Great Northern, Piccadilly and Brompton Railway

Last updated

Geographic route map of the Great Northern, Piccadilly & Brompton Railway GNP&BR.png
Geographic route map of the Great Northern, Piccadilly & Brompton Railway

The Great Northern, Piccadilly and Brompton Railway (GNP&BR), also known as the Piccadilly tube, was a railway company established in 1902 that constructed a deep-level underground "tube" railway in London, England. [note 1] The GNP&BR was formed through a merger of two older companies, the Brompton and Piccadilly Circus Railway (B&PCR) and the Great Northern and Strand Railway (GN&SR). It also incorporated part of a tube route planned by a third company, the District Railway (DR). The combined company was a subsidiary of the Underground Electric Railways Company of London (UERL).

Contents

The B&PCR and the GN&SR were established in 1896 and 1898 respectively, but construction of both railways was delayed while funding was sought. In 1902 the UERL, which already controlled the DR, took control of both companies and quickly raised the funds, mainly from foreign investors. A number of different routes were planned, but most were rejected by the Parliament of the United Kingdom.

When it opened in 1906, the GNP&BR's line served 22 stations and ran for 14.17 kilometres (8.80 mi) between its western terminus at Hammersmith and its northern terminus at Finsbury Park. A short 720-metre (2,362 ft) branch connected Holborn to the Strand. Most of the route was in a pair of tunnels, with 1.1 kilometres (0.68 mi) at the western end constructed above ground. [1] Within the first year of opening it became apparent to the management and investors that the estimated passenger numbers for the GNP&BR and the other UERL lines were over-optimistic. Despite improved integration and cooperation with the other tube railways, the GNP&BR struggled financially. In 1933 it and the rest of the UERL were taken into public ownership. Today, the GNP&BR's tunnels and stations form the core central section of the London Underground's Piccadilly line.

Establishment

Origins

Brompton and Piccadilly Circus Railway, 1896

B&PCR and DR deep-level routes, 1896 GNP&BR 1896.png
B&PCR and DR deep-level routes, 1896
Brompton and Piccadilly Circus Railway Act 1897
Act of Parliament
Royal Coat of Arms of the United Kingdom (variant 1, 1952-2022).svg
Long title An Act for incorporating the Brompton and Piccadilly Circus Railway Company and for empowering them to construct an Underground Railway from Piccadilly Circus to South Kensington and for other purposes.
Citation 60 & 61 Vict. c. cxcii
Dates
Royal assent 6 August 1897
Other legislation
Amended by
Status: Amended
Text of statute as originally enacted

In November 1896 notice was published that a private bill was to be presented to Parliament for the construction of the Brompton and Piccadilly Circus Railway (B&PCR). [2] [note 2] The line was planned to run entirely underground between Air Street near Piccadilly Circus and the south end of Exhibition Road, South Kensington. The route was to run beneath Piccadilly, Knightsbridge, Brompton Road and Thurloe Place, with intermediate stations at Dover Street, Down Street, Hyde Park Corner, Knightsbridge and Brompton Road. A short branch to the east of the South Kensington terminus was planned to a depot south of Brompton Road at the end of Yeoman Row. Electricity to operate the trains was to be provided from a generating station to be built about a mile south of the South Kensington terminus on the north bank of the River Thames at Lots Road, West Brompton. [4] Following parliamentary approval, the bill received royal assent as the Brompton and Piccadilly Circus Railway Act 1897 (60 & 61 Vict. c. cxcii) [5] on 6 August 1897. [6]

District Railway deep-level tube, 1896

Metropolitan District Railway Act 1897
Act of Parliament
Royal Coat of Arms of the United Kingdom (variant 1, 1952-2022).svg
Long title An Act for empowering the Metropolitan District Railway Company to construct an Underground Railway from near Earl's Court Station to the Mansion House Station City to authorise them to work that railway and their existing railway by electricity to extend the time limited for the completion of the Acton Junction Railway of the Company and for the compulsory purchase of lands for and for the completion of the Ealing and South Harrow Railway and for other purposes.
Citation 60 & 61 Vict. c. ccxlvii
Dates
Royal assent 6 August 1897
Other legislation
Amended by
Status: Amended

Also announced in November 1896 was a bill to be presented by the District Railway (DR) for a tube railway to be constructed beneath its existing sub-surface line between Gloucester Road and Mansion House stations. [7] The DR operated a steam railway, running in cut and cover tunnels, and planned to ease congestion along its heavily used route by constructing an express line with just a single intermediate station at Charing Cross (now Embankment). The express line was to surface west of Gloucester Road and connect to the DR's existing line at Earl's Court. Since, like the B&PCR, the DR's deep tube line would be operated with electric trains, the DR planned to build a generating station adjacent to its Walham Green station (now Fulham Broadway). [8] The bill received assent on 6 August 1897 as the Metropolitan District Railway Act 1897 (60 & 61 Vict. c. ccxlvii). [6]

Great Northern and Strand Railway, 1898

B&PCR, GN&SR and DR deep-level routes, 1898 GNP&BR 1898.png
B&PCR, GN&SR and DR deep-level routes, 1898
Great Northern and Strand Railway Act 1899
Act of Parliament
Royal Coat of Arms of the United Kingdom (variant 1, 1952-2022).svg
Long title An Act for incorporating the Great Northern and Strand Railway Company and for empowering them to construct an Underground Railway from the parish of Saint Clement Danes in the Administrative County of London and for other purposes.
Citation 62 & 63 Vict. c. cciii
Dates
Royal assent 1 August 1899
Other legislation
Amended by
Status: Amended

In November 1898 the Great Northern and Strand Railway (GN&SR) was announced as a tube railway, to run from Wood Green to Stanhope Street, north of the Strand. [9] The GN&SR was backed by the Great Northern Railway (GNR), the main line railway operating from King's Cross station. The GNR saw the new company as a means of relieving congestion on its route. The GN&SR was to run beneath the GNR's main line from Wood Green station (now Alexandra Palace) to Finsbury Park station. It was then planned to run south-west through Holloway to King's Cross, and then south to Bloomsbury and Holborn. Intermediate stations were planned at the GNR's Hornsey, Harringay and Finsbury Park stations, and at Holloway, York Road, King's Cross, Russell Square and Holborn. [10] A power station was planned next to the GNR's tracks at Gillespie Road. [9] When the London County Council planned the construction of Kingsway and Aldwych, Stanhope Street was scheduled for demolition so the southern terminus was relocated to the junction of the two new roads. [10] The bill was enacted on 1 August 1899 as the Great Northern and Strand Railway Act 1899 (62 & 63 Vict. c. cciii). [11]

Search for finance, 1896–1903

Although the three companies had permission to construct their railways, they still had to raise the capital for the construction works in a competitive market.

