Eurotrain was a joint venture formed by Siemens and GEC-Alstom to market high-speed rail technology in Asia. In 1997 it was one of two competitors to supply the core system of Taiwan High Speed Rail (THSR), and it was awarded the status of preferred bidder by concessionaire THSRC. Eurotrain assembled a demonstration train, but later THSRC decided to award the contract to a rival consortium, leading to a legal battle ending in damage payments for Eurotrain in 2004.
Eurotrain was a joint venture of Siemens (the main maker of the German ICE) and GEC-Alsthom (the main maker of the French TGV), formed in March 1996 with the aim to pool their high-speed rail technologies and market it jointly in Asia. [1] The companies wanted to avoid a repeat of a competitive battle they had for Korea's KTX, which resulted in a loss for Siemens and limited benefits for victorious GEC-Alsthom. [2] GEC-Alsthom held 60% and Siemens held 40% in the joint venture. [3] The first and only high-speed project Eurotrain was involved in was THSR.
THSR was realised as a Build-Operate-Transfer (BOT) project, but Eurotrain was already involved at the stage of the bidding for the BOT franchise. The bids of the two rival consortia were both based on specific high-speed rail technology platforms: Taiwan High Speed Rail Consortium (THSRC) allied with Eurotrain, while the rival Chunghwa High Speed Rail Consortium (CHSRC) allied with Taiwan Shinkansen Consortium (TSC), which offered Japanese Shinkansen technology. On 25 September 1997, [4] THSRC (later renamed Taiwan High Speed Rail Corporation with the same acronym) was selected as preferred bidder. [5]
Also in 1997, THSRC declared Eurotrain the preferred bidder to supply the core technology, [6] [7] which included the high-speed trains, track, electrification, signalling and communication. [8]
During the final negotiations, THSRC and Eurotrain sought to convince BOHSR about the technical viability of their offer by staging a demonstration run with a hybrid train assembled specifically for this purpose [9] (see Demonstration train).
The Eschede train disaster on 3 June 1998 didn't reduce THSRC's chances: although BOHSR wanted detailed information from Germany about the causes of the accident, it recognised that Eurotrain's train type in the THSRC offer did not use the wheel type the break of which was the root cause of the derailment. [10] THSRC finally signed the agreement about the BOT contract with the government on 23 July 1998. [11]
To meet THSRC's high capacity requirements, Alstom and Siemens planned to create a hybrid train type that combines the lighter and higher capacity TGV Duplex articulated double-deck intermediate cars, extended from 8 to 12 cars, with the more powerful powerheads of German Railways (DB) ICE 2 high-speed trains. [12]
In early 1998, the two companies created a demonstration train by combining cars of three existing French and German high-speed trains: ICE 2 powerheads DB 402 042-6 and 402 046-7 and the intermediate cars of TGV Duplex trainset #224. [12]
The three components of the demonstration train were adapted separately at Siemens's Duewag plant in Uerdingen, Germany and GEC-Alsthom's plant in La Rochelle, France, in March 1998. [12] Adaptations included the connection on the ICE 2 powerheads to the roof-mounted high-voltage cable along the TGV trainset, the installation of electronic and optical cables for the ICE drive control electronics on the roof of the TGV trainset, the installation of a rectifier on a TGV car for the on-board electricity, and the replacement of the automatic coupler on the ICE 2 powerheads with side buffers and standard UIC coupler. [12] Braking systems weren't adapted, only pneumatic braking was used. [12] The ICE 2 powerheads also received a special livery to harmonise with that of the TGV Duplex set. [12]
The train was assembled in Munich in early April 1998, followed by static and quasi-static tests. [12] Then, between 25 and 30 April 1998, the train conducted test runs with speeds of up to 310 km/h on the Hanover–Würzburg high-speed railway and the line from Hannover to Minden, to measure running stability, ride comfort, pressure during tunnel crossings, and pass-by noise. [12]
