Aswan High Dam | |
---|---|
Official name | Aswan High Dam |
Location | Aswan, Egypt |
Coordinates | 23°58′14″N32°52′40″E / 23.97056°N 32.87778°E |
Construction began | 1960 |
Opening date | 1970 |
Owner(s) | Egypt |
Dam and spillways | |
Type of dam | Embankment |
Impounds | River Nile |
Height | 111 m (364 ft) |
Length | 3,830 m (12,570 ft) |
Width (base) | 980 m (3,220 ft) |
Spillway capacity | 11,000 m3/s (390,000 cu ft/s) |
Reservoir | |
Creates | Lake Nasser |
Total capacity | 132 km3 (107,000,000 acre⋅ft) |
Surface area | 5,250 km2 (2,030 sq mi) |
Maximum length | 550 km (340 mi) |
Maximum width | 35 km (22 mi) |
Maximum water depth | 130 m (430 ft) |
Normal elevation | 183 m (600 ft) |
Power Station | |
Commission date | 1967–1971 |
Turbines | 12×175 MW (235,000 hp) Francis-type |
Installed capacity | 2,100 MW (2,800,000 hp) |
Annual generation | 10,042 GWh (2004) [1] |
The Aswan Dam, or Aswan High Dam, is one of the world's largest embankment dams, which was built across the Nile in Aswan, Egypt, between 1960 and 1970. When it was completed, it was the tallest earthen dam in the world, surpassing the Chatuge Dam in the United States. [2] The dam, which created the Lake Nasser reservoir, was built 7 km (4.3 mi) upstream of the Aswan Low Dam, which had been completed in 1902 and was already at its maximum utilization. Construction of the High Dam became a key objective of the military regime that took power following the 1952 Egyptian Revolution. With its ability to better control flooding, provide increased water storage for irrigation and generate hydroelectricity, the dam was seen as pivotal to Egypt's planned industrialization. Like the earlier implementation, the High Dam has had a significant effect on the economy and culture of Egypt.
Before the High Dam was built, even with the old dam in place, the annual flooding of the Nile during late summer had continued to pass largely unimpeded down the valley from its East African drainage basin. These floods brought high water with natural nutrients and minerals that annually enriched the fertile soil along its floodplain and delta; this predictability had made the Nile valley ideal for farming since ancient times. However, this natural flooding varied, since high-water years could destroy the whole crop, while low-water years could create widespread drought and consequently famine. Both these events had continued to occur periodically. As Egypt's population grew and technology increased, both a desire and the ability developed to completely control the flooding, and thus both protect and support farmland and its economically important cotton crop. With the greatly increased reservoir storage provided by the High Aswan Dam, the floods could be controlled and the water could be stored for later release over multiple years.
The Aswan Dam was designed by Nikolai Aleksandrovich Malyshev of the Moscow-based Hydroproject Institute. [3] [4] Designed for both irrigation and power generation, the dam incorporates a number of relatively new features, including a very deep grout curtain below its base. Although the reservoir will eventually silt in, even the most conservative estimates indicate the dam will give at least 200 years of service. [5]
The earliest recorded attempt to build a dam near Aswan was in the 11th century, when the Arab polymath and engineer Ibn al-Haytham (known as Alhazen in the West) was summoned to Egypt by the Fatimid Caliph, Al-Hakim bi-Amr Allah, to regulate the flooding of the Nile, a task requiring an early attempt at an Aswan Dam. [6] His field work convinced him of the impracticality of this scheme. [7]
The British began construction of the first dam across the Nile in 1898. Construction lasted until 1902 and the dam was opened on 10 December 1902. The project was designed by Sir William Willcocks and involved several eminent engineers, including Sir Benjamin Baker and Sir John Aird, whose firm, John Aird & Co., was the main contractor. [8] [9]
In 1952, the Greek-Egyptian engineer Adrian Daninos began to develop the plan of the new Aswan Dam. Although the Low Dam was almost overtopped in 1946, the government of King Farouk showed no interest in Daninos's plans. Instead the Nile Valley Plan by the British hydrologist Harold Edwin Hurst was favored, which proposed to store water in Sudan and Ethiopia, where evaporation is much lower. The Egyptian position changed completely after the overthrow of the monarchy, led by the Free Officers Movement including Gamal Abdel Nasser. The Free Officers were convinced that the Nile Waters had to be stored in Egypt for political reasons, and within two months, the plan of Daninos was accepted. [10] Initially, both the United States and the USSR were interested in helping development of the dam. Complications ensued due to their rivalry during the Cold War, as well as growing intra-Arab tensions.