Financier Charles Yerkes' consortium bought the DR, the B&PCR, and the GN&SR in 1901. Yerkes002.jpg
Financier Charles Yerkes' consortium bought the DR, the B&PCR, and the GN&SR in 1901.

By 1899, there were five other tube railway companies with permission to construct railways that were raising funds – the Baker Street and Waterloo Railway (BS&WR), the Charing Cross, Euston and Hampstead Railway (CCE&HR), the Great Northern and City Railway (GN&CR), the Central London Railway (CLR) and the City and Brixton Railway. [note 3] The already operating City & South London Railway (C&SLR) was also looking for money for extensions to its existing route and numerous others proposed, but unapproved underground railway companies were also seeking investors.

Foreign investors came to the rescue of the DR, B&PCR and GN&SR: American financier Charles Yerkes, who had been lucratively involved in the development of Chicago's tramway system in the 1880s and 1890s, saw the opportunity to make similar investments in London. In March 1901 he and his backers purchased a majority of the shares of the DR and, in September 1901, took over the B&PCR and the GN&SR. [note 4] With the companies under his control, Yerkes established the UERL to raise funds to build the tube railways and to electrify the DR. The UERL was capitalised at £5 million with the majority of shares sold to overseas investors. [note 5] Further share issues followed, which raised a total of £18 million by 1903 (equivalent to approximately £2.06 billion today) [14] for use across all of the UERL's projects. [note 6]

Planning the route, 1898–1905

B&PCR bill, 1899

Brompton and Piccadilly Circus Railway (Extensions) Act 1899
Act of Parliament
Royal Coat of Arms of the United Kingdom (variant 1, 1952-2022).svg
Long title An Act to confer further powers on the Brompton and Piccadilly Circus Railway Company for the construction of extension railways and works in the county of London and for other purposes.
Citation 62 & 63 Vict. c. cclxii
Dates
Royal assent 9 August 1899
Other legislation
Amended by
Status: Amended

During the progress of their 1896 bills through parliament, the DR and the B&PCR established a relationship through a successful joint campaign of opposition to a competing proposal from the City & West End Railway. This was for a tube railway running from Hammersmith to Cannon Street, which would have duplicated parts of the DR's and the B&PCR's approved routes. [16] In late 1898, this common interest led to the purchase of the B&PCR by the DR. In November 1898 [17] a bill for the B&PCR was announced, which sought permission for short extensions at each end of its route: at its eastern end, from Piccadilly Circus to Cranbourn Street and, at the western end, connections between the B&PCR's tunnels and those of the DR's deep tube line. [18] Parliament rejected the eastern extension, but permitted the connection between the two lines and approved a capital injection from the DR into the B&PCR. The bill received royal assent on 9 August 1899 as the Brompton & Piccadilly Circus Railway (Extensions) Act 1899 (62 & 63 Vict. c. cclxii). [19]

DR and B&PCR bills, 1900

Metropolitan District Railway Act 1900
Act of Parliament
Royal Coat of Arms of the United Kingdom (variant 1, 1952-2022).svg
Long title An Act for empowering the Metropolitan District Railway Company to erect a station for generating electrical energy and thereby work certain railways to acquire lands to extend the time for the completion of certain railways and compulsory purchase of lands to make certain provisions with respect to the Ealing and South Harrow and Brompton and Piccadilly Circus Railways to raise further capital and for other purposes.
Citation 63 & 64 Vict. c. cclxxiii
Dates
Royal assent 6 August 1900
Other legislation
Amended by
Status: Amended

In November 1899, the DR published a notice of a bill for the 1900 parliamentary session. The company was still unable to proceed with the construction of its proposed deep line, and the new bill included provisions for extensions of time for this line and for those of the B&PCR. The bill included construction and operation of the power station at the Lots Road site previously chosen by the B&PCR. [20] The B&PCR also published notice for a bill requesting an extension of time, [21] but this was later withdrawn and the extension request in the DR bill was used. [18] The time extensions were granted in the Metropolitan District Railway Act 1900 (63 & 64 Vict. c. cclxxiii), which received assent on 6 August 1900. [22]

B&PCR bill, 1901

B&PCR, GN&SR and DR deep-level routes, 1901 GNP&BR 1901.png
B&PCR, GN&SR and DR deep-level routes, 1901

In November 1900, the B&PCR published a notice of a bill for the 1901 session, in which it sought permission for two extensions. [23] The first, eastward, took a more northerly route than the rejected 1899 extension to Cranbourn Street: it was to run via Shaftesbury Avenue, Hart Street (now Bloomsbury Way), Bloomsbury Square, Theobalds Road and Rosebery Avenue, to Angel, Islington where it terminated under Islington High Street. Where the line crossed other tube routes, stations were planned: at Cambridge Circus to interchange with the planned CCE&HR, and at Museum Street near to the CLR's recently opened British Museum station. [24] The second extension took the line south-west from South Kensington, via Fulham Road, to connect to the DR's line south of Walham Green station (now Fulham Broadway). The bill also included provisions for the B&PCR to take over responsibility for construction of the section of the DR's deep-level line from South Kensington to Earl's Court, and for a further extension of time. [23]

The opening of the CLR on 30 July 1900 had stimulated interest in underground railways, and the B&PCR's bill was submitted to Parliament at the same time as a large number of other bills for tube lines in the capital. [note 7] To review these bills, Parliament established a joint committee under Lord Windsor. [26] Only the part of B&PCR's first extension as far as Museum Street was considered by the committee. The section to The Angel was held back, pending the findings of a separate committee which was investigating problems of vibration experienced on the CLR. [24] [note 8] The extension to Fulham was not discussed. [24] By the time the committee had produced its report, the parliamentary session was almost over so the promoters of the bills were asked to resubmit them for the following 1902 session. [28]

B&PCR, GN&SR and DR bills, 1902

In November 1901, the B&PCR published details of its bill for the 1902 session. The extension to The Angel was dropped, and a different route eastwards from Piccadilly Circus was planned. Once again this ran to Cranbourn Street, but it continued under Long Acre and Great Queen Street to meet and connect to the GN&SR's tunnels at Little Queen Street (now the northern part of Kingsway) just south of the GN&SR's planned Holborn station. The B&PCR planned stations at Wardour Street, Cranbourn Street and Covent Garden.

