Thames Barrier

Last updated
Thames Barrier
Thames Barrier 03.jpg
View of the barrier gates, which are closed when a high tide is forecast
CountryUnited Kingdom
Location London
Coordinates 51°29′49″N0°2′12″E / 51.49694°N 0.03667°E / 51.49694; 0.03667
Purpose Flood control
StatusOperational
Construction began1974
Opening date8 May 1984
Construction cost£534 million
Built by
Operator(s) Environment Agency
Dam and spillways
Type of dam Barrage
ImpoundsRiver Thames
Height (thalweg)20.1 metres
Length520 metres
Turbines 0
Website
GOV.UK page

Far view of the River Thames Flood Barrier Thames Barrier London.jpg
Far view of the River Thames Flood Barrier

The Thames Barrier is a retractable barrier system built to protect the floodplain of most of Greater London from exceptionally high tides and storm surges moving up from the North Sea. It has been operational since 1982. When needed, it is closed (raised) during high tide; at low tide, it can be opened to restore the river's flow towards the sea. Built about 2 miles (3.2 kilometres) east of the Isle of Dogs, its northern bank is in Silvertown in the London Borough of Newham and its southern bank is in the New Charlton area of the Royal Borough of Greenwich.

Contents

History

Background

Flooding in London has been a problem since Roman times. [1] In 1954, the Waverley Committee, established to investigate the serious North Sea flood of 1953 which affected parts of the Thames Estuary and parts of London, recommended that "as an alternative to raising the banks, the possibility and cost of erecting a structure across the Thames which could be closed in a surge should be urgently investigated". [2] A number of designs were put forward, from a huge road viaduct with two 500 foot (150 m) sluice gates crossing the Thames at Crayfordness to flap gates lying on the river bed and floated up by compressed air. [3] [ page needed ] By 1965, when the Greater London Council (GLC) took over responsibility, two major schemes were under consideration, costed at £24 million and £41 million respectively (£500 million and £800 million at 2020 prices). [3] [ page needed ]

In 1966, Sir Hermann Bondi was asked to take an independent view of the situation. He considered the estimated construction costs and the probability of a flood and of damage if the barrier was not built. He strongly recommended that a barrier should be built in order to avoid the catastrophe of flooding central London, and a site was agreed at Woolwich. [3] [ page needed ]

The barrier protects central London against a storm surge, caused when a deep depression forms to the north of Scotland and progresses across the North Sea and south-easterly towards southern Scandinavia. When such a surge coincides with a high spring tide, the high winds associated with the depression can funnel the water up the Thames Estuary and cause surges of up to 3.5 metres (11.6 feet). The planners assessed that in the absence of a barrier, such a surge could inundate 45 square miles (117 km2) of land, put hospitals, power stations and the London Underground out of action and cause damage estimated in 1966 at £2 billion [4] (about £50 billion at 2020 prices). The barrier was designed to provide a flood defence capable of resisting a once in 1000 year surge tide at a base date of 2030.

Design and construction

Diagram showing how the gates work, though the barrier actually rises further than this to allow water to "underspill" under the barrier in a controlled fashion Thames Barrier - simple operation diagram.png
Diagram showing how the gates work, though the barrier actually rises further than this to allow water to "underspill" under the barrier in a controlled fashion

The concept of the rising sector gates was devised by (Reginald) Charles Drapeer. In 1969, from his parents' house in Pellatt Grove, Wood Green, London, he constructed a working model. The novel rotating cylinders were based on the design of the taps on his gas cooker. The barrier was designed by Rendel, Palmer and Tritton for the Greater London Council and the concept tested at the Hydraulics Research Station, Wallingford. [1] The site at New Charlton was chosen because of the relative straightness of the banks, and because the underlying river chalk was strong enough to support the barrier.