In 1955, Nasser was claiming to be the leader of Arab nationalism, in opposition to the traditional monarchies, especially the Hashemite Kingdom of Iraq following its signing of the 1955 Baghdad Pact. At that time the U.S. feared that communism would spread to the Middle East, and it saw Nasser as a natural leader of an anticommunist procapitalist Arab League. America and the United Kingdom offered to help finance construction of the High Dam, with a loan of $270 million, in return for Nasser's leadership in resolving the Arab-Israeli conflict. While opposed to communism, capitalism, and imperialism, Nasser identified as a tactical neutralist, and sought to work with both the U.S. and the USSR for Egyptian and Arab benefit. [11] After the UN criticized a raid by Israel against Egyptian forces in Gaza in 1955, Nasser realized that he could not portray himself as the leader of pan-Arab nationalism if he could not defend his country militarily against Israel. In addition to his development plans, he looked to quickly modernize his military, and he turned first to the U.S. for aid.
American Secretary of State John Foster Dulles and President Dwight Eisenhower told Nasser that the U.S. would supply him with weapons only if they were used for defensive purposes and if he accepted American military personnel for supervision and training. Nasser did not accept these conditions, and consulted the USSR for support.
Although Dulles believed that Nasser was only bluffing and that the USSR would not aid Nasser, he was wrong: the USSR promised Nasser a quantity of arms in exchange for a deferred payment of Egyptian grain and cotton. On 27 September 1955, Nasser announced an arms deal, with Czechoslovakia acting as a middleman for the Soviet support. [12] Instead of attacking Nasser for turning to the Soviets, Dulles sought to improve relations with him. In December 1955, the US and the UK pledged $56 and $14 million, respectively, toward construction of the High Aswan Dam. [13]
Though the Czech arms deal created an incentive for the US to invest at Aswan, the UK cited the deal as a reason for repealing its promise of dam funds. Dulles was angered more by Nasser's diplomatic recognition of China, which was in direct conflict with Dulles's policy of containment of communism. [14]
Several other factors contributed to the US deciding to withdraw its offer of funding for the dam. Dulles believed that the USSR would not fulfill its commitment of military aid. He was also irritated by Nasser's neutrality and attempts to play both sides of the Cold War. At the time, other Western allies in the Middle East, including Turkey and Iraq, were resentful that Egypt, a persistently neutral country, was being offered so much aid. [15]
In June 1956, the Soviets offered Nasser $1.12 billion at 2% interest for the construction of the dam. On 19 July the U.S. State Department announced that American financial assistance for the High Dam was "not feasible in present circumstances." [13]
On 26 July 1956, with wide Egyptian acclaim, Nasser announced the nationalization of the Suez Canal that included fair compensation for the former owners. Nasser planned on the revenues generated by the canal to help fund construction of the High Dam. When the Suez War broke out, the United Kingdom, France, and Israel seized the canal and the Sinai. But pressure from the U.S. and the USSR at the United Nations and elsewhere forced them to withdraw.
In 1958, the USSR proceeded to provide support for the High Dam project.
In the 1950s, archaeologists began raising concerns that several major historical sites, including the famous temple of Abu Simbel were about to be submerged by waters collected behind the dam. A rescue operation began in 1960 under UNESCO (for details see below under Effects).
Despite its size, the Aswan project has not materially hurt the Egyptian balance of payments. The three Soviet credits covered virtually all of the project's foreign exchange requirements, including the cost of technical services, imported power generating and transmission equipment and some imported equipment for land reclamation. Egypt was not seriously burdened by payments on the credits, most of which were extended for 12 years with interest at the very low rate of 2-1/2%. Repayments to the USSR constituted only a small net drain during the first half of the 1960s, and increased export earnings derived from crops grown on newly reclaimed land have largely offset the modest debt service payments in recent years. During 1965–1970, these export earnings amounted to an estimated $126 million, compared with debt service payments of $113 million. [16]
The Soviets also provided technicians and heavy machinery. The enormous rock and clay dam was designed by Nikolai Aleksandrovich Malyshev of the Moscow-based Hydroproject Institute, [3] [4] along with some Egyptian engineers. 25,000 Egyptian engineers and workers contributed to the construction of the dams.