GNP&BR and DR deep-level routes, 1902 GNP&BR 1902.png
GNP&BR and DR deep-level routes, 1902

At Wardour Street station a branch was to leave the main route and head south-east, to connect to the DR's deep-level line east of its station at Charing Cross. Wardour Street station was planned to have platforms on both branches. [29] The south-west extension to Walham Green was retained with minor alterations. The new route was to branch from the original route east of Brompton Road station, which was to have platforms on both routes. Stations were planned along Fulham Road at its junctions with College Street (now Elystan Street), Neville Street, Drayton Gardens, Redcliffe Gardens, Stamford Bridge and Maxwell Road. The route would interchange with the DR at Walham Green before coming to the surface and running parallel with the DR as far as Parsons Green, beyond which the line was to connect to the DR. The requests for an extension of time and for the powers to build the DR deep-level line from South Kensington to Earl's Court were re-presented. As the B&PCR and the GN&SR were now in common ownership, the bill also sought powers to enable the companies to merge and for the B&PCR to change its name. [30]

At the same time, the GN&SR published details of its bill for the 1902 session. The GN&SR sought powers for a short extension of about 350 metres (1,148 ft) from its southern terminus, to Temple station on the DR's existing sub-surface line where an interchange was planned. The GN&SR also sought permission to abandon the section of its route north of Finsbury Park, [note 9] and to transfer its powers and obligations to the B&PCR as part of the merger. [32] The DR also announced a bill for 1902 which included provisions to transfer responsibility for part or all of its deep-level line to the B&PCR. [33]

The B&PCR bill was again examined by a joint committee under Lord Windsor. The GN&SR bill was examined by a separate committee under Lord Ribblesdale. [note 10] The B&PCR's eastward extension to Holborn to connect to the GN&SR was permitted, but the extension to Parsons Green was rejected following objections from hospitals in the Fulham Road, which were concerned that vibrations from trains might affect their patients. The B&PCR link from Piccadilly Circus to Charing Cross was rejected on the grounds that it involved sharp turns and steep gradients to avoid public buildings in the area. The merger with the GN&SR and name change were permitted. [29] The GN&SR's extension to Temple was rejected following objections from the Duke of Norfolk who owned the land under which it would have run. The abandonment of the route north of Finsbury Park was permitted. [31]

Great Northern and Strand Railway Act 1902
Act of Parliament
Coat of arms of the United Kingdom (1901-1952).svg
Long title An Act to authorise the alteration of the railways of the Great Northern and Strand Railway Company and the transfer of their undertaking and powers to the Brompton and Piccadilly Circus Railway Company and for other purposes.
Citation 2 Edw. 7. c. ccxxxv
Dates
Royal assent 8 August 1902
Other legislation
Amended by
Text of statute as originally enacted
Brompton and Piccadilly Circus Railway Act 1902
Act of Parliament
Coat of arms of the United Kingdom (1901-1952).svg
Long title An Act to confer further powers on the Brompton and Piccadilly Circus Railway Company for the construction of new railways and works and for the use of part of the Metropolitan District Railway to extend the time for compulsory purchase of land and completion of works and to authorise working and other agreements with other companies and for other purposes.
Citation 2 Edw. 7. c. cclix
Dates
Royal assent 18 November 1902
Other legislation
Amended by
Text of statute as originally enacted

The bills received royal assent as the Great Northern and Strand Railway Act 1902 (2 Edw. 7. c. ccxxxv) and the Metropolitan District Railway Act 1902 (2 Edw. 7. c. ccxx) on 8 August 1902, and as the Brompton and Piccadilly Circus Railway Act 1902 (2 Edw. 7. c. cclix) on 18 November 1902. [35] [36]

GNP&BR and DR bills, 1903

GNP&BR and DR deep-level routes, 1903 GNP&BR 1903.png
GNP&BR and DR deep-level routes, 1903

In November 1902, the newly merged company announced two bills for the 1903 parliamentary session under the GNP&BR name. [37] [38] The first bill requested minor powers which included the purchase of additional land for stations, and sought minor amendments to previous Acts.

The second bill sought permission for extensions east and west from the approved route. The eastern extension was to diverge from the main route immediately west of Piccadilly Circus station, which was to be expanded to have east and westbound platforms on both lines. The extension was then to pass under Leicester Square to a station at Charing Cross. Continuing eastwards under Strand, the tunnels were to cross under the branch from Holborn, with an interchange at Strand station. The line was then to continue under Fleet Street to Ludgate Circus, where a station was to be constructed to interchange with the London, Chatham and Dover Railway's Ludgate Hill station (since demolished). It would then proceed south under New Bridge Street, and east under Queen Victoria Street, to connect to the DR's proposed deep-level line west of Mansion House station. [39] The western extension was to diverge from the approved route at Albert Gate, east of Knightsbridge station. This station was to have additional platforms on the new branch line which would head west under Knightsbridge, Kensington Road and Kensington High Street, with stations at the Royal Albert Hall, the DR's High Street Kensington station and Addison Road. The tunnels were then to follow Hammersmith Road to the DR's Hammersmith station. There they would turn north under Hammersmith Grove and east under Goldhawk Road, to terminate on the south side of Shepherd's Bush Green near to the CLR's Shepherd's Bush terminus. [39]

The DR also publicised two further bills for the 1903 session. [40] [41] The first included provisions to formalise the agreement for the GNP&BR to build the section of the deep-level line between South Kensington and West Kensington, including the deep-level platforms at Earl's Court. [39] The second bill sought permission to extend the deep-level line from its eastern end at Mansion House by following beneath the existing sub-surface tracks to Whitechapel, where the line would connect to the existing sub-surface lines to Mile End. [42]

Great Northern, Piccadilly and Brompton Railway (Various Powers) Act 1903
Act of Parliament
Coat of arms of the United Kingdom (1901-1952).svg
Long title An Act to confer further powers on the Great Northern Piccadilly and Brompton Railway Company and for other purposes.
Citation 3 Edw. 7. c. clxxxvi
Dates
Royal assent 11 August 1903
Text of statute as originally enacted

