The Cirencester branch line was a five-mile-long single-track branch railway line in Gloucestershire, England that connected Cirencester to the main line at Kemble. It was opened by the Cheltenham and Great Western Union Railway in 1841. The main line was extended from Kemble to a junction near Gloucester in 1845, by the GWR which had taken over the C&GWUR. The branch supported a busy passenger and goods business, but these declined in the 1930s, and closure was threatened in the 1950s. To reduce costs and maintain the viability of the line, lightweight four-wheel diesel railbuses were introduced, and they proved popular. Nevertheless the line's decline was inexorable, passenger service closed in 1964 and the goods service ending the following year.
The route crossed the River Thames near its source and formed the highest rail crossing point on the river.
The Great Western Railway opened its main line between London and Bristol in 1841. [1] During the construction period, an independent company called the Cheltenham and Great Western Union Railway obtained authorisation on 21 June 1836 to make a line from the GWR at Swindon, to Cheltenham by way of Stroud and Gloucester. The estimated cost of construction was £750,000. [2]
As well as the main line between Swindon and Cheltenham, there was to be a branch to Cirencester, terminating at a place there referred to as Botany Bay. A landowner at Kemble, named Robert Gordon, was evidently hostile to the railway, and he secured clauses in the authorising Act requiring a tunnel, not needed for engineering purposes, near Kemble. Moreover the railway was forbidden to open a public station on Gordon's estate. The new line was to be on the broad gauge. [3]
The money market was extremely depressed in the period following authorisation of the line, and subscriptions could not be secured to make material progress on construction. In desperation, the directors determined to construct between Swindon and Cirencester only for the time being, for that would give the best chance of getting an income that would pay a dividend on the outlay. The company arranged a provisional lease with the Great Western Railway, in which the GWR would pay £17,000 annually for the use of the (as yet unbuilt) line. [3]
The Bristol and Gloucester Railway was relying on timely completion of the C&GWUR at the Gloucester and Cheltenham end of the line, and obtained Parliamentary clauses in C&GWUR Acts pressuring the Cheltenham company to complete at the Gloucester end of the line, and the emphasis on early construction passed to that area. In November 1840 even that work proved impossible to finance, and attention reverted to the Swindon end of the line.
Progress was eventually made, and the line opened between Swindon and Cirencester on 31 May 1841. It was a single broad gauge line; stations were at Purton, Minety and Cirencester, so there was no intermediate station on what was to be the branch line. The line was leased to the GWR as arranged, for a period of seven years. [4] In 1842 the C&GWUR obtained Parliamentary authorisation to sell their line to the GWR. The main line company was not yet ready to purchase, but after a delay the transfer was agreed in January 1843. The actual amalgamation took place on 1 July 1843; the GWR spent £230,000 in the acquisition of the line, which so far had cost the C&GWUR £600,000 to construct. [4]
The GWR did not hasten to complete the line, but it opened from Kemble to Standish Junction, joining the Bristol line there, on 12 May 1845. [5] Kemble thus became the junction station for what was now the Cirencester branch. Robert Gordon's restrictive clauses prevented the opening of a public station there, and the GWR contented itself with an exchange station, not accessible for joining and leaving passengers or goods. Tetbury was served by a station named Tetbury Road, located on the main line immediately north of the Cirencester to Tetbury road, just outside Gordon's estate (and near the present-day Thames Head public house). [note 1] [3] [6]
The Cirencester branch had been opened as a broad gauge line. The GWR undertook a widespread conversion to narrow (standard) gauge in the general area in 1872, and the Cirencester branch was closed on 22 May for the conversion work and reopened as a standard gauge line on 27 May. Passengers were conveyed by omnibus to and from Tetbury Road station during the closure. [7]
The station originally had an overall roof, but this was removed in 1874. [6]
Kemble station was fully open to the public on 1 May 1882. [8]
In 1908, the Webb-Thompson electric train staff system was installed on the branch. The Cirencester line was controlled from Kemble East signalbox and Cirencester. During 1929 Kemble East signalbox was abolished, and a new 62 lever Kemble signalbox installed. Because of the curvature of the platform at Kemble there was an auxiliary staff instrument on the platform. In 1936, there were eleven passenger trains each way daily, as well as three goods trains. By 1954, the passenger service was reduced to nine trains daily. [9]
In 1922, there were ten trains daily, but no Sunday service. [10]
In 1956, work was carried out towards renovation of Cirencester station, but the work was suspended, leaving the buildings in a partly completed state. [6]
In an attempt to save the line from closure, diesel railbuses were introduced on the line in February 1959 to reduce costs. The train service was increased to fourteen trains per day and halts were opened at Chesterton Lane and, in January 1960, at Park Leaze. Results were encouraging: 130,000 passengers yearly, an average of about 13 per train. Particularly on Saturdays, the railbus was overcrowded. The original intention was to run railbuses through to Swindon to avoid a change of trains at Kemble, but this proved impossible as the lightweight vehicles did not reliably operate the signalling track circuits on the main line.