Originally designed by West German and French engineers in the early 1950s and slated for financing with Western credits, the Aswan High Dam became the USSR's largest and most famous foreign aid project after the United States, the United Kingdom, and the International Bank for Reconstruction and Development (IBRD) withdrew their support in 1956. The first Soviet loan of $100 million to cover construction of coffer dams for diversion of the Nile was extended in 1958. An additional $225 million was extended in 1960 to complete the dam and construct power-generating facilities, and subsequently about $100 million was made available for land reclamation. These credits of some $425 million covered only the foreign exchange costs of the project, including salaries of Soviet engineers who supervised the project and were responsible for the installation and testing of Soviet equipment. Actual construction, which began in 1960, was done by Egyptian companies on contract to the High Dam Authority, and all domestic costs were borne by the Egyptians. Egyptian participation in the venture has raised the construction industry's capacity and reputation significantly. [5]
On the Egyptian side, the project was led by Osman Ahmed Osman's Arab Contractors. The relatively young Osman underbid his only competitor by one-half. [17]
This article needs additional citations for verification .(October 2020) |
The Aswan High Dam is 3,830 metres (12,570 ft) long, 980 m (3,220 ft) wide at the base, 40 m (130 ft) wide at the crest and 111 m (364 ft) [20] tall. It contains 43,000,000 cubic metres (56,000,000 cu yd) of material. At maximum, 11,000 cubic metres per second (390,000 cu ft/s) of water can pass through the dam. There are further emergency spillways for an extra 5,000 cubic metres per second (180,000 cu ft/s), and the Toshka Canal links the reservoir to the Toshka Depression. The reservoir, named Lake Nasser, is 500 km (310 mi) long [21] and 35 km (22 mi) at its widest, with a surface area of 5,250 square kilometres (2,030 sq mi). It holds 132 cubic kilometres (1.73×1011 cu yd) of water.
This article needs additional citations for verification .(June 2020) |
Due to the absence of appreciable rainfall, Egypt's agriculture depends entirely on irrigation. With irrigation, two harvests per year are possible, except for sugar cane which has a growing period of almost one year.
The high dam at Aswan releases, on average, 55 cubic kilometres (45,000,000 acre⋅ft) water per year, of which some 46 cubic kilometres (37,000,000 acre⋅ft) are diverted into the irrigation canals.
In the Nile valley and delta, almost 336,000 square kilometres (130,000 sq mi) benefit from these waters producing on average 1.8 crops per year. The annual crop consumptive use of water is about 38 cubic kilometres (31,000,000 acre⋅ft). Hence, the overall irrigation efficiency is 38/46 = 0.826 or 83%. This is a relatively high irrigation efficiency. The field irrigation efficiencies are much less, but the losses are reused downstream. This continuous reuse accounts for the high overall efficiency.
The following table shows the distribution of irrigation water over the branch canals taking off from the one main irrigation canal, the Mansuriya Canal near Giza. [22]
Branch canal | Water delivery in m3/feddan * |
---|---|
Kafret Nasser | 4,700 |
Beni Magdul | 3,500 |
El Mansuria | 3,300 |
El Hammami upstream | 2,800 |
El Hammami downstream | 1,800 |
El Shimi | 1,200 |
The salt concentration of the water in the Aswan reservoir is about 0.25 kilograms per cubic metre (0.42 lb/cu yd), a very low salinity level. At an annual inflow of 55 cubic kilometres (45,000,000 acre⋅ft), the annual salt influx reaches 14 million tons. The average salt concentration of the drainage water evacuated into the sea and the coastal lakes is 2.7 kilograms per cubic metre (4.6 lb/cu yd). [24] At an annual discharge of 10 cubic kilometres (2.4 cu mi) (not counting the 2 kilograms per cubic metre [3.4 lb/cu yd] of salt intrusion from the sea and the lakes, see figure "Water balances"), the annual salt export reaches 27 million ton. In 1995, the output of salt was higher than the influx, and Egypt's agricultural lands were desalinizing. Part of this could be due to the large number of subsurface drainage projects executed in the last decades to control the water table and soil salinity. [25]
Drainage through subsurface drains and drainage channels is essential to prevent a deterioration of crop yields from waterlogging and soil salinization caused by irrigation. By 2003, more than 20,000 square kilometres (7,700 sq mi) have been equipped with a subsurface drainage system and approximately 7.2 square kilometres (2.8 sq mi) of water is drained annually from areas with these systems. The total investment cost in agricultural drainage over 27 years from 1973 to 2002 was about $3.1 billion covering the cost of design, construction, maintenance, research and training. During this period 11 large-scale projects were implemented with financial support from World Bank and other donors. [26]
The High Dam has resulted in protection from floods and droughts, an increase in agricultural production and employment, electricity production, and improved navigation that also benefits tourism. Conversely, the dam flooded a large area, causing the relocation of over 100,000 people. Many archaeological sites were submerged while others were relocated. The dam is blamed for coastline erosion, soil salinity, and health problems.
