bridge and approach roads, [31] were submitted in January 2011. [29] In March 2011 the Scottish Government announced FCBC as preferred bidder, with a bid of £790 million. [32] [33] Ramboll is leading the Design Joint Venture which includes Sweco and Leonhardt Andra and Partners. [34]
In addition to the main contract, two smaller contracts form part of the scheme. The contract to implement the Intelligent Transport System (ITS) traffic management system in Fife was awarded to John Graham (Dromore) Ltd, with a tender of £12.9 million, while the upgrade of M9 Junction 1a was awarded to a joint venture between John Sisk and Roadbridge, with a tender of £25.6 million. As with the main contract, the tenders received were below the original estimated budgets. [35] [36] Naeem Hussain, Global Bridge Design Practice Leader at Arup, was the lead design engineer for the project. [37]
Preparatory works for the new bridge began in September 2011 with works beginning at the southern end of the M90 to build the northern approach roads. 149 segments of bridge deck, each of which is 12 metres (39 ft) long and 40 metres (130 ft) wide, were constructed in China and Spain, then delivered by sea in October 2013. [38] The approach steel bridge sections were manufactured by Cleveland Bridge & Engineering Company in Darlington. [39]
The towers reached 160 metres (525 ft) in height in August 2015, making it the UK's tallest bridge. [40] The completed towers stand at 207 metres (679 ft). [40]
On 28 April 2016, one construction worker was killed and another injured in an accident involving a crane. Work on the bridge was halted to allow an investigation to take place. [41] [42]
The bridge was due to be completed by December 2016, but that date was put back to May 2017 due to weather delays slowing construction, [43] with 25 days lost due to high winds during April and May 2016. [44] An additional delay was announced in March 2017 again due to weather (more specifically, high winds) and an estimation period of six weeks in July / August 2017 was proposed. [45]
The bridge opened on 30 August 2017 and formally opened by the Queen on 4 September 2017. [46]
The bridge is a cable-stayed structure, with three towers each 207 metres (679 ft) high. [38] Including approaches, the overall length of the bridge is 2.7 kilometres (1.7 miles); at opening, it is the longest triple tower cable-stayed bridge in the world. [47] The bridge carries motorcycles, cars and heavy goods vehicles, while public transport, cyclists and pedestrians use the Forth Road Bridge. Wind shielding has been built into the design, to enable use of the bridge in high winds, which regularly led to restrictions on the existing bridge. [1] [48] The bridge was closed for the first time on 11 February 2020, 30 months after opening, due to accumulations of ice on the towers. [49] Some of the ice then fell onto the carriageway, which caused damage to eight vehicles and prompted the closure. [49]
The bridge is the third crossing of the Forth at Queensferry, alongside the Forth Road Bridge, completed in 1964, and the Forth Bridge, a railway bridge completed in 1890. It is sited west of the road bridge, with the northern landfall at St Margaret's Hope, between Rosyth Dockyard and North Queensferry and the southern landfall just west of Port Edgar in South Queensferry. The central tower was constructed on the Beamer Rock, a small islet in the Forth. [50]
The project was known as the Forth Replacement Crossing, and a name for the new bridge was selected in a public vote in 2013 after a panel of independent advisers provided a shortlist of possible names. [51] [52] Five names were shortlisted: Caledonia Bridge, Firth of Forth Crossing, Queensferry Crossing, Saltire Crossing and St Margaret's Crossing. A public vote was held up until 7 June 2013 and the name Queensferry Crossing received the most votes: 12,039 out of 37,000 (32%). [53]
Several new and upgraded roads connect the bridge into the existing road network with around 4 kilometres (2.5 miles) of new roads constructed. These new roads join the M9 and M90 motorways together for the first time, with the Queensferry Crossing being built to motorway standard in order to carry the M90 across the Forth. The M90 motorway previously terminated at Admiralty Junction, around 3 kilometres (1.9 miles) north of the current Forth Road Bridge, with the road continuing as all-purpose dual carriageway across the existing bridge and joining the M9 via the M9 Spur. [54] [55]
Admiralty Junction, previously Junction 1 of the M90 motorway remains unaltered, with the exception of a bus lane added on the southbound carriageway. The junction was renumbered to Junction 1C of the M90 when the Queensferry Crossing opened. [55]
Ferrytoll Junction was redesigned to give access to the new crossing and to maintain public transport access to the Forth Road Bridge. The design of the new junction required the realignment of the B981 road to North Queensferry. [56] Ferrytoll Junction was numbered Junction 1B of the M90 following completion of the Queensferry Crossing. [55]
The M90 was extended west from the existing bridge access at Ferry Muir, wrapping around South Queensferry to the southern landfall of the new crossing. A grade-separated junction was built on the A904 just west of Echline, at the south-west edge. The existing access from the Forth Road Bridge to the A90 remains open to public transport. [57] South Queensferry Junction became Junction 1A of the M90 when the Queensferry Crossing opened. [55]
