| | |
| Class overview | |
|---|---|
| Name | P76-class submarines |
| Operators | |
| Preceded by | Project 75I class |
| Cost | ₹ 70,000 crore (US$8.3 billion) |
| Planned | 6 |
| General characteristics | |
| Type | Attack submarine |
| Displacement | 3,000 tonnes |
| Propulsion | |
| Armament | Heavyweight torpedoes and land-attack cruise missiles |
Project-76, also referred to as P76, is an initiative by India's Ministry of Defence (MoD) to develop diesel-electric submarines for the Indian Navy (IN). The submarine is being developed by the Defence Research and Development Organisation (DRDO). [1]
In 1997, the Cabinet Committee on Security (CCS) - the highest-decision making body of India's Ministry of Defence (MoD), approved the construction of two Type 209/1500 attack submarines (SSK) at a then-estimated cost of INR ₹700 crore. This effort, which was conceived in the wake of an international corruption scandal related to India's acquisition of the Shishumar-class submarines, called for the construction of two Type 209/1500 SSKs at Mazagon Dock Shipbuilders Limited (MDL) with the assistance of a foreign naval firm in a corroborative role. In accordance with the scheme, the Indian Navy (IN) and MDL approached several naval enterprises for assistance; however, the French-based Thomson-CSF (TCSF) was the only firm willing to participate. [2]
Two years later, on 12 July 1999, the Cabinet Committee on Security (CCS) approved a two-phase plan to build 24 submarines over a span of 30 years. [3] [4] The plan was named 'Project for Series Construction of Submarines for the Indian Navy and Acquisition of National Competence in Submarine Building', also referred as 'Submarine-building Perspective Plan'. For the first phase, six submarines each were to be built at MDL under Project 75 (P-75) along with a parallel production line of another public/private shipyard [5] under Project-75 (India) or P-75(I) with technology transfer. Under the second phase, twelve submarines would be built including complete indigenous design, development and construction of submarines in India. [2] [6] While the first phase was scheduled for completion within 2012, the second phase would be executed in 2012–2030. [7]
For the Project-75 , two options emerged. The first being construction of the Type 209/1500 at MDL initially with the combat suite of TCSF with the rest being based on modified Scorpène submarine design based on Naval requirements. The second option recommended the construction of all the SSKs based on the newer Scorpène design. Ultimately, the Naval Heqadquarters chose the latter, reasoning that the Scorpène, which had been offered with a provision of technology transfer (TOT), was more advanced than the Type 209/1500. The initial plan to ally with TCSF was dropped in April 2001 and negotiations for the procurement of the Scorpène design under the first phase, dubbed Project-75 (P-75), began in November 2001. The Scorpène design was offered by another French-based naval firm, Armaris (later DCNS, now Naval Group). [2] The P-75 contract signed on 6 October 2005 [8] resulted in the construction of six Kalvari-class submarines [6] beginning 23 May 2009. [9] The final unit, INS Vagsheer (S26), was commissioned in January 2025. [10]
Though the second batch of six submarines, under Project-75 (India), was to be executed simultaneously alongside P-75, financial constraints within the MoD led to P-75 being the only project sanctioned for six submarines. [11] Proposals to move ahead with the acquisition failed twice after the project was approved in 2010 and 2014. [12] [13] Following delays, the Navy mandated the presence of an operational air-independent propulsion (AIP) plant with the submarine design. This was done to maintain the submarine's relevance in future as the boats' induction timeline was already delayed to 2022. [13] [14] The third approval from the Defence Acquisition Council (DAC), chaired by the Indian Minister of Defence, was accorded in January 2019. [15] [16] In January 2025, the bid by Larsen & Toubro to build S-80 Plus-class submarine, in collaboration with Spain's Navantia, was disqualified. [17] [18] Mazagon Dock's partnership with TKMS remained the only bidder who were thereafter invited for techno-commercial negotiations with the Indian Ministry of Defence. [19] Negotiations were reported to have began in July 2025 [20] while the deal could be signed in January 2026. [21] [22]
The second phase of the plan was amended midway to maintain the relevance of the submarine fleets as per evolving threats. [7] The program to construct and deploy a fleet of nuclear submarines was first envisaged in late 1990s was fast-tracked following growing patrols by the People's Liberation Army Navy ships. This included a solitary two-month "anti-piracy" patrol by a Type 093 submarine in the Indian Ocean before returning to Yulin Naval Base on 13 December 2013. On 12 February 2014, R&AW evaluations described the deployment as having significantly intensified India’s security concerns. [23] The Navy has already acquired experience of operating nuclear submarines after leasing of INS Chakra (1987) and INS Chakra (2011) for three and nine years, respectively. [24] [25] [26] The force has also ordered a third Chakra submarine for a lease of 10 years starting 2025. [27] [28] The submarine is expected to be delivered to India in 2028 following delays. [29] [30]