The assessment of the costs and benefits of the dam remains controversial decades after its completion. According to one estimate, the annual economic benefit of the High Dam immediately after its completion was E£255 million, $587 million using the exchange rate in 1970 of $2.30 per E£1): E£140 million from agricultural production, E£100 million from hydroelectric generation, E£10 million from flood protection, and E£5 million from improved navigation. At the time of its construction, total cost, including unspecified "subsidiary projects" and the extension of electric power lines, amounted to E£450 million. Not taking into account the negative environmental and social effects of the dam, its costs are thus estimated to have been recovered within only two years. [27] One observer notes: "The impacts of the Aswan High Dam (...) have been overwhelmingly positive. Although the Dam has contributed to some environmental problems, these have proved to be significantly less severe than was generally expected, or currently believed by many people." [28] Another observer disagreed and he recommended that the dam should be torn down. Tearing it down would cost only a fraction of the funds required for "continually combating the dam's consequential damage" and 500,000 hectares (1,900 sq mi) of fertile land could be reclaimed from the layers of mud on the bed of the drained reservoir. [29] Samuel C. Florman wrote about the dam: "As a structure it is a success. But in its effect on the ecology of the Nile Basin – most of which could have been predicted – it is a failure". [30]
Periodic floods and droughts have affected Egypt since ancient times. The dam mitigated the effects of floods, such as those in 1964, 1973, and 1988. Navigation along the river has been improved, both upstream and downstream of the dam. Sailing along the Nile is a favorite tourism activity, which is mainly done during the winter when the natural flow of the Nile would have been too low to allow navigation of cruise ships.[ clarification needed ] A new fishing industry has been created around Lake Nasser, though it is struggling due to its distance from any significant markets. The annual production was about 35,000 tons in the mid-1990s. Factories for the fishing industry and packaging have been set up near the Lake. [31]
According to a 1971 CIA declassified report, although the High Dam has not created ecological problems as serious as some observers have charged, its construction has brought economic losses as well as gains. These losses derive largely from the settling in dam's lake of the rich silt traditionally borne by the Nile. To date (1971), the main impact has been on the fishing industry. Egypt's Mediterranean catch, which once averaged 35,000–40,000 tons annually, has shrunk to 20,000 tons or less, largely because the loss of plankton nourished by the silt has eliminated the sardine population in Egyptian waters. Fishing in high dam's lake may in time at least partly offset the loss of saltwater fish, but only the most optimistic estimates place the eventual catch as high as 15,000–20,000 tons. Lack of continuing silt deposits at the mouth of the river also has contributed to a serious erosion problem. Commercial fertilizer requirements and salination and drainage difficulties, already large in perennially irrigated areas of Lower and Middle Egypt, will be somewhat increased in Upper Egypt by the change to perennial irrigation. [5]
The dams also protected Egypt from the droughts in 1972–1973 and 1983–1987 that devastated East and West Africa. The High Dam allowed Egypt to reclaim about 2.0 million feddan (840,000 hectares) in the Nile Delta and along the Nile Valley, increasing the country's irrigated area by a third. The increase was brought about both by irrigating what used to be desert and by bringing under cultivation of 385,000 hectares (950,000 acres) that were previously used as flood retention basins. [32] About half a million families were settled on these new lands. In particular the area under rice and sugar cane cultivation increased. In addition, about 1 million feddan (420,000 hectares), mostly in Upper Egypt, were converted from flood irrigation with only one crop per year to perennial irrigation allowing two or more crops per year. On other previously irrigated land, yields increased because water could be made available at critical low-flow periods. For example, wheat yields in Egypt tripled between 1952 and 1991 and better availability of water contributed to this increase. Most of the 32 km3 of freshwater, or almost 40 percent of the average flow of the Nile that were previously lost to the sea every year could be put to beneficial use. While about 10 km3 of the water saved is lost due to evaporation in Lake Nasser, the amount of water available for irrigation still increased by 22 km3. [31] Other estimates put evaporation from Lake Nasser at between 10 and 16 cubic km per year. [33]
The dam powers twelve generators each rated at 175 megawatts (235,000 hp), with a total of 2.1 gigawatts (2,800,000 hp). Power generation began in 1967. When the High Dam first reached peak output in 1970, it produced around half of Egypt's production of electric power (about 15 percent by 1998), and it gave most Egyptian villages the use of electricity for the first time. The High Dam has also improved the efficiency and the extension of the Old Aswan Hydropower stations by regulating upstream flows. [31] At the time of completion, it was the largest power station in Africa and the 6th largest hydroelectric power station in the world.
