Robert Moses Niagara Hydroelectric Power Station | |
---|---|
Country | United States |
Location | Lewiston, New York |
Coordinates | 43°08′35″N79°02′23″W / 43.14306°N 79.03972°W |
Purpose | Power |
Status | Operational |
Construction began | 1957 |
Opening date | 1961 |
Construction cost | US$800 million (1957) |
Owner(s) | New York Power Authority |
Dam and spillways | |
Type of dam | Gravity dam |
Impounds | Niagara River |
Reservoir | |
Creates | Moses Niagara Power Plant forebay |
Total capacity | 740,000,000 US gal (2.8×109 L; 620,000,000 imp gal) |
Commission date | 1961 |
Type | Conventional |
Turbines | 13 |
Installed capacity | 2,525 MW (3,386,000 hp) [1] |
Capacity factor | 71.9% |
Annual generation | 15,896,756 MWh [2] |
Website https://www.nypa.gov/power/generation/niagara-power-project | |
Works in conjunction with the Lewiston Pump-Generating Plant |
The Robert Moses Niagara Hydroelectric Power Station is a hydroelectric power station in Lewiston, New York, near Niagara Falls. Owned and operated by the New York Power Authority (NYPA), the plant diverts water from the Niagara River above Niagara Falls and returns the water into the lower portion of the river near Lake Ontario. It uses 13 generators at an installed capacity of 2,525 MW (3,386,000 hp) with an average annual net generation of 15,897,000 MWh between 2014 and 2023, and a capacity factor of 71.9%. [3]
Named for New York City planner Robert Moses, the plant was built to replace power production after the Schoellkopf Power Station, a nearby hydroelectric plant, collapsed in 1956. It stands across the river from Sir Adam Beck Hydroelectric Power Stations in Niagara Falls, Ontario, Canada.
The land that the Robert Moses Niagara Power Plant occupies has a long history of use. In 1805, Augustus and Peter Porter of Buffalo, New York, purchased the American Falls from New York in a public auction (and later acquired the rights to the eastern rapids above the falls) with a stated plan to generate power by way of a "hydraulic raceway". The men were unable to secure funding for the project, however, each died without achieving significant progress toward their planned infrastructure. Several other companies later attempted similar projects, all without success. [4]
In 1853, the Niagara Falls Hydraulic Power and Manufacturing Company was chartered; in 1861, it completed a 35 ft (11 m) wide and 8 ft (2.4 m) deep canal. The powerhouse finally opened in 1874, but produced little electricity even by the standards of the day. [4]
In 1877, Jacob F. Schoellkopf purchased the canal, along with the water and power rights, for $71,000. He improved the canal and put the powerhouse to commercial use. In 1881, his company completed Schoellkopf Power Station No. 1; it would operate until 1904. In 1891, Schoellkopf Power Station No. 2 opened directly in front of the original, in the gorge below the falls, with a higher 210 ft (64 m) drop and capacity of 25 MW (34,000 hp). In 1914 and 1918, the company built Schoellkopf Stations No. 3A and 3B respectively, with a total capacity of 180.8 MW (242,500 hp). [5]
In 1886, the competing Niagara Falls Power Company, owned by the Cataract Construction Company, built the Adams Power Plant. Between 1900 and 1904, the company built the Powerhouse No. 2, bringing its total generators to 21, with a total capacity of 78 MW (105,000 hp). [5]
In 1918, World War I led the power companies to merge into the Niagara Falls Power Company. From 1921 to 1924, the company built Schoellkopf Station No. 3C next to the previous ones. It contained three 25 Hz generators with a total capacity of 160 MW (210,000 hp), [5] bringing the Schoellkopf Power Stations to 19 generators with a capacity of 337.4 MW (452,500 hp).
On June 7, 1956, water seeping into a back wall caused the collapse of two-thirds of Schoellkopf Power Station No. 3b and 3c, killing one worker and causing an estimated $100 million in damage. [6]
To replace the antiquated and now partially destroyed Schoellkopf power stations, the New York Power Authority (NYPA) planned an $800 million power plant that would produce 2.4 GW. During planning, it was called the Niagara Power Project; later, it was named for NYPA head Robert Moses.
In 1957, the United States Congress approved the project. Construction began that year, although its completion would require the NYPA to gain the rights to 550 acres (220 ha) of Tuscarora Indian Reservation for a new 1,900-acre (770 ha), 22-billion-US-gallon (83,000,000 m3) reservoir. This it did in 1960, through a United States Supreme Court decision, the Federal Power Commission v. Tuscarora Indian Nation. [4] [7]
During construction, over 12 million cubic yards (9.2 million cubic meters) of rock were excavated and twenty workers died. Construction was complete in 1961. [4] When it opened in 1961, it was the Western world's largest hydropower facility. [8]
The generation facilities were listed on the National Register of Historic Places in 2017.