On 3 May 1998, the Eurotrain demonstration train was presented to the public in Hamburg. [12] The next day, on 4 May 1998, the train made a presentation run from Göttingen to Hannover with THSRC and BOHSR representatives present, achieving a maximum speed of 316 km/h. [13] [14]
THSRC had difficulty raising capital for the project. In May 1999, the government of Japan promised soft loans if THSRC switched to TSC, [15] and the head of the losing CHSRC bid, who was the top financier of the governing Kuomintang, promised funds, too. [15] In light of these offers, in May 1999, THSRC signalled that the selection of the core system supplier is still open, and formally relaunched a tender on 15 June 1999. [16]
To balance the perceived financial advantages of the TSC offer, Eurotrain offered to take a 10% stake in THSRC in September 1999. [17] (The next year, TSC, too, would sign an agreement to buy a 10% stake in THSRC. [18] ) The competitors also received public government backing for their offers. While the Japanese government supported TSC with the above-mentioned promise of loans, [17] a letter from the European Union's Trade Commission to Taiwan's government expressed Europe-wide support for Eurotrain. A visit by France's Transport Minister was only called off in the wake of the Taiwan frigates kickback scandal, leading to rumours that Eurotrain may have links to the lobby group at the centre of the scandal. [19] However, further ministerial visits from both France and Germany were planned before the decision came. [20]
THSRC announced on 28 December 1999 that it would negotiate a final contract with the Taiwan Shinkansen Consortium, saying that while both trains were satisfactory, TSC had "technology, price, finance and maintenance merits". [21] THSRC emphasized that expectations on exchange rate fluctuations played a role, but also noted that TSC offered a newer Shinkansen than they had in 1997. [21]
It was rumoured that the decision for TSC over Eurotrain was political: [22] according to Taiwanese media, the choice was made to pave the way for then-President Lee Teng-hui's visit to Japan. [21] THSRC denied the allegations. [22] [23] However, in a book published earlier in May 1999, Lee made a case for picking the Japanese offer, claiming that while it was more expensive, the Shinkansen was superior based on safety and political considerations. [15]
The losing Eurotrain consortium interpreted the terms of its earlier preferred bidder status as a binding agreement that THSRC violated by starting negotiations with TSC, [24] and filed an injunction against it. [25] On behalf of Eurotrain, Siemens chairman Heinrich von Pierer also lobbied President Lee Teng-hui for intervention, but was rejected. [22] The German, French, and British trade offices also questioned THSRC's chairwoman. [24] Eurotrain lost the injunction case both on the initial filing [7] and at the appeal in the High Court. [26]
While Eurotrain eventually conceded the train system bid, it filed a US$800 million damage claim at the Singapore International Arbitration Centre in February 2001. In response, THSRC contended that their decision was a commercial one, reiterating that "price, financial planning, and maintenance" were the only deciding factors. [27] After a lengthy arbitration process, the court ruled in March 2004 that THSRC should pay a compensation for the US$32.4 million Eurotrain spent on development and US$35.7 million for unjust enrichment. [6] THSRC agreed to pay US$65 million (US$89 million with interest) to Eurotrain in November 2004. [23]
THSRC's working with Eurotrain resulted in the use of European high-speed rail technology or specialists in some fields.
Although in the nineties, Eurotrain seriously considered to participate in the expected competition for the Beijing–Shanghai high-speed railway, the constituent companies didn't pursue the joint venture further, and competed for further contracts separately.
