INS Vikrant under construction. | |
Class overview | |
---|---|
Name | Vikrant-class aircraft carrier |
Builders | Cochin Shipyard Limited |
Operators | Indian Navy |
Preceded by | INS Vikramaditya |
Succeeded by | INS Vishal |
In service | 2022–present |
Planned | 2 [1] [2] [3] |
Completed | 1 |
Active | 1 |
General characteristics | |
Type | Aircraft carrier |
Displacement | 44,000 t (43,000 long tons) |
Length | 262 metres (859 ft 7 in) |
Beam | 62 metres (203 ft 5 in) |
Draught | 8.4 metres (27 ft 7 in) |
Depth | 25.6 metres (84 ft 0 in) |
Decks | 2.5 acres (110,000 sq ft; 10,000 m2) |
Propulsion |
|
Speed | 28 kn (52 km/h) |
Range | 8,000 nautical miles (15,000 km) [4] |
Complement | 1,400 (including air crew) |
Sensors and processing systems |
|
Electronic warfare & decoys | C/D band early air-warning radar [4] |
Armament | |
Aircraft carried |
|
The Vikrant class (formerly Project 71 Air Defence Ship (ADS) or Indigenous Aircraft Carrier (IAC)) is a class of aircraft carrier being built for the Indian Navy. The class represents the largest warships and the first aircraft carriers to be designed and built in India.
Preparations for building the lead vessel of the class, INS Vikrant, started in 2008, and the keel was laid in February 2009. The carrier was floated out of its dry dock on 29 December 2011, [7] launched on 12 August 2013 and commissioned on 2 September 2022. [8] [9] The scale and complexity of the project caused problems which delayed the commencement and timeline of construction for the carrier. Technical difficulties, the cost of refitting the Russian-built carrier INS Vikramaditya, and billions in cost overruns [10] delayed plans for the first of the vessels to enter service. [11]
In 1989 India announced a plan to replace its ageing British-built aircraft carriers, Vikrant and Viraat, with two new 28,000 ton Air Defence Ships (ADS) that would operate the BAe Sea Harrier aircraft. The first vessel was to replace Vikrant, which was set to decommission in early 1997. Construction of the ADS was to start at the Cochin Shipyard (CSL) in 1993 after the Indian Naval Design Organisation had translated this design study into a production model. Following the 1991 economic crisis, the plans for construction of the vessels were put on hold indefinitely.
In 1999, then Defence Minister George Fernandes revived the project and sanctioned the construction of the Project 71 ADS. [12] By that time, given the ageing Sea Harrier fleet, the letter of intent called for a carrier that would carry more modern jet fighters. In 2001, CSL released a graphic illustration showing the 32,000-ton STOBAR (Short Take-Off But Arrested Recovery) design with a pronounced ski jump. [13] The aircraft carrier project finally received formal government approval in January 2003. By then, design updates called for a 37,500 ton carrier to operate the MiG-29K. India opted for a three-carrier fleet consisting of one carrier battle group stationed on each seaboard, and a third carrier held in reserve, in order to continuously protect both its flanks, to protect economic interests and mercantile traffic, and to provide humanitarian platforms in times of disasters, since a carrier can provide a self-generating supply of fresh water, medical assistance or engineering expertise to populations in need for assistance. [14]
In August 2006, then Chief of the Naval Staff, Admiral Arun Prakash stated that the designation for the vessel had been changed from Air Defence Ship (ADS) to Indigenous Aircraft Carrier (IAC). The euphemistic ADS had been adopted in planning stages to ward off concerns about a naval build-up. Final revisions to the design increased the displacement of the carriers from 37,500 tons to over 40,000 tons. The length of the ship also increased from 252 metres (827 ft) to over 260 metres (850 ft). [15]
The first ship of the class, Vikrant, displaces about 40,000 metric tons (39,000 long tons ), is 262 metres (859 ft 7 in) long and has a tailored air group of up to thirty aircraft. The IAC-I features a STOBAR [16] (Short Take-Off But Arrested Recovery) configuration with a ski-jump. The deck is designed to enable aircraft such as the MiG-29K to operate from the carrier. It will deploy up to 30 fixed-wing aircraft, [17] primarily the Mikoyan MiG-29K, besides carrying 10 Kamov Ka-31 or Westland Sea King helicopters. The Ka-31 will fulfill the airborne early warning (AEW) role and the Sea King will provide anti-submarine warfare (ASW) capability. [18] [19]