Lewiston Pump-Generating Plant | |
---|---|
Country | United States |
Location | Lewiston, New York |
Purpose | Power |
Status | Operational |
Construction began | 1957 |
Opening date | 1961 |
Construction cost | $48.72 million USD (1962) [9] |
Owner(s) | New York Power Authority |
Dam and spillways | |
Type of dam | Gravity dam |
Impounds | Moses Niagara Power Plant forebay |
Reservoir | |
Creates | Lewiston Reservoir |
Total capacity | 22,000,000,000 US gal (8.3×1010 L; 1.8×1010 imp gal) |
Surface area | 1,900 acres (770 ha) |
Coordinates | 43°08′35″N79°01′18.4″W / 43.14306°N 79.021778°W |
Commission date | 1961 |
Type | Pumped-storage |
Turbines | 12 × 20 MW |
Installed capacity | 240 MW |
Website http://www.nypa.gov/facilities/niagara.htm | |
Works in conjunction with the Robert Moses Niagara Power Plant |
The pump-generating plant in the Lewiston Dam is atypical, in that the dam was constructed not to control the flow of water in a natural river, but to contain a man-made 1,900-acre (770 ha), 22-billion-US-gallon (83,000,000 m3) upper reservoir (named the Lewiston Reservoir) which stores water pumped into the reservoir from the forebay of the Robert Moses Power Station. Water enters the forebay by tunnels from the Niagara River controlled by the International Control Dam upstream of the natural falls. Water in the forebay can be either pumped up into the upper reservoir for later use or immediately sent down over the escarpment downstream of the natural falls through the Robert Moses Power Station turbines. The Lewiston Pump-Generating Plant 43°08′33″N79°01′18″W / 43.14250°N 79.02167°W houses 12 electrically powered pump-generators that can generate a combined 240 MW (320,000 hp) when water in the upper reservoir is released.
At night, two 46 ft (14 m) wide by 66 ft (20 m) tall tunnels [10] divert a substantial fraction (600,000 US gal (2,300 m3) per second) of the water in the Niagara River 4.5 mi (7.2 km) to the forebay. Electricity generated in the Moses plant powers the Lewiston pumps to push water into the upper reservoir. The water is pumped at night because the demand for electricity is much lower than during the day. In addition to the lower demand for electricity at night, less water can be diverted from the river during the day because of the desire to preserve the appearance of the falls.
During the day, when electrical demand is high, water is released from the upper reservoir through the Lewiston Dam pump-generators, generating electricity. The water flows into the forebay, where it then flows through the turbines of the Moses plant back to the main river. This allows water diverted from above Niagara Falls to pass through two sets of turbines, generating electricity both times. This arrangement is an example of pumped-storage hydroelectricity. Engineers copied what had been built by Ontario Hydro, across the river, when a similar system was built during construction of the Sir Adam Beck Generating Station II in the 1950s.
This system allows energy to be stored in vast quantities. The potential energy in the diverted water is converted into electrical energy in the Moses plant. At night, some of that electrical energy is converted back to potential energy when water is pumped into the upper reservoir behind the Lewiston Dam. During the day, part of the potential energy of the water in the Lewiston reservoir is converted into electricity at the Lewiston Dam, and then its remaining potential energy is captured by the Moses plant, which is also capturing the potential energy of the water diverted from the river in real-time.
The Robert Moses Plant was refurbished in 2006, [11] which required the southbound lanes of the nearby Robert Moses State Parkway to be closed during said repairs. [12]
Beginning in 2012 and until 2021, the pump-generating plant has undergone a $460 million modernization that increased the plant's efficiency and service life. [13]
During the mid-1980s, the New York Power Authority began an expansion project at the site, known as FERC (Federal Energy Regulatory Commission) Project 2216. Soon after, the project was halted due to discovery of hazardous chemicals such as dioxins, which chemical companies which owned the land had dumped underground. A civil lawsuit was filed in the State of New York against the New York Power Authority, Occidental Petroleum, Hooker Chemicals, Bechtel Corporation, and Parsons Brinckerhoff, which was settled out of court in 1999. [14] Subsequent testing near the Lewiston Reservoir near the project still confirms mercury and organic contamination which restricts the consumption of fish. [15]
The Niagara Power Visitors Center is adjacent to the Robert Moses plant, with an observation deck along Niagara Gorge. The Center features interactive exhibits about hydroelectricity and its history in the Niagara Frontier.