After a meeting on 17 December 1999, freshly installed DB CEO Hartmut Mehdorn and SNCF CEO Louis Gallois called on the European rail industry to create a joint high-speed train platform, to realise economies of scale. [34] DB's spokesman argued that if it is possible for German and French companies to jointly offer Eurotrain in Taiwan, the same should be possible in Europe. [34]
The proposal, dubbed Euro-Train by the media, was taken up as a joint project of European state railways and train producers, with Eurotrain constituents Alstom and Siemens remaining the only industry partners in the project by September 2000. [35] The project was officially named Highspeed Train Europe (HTE), and Italy's state railway FS was won as additional partner. However, after the evaluation of 10,000 detail questions, 500 remained in which the partners couldn't compromise, [36] and the HTE project was abandoned in September 2009. [37]
High-speed rail (HSR) is a type of rail transport network utilizing trains that run significantly faster than those of traditional rail, using an integrated system of specialized rolling stock and dedicated tracks. While there is no single standard that applies worldwide, lines built to handle speeds above 250 km/h (155 mph) or upgraded lines in excess of 200 km/h (124 mph) are widely considered to be high-speed.
Alstom SA is a French multinational rolling stock manufacturer which operates worldwide in rail transport markets. It is active in the fields of passenger transportation, signaling, and locomotives, producing high-speed, suburban, regional and urban trains along with trams.
Intercity Express is a high-speed rail system in Germany. It also serves destinations in Austria, France, Belgium, Switzerland and the Netherlands as part of cross-border services. It is the flagship of the German state railway, Deutsche Bahn. ICE fares are fixed for station-to-station connections, on the grounds that the trains have a higher level of comfort. Travelling at speeds up to 320 km/h (200 mph), they are aimed at business travellers and long-distance commuters and marketed by Deutsche Bahn as an alternative to flights.
The Acela is Amtrak's flagship passenger train service along the Northeast Corridor (NEC) in the Northeastern United States between Washington, D.C., and Boston via 13 intermediate stops, including Baltimore, New York City and Philadelphia. Acela trains are the fastest in the Americas, reaching 150 miles per hour (240 km/h), but only over 49.9 miles (80.3 km) of the 457-mile (735 km) route.
Taiwan High Speed Rail (THSR) is the high-speed railway of Taiwan consisting of one line that runs approximately 350 km (217 mi) along the west coast, from the capital Taipei to the southern city of Kaohsiung. With construction and operations managed by a private company, Taiwan High Speed Rail Corporation (THSRC), which also operates the line, the total cost of the project was NT$513.3 billion in 1998. The system's technology is based primarily on Japan's Shinkansen.
The THSR 700T is the high-speed electric multiple unit trainset derived from the Japanese Shinkansen family for Taiwan High Speed Rail (THSR), Taiwan's high-speed rail line. The THSR 700T is based primarily on the 700 Series Shinkansen that currently operates on the San'yō Shinkansen line and previously on the Tokaido Shinkansen line in Japan, with the "T" referring to Taiwan. The trains were manufactured in Japan by Kawasaki Heavy Industries, Nippon Sharyo, and Hitachi, Ltd., marking the first time Japanese Shinkansen trains have been exported overseas. 30 trains were delivered to THSR operator Taiwan High Speed Rail Corporation (THSRC), and are in regular service with a top speed of 300 kilometres per hour (186 mph) since the line's opening on January 5, 2007.
Thalys PBKA is a high-speed trainset, manufactured by the French company GEC-Alsthom, and used on the international Eurostar service. Originally built for Thalys they were intended to operate between Paris, Brussels, Köln and Amsterdam, forming the abbreviation PBKA. They were initially intended to be sole rolling stock of the service, but their extreme cost and complexity due to their quadri-current capability led the order of a simpler tri-current sister class, the Thalys PBA, a TGV Réseau derivative, with which they can work in multiple.
The TGV Duplex is a French high-speed train of the TGV family, manufactured by Alstom, and operated by the French national railway company SNCF. They were the first TGV trainsets to use bi-level passenger carriages with a seating capacity of 508 passengers, increasing capacity on busy high-speed lines. While the TGV Duplex started as a small component of the TGV fleet, it has become one of the system's workhorses.