Neither extension bill was debated. In February 1903, Parliament had established the Royal Commission on London Traffic to assess the manner in which transport in London should be developed. While the Commission deliberated, any review of bills for new lines and extensions was postponed. Both bills were later withdrawn by their promoters. The powers bills were approved as the Metropolitan District Railway Act 1903 (3 Edw. 7. c. cxxvi) on 21 July 1903 and the Great Northern, Piccadilly and Brompton Railway (Various Powers) Act 1903 (3 Edw. 7. c. clxxxvi) on 11 August 1903. [43] [44]

GNP&BR bills, 1905

The royal commission investigations continued from 1903 to early 1905, concluding with the issue of a report in June 1905. [45] No bills were submitted for the 1904 parliamentary session, but in November 1904 the GNP&BR announced two bills for the 1905 session. [46] [47]

GNP&BR and DR routes, 1905 GNP&BR 1905.png
GNP&BR and DR routes, 1905

Great Northern, Piccadilly and Brompton Railway (Various Powers) Act 1905
Act of Parliament
Coat of arms of the United Kingdom (1901-1952).svg
Long title An Act to confer further powers on the Great Northern Piccadilly and Brompton Railway Company.
Citation 5 Edw. 7. c. clxiii
Dates
Royal assent 4 August 1905
Other legislation
Amended by
Text of statute as originally enacted

The first dealt with the Strand branch: it confirmed the layout of the junction between the branch and the main route at Holborn, and sought powers to extend the branch south under the River Thames to the London and South Western Railway's (L&SWR's) terminus at Waterloo station. The extension included moving Strand station to the corner of Surrey Street, and constructing a single tunnel from there to the BS&WR's Waterloo station which would be provided with additional lifts to serve the GNP&BR's platforms. The branch was to be operated as a shuttle with trains passing at Strand station. [48] The junction layout and short extension to re-site Strand station were permitted, but not the extension to Waterloo. [49] The bill received royal assent on 4 August 1905 as the Great Northern, Piccadilly and Brompton Railway (Various Powers) Act 1905 (5 Edw. 7. c. clxiii). [50]

The second bill again proposed extensions to the east and west, modifying the 1903 plans. In the east, the route was the same as the previous proposal as far as Ludgate Circus. Then, instead of heading south under New Bridge Street and east into Queen Victoria Street to connect to the DR deep level route, the 1905 proposal followed under Carter Lane and Cannon Street to a station at the junction of Queen Street and Watling Street, a short distance north-east of the DR's Mansion House station. The route then followed Queen Victoria Street to Lombard Street where an interchange was to be provided with the C&SLR and the CLR at Bank station. The route continued under Cornhill and Leadenhall Street to end at Aldgate High Street, adjacent to the DR's Aldgate station. [51]

To the west, the 1903 proposed extension from Knightsbridge to Hammersmith via Kensington High Street remained, but it was to continue beyond Hammersmith under King Street, the final station being at the junction of King Street, Goldhawk Road and Chiswick High Road. The tunnels were to continue beyond the final station for a further 350 metres (1,148 ft) under Chiswick High Road, to end at the junction with Homefield Road. The loop north from Hammersmith to Shepherd's Bush was dropped; instead a more direct route to Shepherd's Bush was proposed as a branch from the Hammersmith extension at Addison Road. It was to run under Holland Road to Shepherd's Bush Green, with a station being constructed opposite the CLR station there. It would then continue west under Uxbridge Road to Acton Vale, where a depot was to be built on the surface between Agnes Road and Davis Road. [49] To cover the cost of the proposed extensions, powers to raise further capital of £4.2 million were sought. The review of the bill in Parliament was delayed as the Royal Commission was still sitting during the first half of 1905; the bill was withdrawn by the GNP&BR in July 1905, as insufficient time then remained for completion the parliamentary process before the end of the session. [49]

Construction, 1902–1906

Russell Square station, an example of the Leslie Green design used for the GNP&BR's stations Russell Square station.jpg
Russell Square station, an example of the Leslie Green design used for the GNP&BR's stations

With the funds available from the UERL, construction began in July 1902 at Knightsbridge, before the formal approval of the merger of the B&PCR and GN&SR. [52] Messrs Walker, Price & Reeves was the main contractor appointed for the line's construction, with the exception of Messrs Walter Scott & Middleton in charge of the portal at Barons Court. [53] Work proceeded quickly, enabling the UERL to record in its annual report in October 1904 that 80 per cent of the tunnels had been completed and that track laying was about to begin. [54] Stations were provided with surface buildings designed by architect Leslie Green in the UERL house-style. [55] This consisted of two-storey steel-framed buildings faced with dark oxblood red glazed terracotta blocks, with wide semi-circular windows on the upper floor. [note 11] Except for Finsbury Park, where the platforms were close enough to the surface to be accessed by stairs, and Gillespie Road where a long ramp was used, each of the stations with platforms in tube tunnels was provided with between two and four lifts and an emergency spiral staircase in a separate shaft. [note 12]

The existing DR section between West Kensington and Hammersmith was widened in 1905 to accommodate the new tracks for the GNP&BR. [53] Works on the main route were largely complete by the Autumn of 1906, [52] and after a period of test running the railway was ready to open in December 1906. As a result of the electrification and resignalling of the DR's surface and sub-surface tracks in 1905, the capacity of the existing route was sufficiently increased that the construction of deep-level tunnels east of South Kensington was unnecessary, and the powers were allowed to lapse. [59]

Opening

Newspaper advertisement for the opening of the Piccadilly Tube London's Latest Tube (1906 advert).jpg
Newspaper advertisement for the opening of the Piccadilly Tube

The official opening of the GNP&BR by David Lloyd George, President of the Board of Trade, took place on 15 December 1906. [52] Progress on the Strand branch was delayed, and it opened in November 1907. [60] From its opening, the GNP&BR was generally known by the abbreviated names Piccadilly Tube or Piccadilly Railway, and the names appeared on the station buildings and on contemporary maps of the tube lines. [61] [62]

The railway had stations at:

The service was provided by a fleet of carriages manufactured for the UERL in France and Hungary. [56] These carriages were built to the same design used for the BS&WR and the CCE&HR, and operated as electric multiple unit trains without the need for separate locomotives. Passengers boarded and left the trains through folding lattice gates at each end of cars; these gates were operated by Gate-men who rode on an outside platform and announced station names as trains arrived. The design became known on the Underground as the 1906 stock or Gate stock. Trains for the line were stabled at the Lillie Bridge Depot in West Kensington. [note 13]