Following the formal commissioning of Vikrant, a proposal was made to build another IAC-class carrier before INS Vishal. By November 2023, a ₹400 billion worth proposal for a new carrier was on track to be approved by the Defense Acquisition Council — the country's top defense decision-making body headed by Defence Minister, Rajnath Singh. [20] [21]
The new carrier, which can hold at least 28 fighter jets and helicopters will displace 45,000 tons of water and will be flying the French Rafale jets initially, but will fly HAL TEDBF fighters in 2030s. [22]
As of March 2024, Indian Navy has been submitted the proposal to acquire another aircraft carrier to Ministry of Defence. IAC-2 will have an increased indigenous content than INS Vikrant (IAC-1). The major components which will be indigenised includes arresting gear system, restraining gear used to launch aircraft and precision approach radar. [23] [24]
The carrier is powered by four General Electric LM2500 gas turbines on two shafts, generating over 80MW of power. The gearboxes for the carriers were designed and supplied by Elecon Engineering. [7] [25] [26]
India considered a number of aircraft for operation from its INS Vikramaditya and the planned indigenous aircraft carrier. India evaluated the Russian Sukhoi Su-33, but chose the lighter Mikoyan MiG-29K as Vikramaditya was smaller and lacked an aircraft catapult. [27] On 18 January 2010, it was reported that India and Russia were close to signing a deal for 29 MiG-29K fighters to operate from IAC-I. [28] In addition, the navy signed a deal for six naval-variants of the HAL Tejas. [29] In June 2012, Flight Global reported that the Indian Navy was considering the use of Rafale M (Naval variant) on these carriers. [30]
In December 2016, the navy announced that the HAL Tejas is overweight for carrier operations, and other alternatives will be looked at. [31] [32]
Amongst the first construction problems experienced was the lack of supply of carrier-grade steel due to the inability of Russia to supply the AB/A grade steel. Finally, the Defence Metallurgical Research Laboratory (DMRL) worked with the Steel Authority of India Limited (SAIL) to create suitable production facilities for the steel in India. [7] [18] The SAIL Steel Plants of the Steel at Bhilai, Rourkela, Durgapur and Bokaro manufactured 26,000 tonnes of three special steels being used for the hull, flight deck and floor compartments of the carrier. [33]
The keel for Vikrant was laid by Defence Minister A.K. Antony at the Cochin Shipyard on 28 February 2009. [34] [35] The ship uses modular construction, with 874 blocks joined together for the hull. By the time the keel was laid, 423 blocks weighing over 8,000 tonnes had been completed. [36] The construction plan called for the carrier to be launched in 2010, when it would displace some 20,000 tonnes, as a larger displacement could not be accommodated in the building bay. It was planned that after about a year’s development in the refit dock, the carrier would be launched when all the major components, including underwater systems, would be in place. Outfitting would then be carried out after launch. As per the Cabinet Committee on Security (CCS), sea trials were initially planned to commence in 2013, with the ship to be commissioned in 2014. [37] [38]
In March 2011, it was reported that the project had been affected by the delay in delivery of the huge main gearboxes for the carrier. The supplier, Elecon Engineering, had to work around a number of technical complexities due to the length of the propulsion shafts. [39] Other issues resulting in delays included an accident with a diesel generator and an issue with its alignment. [40] In August 2011, the defence ministry reported to the Lok Sabha that 75% of the construction work for the hull of the lead carrier had been completed and the carrier would be first launched in December 2011, following which further works would be completed until commissioning. [41] [42] On 29 December 2011, the completed hull of the carrier was first floated out of its dry dock at CSL, with its displacement at over 14,000 tonnes. [25] Interior works and fittings on the hull would be carried out until the second half of 2012, when it would again be dry-docked for integration with its propulsion and power generation systems. [4] [7]