The Thames Barrier and Flood Prevention Act, authorising construction, was passed in 1972. In 1974 the GLC placed the two major construction contracts. Civil construction was undertaken by a Costain/Hollandsche Beton Maatschappij/Tarmac Construction consortium. [3] [ page needed ] A separate contract for the gates and operating machinery was placed with the Davy Cleveland Barrier Consortium, formed by Davy McKee Ltd of Sheffield and Cleveland Bridge UK Ltd. [5] [3] [ page needed ]

Work began at the barrier site in 1974 and progressed in two phases. The southern piers (9 to 6) were built first, with river traffic diverted to the north side, then traffic routed through the completed southern spans whilst the north side piers (1 to 5) were built. During construction of the piers, precast concrete sills were built in a cofferdam on the north side of the river and floated out and sunk between the piers to form the gate recesses, with access tunnels at the upstream and downstream ends. [6]

The gates of the barrier were fabricated in sections at Cleveland Bridge's Darlington works and assembled at Port Clarence on the River Tees. [7] :251 The gates, gate arms and rocking beams were transported from the Tees to the Thames by barge and lifted into position by two very large floating cranes operated by Neptun of Hamburg (now part of Smit International). [8] The mechanical and hydraulic machinery was built by Davy Loewy, Henry Berry and Vickers and trial assembled in Davy's Darnall works. Delays to the civil works required changes to the construction and installation sequence, but commissioning was relatively uneventful and the first trial operation of all the gates together was carried out on 31 October 1982. [9]

In addition to the barrier, the flood defences 18 kilometres (11 mi) down river were raised and strengthened. The barrier was officially opened on 8 May 1984 by Queen Elizabeth II. [10] The barrier cost £461 million1.23 billion now). [10] [11] Total construction cost was around £534 million (£1.6 billion at 2016 prices) with an additional £100 million for river defences.[ citation needed ]

Built across a 520-metre (1,710 ft) wide stretch of the river, the barrier divides the river into four 61-metre (200 ft) and two approximately 30-metre (100 ft) navigable spans. There are also four smaller non-navigable channels between nine concrete piers and two abutments. The flood gates across the openings are circular segments in cross section, and they operate by rotating, raised to allow "underspill" to allow operators to control upstream levels and a complete 180 degree rotation for maintenance. All the gates are hollow and made of steel up to 40 millimetres (1.6 in) thick. The gates are filled with water when submerged and empty as they emerge from the river. The four large central gates are 20.1 metres (66 ft) high and weigh 3,700 tonnes each. [12] Four radial gates by the river banks, also about 30 metres (100 ft) wide, can be lowered. These gate openings, unlike the main six, are non-navigable.[ citation needed ]

Predictions for operation

A Thames Barrier flood defence closure is triggered when a combination of high tides forecast in the North Sea and high river flows at the tidal limit at Teddington Lock indicate that water levels would exceed 16 feet (4.9 m) in central London. Though Teddington marks the Normal Tidal Limit, in periods of very high fluvial flow the tidal influence can be seen as far upstream as East Molesey on the Thames. [13]

Thames Barrier, London, England - Feb 2010.jpg
The barrier from Silvertown on the north bank of the river during normal operation, looking across to New Charlton.

Barrier closures and incidents

Closures per season (Sept–May) and flooding source
SeasonTidalCombined
tidal/
fluvial
Total
[14]
1982–83101
1983–84000
1984–85000
1985–86011
1986–87101
1987–88000
1988–89101
1989–90134
1990–91202
1991–92000
1992–93404
1993–94347
1994–95224
1995–96404
1996–97101
1997–98101
1998–99202
1999–00336
2000–0116824
2001–02314
2002–0381220
2003–04101
2004–05404
2005–06303
2006–07808
2007–08606
2008–09145
2009–10235
2010–11000
2011–12000
2012–13055
2013–1494150
2014–15101
2015–16101
2016–17202
2017–18303
2018–19303
2019–20909
2020–21246
2021–22707
2022–23202
2023–24101
Totals11891209

As of November 2023, there have been 209 flood defence closures. [14] The barrier was closed twice on 9 November 2007 after a storm surge in the North Sea which was compared to the one in 1953. [15] The main danger of flooding from the surge was on the coast above the Thames Barrier, where evacuations took place, but the winds abated a little and, at the Thames Barrier, the 9 November 2007 storm surge did not completely coincide with high tide. [16]

On 20 August 1989, hours after the Marchioness disaster, the barrier was closed against a spring tide for 16 hours "to assist the diving and salvage operations". [17]

The barrier has survived 15 boat collisions without serious damage. [18]

On 27 October 1997, the barrier was damaged when the dredger MV Sand Kite hit one of the piers in thick fog. As the ship started to sink she dumped her 3,300-tonne load of aggregate, finally sinking by the bow on top of one of the barrier's gates, where she lay for several days. Initially the gate could not be closed as it was covered in a thick layer of gravel. A longer-term problem was the premature loss of paint on the flat side of the gate caused by abrasion. The vessel was refloated in mid-November 1997. [19]