All High Dam power facilities were completed ahead of schedule. Twelve turbines were installed and tested, giving the plant an installed capacity of 2,100 megawatts (MW), or more than twice the national total in 1960. With this capacity, the Aswan plant can produce 10 billion kWh of energy yearly. Two 500-kilovolt trunk lines to Cairo have been completed, and initial transmission problems, stemming mainly from poor insulators, were solved. Also, the damage inflicted on a main transformer station in 1968 by Israeli commandos has been repaired, and the Aswan plant is fully integrated with the power network in Lower Egypt. [34] By 1971 estimation, power output at Aswan won't reach much more than half of the plant's theoretical capacity, because of limited water supplies and the differing seasonal water-use patterns for irrigation and power production. Agricultural demand for water in the summer far exceeds the amount needed to meet the comparatively low summer demand for electric power. Heavy summer irrigation use, however, will leave insufficient water under Egyptian control to permit hydroelectric power production at full capacity in the winter. Technical studies indicate that a maximum annual output of 5 billion kWh appears to be all that can be sustained due to fluctuations in Nile flows. [35]
Lake Nasser flooded much of lower Nubia and 100,000 to 120,000 people were resettled in Sudan and Egypt. [36]
In Sudan, 50,000 to 70,000 Sudanese Nubians were moved from the old town of Wadi Halfa and its surrounding villages. Some were moved to a newly created settlement on the shore of Lake Nasser called New Wadi Halfa, and some were resettled approximately 700 kilometres (430 mi) south to the semi-arid Butana plain near the town of Khashm el-Girba up the Atbara River. The climate there had a regular rainy season as opposed to their previous desert habitat in which virtually no rain fell. The government developed an irrigation project, called the New Halfa Agricultural Development Scheme to grow cotton, grains, sugar cane and other crops. The Nubians were resettled in twenty five planned villages that included schools, medical facilities, and other services, including piped water and some electrification.
In Egypt, the majority of the 50,000 Nubians were moved three to ten kilometers from the Nile near Edna and Kom Ombo, 45 kilometers (28 mi) downstream from Aswan in what was called "New Nubia". [37] Housing and facilities were built for 47 village units whose relationship to each other approximated that in Old Nubia. Irrigated land was provided to grow mainly sugar cane. [38] [39]
In 2019–20, Egypt started to compensate the Nubians who lost their homes following the dam impoundment. [40]
Twenty-two monuments and architectural complexes that were threatened by flooding from Lake Nasser, including the Abu Simbel temples, were preserved by moving them to the shores of the lake under the UNESCO Nubia Campaign. [41] Also moved were Philae, Kalabsha and Amada. [31]
These monuments were granted to countries that helped with the works:
These items were removed to the garden area of the Sudan National Museum of Khartoum: [42]
The Temple of Ptah at Gerf Hussein had its free-standing section reconstructed at New Kalabsha, alongside the Temple of Kalabsha, Beit el-Wali, and the Kiosk of Qertassi.
The remaining archaeological sites, including the Buhen fort and the cemetery of Fadrus have been flooded by Lake Nasser.