Co-operation and consolidation, 1906–1913

Despite the UERL's success in financing and constructing the railway in only seven years, its opening did not bring the financial success that had been expected. In the Piccadilly Tube's first twelve months of operation it carried 26 million passengers, less than half of the 60 million that had been predicted during the planning of the line. [64] The UERL's pre-opening predictions of passenger numbers for its other new lines proved to be similarly over-optimistic, as did the projected figures for the newly electrified DR – in each case, numbers achieved only around fifty per cent of their targets. [note 14]

Pamphlet promoting the line from 1906 Gn piccadilly and brompton tube poster.jpg
Pamphlet promoting the line from 1906

The lower than expected passenger numbers were partly due to competition between the tube and sub-surface railway companies, but the introduction of electric trams and motor buses, replacing slower, horse-drawn road transport, took a large number of passengers away from the trains. The problem was not limited to the UERL; all of London's seven tube lines and the sub-surface DR and Metropolitan Railway were affected to some degree. The reduced revenues generated from the lower passenger numbers made it difficult for the UERL and the other railways to pay back the capital borrowed, or to pay dividends to shareholders. [65]

From 1907, in an effort to improve their finances, the UERL, the C&SLR, the CLR and the GN&CR began to introduce fare agreements. From 1908, they began to present themselves through common branding as the Underground. [65] The W&CR was the only tube railway that did not participate in the arrangement as it was owned by the mainline L&SWR.

The UERL's three tube railway companies were still legally separate entities, with their own management, shareholder and dividend structures. There was duplicated administration between the three companies and, to streamline the management and reduce expenditure, the UERL announced a bill in November 1909 that would merge the Piccadilly, the Hampstead and the Bakerloo Tubes into a single entity, the London Electric Railway (LER), although the lines retained their own individual branding. [66] [note 15] The bill received royal assent on 26 July 1910 as the London Electric Railway Amalgamation Act 1910 (10 Edw. 7. & 1 Geo. 5. c. xxxii). [67] This took effect on 1 July that year. [68]

In October 1911, the Piccadilly tube platforms at Earl's Court station became the first on the Underground network to be served by escalators when a link between the District and Piccadilly platforms was created. [69] [note 16]

In November 1912, a bill was publicised under the LER name that included a plan to extend the Piccadilly tube tracks westwards from Hammersmith to connect to the L&SWR's Richmond branch tracks. [70] The District line already ran trains over this route, and the Piccadilly tube service would provide additional connections. The bill received assent as the London Electric Railway Act 1913 (3 & 4 Geo. 5. c. xcvii) on 15 August 1913. [71] The advent of World War I prevented work on the extension starting. Post-war, a shortage of funds and other priorities meant that the extension was postponed until the early 1930s.

Move to public ownership, 1923–1933

Despite improvements made to other parts of the network, [note 17] the Underground railways continued to struggle financially. The UERL's ownership of the highly profitable London General Omnibus Company (LGOC) since 1912 had enabled the UERL group, through the pooling of revenues, to use profits from the bus company to subsidise the less profitable railways. [note 18] However, competition from numerous small bus companies during the early 1920s eroded the profitability of the LGOC and had a negative impact on the profitability of the whole UERL group.

In an effort to protect the UERL group's income, its chairman Lord Ashfield lobbied the government for regulation of transport services in the London area. Starting in 1923, a series of legislative initiatives were made in this direction, with Ashfield and Labour London County Councillor (later MP and Minister of Transport) Herbert Morrison, at the forefront of debates as to the level of regulation and public control under which transport services should be brought. Ashfield aimed for regulation that would give the UERL group protection from competition and allow it to take substantive control of the LCC's tram system; Morrison preferred full public ownership. [74] After seven years of false starts, a bill was announced at the end of 1930 for the formation of the London Passenger Transport Board (LPTB), a public corporation that would take control of the UERL, the Metropolitan Railway and all bus and tram operators within an area designated as the London Passenger Transport Area. [75] The Board was a compromise – public ownership but not full nationalisation – and came into existence on 1 July 1933. On this date, the LER and the other Underground companies were liquidated. [76]

Legacy

The original GNP&BR route was extended at both ends in the early 1930s. In the north, a new route was constructed to Wood Green, Southgate and Cockfosters. In the west, the extension from Hammersmith approved in 1913 was finally carried out. The extension paralleled the District line's route to Acton and Hounslow, and took over the District line's route to Uxbridge. In 1977, the Hounslow branch was extended to Heathrow Airport. The Strand branch was closed in 1994. [63] Today, the GNP&BR's tunnels form the core of the Piccadilly line's 73.97-kilometre (45.96 mi) route. [1]

York Road, Down Street and Brompton Road stations were closed in the early 1930s due to low usage, [77] but in the lead-up to World War II the underground passageways at Down Street and Brompton Road were considered useful as protected deep shelters for critical government and military operations. Down Street was fitted out for use by the Railway Executive Committee and the War Cabinet. [78] Brompton Road was used as a control centre for anti-aircraft operations, and after the war was used by the Territorial Army. [79] Between September 1940 and July 1946, the Strand branch was temporarily closed, its tunnels used to store exhibits from the British Museum as well as serving as an air-raid shelter. [80]