The annual full test closure in 2012 was scheduled for 3 June to coincide with the Thames pageant celebrating the Diamond Jubilee of Elizabeth II. Environment Agency said the pageant provided "a unique opportunity to test its design for a longer period than we would normally be able to", and performance under conditions of "a higher water level upstream than downstream"; also that the "more stable tidal conditions … in central London … will help the vessels taking part". [20]

Ownership and operating authority

The barrier was originally commissioned by the Greater London Council under the guidance of Ray Horner. After the 1986 abolition of the GLC it was operated successively by Thames Water Authority (dissolved 1989) and then the National Rivers Authority until April 1996 when it passed to the Environment Agency.

Future

The barrier was originally designed to protect London against a very high flood level (with an estimated return period of one hundred years) up to the year 2030, after which the protection would decrease, while remaining within acceptable limits. [21] At the time of its construction, the barrier was expected to be used 2–3 times per year. By the mid-2000s it was being operated 6–7 times a year. [22] In the 2010s, the barrier was generally (as a median) closed twice a year but the average is still 6–7 due to the extreme of 50 times in 2013–14.

This defence level allowed for long-term changes in sea and land levels as understood at that time (c. 1970). From 1982 until 19 March 2007, the barrier was raised one hundred times to prevent flooding. It is also raised monthly for testing, [23] with a full test closure over high tide once a year. [20]

Released in 2005, a study by four academics contained a proposal to supersede the Thames Barrier with a more ambitious 16 km (10 mi) long barrier across the Thames Estuary from Sheerness in Kent to Southend-on-Sea in Essex. [24]

In November 2011, a new Thames Barrier, further downstream at Lower Hope between East Tilbury in Essex and Cliffe in Kent, was proposed as part of the Thames Hub integrated infrastructure vision. The barrier would incorporate turbines to generate renewable energy and include road and rail tunnels, providing connections from Essex to a major new Thames Estuary Airport on the Isle of Grain. [25]

In a January 2013 letter to The Times , a former member of the Thames Barrier Project Management Team, Dr Richard Bloore, stated that it was not designed with increased storminess and sea level rises in mind, and called for a new barrier to be looked into immediately. [26] [27] The Environment Agency responded that it did not plan to replace the Thames Barrier before 2070, [28] as it was designed with an allowance for sea level rise of 8 mm (0.31 in) per year, which has not happened in the intervening years. [29] At the time, the barrier was around halfway through its designed lifespan. The standard of protection it provides will gradually decline over time after 2030, from a 1-in-1000-year event. The Environment Agency is examining the Thames Barrier for its potential design life under climate change, with early indications being that subject to appropriate modification, the Thames Barrier will be capable of providing continued protection to London against rising sea levels. [18] [29]

Architects Lifschutz Davidson Sandilands and marine engineers Beckett Rankine launched a proposal for a pedestrian and cycle bridge located next to the Thames Barrier; the scheme, called the Thames Barrier Bridge, was promoted as the only location in east London where a low-level opening bridge across the Thames could have relatively moderate opening spans of about 60 m (200 ft). [30] [31] [32]

See also

Related Research Articles

<span class="mw-page-title-main">River Thames</span> River in southern England

The River Thames, known alternatively in parts as the River Isis, is a river that flows through southern England including London. At 215 miles (346 km), it is the longest river entirely in England and the second-longest in the United Kingdom, after the River Severn.

<span class="mw-page-title-main">River Parrett</span> River in Dorset and Somerset, England

The River Parrett flows through the counties of Dorset and Somerset in South West England, from its source in the Thorney Mills springs in the hills around Chedington in Dorset. Flowing northwest through Somerset and the Somerset Levels to its mouth at Burnham-on-Sea, into the Bridgwater Bay nature reserve on the Bristol Channel, the Parrett and its tributaries drain an area of 660 square miles (1,700 km2) – about 50 per cent of Somerset's land area, with a population of 300,000.

The Delta Works is a series of construction projects in the southwest of the Netherlands to protect a large area of land around the Rhine–Meuse–Scheldt delta from the sea. Constructed between 1954 and 1997, the works consist of dams, sluices, locks, dykes, levees, and storm surge barriers located in the provinces of South Holland and Zeeland.