In February 2015, the Government of India through a Cabinet Committee on Security (CCS) approval, gave rise to another indigenous submarine project — the Project 75 Alpha (now Project 77). A fleet of six nuclear attack submarine s, with a displacement of 6,000 tonnes, were to be built under the project. [31] The design phase had begun by December 2017 [32] with constructions to commence by 2023–24 and first unit to enter service in 2032. [33] The preliminary design phase was completed by February 2020. [34] In October 2024, the CCS cleared the construction of first two units in the Shipbuilding Centre (SBC), Visakhapatnam, of the Ministry of Defence where the Arihant-class submarines were built. [35] The displacement was increased to 9,800 tonnes [36] and equipped with 200 MWe-rated nuclear reactor. [37]
With the approval of the Project 77, the number of boats under Project-76 was reduced to six units. The design was expected to inherit elements from the Project-75 and Project-75(I) designs. [7] The development was cleared by defence ministry in June 2024 followed by a feasibility study conducted by DRDO. [38] An approval from the Cabinet Committee on Security (CCS) for the further detailed design of the submarine is due as of February 2025. [39]
Both Project 76 and Project 77 are being led by the Advanced Technology Vessel headquarters which is responsible for the development and construction of India's nuclear-powered, ballistic missile submarine fleet including Arihant class and S5-class submarines. [38] [23] While the final two submarines from the Arihant class is expected to be commissioned in early 2026 and 2027, respectively, the construction of first two units of S5 submarines has also begun in the Shipbuilding Centre (SBC), Visakhapatnam. [40] [41] [42]
Naval Design Bureau, under the command of Director General (Naval Design) was working on diesel-electric submarines equipped with air-independent propulsion (AIP) in 2022. [1] [7]
On 25 August 2023, Mazagon Dock Limited (MDL) signed a memorandum of understanding with Directorate of Naval Design (Submarine Design Group) for collaboration in R&D of technology and equipment for submarine applications. [43] [44]
In July 2024, the Defence Research and Development Organisation (DRDO) started a one-year feasibility study on the design and development of an indigenous conventional submarine under Project-76. The defence ministry had cleared the project to calculate the "contours". This programme has been taken up on the lines of the Advanced Technology Vessel (ATV) project. Following the study a formal case will be forwarded to the Cabinet Committee on Security (CCS) for project sanction. The design would include a high indigenous content including missiles, armament, sonar, communication equipment suite, mast and periscope. The design will also include the DRDO-developed AIP module for the Kalvari-class submarines. However, the AIP module's current power output of 13.5 kW (18.1 hp) would be scaled up to 20 kW (27 hp) in order to meet the power outputs of future P76 design. The overall AIP is a stack of 24 phosphoric acid fuel cells (PAFC). [38] The module also includes an on-board Hydrogen generation system. [45]
The activation of the programme was part of the 100-day Action Plan of the Ministry of Defence (MoD) [46] following the formation of new government. [47] [48]
As of February 2025, development proposal for the Cabinet Committee on Security (CCS) approval would be ready by 2 months. The inter-ministerial consultation was underway. Post approval, two to three years would be required for design phase followed by five years for construction and induction. The submarines would be equipped with torpedo tube-launched land-attack cruise missiles and displace 3,000 tonnes. The indigenous content is expected to be 90-95%. Imports will only include some chips, electronics, and tubes. [39] The submarine will include indigenous weapon control systems and lithium-ion batteries. The construction of the first submarine would begin in 2028. [49]
The development is scheduled for completion by 2026–27 followed by construction of first submarine in 6–7 years and all six to be delivered within ten years. A 15-year roadmap, named Technology Perspective and Capability Roadmap 2025 (TPCR-25), unveiled development multiple key components for an Indigenous Conventional Submarine. [44] Meanwhile, MDL and Larsen & Toubro have demonstrated Arowana and SOV-400, respectively. MDL is also reportedly undertaken simultaneous design and development of full-scale indigenous conventional submarine by 2028. [44]
References to the Indian Navy
Immediately after assumption of charge, Shri Rajnath Singh chaired a review meeting on the first 100 days' Action Plan of MoD under the new government led by Prime Minister Shri Narendra Modi.