Nevertheless, despite the initial success, the passenger service was not financially viable, and it was withdrawn on 6 April 1964. Goods traffic was withdrawn on 4 October 1965. [8] [6] [10]
A Cirencester ring road was built on part of the railway in the mid 1970s. [11]
In 2016, discussions took place regarding the potential of relaying 5km of track from Kemble station to the edge of Cirencester [12] at Chesterton Halt. [13]
In January 2019, the Campaign for Better Transport identified the line as Priority 2 for reopening. Priority 2 is for those lines which require further development or a change in circumstances (such as housing developments). [14]
Two bids for feasibility study funding were made to the Department for Transport's 'restoring your railway' fund in March and June 2020, and the second was successful. [15]
Cirencester branch line | ||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
The Great Western Railway (GWR) was a British railway company that linked London with the southwest and west of England, the West Midlands, and most of Wales. It was founded in 1833, received its enabling Act of Parliament on 31 August 1835 and ran its first trains in 1838. It was engineered by Isambard Kingdom Brunel, who chose a broad gauge of 7 ft —later slightly widened to 7 ft 1⁄4 in —but, from 1854, a series of amalgamations saw it also operate 4 ft 8 1⁄2 in standard-gauge trains; the last broad-gauge services were operated in 1892.
The Golden Valley line is the popular name given to the railway line between Swindon and Gloucester or Cheltenham Spa in England.
Gloucester railway station is a railway station serving the city of Gloucester in England. The station was originally built as the terminus of the Birmingham and Gloucester Railway in 1840, but the arrival of the Bristol and Gloucester Railway and Cheltenham and Great Western Union Railway in 1844, and then conversion to a through station for the South Wales Railway in 1851 resulted in a very complex layout. Subsequent closures and rationalization have left Gloucester with a station that is located off the main Bristol-Birmingham line, meaning trains that call at Gloucester must reverse except for trains that continue along the Gloucester to Newport Line.
Kemble railway station is a railway station that serves the village of Kemble in Gloucestershire, England. The station is on the Swindon to Gloucester "Golden Valley" line. Despite its rural location, Kemble station has a high number of passengers, due mainly to the proximity of Cirencester.
The Bristol and Gloucester Railway was a railway company opened in 1844 to run services between Bristol and Gloucester. It was built on the 7 ftBrunel gauge, but it was acquired in 1845 by the 4 ft 8 1⁄2 instandard gauge Midland Railway, which also acquired the Birmingham and Gloucester Railway at the same time.
Swindon railway station is on the Great Western Main Line in South West England, serving the town of Swindon, Wiltshire. It is 77 miles 23 chains (124.4 km) down the line from London Paddington and is situated between Didcot Parkway and Chippenham on the main line. It is managed by Great Western Railway, which also operates all the trains.
The Cheltenham and Great Western Union Railway was a railway company intended to link Cheltenham, Gloucester and Swindon, in England. It was authorised in 1836 but it found it very hard to raise money for the construction, and it opened only a part of its line, between Swindon and Cirencester, in 1841. It sold its business to the Great Western Railway, which quickly built the line through to Gloucester in 1845 and Cheltenham in 1847; part of that route was shared with other companies.