<span class="mw-page-title-main">River Orwell</span> River in Suffolk, England

The River Orwell flows through the county of Suffolk in England from Ipswich to Felixstowe. Above Ipswich, the river is known as the River Gipping, but its name changes to the Orwell at Stoke Bridge, where the river becomes tidal. It broadens into an estuary at Ipswich, where the Ipswich dock has operated since the 7th century, and then flows into the North Sea at Felixstowe, the UK's largest container port, after joining the River Stour at Shotley forming Harwich harbour.

<span class="mw-page-title-main">Storm tides of the North Sea</span> Storm tides in the North Sea are coastal floods caused by storms

Storm tides of the North Sea are coastal floods associated with extratropical cyclones crossing over the North Sea, the severity of which is affected by the shallowness of the sea and the orientation of the shoreline relative to the storm's path, as well as the timing of tides. The water level can rise to more than 5 metres (17 ft) above the normal tide as a result of storm tides.

<span class="mw-page-title-main">Port of London Authority</span> Port authority in the United Kingdom

The Port of London Authority (PLA) is a self-funding public trust established on 31 March 1909 in accordance with the Port of London Act 1908 to govern the Port of London. Its responsibility extends over the Tideway of the River Thames and its continuation. It maintains and supervises navigation, and protects the river's environment.

<span class="mw-page-title-main">Locks and weirs on the River Thames</span>

The English River Thames is navigable from Cricklade or Lechlade to the sea, and this part of the river falls 71 meters (234 feet). There are 45 locks on the river, each with one or more adjacent weirs. These lock and weir combinations are used for controlling the flow of water down the river, most notably when there is a risk of flooding, and provide for navigation above the tideway.

<span class="mw-page-title-main">Teddington Lock</span> Series of locks on the River Thames in London

Teddington Lock is a complex of three locks and a weir on the River Thames between Ham and Teddington in the London Borough of Richmond upon Thames, England. Historically in Middlesex, it was first built in 1810.

<span class="mw-page-title-main">Thames Estuary</span> Estuary in which the River Thames meets the waters of the North Sea

The Thames Estuary is where the River Thames meets the waters of the North Sea, in the south-east of Great Britain.

<span class="mw-page-title-main">North Sea flood of 1953</span> Late January-early February 1953 North sea flood storm

The 1953 North Sea flood was a major flood caused by a heavy storm surge that struck the Netherlands, north-west Belgium, England and Scotland. Most sea defences facing the surge were overwhelmed, resulting in extensive flooding.

<span class="mw-page-title-main">The Haven, Boston</span> River in Lincolnshire, England

The Haven is the tidal river of the port of Boston, Lincolnshire in England. It provides access for shipping between Boston Deeps in The Wash and the town, particularly, the dock. It also serves as the outfall into the sea, of the River Witham and of several major land drains of the northern Fens of eastern England, which are known collectively as the Witham Navigable Drains..

<span class="mw-page-title-main">Tideway</span> Part of the River Thames subject to tides

The Tideway is a part of the River Thames in England which is subject to tides. This stretch of water is downstream from Teddington Lock. The Tideway comprises the upper Thames Estuary including the Pool of London.

<span class="mw-page-title-main">1928 Thames flood</span> Combined storm surge and river flood of the River Thames

The 1928 Thames flood was a disastrous flood of the River Thames that affected much of riverside London on 7 January 1928, as well as places further downriver. Fourteen people died and thousands were made homeless when floodwaters poured over the top of the Thames Embankment and part of the Chelsea Embankment collapsed. It was the last major flood to affect central London, and, along with the disastrous North Sea flood of 1953, helped lead to the implementation of new flood control measures that culminated in the construction of the Thames Barrier in the 1970s.

<i>Flood</i> (Doyle novel)

Flood is a 2002 disaster thriller novel by Richard Doyle. Set in present-day London, the novel depicts a disastrous flood and fire of London, caused by a storm, and the consequential accident at an oil refinery, and failure of the Thames Barrier. The plot is similar to his 1976 novel Deluge, updated to include the construction of the Thames Flood Barrier.