Before the construction of the High Dam, the Nile deposited sediments of various particle size – consisting of fine sand, silt and clay – on fields in Upper Egypt through its annual flood, contributing to soil fertility. However, the nutrient value of the sediment has often been overestimated. 88 percent of the sediment was carried to the sea before the construction of the High Dam. The nutrient value added to the land by the sediment was only 6,000 tons of potash, 7,000 tons of phosphorus pentoxide and 17,000 tons of nitrogen. These amounts are insignificant compared to what is needed to reach the yields achieved today in Egypt's irrigation. [43] Also, the annual spread of sediment due to the Nile floods occurred along the banks of the Nile. Areas far from the river which never received the Nile floods before are now being irrigated. [44]
A more serious issue of trapping of sediment by the dam is that it has increased coastline erosion surrounding the Nile Delta. There is a lack of reliable statistics.
Before the construction of the High Dam, groundwater levels in the Nile Valley fluctuated 8–9 m (26–30 ft) per year with the water level of the Nile. During summer when evaporation was highest, the groundwater level was too deep to allow salts dissolved in the water to be pulled to the surface through capillary action. With the disappearance of the annual flood and heavy year-round irrigation, groundwater levels remained high with little fluctuation leading to waterlogging. Soil salinity also increased because the distance between the surface and the groundwater table was small enough (1–2 m depending on soil conditions and temperature) to allow water to be pulled up by evaporation so that the relatively small concentrations of salt in the groundwater accumulated on the soil surface over the years. Since most of the farmland did not have proper subsurface drainage to lower the groundwater table, salinization gradually affected crop yields. [32] Drainage through sub-surface drains and drainage channels is essential to prevent a deterioration of crop yields from soil salinization and waterlogging. By 2003, more than 2 million hectares have been equipped with a subsurface drainage system at a cost from 1973 to 2002 of about $3.1 billion. [45]
Contrary to many predictions made prior to the Aswan High Dam construction and publications that followed, that the prevalence of schistosomiasis (bilharzia) would increase, it did not. [46] This assumption did not take into account the extent of perennial irrigation that was already present throughout Egypt decades before the high dam closure. By the 1950s only a small proportion of Upper Egypt had not been converted from basin (low transmission) to perennial (high transmission) irrigation. Expansion of perennial irrigation systems in Egypt did not depend on the high dam. In fact, within 15 years of the high dam closure there was solid evidence that bilharzia was declining in Upper Egypt. S. haematobium has since disappeared altogether. Suggested reasons for this include improvements in irrigation practice. In the Nile Delta, schistosomiasis had been highly endemic, with prevalence in the villages 50% or higher for almost a century before. This was a consequence of the conversion of the Delta to perennial irrigation to grow long staple cotton by the British. This has changed. Large-scale treatment programmes in the 1990s using single-dose oral medication contributed greatly to reducing the prevalence and severity of S. mansoni in the Delta.
Sediment deposited in the reservoir is lowering the water storage capacity of Lake Nasser. The reservoir storage capacity is 162 km3, including 31 km3 dead storage at the bottom of the lake below 147 m (482 ft) above sea level, 90 km3 live storage, and 41 km3 of storage for high flood waters above 175 m (574 ft) above sea level. The annual sediment load of the Nile is about 134 million tons. This means that the dead storage volume would be filled up after 300–500 years if the sediment accumulated at the same rate throughout the area of the lake. Obviously sediment accumulates much faster at the upper reaches of the lake, where sedimentation has already affected the live storage zone. [43]
Before the construction of the High Dam, the 50,000 km (31,000 mi) of irrigation and drainage canals in Egypt had to be dredged regularly to remove sediments. After construction of the dam, aquatic weeds grew much faster in the clearer water, helped by fertilizer residues. The total length of the infested waterways was about 27,000 km (17,000 mi) in the mid-1990s. Weeds have been gradually brought under control by manual, mechanical and biological methods. [31]
Mediterranean fishing and brackish water lake fishery declined after the dam was finished because nutrients that flowed down the Nile to the Mediterranean were trapped behind the dam. For example, the sardine catch off the Egyptian coast declined from 18,000 tons in 1962 to a mere 460 tons in 1968, but then gradually recovered to 8,590 tons in 1992. A scientific article in the mid-1990s noted that "the mismatch between low primary productivity and relatively high levels of fish production in the region still presents a puzzle to scientists." [47]
A concern before the construction of the High Dam had been the potential drop in river-bed level downstream of the Dam as the result of erosion caused by the flow of sediment-free water. Estimates by various national and international experts put this drop at between and 2 and 10 meters (6.6 and 32.8 ft). However, the actual drop has been measured at 0.3–0.7 meters (0.98–2.30 ft), much less than expected. [31]
The red-brick construction industry, which consisted of hundreds of factories that used Nile sediment deposits along the river, has also been negatively affected. Deprived of sediment, they started using the older alluvium of otherwise arable land taking out of production up to 120 square kilometers (46 sq mi) annually, with an estimated 1,000 square kilometers (390 sq mi) destroyed by 1984 when the government prohibited, "with only modest success," further excavation. [48] According to one source, bricks are now being made from new techniques which use a sand-clay mixture and it has been argued that the mud-based brick industry would have suffered even if the dam had not been built. [44]
Because of the lower turbidity of the water sunlight penetrates deeper in the Nile water. Because of this and the increased presence of nutrients from fertilizers in the water, more algae grow in the Nile. This in turn increases the costs of drinking water treatment. Apparently few experts had expected that water quality in the Nile would actually decrease because of the High Dam. [32]
The geography of Egypt relates to two regions: North Africa and West Asia.