Notes and references

Notes

  1. A "tube" railway is an underground railway constructed in a cylindrical tunnel by the use of a tunnelling shield, usually deep below ground level.
  2. Rules and procedures known as standing orders existed covering the presentation of private bills to Parliament and a failure to comply with these could result in a bill's rejection. Standing orders for railway bills included requirements to publish a notice of intention to submit the bill in the London Gazette in the November of the preceding year, to submit maps and plans of the route to various interested parties, to provide an estimate of the cost and to deposit 5% of the estimated cost into the Court of Chancery. [3]
  3. The Central London Railway received permission in 1891, the Great Northern and City Railway received permission in 1892, the Baker Street and Waterloo Railway and Charing Cross, Euston and Hampstead Railway received permissions in 1893 and the City and Brixton Railway received permission in 1898. [12]
  4. Yerkes' consortium had first purchased the CCE&HR in September 1900, and also took over the BS&WR in March 1902. [13]
  5. Yerkes was Chairman of the UERL with the other main investors being investment banks Speyer Brothers (London), Speyer & Co. (New York) and Old Colony Trust Company (Boston). [13]
  6. Like many of Yerkes' schemes in the United States, the structure of the UERL's finances was highly complex and involved the use of novel financial instruments linked to future earnings. Over-optimistic expectations of passenger usage meant that many investors failed to receive the returns expected. [15]
  7. In addition to bills for extensions to existing tube railways, bills for seven new tube railways were submitted to Parliament in 1901. [25] While a number received royal assent, none were built.
  8. When the CLR opened, it used heavy unsprung electric locomotives to pull the carriages. These caused significant vibrations on the surface which led to complaints from property owners and occupiers along its route. A committee headed by Lord Rayleigh examined the problem. [27]
  9. As part of the deal by which Yerkes purchased the GN&SR, the GNR imposed a condition that the GN&SR's planned route from Finsbury Park to Wood Green be abandoned and that GNR would build the GN&SR's terminus below ground. [31]
  10. The Windsor committee examined bills for tube railways on an east-west alignment, and the Ribblesdale committee examined bills for tube railways on a north-south alignment. [34]
  11. The existing DR stations at South Kensington and Gloucester Road had extensions added in the UERL style, to accommodate the lifts to the deep level platforms. The DR stations at Earl's Court, Barons Court and Hammersmith were rebuilt to designs by Harry W. Ford. The station at Finsbury Park was constructed by the GNR to its own design without a significant surface building.
  12. The lifts, supplied by American manufacturer Otis, [56] were installed in pairs within 23-foot (7.0 m) diameter shafts. [57] The number of lifts depended on the expected passenger demand at the stations, for example, Down Street had two lifts, but Russell Square, Gloucester Road and Caledonian Road originally had four each. [58]
  13. Trains entered and exited the depot via a loop from the eastbound DR line to the east of West Kensington station.
  14. The UERL had predicted 35 million passengers for the B&SWR and 50 million for the CCE&HR in their first year of operation, but achieved 20.5 and 25 million respectively. For the DR it had predicted an increase to 100 million passengers after electrification, but achieved 55 million. [64]
  15. The merger was carried out by transferring the assets of the CCE&HR and the BS&WR to the GNP&BR and renaming the GNP&BR as the London Electric Railway.
  16. The success of the Earl's Court escalators led to all later deep-tube stations being built with escalators rather than lifts. Where possible, escalators were gradually installed to replace lifts in existing stations.
  17. During World War I, the BS&WR was extended from Paddington to Watford Junction. Post war; the extension of the CLR from Wood Lane to Ealing Broadway (1920) was opened. [72]
  18. By having a virtual monopoly of bus services, the LGOC was able to make large profits and pay dividends far higher than the underground railways ever had. In 1911, the year before its take over by the UERL, the dividend had been 18 per cent. [73]

Related Research Articles

<span class="mw-page-title-main">Piccadilly line</span> London Underground line

The Piccadilly line is a deep-level London Underground line running from the north to the west of London. It has two branches, which split at Acton Town, and serves 53 stations. The line serves Heathrow Airport, and some of its stations are near tourist attractions such as Piccadilly Circus and Buckingham Palace. The District and Metropolitan lines share some sections of track with the Piccadilly line. Printed in dark blue on the Tube map, it is the fourth-busiest line on the Underground network, with over 210 million passenger journeys in 2011/12.

<span class="mw-page-title-main">Charing Cross tube station</span> London Underground station

Charing Cross is a London Underground station at Charing Cross in the City of Westminster. The station is served by the Bakerloo and Northern lines and provides an interchange with Charing Cross mainline station. On the Bakerloo line it is between Embankment and Piccadilly Circus stations and on the Northern line it is between Embankment and Leicester Square stations. The station is in fare zone 1.

<span class="mw-page-title-main">Embankment tube station</span> London Underground station

Embankment is a London Underground station in the City of Westminster, known by various names during its history. It is served by the Circle, District, Northern and Bakerloo lines. On the Bakerloo line and the Charing Cross branch of the Northern line, the station is between Waterloo and Charing Cross stations; on the Circle and District lines, it is between Westminster and Temple and is in Travelcard Zone 1. The station has two entrances, one on Victoria Embankment and the other on Villiers Street. The station is adjacent to Victoria Embankment Gardens and is close to Charing Cross station, Embankment Pier, Hungerford Bridge, Cleopatra's Needle, the Royal Air Force Memorial, the Savoy Chapel and Savoy Hotel and the Playhouse and New Players Theatres.

<span class="mw-page-title-main">Aldwych tube station</span> London Underground station, 1907–1994

Aldwych is a closed station on the London Underground, located in the City of Westminster in Central London. It was opened in 1907 with the name Strand, after the street on which it is located. It was the terminus of the short Piccadilly line branch from Holborn that was a relic of the merger of two railway schemes. The station building is close to the Strand's junction with Surrey Street, near Aldwych. During its lifetime, the branch was the subject of a number of unrealised extension proposals that would have seen the tunnels through the station extended southwards, usually to Waterloo.

<span class="mw-page-title-main">Holborn tube station</span> London Underground station

Holborn is a London Underground station in Holborn, Central London, located at the junction of High Holborn and Kingsway. It is served by the Central and Piccadilly lines. On the Central line the station is between Tottenham Court Road and Chancery Lane stations; on the Piccadilly line it is between Covent Garden and Russell Square and is in Travelcard Zone 1. Close by are the British Museum, Lincoln's Inn Fields, Red Lion Square, Bloomsbury Square, London School of Economics and Sir John Soane's Museum.

<span class="mw-page-title-main">Green Park tube station</span> London Underground station

Green Park is a London Underground station located on the edge of Green Park, with entrances on both sides of Piccadilly. It is served by the Jubilee, Piccadilly and Victoria lines. On the Jubilee line it is between Bond Street and Westminster; on the Piccadilly line it is between Piccadilly Circus and Hyde Park Corner and on the Victoria line it is between Victoria and Oxford Circus. It is in fare zone 1.