<span class="mw-page-title-main">North Sea flood of 1978</span> Storm surge on the east coast of England

The North Sea flood of 1978 was a storm surge which occurred over 11–12 January causing extensive coastal flooding and considerable damage on the east coast of England between the Humber and Kent. Higher water levels were reached than during the devastating North Sea flood of 1953 from North Shields to King's Lynn, but values were lower towards the Thames. Locally severe flooding occurred in Lincolnshire, The Wash, north Norfolk and Kent. Improvements in flood protection following the devastating flood of 1953 meant that the catastrophic losses seen during that storm were not repeated. The storm caused severe damage to many piers along the east coast of England.

<span class="mw-page-title-main">Cyclone Xaver</span> Winter storm that affected northern Europe in 2013

Cyclone Xaver, also known as the North Sea flood or tidal surge of 2013, was a winter storm that affected northern Europe. Force 12 winds and heavy snowfall were predicted along the storm's path, and there were warnings of a significant risk of storm surge leading to coastal flooding along the coasts of the North and Irish Seas.

<span class="mw-page-title-main">Cyclone Anne (2014)</span> 2014 European windstorm

Cyclone Anne was a European windstorm which caused €75 million in damage across western Europe in early January 2014, followed days later by Cyclone Christina.

<span class="mw-page-title-main">River Hull tidal surge barrier</span> A flood barrier in Kingston upon Hull, England

The River Hull tidal surge barrier is a flood control gate located on the River Hull in the city of Kingston upon Hull, in the East Riding of Yorkshire, England. The barrier impounds the river in times of tidal surges, preventing water moving upstream of the river from the Humber Estuary, and flooding the areas of the city which are near to the river, or susceptible to flooding. It is held horizontal when not in use, and turns 90 degrees before being lowered to the riverbed in the event of a tidal surge. It is the second largest flood barrier in the United Kingdom after the Thames Barrier in London.

<span class="mw-page-title-main">Lagoon Hull</span> Proposed lagoon in the Humber Estuary, England

Lagoon Hull is a proposed £1.5 billion development on the Humber Estuary foreshore between Hessle and Kingston upon Hull, in the East Riding of Yorkshire, England. The proposed lagoon would be formed from a stone causeway and will provide an outer lock gate in the Humber Estuary which would effectively dam the River Hull, making it a non-tidal waterway. The 11-kilometre (6.8 mi) long causeway would also provide a dual carriageway from the A63 at Hessle which would run to Hull Docks, taking traffic away from the city centre. The scheme is being vaunted as one that will prevent future flooding in Hull when sea levels rise, and contribute to less flooding in the wider Humber Estuary.

<span class="mw-page-title-main">Embanking of the tidal Thames</span> Historical process by which the shallow, natural River Thames was turned into a tidal canal

The Embanking of the tidal Thames is the historical process by which the lower River Thames, at one time a broad, shallow waterway winding through malarious marshlands, has been transformed by human intervention into a deep, narrow tidal canal flowing between solid artificial walls, and restrained by these at high tide. The Victorian civil engineering works in central London, usually called "the Embankment", are just a small part of the process.