Cirencester Watermoor railway station was on the Midland and South Western Junction Railway (M&SWJR) at Cirencester in Gloucestershire. The station opened on 18 December 1883, as the terminus of the Swindon and Cheltenham Extension Railway line from Swindon Town. That line then amalgamated with the Swindon, Marlborough and Andover Railway to form the M&SWJR. Cirencester became a through-station in 1891, with the opening of the northern extension of the line between Cirencester and the junction at Andoversford with the Great Western Railway (GWR)'s Cheltenham Lansdown to Banbury line, which had opened in 1881.
South Cerney railway station was on the Midland and South Western Junction Railway in Gloucestershire. The station opened on 18 December 1883 on the Swindon and Cheltenham Extension Railway line from Swindon Town to the temporary terminus at Cirencester Watermoor. The S&CER line amalgamated in 1884 with the Swindon, Marlborough and Andover Railway to form the M&SWJR, and through services beyond Cirencester to the junction at Andoversford with the Great Western Railway's Cheltenham Lansdown to Banbury line, which had opened in 1881, started in 1891.
The Banbury and Cheltenham Direct Railway (B&CDR) was a railway company through the Cotswolds in England that built a line between points near Banbury and Cheltenham. Its principal objective, as well as a general rural rail service, was the conveyance of iron ore from the East Midlands to South Wales.
Marlborough railway stations refers to the two railway stations which served Marlborough, Wiltshire, England; the town supported two railway routes and Savernake, the junction station at first, later had a second station.
The Gloucester and Cheltenham Tramroad, also known as the Gloucester and Cheltenham Railway, connected Gloucester and Cheltenham with horse-drawn trams. Its primary economic purpose was the transport of coal from Gloucester's docks to the rapidly developing spa town of Cheltenham and the transport of building stone from quarries on nearby Leckhampton Hill.
The Midland and South Western Junction Railway (M&SWJR) was an independent railway built to form a north–south link between the Midland Railway and the London and South Western Railway in England, allowing the Midland and other companies' trains to reach the port of Southampton. The M&SWJR was formed in 1884 from the amalgamation of the Swindon, Marlborough and Andover Railway and the Swindon and Cheltenham Extension Railway. The line was absorbed by the Great Western Railway at the 1923 Grouping and became part of British Railways on nationalisation in 1948. The railway closed to passengers in 1961, and to goods between 1964 and 1970. A small part of it has been reopened as the heritage Swindon and Cricklade Railway.
The Tetbury branch line was a 7.5-mile (12.1 km) single-track branch railway line that connected Tetbury with the main line at Kemble on the line between Swindon and Gloucester.
Cheltenham Spa St. James railway station was a station in the town of Cheltenham.
Tetbury Road railway station was built by the Cheltenham and Great Western Union Railway to serve the Gloucestershire villages of Kemble and Coates, and the town of Tetbury.
Cirencester Town railway station was one of three railway stations which formerly served the town of Cirencester, Gloucestershire, England; the others were Cirencester Watermoor and Chesterton Lane Halt.
Chalford railway station was situated on the Great Western Railway's Golden Valley Line, between Swindon and Gloucester. It was just east of the bridge carrying Cowcombe Hill over the railway. To the east of the station site lies Chalford Viaduct, and beyond that, Sapperton Long Tunnel.
Park Leaze Halt railway station was one of two intermediate halts on the Cirencester branch line from Kemble, Gloucestershire, England. It was one of the shortest-lived stations in post-World War II Britain, being open for just over four years, between 1960 and 1964.
The Badminton railway line is a railway line opened in 1903 by the Great Western Railway between Wootton Bassett in Wiltshire and Patchway and Filton, north of Bristol, England. Forming the eastern section of the South Wales Main Line, it shortened the distance between South Wales and London for heavy mineral traffic and for express passenger trains, and relieved congestion on the line through Bath.