Siemens Velaro is a family of high-speed electric multiple unit trains built by Siemens and used in Germany, Belgium, France, the United Kingdom, the Netherlands, Spain, China, Russia, and Turkey. The Velaro is based on the ICE 3M/F high-speed trains manufactured by Siemens for Deutsche Bahn (DB). Deutsche Bahn were the first to order Siemens high-speed trains; it ordered 13 of these units in 1994, the Nederlandse Spoorwegen (NS) 4 units. The trains were delivered in 1999 for service and were labeled and marketed as the Velaro by their manufacturer, Siemens.
The ICE 2 is the second series of German high-speed trains and one of six in the Intercity-Express family since 1995. The ICE 2 (half-) trains are even closer to a conventional push–pull train than the ICE 1, because each train consists of only one locomotive, six passenger cars and a cab car. The maximum speed is 280 km/h (175 mph), but this is limited to 250 km/h (155 mph) when the cab car is leading the train and even further down to 160 km/h (100 mph) when two units are coupled at the powerheads due to the forces on the overhead line by their respective pantographs.
The Buenos Aires–Rosario–Córdoba high-speed railway was a project designed to link the Argentine cities of Buenos Aires, Rosario and Córdoba through a 710 km (440 mi) high-speed rail network. The plan, announced by then-President Néstor Kirchner during a press conference at the Casa Rosada on 26 April 2006, would have been the first in Argentina operating at up to 320 km/h (200 mph). The entire project was dismissed due to the financial crisis of 2007–08.
HSR-350x, alternatively called G7, KHST or NG-KTX, is a South Korean experimental high-speed train. It was developed and built in a joint project of government research institutes, universities and private companies that started in 1996, which aimed to reduce import dependence in high-speed rail technology. New components developed for the HSR-350x included motors, electronics, and the carbody of passenger cars. Test runs were conducted between 2002 and 2008. The experimental train achieved the South Korean rail speed record of 352.4 km/h (219.0 mph) in 2004. The HSR-350x was the basis for Korail's KTX-II (KTX-Sancheon) commercial high-speed trains.
Construction of the first high-speed rail in Germany began shortly after that of the French LGVs. However, legal battles caused significant delays, so that the German Intercity-Express (ICE) trains were deployed ten years after the TGV network was established. Germany has around 1,658 kilometers of high speed lines.
The Scharfenberg coupler is a commonly used type of fully automatic railway coupling.
The Ministry of Transportation and Communications governs transportation in Taiwan.
The KTX-I, also known as the TGV-K or Korail Class 100000, is a South Korean high speed train class based on the French TGV Réseau. The 20-car formation of the trainsets without restaurant car is optimized for high capacity. The 46 trainsets were built partly in France and partly in South Korea in the framework of a technology transfer agreement, which was the basis for further domestic high-speed train development in South Korea.
The British Rail Class 374, also referred to as the Eurostar e320, is a type of electric multiple unit passenger train used on Eurostar services through the Channel Tunnel to serve destinations beyond the core routes to Paris and Brussels. They began to run passenger services in November 2015. The trains, owned by Eurostar International Limited, are sixteen-coach versions of the Siemens Velaro. Each train is 390.2 m (1,280 ft) long. The trains are compliant with the Technical Specifications for Interoperability (TSI).
The first-generation Acela Express trainset is a unique set of vehicles used on the Acela, Amtrak's flagship high-speed service along the Northeast Corridor (NEC) in the Northeastern United States. When they debuted in 2000, the sets were the fastest in the Americas, reaching 150 mph (240 km/h) on 33.9 mi (54.6 km) of the route. They were built between 1998 and 2001 by a consortium of Alstom and Bombardier. Each set has two power cars derived from units that Alstom built for the TGV, and six passenger cars derived from the LRC that Bombardier built for Via Rail.
In Taiwan böten bereits deutsche und französische Firmen gemeinsam den Hochgeschwindigkeitszug "Eurotrain" an, ergänzte Bahnsprecher Stephan Heimbach gegenüber SPIEGEL ONLINE. "Warum sollte in Europa nicht das möglich sein, was in Asien schon praktiziert wird?"