References

  1. 1 2 Kendrick, Mary (1988). "The Thames Barrier". Landscape and Urban Planning. 16 (1–2): 57–68. doi:10.1016/0169-2046(88)90034-5.
  2. D. Maxwell Fyfe,  Home Secretary (3 June 1954). "Coastal Flooding (Committee's Report)". Written Answers (Hansard). Vol. 528. House of Commons. col. 104–5W.{{cite book}}: CS1 maint: numeric names: authors list (link)
  3. 1 2 3 4 5 Gilbert, Stuart; Horner, Ray (1984). The Thames Barrier. London: T. Telford. ISBN   978-0-7277-0182-4. OCLC   11594001.
  4. The Thames Barrier: The Background and Basic Engineering Requirements. D Ayres Director of Public Health Engineering, GLC. 1983. Paper presented to a meeting of the Institution of Mechanical Engineers, 8th June 1983
  5. "Davy Cleveland Barrier Consortium". Grace's Guide. 30 July 2019. Archived from the original on 24 November 2020.
  6. "Engineers and main contractors for the building of the Thames Barrier". Environment Agency. Archived from the original on 5 February 2009. Retrieved 13 March 2021.
  7. Horner, R. W. (July 1979). "The Thames Barrier Project". The Geographical Journal. 145 (2): 242–253. doi:10.2307/634390. JSTOR   634390.
  8. Manufacture and Installation of the Barrier Gates and Operating Machinery - P F Harvey, Davy Cleveland Barrier Consortium - Institution of Mechanical Engineers - Paper presented at a meeting on 8th June 1983.
  9. Clayton, Hugh (4 November 1982). "All 10 gates being raised at the Thames barrier". The Times. p. 3. Retrieved 12 March 2021.
  10. 1 2 "Better way to turn the tide". The Guardian . 9 May 1984. p. 2.  via newspapers.com (subscription required)
  11. United Kingdom Gross Domestic Product deflator figures follow the Measuring Worth "consistent series" supplied in Thomas, Ryland; Williamson, Samuel H. (2018). "What Was the U.K. GDP Then?". MeasuringWorth. Retrieved 2 February 2020.
  12. "The Thames Barrier Project Pack 2010" (PDF). Environment Agency. Archived from the original (PDF) on 16 December 2010. Retrieved 18 October 2011.
  13. de Castella, Tom (11 February 2014). "How does the Thames Barrier stop London flooding?". BBC News. Archived from the original on 8 June 2020.
  14. 1 2 "The Thames Barrier". Environment Agency. GOV.UK . 29 January 2021. Archived from the original on 13 March 2021.
  15. "North Sea flood tide fears recede". BBC News. 9 November 2007. Archived from the original on 30 June 2020.
  16. "Surge of 9 November 2007-11-09". Proudman Oceanographic Laboratory. Natural Environment Research Council. 9 November 2007. Archived from the original on 21 February 2012.{{cite web}}: CS1 maint: unfit URL (link)
  17. "Part III". Report of the Chief Inspector of Marine Accidents into the collision between the passenger launch Marchioness and MV Bowbelle with loss of life on the River Thames on 20 August 1989 (PDF) (Report). Department of Transport, Marine Accident Investigation Branch. 5 June 1990. Retrieved 12 March 2021.
  18. 1 2 Hanlon, Michael (18 February 2014). "The Thames Barrier has saved London – but is it time for TB2?" . The Telegraph. London. Archived from the original on 12 November 2016.
  19. Report of the Inspector's Inquiry into the collision of MV Sand Kite with the Thames Flood Barrier on 27 October 1997 (PDF) (Report). Department of the Environment, Transport and the Regions, Marine Accident Investigation Branch. April 1999. Retrieved 12 March 2021.
  20. 1 2 "Thames Barrier test closure to be on Jubilee pageant day". BBC News. 6 March 2012. Archived from the original on 13 March 2021.
  21. "Managing flood water: The future". Environment Agency. Archived from the original on 6 June 2009. Retrieved 25 November 2009.
  22. World Heritage Centre (May 2007). "Predicting and Managing the Impacts of Climate Change on World Heritage" (PDF). Climate Change and World Heritage (Report). Paris: UNESCO. p. 29. Archived from the original on 15 July 2020.
  23. "Thames Barrier Clocks 100 Closures". ThamesWEB. Thames Estuary Partnership. 19 March 2007. Archived from the original on 23 December 2008.{{cite web}}: CS1 maint: unfit URL (link)
  24. Leake, Jonathan (9 January 2005). "Ten mile barrier to stop London flood" . The Sunday Times. Archived from the original on 12 March 2021.
  25. "Thames Hub: An Integrated Vision for Britain" (PDF). Foster+Partners, Halcrow, Volterra. Archived from the original (PDF) on 10 November 2011.
  26. "Letters to the Editor: Thames Barrier". The Times. 3 January 2013. Archived from the original on 28 November 2020.
  27. "Thames Barrier engineer says second defence needed". BBC News. 5 January 2013. Archived from the original on 12 March 2021.
  28. Cole, Margo (10 January 2013). "Environment Agency rejects calls for new Thames Barrier" . New Civil Engineer. Archived from the original on 13 March 2021.
  29. 1 2 "Thames Barrier Project Pack 2012" (PDF). Environment Agency. Archived from the original (PDF) on 6 December 2012. Retrieved 28 December 2012.
  30. Horgan, Rob (3 June 2019). "Thames Barrier Bridge proposal revealed" . New Civil Engineer. Archived from the original on 29 January 2021.
  31. Waite, Richard (3 June 2019). "Lifschutz Davidson Sandilands reveals Thames Barrier bridge plans". Architects' Journal. Archived from the original on 13 March 2021.
  32. "Thames Barrier Bridge". Lifschutz Davidson Sandilands, Beckett Rankine. Retrieved 11 June 2019.