The Nile is a major north-flowing river in northeastern Africa. It flows into the Mediterranean Sea. The Nile is the longest river in Africa. It has historically been considered the longest river in the world, though this has been contested by research suggesting that the Amazon River is slightly longer. Of the world's major rivers, the Nile is one of the smallest, as measured by annual flow in cubic metres of water. About 6,650 km (4,130 mi) long, its drainage basin covers eleven countries: the Democratic Republic of the Congo, Tanzania, Burundi, Rwanda, Uganda, Kenya, Ethiopia, Eritrea, South Sudan, Sudan, and Egypt. In particular, the Nile is the primary water source of Egypt, Sudan and South Sudan. The Nile is an important economic driver supporting agriculture and fishing.
Lake Nasser is a vast reservoir in southern Egypt and northern Sudan. It was created by the construction of the Aswan High Dam and is one of the largest man-made lakes in the world. Before its creation, the project faced opposition from Sudan as it would encroach on land in the northern part of the country, where many Nubian people lived who would have to be resettled. In the end Sudan's land near the area of Lake Nasser was mostly flooded by the lake. The lake has become an important economic resource in Egypt, improving agriculture and touting robust fishing and tourism industries.
Toshka Lakes is the name given to recently formed endorheic lakes in the Sahara Desert of Egypt. Their presence is caused by periodic overflow from Lake Nasser.
The Merowe Dam, also known as Merowe High Dam, Merowe Multi-Purpose Hydro Project or Hamdab Dam, is a large dam near Merowe Town in northern Sudan, about 350 kilometres (220 mi) north of the capital Khartoum. Its dimensions make it the largest contemporary hydropower project in Africa. It is situated on the river Nile, close to and inundating the 4th Cataract where the river divides into multiple smaller branches with large islands in between. Merowe is a city about 40 kilometres (25 mi) downstream from the construction site at Hamdab. The main purpose for building the dam was the generation of electricity.
Pine Flat Dam is a concrete gravity dam on the Kings River in the Central Valley of Fresno County, California United States. Situated about 28 miles (45 km) east of Fresno, the dam is 440 feet (130 m) high and impounds Pine Flat Lake, in the foothills of the Sierra Nevada just outside the boundary of Kings Canyon National Park. The dam's primary purpose is flood control, with irrigation, hydroelectric power generation and recreation secondary in importance.
Tarbela Dam is an earth-filled dam along the Indus River in Pakistan's Khyber Pakhtunkhwa province. It is mainly located in Haripur Tehsil. It is about 20 km (10 mi) from the city of Swabi KPK, 105 km (65 mi) northwest of Islamabad, and 125 km (80 mi) east of Peshawar. It is the largest earth-filled dam in the world. The dam is 143 metres (470 ft) high above the riverbed and its reservoir, Tarbela Lake, has a surface area of approximately 250 square kilometres (97 sq mi).
The New Halfa Project in Sudan is a 164,000 feddan site constructed in 1964 to house 50,000 Nubians displaced from Wadi Halfa, a town situated on the Nile near the border with Egypt, which was flooded when Lake Nasser formed behind the Aswan Dam. The site draws its water from the Atbara River, where the Khashm el Girba Dam provides a reliable source for the irrigation project intended to convert the nomads of the area to farmers of cotton and sugar.
A reservoir is an enlarged lake behind a dam, usually built to store fresh water, often doubling for hydroelectric power generation.