Pumped-storage hydroelectricity (PSH), or pumped hydroelectric energy storage (PHES), is a type of hydroelectric energy storage used by electric power systems for load balancing. A PHS system stores energy in the form of gravitational potential energy of water, pumped from a lower elevation reservoir to a higher elevation. Low-cost surplus off-peak electric power is typically used to run the pumps. During periods of high electrical demand, the stored water is released through turbines to produce electric power.
An underground power station is a type of hydroelectric power station constructed by excavating the major components from rock, rather than the more common surface-based construction methods.
The New York Power Authority (NYPA), is the largest state public power utility in the United States providing some of the lowest-cost electricity in the nation, operating 16 generating facilities and more than 1,400 circuit-miles of transmission lines. Its main administrative offices are in White Plains, New York
The Shoalhaven Scheme is a dual-purpose water supply and Pumped-storage Hydroelectricity scheme located on the South Coast region of New South Wales, Australia.
Sir Adam Beck Hydroelectric Generating Stations are two hydroelectric generating stations in Niagara Falls, Ontario, Canada. Sir Adam Beck Generating Station I, Sir Adam Beck Generating Station II and the Sir Adam Beck Pump Generating Station are all owned by Ontario Power Generation. Following the development of several smaller generating stations around Niagara Falls in the late 19th and early 20th centuries, the Province of Ontario authorized the construction of the first major publicly owned generating station in the province. At the time it was built, it was the largest hydroelectric generating station in the world.
The Rubicon Hydroelectric Scheme is a small run-of-the-river hydroelectric scheme located on the Rubicon and Royston Rivers, north east of Melbourne, 40 km (25 mi) south-west of Alexandra, Victoria, Australia. The scheme commenced in 1922, and was the first state-owned hydroelectric scheme to generate electricity in mainland Australia, and among the first in the world to be remotely controlled. For the first ten years of its operation it supplied on average 16.9% of electricity generated by the State Electricity Commission of Victoria. It is now owned and operated by AGL Energy and contributes approximately 0.02% of Victoria's energy supply.
The Blenheim–Gilboa Pumped Storage Power Station is a pumped-storage hydroelectricity plant in the Catskill Mountains of New York State. The plant is part of the New York Power Authority, and can generate over 1,100 megawatts (1,500,000 hp) of electricity. It is used daily to cover peak demand. There are two reservoirs that are involved in the project, both with a capacity of 5 billion US gallons (19,000,000 m3); one at the foot of Brown Mountain in the Schoharie Valley, and another one at the top of the mountain. The power station has an accumulated capacity of about 12,000 megawatt-hours (43,000 GJ) after storing up to 17,000 megawatt-hours (61,000 GJ).
Run-of-river hydroelectricity (ROR) or run-of-the-river hydroelectricity is a type of hydroelectric generation plant whereby little or no water storage is provided. Run-of-the-river power plants may have no water storage at all or a limited amount of storage, in which case the storage reservoir is referred to as pondage. A plant without pondage is subject to seasonal river flows, so the plant will operate as an intermittent energy source. Conventional hydro uses reservoirs, which regulate water for flood control, dispatchable electrical power, and the provision of fresh water for agriculture.
Adams Power Plant Transformer House in Niagara Falls, New York is a National Historic Landmarked building constructed in 1895. It is the only remaining structure that was part of the historic Edward Dean Adams Power Plant, the first large-scale, alternating current electric generating plant in the world, built in 1895. The building's eponym was Edward Dean Adams, a businessman and entrepreneur in the electrical field.
Hydroelectricity is, as of 2019, the second-largest renewable source of energy in both generation and nominal capacity in the United States. In 2021, hydroelectric power produced 31.5% of the total renewable electricity, and 6.3% of the total U.S. electricity.
The Siah Bisheh Pumped Storage Power Plant, also spelled Siyāhbisheh and Siah Bishe, is located in the Alborz Mountain range near the village of Siah Bisheh and 48 km (30 mi) south of Chalus in Mazandaran Province, Iran. The power plant uses the pumped-storage hydroelectric method to generate electricity during periods of high energy demand, making it a peaking power plant, intended to fulfill peak electricity demand in Tehran 60 km (37 mi) to the south. When complete it will have an installed generating capacity of 1,040 megawatts (1,390,000 hp) and a pumping capacity of 940 megawatts (1,260,000 hp). Planning for the project began in the 1970s and construction began in 1985. It was delayed from 1992 until 2001 and the first generator went online in May 2013. The remaining generators were commissioned by 1 September 2015. The power plant is the first pumped-storage type in Iran and will also use the country's first concrete-face rock-fill dam – two of them.