In July 2012, The Times of India reported that construction of Vikrant has been delayed by 3 years, and the ship would be ready for commissioning by 2017. Then again in November 2012, NDTV reported that cost of the aircraft carrier had increased and the delivery has been delayed by at least five years and is expected to be with the Indian Navy only after 2018 as against the scheduled date of delivery of 2014. [43] Work has begun for next stage which includes installation of the integrated propulsion system. Italian defence company Avio is installing the integrated platform management system (IPMS). [44]
In July 2016, the Comptroller & Auditor General (CAG) published a 2014 project plan, supplied by the Cochin Shipyard, that shows an expected completion date in 2023, though the Navy hopes to partially commission the ship before this date. [11]
In July 2013, Defence Minister A K Antony announced that Vikrant would be launched on 12 August at the Cochin Shipyard. After its launch, Vikrant would be re-docked for completion of rest of the work including the flight deck. According to Vice Admiral Robin Dhowan, about 83% of the fabrication work and 75% of the construction work has been completed. He said that 90% of the body work of the aircraft carrier had been designed and made in India, about 50% of the propulsion system, and about 30% of the fighting capability of the carrier was Indian. He also said that the ship will be equipped with a long range missile system with multi-function radar and a close-in weapon system (CIWS). The ship was launched by Elizabeth Antony, wife of Defence Minister A K Antony on 12 August 2013. [45]
Name | Pennant | Tonnage | Laid down | Launched | Sea trials | Commissioning | Details |
---|---|---|---|---|---|---|---|
Vikrant | TBD | 40,000 | 28 February 2009 | 12 August 2013 [46] | 2019 [45] | 2022 [8] | Active in service |
IAC-2 | TBD | 45,000 | TBD | TBD | TBD | TBD |
A carrier battle group (CVBG) is a naval fleet consisting of an aircraft carrier capital ship and its large number of escorts, together defining the group. The CV in CVBG is the United States Navy hull classification code for an aircraft carrier.
INSVikrant was a Majestic-class aircraft carrier of the Indian Navy. The ship was laid down as HMS Hercules for the British Royal Navy during World War II, but was put on hold when the war ended. India purchased the incomplete carrier in 1957, and construction was completed in 1961. Vikrant was commissioned as the first aircraft carrier of the Indian Navy and played a key role in enforcing the naval blockade of East Pakistan during the Indo-Pakistani War of 1971.
INS Viraat was a Centaur-class light aircraft carrier of the Indian Navy. INS Viraat was the flagship of the Indian Navy until INS Vikramaditya was commissioned in 2013. The ship was completed and commissioned in 1959 as the Royal Navy's HMS Hermes, and decommissioned in 1984. It was sold to India in 1987. INS Viraat was commissioned into the Indian Navy on 12 May 1987, and served for almost 30 years.
STOBAR is a system used for the launch and recovery of aircraft from the deck of an aircraft carrier, combining elements of "short take-off and vertical landing" (STOVL) with "catapult-assisted take-off, barrier-arrested recovery" (CATOBAR).
INS Kadamba or Naval Base Karwar or Project Seabird is an Indian Navy base located near Karwar in Karnataka. The first phase of construction of the base, code-named Project Seabird, was completed in 2005 and the base was commissioned on 31 May 2005. Development of Phase II commenced in 2011. INS Kadamba is currently the third largest Indian naval base, and is expected to become the largest naval base in the eastern hemisphere after completion of expansion Phase IIB. The construction of Naval Base covers an area of 11,169 acres in Phase I.
INS Vikramaditya is a modified Kiev-class aircraft carrier and the flagship of the Indian Navy. The carrier entered into service in 2013.
The Mikoyan MiG-29K is a Russian all-weather carrier-based multirole fighter aircraft developed by the Mikoyan Design Bureau. The MiG-29K was developed in the late 1980s from the MiG-29M. Mikoyan describes it as a 4+ generation aircraft.