Junction 1a provides access from the M9 to the Forth Road Bridge and Queensferry Crossing via the M9 Spur, which was renumbered as M90 upon completion of the Queensferry Crossing. Originally, only east-facing connections were provided to the M9, forcing traffic heading west from the bridge onto the A904 through the village of Newton in West Lothian. The upgrade of the junction included new west-facing slip roads, enabling direct access onto the M9 from the Forth Road Bridge and the new crossing, as well as the widening of the existing connections to assist the flow of traffic at peak times. [58] The improvements were completed in February 2013 at a cost of £25.6m. [59] The junction connecting the A90 / M90 at the southern end of the bridges with the A90 towards Edinburgh city centre and the M90 extension is named the Scotstoun Junction and is numbered as Junction 1 of the M90. [55]
An "Intelligent transportation system" (ITS) was installed between Halbeath on the M90, and the M9, covering the whole scheme. The ITS is an active traffic management, enabling variable speed restrictions and lane closures to be displayed on overhead gantries. [55]
During routine archaeological excavations by Headland Archaeology in advance of work on the new bridge archaeological deposits from the Mesolithic were found on both sides of the Forth. [60]
On the northern side two post built structures and their surrounding pits and were dated to the mid to late Mesolithic period.
On the south bank in a field at Echline the remnants of a sunken floor structure with in situ floor deposits was found. The structure, based around an oval pit approximately 7 metres (23 ft) in length, contained the remains of a hearth, stone tools, and bone from a variety of animals. Radio-carbon analysis returned a date of c.8300, approximately 1000 years older than the northern site, making it the earliest known dwelling in Scotland. Additionally three isolated Neolithic pits and a Bronze Age pit group and pit alignment were identified. [61] [62]
The M25 or London Orbital Motorway is a major road encircling most of Greater London. The 117-mile (188-kilometre) motorway is one of the most important roads in the UK and one of the busiest. Margaret Thatcher opened the final section in 1986, making the M25 the longest ring road in Europe upon opening. The Dartford Crossing completes the orbital route but is not classed as motorway; it is classed as a trunk road and designated as the A282. In some cases, including notable legal contexts such as the Communications Act 2003, the M25 is used as a de facto alternative boundary for Greater London.
The Forth Road Bridge is a suspension bridge in east central Scotland. The bridge opened in 1964 and at the time was the longest suspension bridge in the world outside the United States. The bridge spans the Firth of Forth, connecting Edinburgh, at South Queensferry, to Fife, at North Queensferry. It replaced a centuries-old ferry service to carry vehicular traffic, cyclists and pedestrians across the Forth; railway crossings are made by the nearby Forth Bridge, opened in 1890.
The Humber Bridge, near Kingston upon Hull, East Riding of Yorkshire, England, is a 2.22 km single-span road suspension bridge, which opened to traffic on 24 June 1981. When it opened, the bridge was the longest of its type in the world; it was not surpassed until 1998, with the completion of the Akashi Kaikyō Bridge, and is now the twelfth-longest.
The A9 is a major road in Scotland running from the Falkirk council area in central Scotland to Scrabster Harbour, Thurso in the far north, via Stirling, Bridge of Allan, Perth and Inverness. At 273 mi (439 km), it is the longest road in Scotland and the fifth-longest A-road in the United Kingdom. Historically it was the main road between Edinburgh and John o' Groats, and has been called the spine of Scotland. It is one of the three major north–south trunk routes linking the Central Belt to the Highlands - the others being the A82 and the A90.
The A90 road is a major north to south road in eastern Scotland, running from Edinburgh to Fraserburgh, through Dundee and Aberdeen. Along with the A9 and the A82 it is one of the three major north–south trunk roads connecting the Central Belt to the North.
The M90 is a motorway in Scotland. It runs from Junction 1A of the M9 motorway, south of the Queensferry Crossing, to Perth. It is the northernmost motorway in the United Kingdom. The northern point goes to the western suburbs of Perth at Broxden. A small part of the M90 was originally numbered as the M85 motorway.
Stagecoach East Scotland is an operating region of Stagecoach UK Bus, with its regional base in Dunfermline, Scotland. The company operators under six different brands.
The Forth Estuary Transport Authority (FETA) was the authority responsible for the maintenance of the Forth Road Bridge over the Firth of Forth in eastern central Scotland. FETA was created in 2001 by the Transport (Scotland) Act 2001 - to replace the Forth Road Bridge Joint Board.
Edinburgh is a major transport hub in east central Scotland and is at the centre of a multi-modal transport network with road, rail and air communications connecting the city with the rest of Scotland and internationally.