<span class="mw-page-title-main">South Kensington tube station</span> London Underground station

South Kensington is a London Underground station in the district of South Kensington, south west London. It is served by the District, Circle and Piccadilly lines. On the District and Circle lines it is between Gloucester Road and Sloane Square, and on the Piccadilly line between Gloucester Road and Knightsbridge. It is in Travelcard Zone 1. The main station entrance is located at the junction of Old Brompton Road (A3218), Thurloe Place, Harrington Road, Onslow Place and Pelham Street. Subsidiary entrances are located in Exhibition Road giving access by pedestrian tunnel to the Natural History, Science and Victoria and Albert Museums. Also close by are the Royal Albert Hall, Imperial College London, the Royal College of Music, the London branch of the Goethe-Institut and the Ismaili Centre.

<span class="mw-page-title-main">Earl's Court tube station</span> London Underground station

Earl's Court tube station is a Grade II listed London Underground station in Earl's Court, London, on the District and Piccadilly lines. It is an important interchange for both lines and is situated in both Travelcard Zone 1 and Zone 2. The station has an eastern entrance on Earl's Court Road and a western entrance on Warwick Road. Another former entrance allowed passengers to enter the station from the other side of Warwick Road, via a ticket hall and subway leading to a concourse beneath the District line platforms. Earl's Court is a step-free tube station; the Earls Court Road entrance provides lift access between street and platform levels.

<span class="mw-page-title-main">Covent Garden tube station</span> London Underground station

Covent Garden is a London Underground station serving Covent Garden and the surrounding area in the West End of London. It is on the Piccadilly line between Leicester Square and Holborn stations and is in Travelcard Zone 1. The station is at the corner of Long Acre and James Street and the street-level concourse is a Grade II listed building.

<span class="mw-page-title-main">Gloucester Road tube station</span> London Underground station

Gloucester Road is a London Underground station in Kensington, west London. The station entrance is located close to the junction of Gloucester Road and Cromwell Road. Close by are the Cromwell Hospital and Baden-Powell House.

<span class="mw-page-title-main">Down Street tube station</span> Closed London Underground station

Down Street, also known as Down Street (Mayfair), is a disused station on the London Underground, located in Mayfair, west London. The Great Northern, Piccadilly and Brompton Railway opened it in 1907. It was latterly served by the Piccadilly line and was situated between Dover Street (now named Green Park) and Hyde Park Corner stations.

<span class="mw-page-title-main">City and South London Railway</span> Underground railway company in London

The City and South London Railway (C&SLR) was the first successful deep-level underground "tube" railway in the world, and the first major railway to use electric traction. The railway was originally intended for cable-hauled trains, but owing to the bankruptcy of the cable contractor during construction, a system of electric traction using electric locomotives—an experimental technology at the time—was chosen instead.

<span class="mw-page-title-main">District Railway</span> Former underground railway in London (1868–1933)

The Metropolitan District Railway, also known as the District Railway, was a passenger railway that served London, England, from 1868 to 1933. Established in 1864 to complete an "inner circle" of lines connecting railway termini in London, the first part of the line opened using gas-lit wooden carriages hauled by steam locomotives. The Metropolitan Railway operated all services until the District Railway introduced its own trains in 1871. The railway was soon extended westwards through Earl's Court to Fulham, Richmond, Ealing and Hounslow. After completing the inner circle and reaching Whitechapel in 1884, it was extended to Upminster in Essex in 1902.

<span class="mw-page-title-main">Central London Railway</span> Underground railway company in London

The Central London Railway (CLR), also known as the Twopenny Tube, was a deep-level, underground "tube" railway that opened in London in 1900. The CLR's tunnels and stations form the central section of the London Underground's Central line.

<span class="mw-page-title-main">Charing Cross, Euston and Hampstead Railway</span> Underground railway company in London

The Charing Cross, Euston and Hampstead Railway (CCE&HR), also known as the Hampstead Tube, was a railway company established in 1891 that constructed a deep-level underground "tube" railway in London. Construction of the CCE&HR was delayed for more than a decade while funding was sought. In 1900 it became a subsidiary of the Underground Electric Railways Company of London (UERL), controlled by American financier Charles Yerkes. The UERL quickly raised the funds, mainly from foreign investors. Various routes were planned, but a number of these were rejected by Parliament. Plans for tunnels under Hampstead Heath were authorised, despite opposition by many local residents who believed they would damage the ecology of the Heath.

<span class="mw-page-title-main">London Electric Railway</span> United Kingdom legislation

The London Electric Railway (LER) was an underground railway company operating three lines on the London Underground. It was formed in 1910 and existed until 1933, when it was merged into the London Passenger Transport Board.

<span class="mw-page-title-main">Baker Street and Waterloo Railway</span> Underground railway company in London

The Baker Street and Waterloo Railway (BS&WR), also known as the Bakerloo tube, was a railway company established in 1893 that built a deep-level underground "tube" railway in London. The company struggled to fund the work, and construction did not begin until 1898. In 1900, work was hit by the financial collapse of its parent company, the London & Globe Finance Corporation, through the fraud of Whitaker Wright, its main shareholder. In 1902, the BS&WR became a subsidiary of the Underground Electric Railways Company of London (UERL) controlled by American financier Charles Yerkes. The UERL quickly raised the funds, mainly from foreign investors.

The transport system now known as the London Underground began in 1863 with the Metropolitan Railway, the world's first underground railway. Over the next forty years, the early sub-surface lines reached out from the urban centre of the capital into the surrounding rural margins, leading to the development of new commuter suburbs. At the turn of the nineteenth century, new technology—including electric locomotives and improvements to the tunnelling shield—enabled new companies to construct a series of "tube" lines deeper underground. Initially rivals, the tube railway companies began to co-operate in advertising and through shared branding, eventually consolidating under the single ownership of the Underground Electric Railways Company of London (UERL), with lines stretching across London.

The Piccadilly, City and North East London Railway (PC&NELR) was a tube railway in London proposed in 1902. The railway was to run from Southgate to Hammersmith and Shepherd's Bush via Palmers Green, Tottenham, Stoke Newington, Dalston, Shoreditch, the City of London, the West End and Kensington.

<span class="mw-page-title-main">Underground Electric Railways Company of London</span> Holding company for underground railways and bus operators in London

The Underground Electric Railways Company of London Limited (UERL), known operationally as the Underground for much of its existence, was established in 1902. It was the holding company for the three deep-level "tube" underground railway lines opened in London during 1906 and 1907: the Baker Street and Waterloo Railway, the Charing Cross, Euston and Hampstead Railway and the Great Northern, Piccadilly and Brompton Railway. It was also the parent company from 1902 of the District Railway, which it electrified between 1903 and 1905. The UERL is a precursor of today's London Underground; its three tube lines form the central sections of today's Bakerloo, Northern and Piccadilly lines.