Niagara Falls Hydraulic Power & Manufacturing Company was an American company, based in Niagara Falls, New York that was the first company to generate hydroelectric power from Niagara Falls in 1882. The company built upon several predecessor companies efforts to construct a canal used for hydraulic mill power. In 1918, the company merged with Niagara Falls Power Company, which later became Niagara Mohawk and in 2002 was acquired by National Grid plc.
The Minghu Dam (Chinese: 明湖水壩; pinyin: Mínghú Shuǐbà, renamed the Takuan Dam, is a concrete gravity dam on the Shuili River located 7 km north of Shuili Township in Nantou County, Taiwan. The reservoir formed by the dam serves as the lower reservoir for the Minhu Pumped Storage Hydro Power Station. Sun Moon Lake serves as the upper reservoir.
The Edolo Pumped Storage Plant is located along the Oglio River just downstream of Edolo, Brescia Province in the Lombardy region of Italy. Using the pumped-storage hydroelectric method, it has an installed capacity of 1,000 megawatts (1,300,000 hp). Its generators were commissioned between April 1984 and November 1985. Lake Avio was previously completed in 1929 and Lake Benedetto completed in 1940.
The Rocky Mountain Hydroelectric Plant is a pumped-storage power plant located 10 miles (16 km) northwest of Rome in the U.S. state of Georgia. It is named after Rock Mountain on top of which the plant's upper reservoir is located. Construction on the plant began in 1977 and it was commissioned in 1995. After upgrades were completed in 2011, the plant has an installed capacity of 1,095 megawatts (1,468,000 hp). It is owned by both Oglethorpe Power and Georgia Power which have 75 percent and 25 percent stakes, respectively.
The Vianden Pumped Storage Plant is located just north of Vianden in Diekirch District, Luxembourg. The power plant uses the pumped-storage hydroelectric method to generate electricity and serves as a peaking power plant. Its lower reservoir is located on the Our River, bordering Germany, and the upper is elevated above on the nearby Saint Nicholas Mountain. Construction on the plant began in 1959 and the first pump-generators were commissioned in 1962. A tenth pump-generator was installed in 1976 bringing the plant's installed generating capacity to 1,096 megawatts (1,470,000 hp). The plant generates an average of 1,650 gigawatt-hours (5,900 TJ) annually but of course consumes even more. Generally the efficiency of this energy storage method is around 70–80%. The plant is owned by Société électrique de l'Our and RWE. Construction on an eleventh pump-generator began in 2010 and it is expected to be commissioned in 2013, which will bring the plant's installed capacity to 1,296 megawatts (1,738,000 hp).
The Kyiv Pumped-Storage Power Plant is a pumped-storage power station on the west bank of the Kyiv Reservoir in Vyshhorod, Ukraine. The Kyiv Reservoir serves as the lower reservoir and the upper reservoir is located 70 m (230 ft) above the lower. Water sent from the upper reservoir generates electricity with three 33.3 megawatts (44,700 hp) conventional hydroelectric generators and three 45 megawatts (60,000 hp) reversible pump generators. During periods of low demand, such as nighttime, the pump generators push water from the lower reservoir to the upper for use during peak hours. The first generator was commissioned in 1970, and the last in 1972.
The Schoellkopf Power Station was built on land owned by Jacob F. Schoellkopf above the Niagara Gorge near the American Falls, 1,600 feet (490 m) downriver from Rainbow Bridge. Understanding the growing need for electricity and the role of harnessing the Falls, Schoellkopf purchased the land for the hydraulic canal on May 1, 1877 for $71,000. After Schoellkopf Sr.'s death in 1903, his sons took over the operation of the power business. In 1918, Schoellkopf's Niagara Falls Hydraulic Power and Manufacturing Company merged with the Niagara Falls Power Company, which was owned by Edward Dean Adams. Much of the site is, as of 2014, occupied by the Maid of the Mist tour boat company as a maintenance area and off-season boat storage yard. The power station remains form a part of a fully accessible tourist attraction associated with Niagara Falls State Park and is connected with its Niagara Gorge hiking trail system.
The Snoqualmie Falls Hydroelectric Plant is located just north of Snoqualmie in King County, Washington state, US. It is situated about 22 mi (35 km) east of Seattle. Located just below the Snoqualmie Falls, the power plant consists of two power houses, Plant 1 and Plant 2. Plant 1 was completed in 1899 and is located underground. It is the first completely underground hydroelectric power plant ever built in the world. Plant 2 was built in 1910 and is located along the right bank of the Snoqualmie River. Both plants receive water from a small reservoir created by a weir atop the falls. Plant 1 has an installed capacity of 13.7 MW and Plant 2 a capacity of 40.2 MW for a total installed capacity of 53.9 MW, enough to power 40,000 homes.