The flooding of the Nile has been an important natural cycle in Nubia and Egypt since ancient times. It is celebrated by Egyptians as an annual holiday for two weeks starting August 15, known as Wafaa El-Nil. It is also celebrated in the Coptic Church by ceremonially throwing a martyr's relic into the river, hence the name, The Martyr's Finger. The flooding of the Nile was poetically described in myth as Isis's tears of sorrow for Osiris when killed by his brother Set.
Navajo Dam is a dam on the San Juan River, a tributary of the Colorado River, in northwestern New Mexico in the United States. The 402-foot (123 m) high earthen dam is situated in the foothills of the San Juan Mountains about 44 miles (71 km) upstream and east of Farmington, New Mexico. It was built by the U.S. Bureau of Reclamation (Reclamation) in the 1960s to provide flood control, irrigation, domestic and industrial water supply, and storage for droughts. A small hydroelectric power plant was added in the 1980s.
The environmental impact of reservoirs comes under ever-increasing scrutiny as the global demand for water and energy increases and the number and size of reservoirs increases.
The environmental impact of irrigation relates to the changes in quantity and quality of soil and water as a result of irrigation and the subsequent effects on natural and social conditions in river basins and downstream of an irrigation scheme. The effects stem from the altered hydrological conditions caused by the installation and operation of the irrigation scheme.
Shihmen Dam is a major rock fill dam across the Dahan River in northern Taoyuan City. It forms the Shihmen Reservoir (石門水庫), Taiwan's third largest reservoir or artificial lake. It provides irrigation in Taoyuan, flood control for the Taipei Basin, and hydroelectricity and domestic water supply for more than three million people in northern Taiwan.
Water resources management in modern Egypt, is a complex process that involves multiple stakeholders who use water for irrigation, municipal and industrial water supply, hydropower generation and navigation. In addition, the waters of the Nile support aquatic ecosystems that are threatened by abstraction and pollution. Egypt also has substantial fossil groundwater resources in the Western Desert.
Egypt's environmental problems include, but are not limited to, water scarcity, air pollution, damage to historic monuments, animal welfare issues and deficiencies in its waste management system.
Al Wahda Dam, formerly known as M'Jaara Dam, is an embankment dam on the Ouergha River near M´Jaara in Ouezzane Province, Morocco. It was constructed for flood control, irrigation, water supply and hydroelectric power production. It is the second largest dam in Africa and the largest in Morocco. It was described by Land Ocean Interactions in the Coastal Zone (LOICZ) as "the second most important dam in Africa after the High Aswan dam."
The Aswan Low Dam or Old Aswan Dam is a gravity masonry buttress dam on the Nile River in Aswan, Egypt. The dam was built by the British at the former first cataract of the Nile, and is located about 1000 km up-river and 690 km south-southeast of Cairo. When initially constructed between 1899 and 1902, nothing of its scale had ever been attempted; on completion, it was the largest masonry dam in the world. The dam was designed to provide storage of annual floodwater and augment dry season flows to support greater irrigation development and population growth in the lower Nile. The dam, originally limited in height by conservation concerns, worked as designed, but provided inadequate storage capacity for planned development and was raised twice: between 1907 and 1912 and again between 1929 and 1933. These heightenings still did not meet irrigation demands and in 1946 it was nearly over-topped in an effort to maximize pool elevation. This led to the investigation and construction of the Aswan High Dam 6 kilometres (3.7 mi) upstream.
The Grand Ethiopian Renaissance Dam, formerly known as the Millennium Dam and sometimes referred to as the Hidase Dam, is a gravity dam on the Blue Nile River in Ethiopia. The dam is in the Benishangul-Gumuz Region of Ethiopia, about 14 km (9 mi) east of the border with Sudan.
The International Campaign to Save the Monuments of Nubia was the effort to relocate 22 monuments in Lower Nubia, in Southern Egypt and northern Sudan, between 1960 and 1980. This was done in order to make way for the building of the Aswan Dam, at the Nile's first cataract, a project launched following the 1952 Egyptian Revolution. This project was undertaken under UNESCO leadership and a coalition of fifty countries. This process led to the creation of the World Heritage Convention in 1972, and thus the system of UNESCO World Heritage Sites.
robert collins the nile.
{{cite book}}
: CS1 maint: multiple names: authors list (link)