Cochin Shipyard Ltd (CSL) is the largest shipbuilding and maintenance facility in India. It is part of a line of maritime-related facilities in the port-city of Kochi, in the state of Kerala, India. Of the services provided by the shipyard are building platform supply vessels and double-hulled oil tankers. It built the first indigenous aircraft carrier for the Indian Navy, the INS Vikrant. The company has Miniratna status.
Barak is an Israeli surface-to-air missile (SAM) designed to be used as a ship-borne point-defense missile system against aircraft, anti-ship missiles, and UAVs.
The Shivalik class or Project 17 class is a class of multi-role frigates in service with the Indian Navy. They are the first warships designed with low observability features built in India. They were designed to have better stealth features and land-attack capabilities than the preceding Talwar-class frigates. A total of three ships were built between 2000 and 2010, and all three were in commission by 2012.
The Indian Naval Air Arm is the aviation branch and a fighting arm of the Indian Navy which is tasked to provide an aircraft carrier-based strike capability, fleet air defence, maritime reconnaissance, and anti-submarine warfare.
INS Aditya (A59) is an Aditya class replenishment and repair ship currently in service with the Indian Navy. The ship was launched on 15 November 1993 and commissioned on 3 April 2000.
INS Vishal, also known as Indigenous Aircraft Carrier 3 (IAC-3), is a planned aircraft carrier to be built by Cochin Shipyard Limited for the Indian Navy. It is intended to be the third aircraft carrier to be built in India after INS Vikrant (IAC-1) and another Vikrant-class aircraft carrier, provisionally called (IAC-2). The proposed design of this class will be a new design, featuring significant changes from Vikrant, including an increase in size and displacement. An Electromagnetic Aircraft Launch System (EMALS) CATOBAR system is also under consideration. Its name Vishal means 'Gargantuan' in Sanskrit.
INS Hansa, is an Indian naval air station located near Dabolim in Goa, India. It is India's biggest naval airbase. The military air base has a civil enclave, that operates as Dabolim Airport.
INS Jyoti (A58) is the third of four Komandarm Fedko-class replenishment oilers. She was modified for naval use and is now being operated by the Eastern Naval Command of the Indian Navy. Jyoti was the largest ship in the navy until INS Vikramaditya (R33) was commissioned in November 2013. It is the third largest ship in the Indian Navy after the aircraft carriers INS Vikrant and INS Vikramaditya. Its primary role is fleet replenishment and sustaining blue-water operations. It was later fitted with close-in weapon systems for self-defence.
INS Vikrant is an aircraft carrier in service with Indian Navy. The carrier is India's fourth carrier and the first to be built in India. It was constructed by the Cochin Shipyard Limited (CSL) in Kochi, Kerala. The namesake Vikrant is a tribute to India's first aircraft carrier INS Vikrant (1961). Vikrant means "courageous" in Sanskrit. The motto of the ship, "जयेम सम् युधिस्पृधः" (Sanskrit), means "I defeat those who dare to challenge me" (English). It is currently one of two active aircraft carriers in the Indian Navy, the other being the flagship INS Vikramaditya.
The Western Fleet is a Naval fleet of the Indian Navy. It is known as the 'Sword Arm' of the Indian Navy. It is headquartered at Mumbai, Maharashtra on the west coast of India. It is a part of the Western Naval Command and is responsible for the naval forces in the Arabian Sea and parts of the Indian Ocean.
The HAL Twin Engine Deck Based Fighter (TEDBF) is a canard delta wing, twin-engine, carrier-based, multirole combat aircraft currently under development for the Indian Navy. The TEDBF is being designed and developed by the Aeronautical Development Agency (ADA), and will be manufactured by Hindustan Aeronautics Limited (HAL). The TEDBF is intended to perform a multitude of missions, including air supremacy, air interdiction, anti-access/area denial (A2/AD), anti-ship warfare (ASW) and electronic warfare (EW) missions. The TEDBF is expected to replace the Mikoyan MiG-29K onboard the INS Vikramaditya and the INS Vikrant.