The A494 is a trunk road in Wales and England. The route, which is officially known as the Dolgellau to South of Birkenhead Trunk Road, runs between the terminus of the M56 motorway between Mollington and Capenhurst and the A470 at Dolgellau, Gwynedd. Its northern sections remain among the busiest roads in Wales.
The B800 is a short road in eastern Scotland, connecting the Forth Road Bridge to Kirkliston. It is a two-way single carriageway road.
The Lower Thames Crossing is a proposed road crossing of the Thames estuary downstream of the Dartford Crossing that links the counties of Kent and Essex, and its proposed approaches. If built it would pass through the districts of Thurrock and Gravesham, supplementing the Dartford route. The approximately 14.3-mile (23.0 km) route will be assessed by the Planning Inspectorate.
The Clackmannanshire Bridge is a road bridge over the Firth of Forth in Scotland which opened to traffic on 19 November 2008. Prior to 1 October 2008 the bridge was referred to as the upper Forth crossing while the name was chosen.
The Aberdeen Western Peripheral Route (AWPR), unofficially also the City of Aberdeen Bypass, is a major road that wraps around the city of Aberdeen, Scotland. The road stretches north from Stonehaven through Kincardineshire and crosses both the River Dee and River Don before terminating at Blackdog. The main stretch of the AWPR is 22 miles (35 km) in length.
Newton or is a small village in the county of West Lothian, Scotland. It lies on the A904 trunk road 2.6 miles (4.2 km) west of South Queensferry and the Forth Road Bridge and 6 miles (9.7 km) east of Linlithgow.
A smart motorway, also known in Scotland as an intelligent transport system, is a section of motorway in the United Kingdom that employs active traffic management (ATM) techniques to increase capacity through the use of MIDAS technology including variable speed limits and occasionally hard shoulder running and ramp metering at busy times. They were developed at the turn of the 21st century as a cost-effective alternative to traditional carriageway widening, with intended benefits ranging from more reliable journey times to lower vehicle emissions. However, despite the risk of a collision occurring between two moving vehicles being found to be decreased, there has been an acknowledged rise in the incidence of collisions involving vehicles where at least one was stationary in the first few years following the widespread removal of the hard shoulder on the country's busiest sections of motorway. Smart motorways garnered intense criticism from politicians, police representatives and motoring organisations, particularly from 2020 onwards, after a surge in near miss incidents and dozens of fatalities were revealed, and as of April 2023, no new smart motorways will be built.
The Forth Bridge is a cantilever railway bridge across the Firth of Forth in the east of Scotland, 9 miles west of central Edinburgh. Completed in 1890, it is considered a symbol of Scotland, and is a UNESCO World Heritage Site. It was designed by English engineers Sir John Fowler and Sir Benjamin Baker. It is sometimes referred to as the Forth Rail Bridge, although this has never been its official name.
Trinity Chain Pier, originally called Trinity Pier of Suspension, was built in Trinity, Edinburgh, Scotland in 1821. The pier was designed by Samuel Brown, a pioneer of chains and suspension bridges. It was intended to serve ferry traffic on the routes between Edinburgh and the smaller ports around the Firth of Forth, and was built during a time of rapid technological advance. It was well used for its original purpose for less than twenty years before traffic was attracted to newly developed nearby ports, and it was mainly used for most of its life for sea bathing. It was destroyed by a storm in 1898; a building at the shore end survives, much reconstructed, as a pub and restaurant called the Old Chain Pier.
The Forth Bridge approach railways were railway lines constructed in the period 1887 to 1890 to form new main lines on the opening of the Forth Bridge at the Queensferry crossing. Until then, only local branch lines approached the location. The North British Railway built new main lines and upgraded some existing lines.
Michael Martin OBE is a British bridge engineer. He grew up in Carlisle and studied at the Carlisle Technical College before achieving a degree in civil engineering from the University of Leeds. Martin began his career as a design engineer at Ove Arup & Partners and served as their representative during the construction of the Kessock Bridge. He thereafter joined the contractor Morrison and was their chief engineer for the construction of the Dornoch Firth and Kylesku Bridges. Under Martin's direction the company won some of the first Private Finance Initiative infrastructure contracts in the UK. He transferred to Anglian Water after that company purchased Morrison in 2000 and became their head of health and safety. After a brief early retirement he returned as a consultant for WS Atkins and to lead a £2.2 billion water infrastructure partnership programme. He returned from retirement for a second time to act as Galliford Try representative on the board of the company constructing the £1.4 billion Queensferry Crossing. In 2014 he was appointed project director for all companies in the contracting joint venture and oversaw the project's completion in 2017.
{{cite web}}
: CS1 maint: others (link)