References

  1. 1 2 Length of line calculated from distances given at "Clive's Underground Line Guides, Piccadilly line, Layout". Clive D. W. Feather. Retrieved 21 March 2009.
  2. "No. 26796". The London Gazette . 20 November 1896. pp. 6428–6430.
  3. Badsey-Ellis 2005, p. 41.
  4. Badsey-Ellis 2005, p. 71.
  5. 60 & 61 Vict. c. cxcii "An Act for incorporating the Brompton and Piccadilly Circus Railway Company and for empowering them to construct an Underground Railway from Piccadilly Circus to South Kensington and for other purposes."
  6. 1 2 "No. 26881". The London Gazette . 10 August 1897. pp. 4481–4483.
  7. "No. 26797". The London Gazette . 22 November 1896. pp. 6764–6767.
  8. Badsey-Ellis 2005, pp. 70–71.
  9. 1 2 "No. 27025". The London Gazette . 22 November 1898. pp. 7040–7043.
  10. 1 2 Badsey-Ellis 2005, p. 77.
  11. "No. 27105". The London Gazette . 4 August 1899. pp. 4833–4834.
  12. Badsey-Ellis 2005, pp. 47, 56, 59, 60 and 76.
  13. 1 2 Badsey-Ellis 2005, p. 118.
  14. UK Retail Price Index inflation figures are based on data from Clark, Gregory (2017). "The Annual RPI and Average Earnings for Britain, 1209 to Present (New Series)". MeasuringWorth. Retrieved 11 June 2022.
  15. Wolmar 2004, pp. 170–172.
  16. Badsey-Ellis 2005, pp. 73–74.
  17. "No. 27025". The London Gazette . 22 November 1898. pp. 7245–7247.
  18. 1 2 Badsey-Ellis 2005, p. 85.
  19. "No. 27107". The London Gazette . 11 August 1899. pp. 5011–5012.
  20. "No. 27137". The London Gazette . 21 November 1899. pp. 7252–7255.
  21. "No. 27138". The London Gazette . 24 November 1899. pp. 7855–7856.
  22. "No. 27218". The London Gazette . 7 August 1900. pp. 4857–4858.
  23. 1 2 "No. 27251". The London Gazette . 27 November 1900. pp. 7887–7890.
  24. 1 2 3 Badsey-Ellis 2005, p. 96.
  25. Badsey-Ellis 2005, p. 92.
  26. Badsey-Ellis 2005, p. 93.
  27. Badsey-Ellis 2005, p. 91.
  28. Badsey-Ellis 2005, p. 111.
  29. 1 2 Badsey-Ellis 2005, pp. 152–153.
  30. "No. 27379". The London Gazette . 22 November 1901. pp. 7789–7793.
  31. 1 2 Badsey-Ellis 2005, p. 138.
  32. "No. 27379". The London Gazette . 22 November 1901. pp. 7746–7749.
  33. "No. 27379". The London Gazette . 22 November 1901. pp. 7793–7795.
  34. Badsey-Ellis 2005, p. 131.
  35. "No. 27464". The London Gazette . 12 August 1902. pp. 5247–5248.
  36. "No. 27497". The London Gazette . 21 November 1902. p. 7533.
  37. "No. 27497". The London Gazette . 21 November 1902. pp. 7804–7805.
  38. "No. 27497". The London Gazette . 21 November 1902. pp. 7815–7817.
  39. 1 2 3 Badsey-Ellis 2005, p. 215.
  40. "No. 27497". The London Gazette . 21 November 1902. pp. 7789–7796.
  41. "No. 27497". The London Gazette . 21 November 1902. pp. 7813–7815.
  42. Badsey-Ellis 2005, pp. 216–217.
  43. "No. 27580". The London Gazette . 24 July 1903. p. 4668.
  44. "No. 27588". The London Gazette . 14 August 1903. pp. 5143–5144.
  45. Badsey-Ellis 2005, p. 226.
  46. "No. 27737". The London Gazette . 22 November 1904. pp. 7764–7767.
  47. "No. 27737". The London Gazette . 22 November 1904. pp. 7767–7769.
  48. Badsey-Ellis 2005, p. 238.
  49. 1 2 3 Badsey-Ellis 2005, p. 242.
  50. "No. 27825". The London Gazette . 8 August 1905. pp. 5447–5448.
  51. Badsey-Ellis 2005, pp. 241–242.
  52. 1 2 3 Wolmar 2004, p. 181.
  53. 1 2 Horne 2007, p.17.
  54. "Railways and Other Companies". The Times. 14 October 1904. p. 10. Retrieved 21 March 2009.
  55. Wolmar 2004, p. 175.
  56. 1 2 Wolmar 2004, p. 188.
  57. Connor 1999, plans of stations
  58. "Clive's Underground Line Guides, Lifts and Escalators". Clive D. W. Feather. Retrieved 21 March 2009.
  59. Badsey-Ellis 2005, p. 218.
  60. Wolmar 2004, p. 183.
  61. Photograph of Holborn station, 1907 London Transport Museum photographic archive. Retrieved 21 March 2009.
  62. "1908 tube map". A History of the London Tube Maps. Archived from the original on 23 February 2009. Retrieved 21 March 2009.
  63. 1 2 3 4 5 6 7 8 9 10 Rose 1999
  64. 1 2 Wolmar 2004, p. 191.
  65. 1 2 Badsey-Ellis 2005, pp. 282–283.
  66. "No. 28311". The London Gazette . 23 November 1909. pp. 8816–8818.
  67. "No. 28402". The London Gazette . 29 July 1910. pp. 5497–5498.
  68. Day & Reed 2008 , p. 79.
  69. Wolmar 2004, p. 182.
  70. "No. 28665". The London Gazette . 22 November 1912. pp. 8798–8801.
  71. "No. 28747". The London Gazette . 19 August 1913. pp. 5929–5931.
  72. Rose 1999.
  73. Wolmar 2004, p. 204.
  74. Wolmar 2004, pp. 259–262.
  75. "No. 33668". The London Gazette . 9 December 1930. pp. 7905–7907.
  76. Wolmar 2004, p. 266.
  77. Connor, pp. 31, 36 and 44.
  78. Connor, p. 33.
  79. Connor, p. 50.
  80. Connor, pp. 98–99.

Bibliography