Mission type | Deployment of three satellites. |
---|---|
Operator | ISRO |
Website | ISRO website |
Mission duration | 1,658 seconds |
Apogee | 586.7 kilometres (365 mi) |
Spacecraft properties | |
Spacecraft | Polar Satellite Launch Vehicle |
Spacecraft type | Expendable launch vehicle |
Manufacturer | ISRO |
Launch mass | 294,000 kilograms (648,000 lb) |
Payload mass | 1,294 kilograms (2,853 lb) |
Dimensions | 44.4 metres (146 ft) (overall height) |
Start of mission | |
Launch date | 10:23:00,October 22, 2001 (IST) |
Rocket | Polar Satellite Launch Vehicle |
Launch site | Sriharikota Launching Range |
Contractor | ISRO |
End of mission | |
Disposal | Placed in graveyard orbit |
Deactivated | October 22, 2001 |
Orbital parameters | |
Reference system | Sun-synchronous |
Regime | Low Earth orbit |
Payload | |
TES BIRD PROBA | |
Mass | 1,294 kilograms (2,853 lb) |
PSLV-C3 was the third operational launch and overall sixth mission of the PSLV program. This launch was also the forty-sixth launch by Indian Space Research Organisation since its first mission on 1 January 1962. The vehicle carried three satellites which were deployed in the Sun-synchronous Low Earth orbit. [1] [2] The vehicle carried Technology Experiment Satellite (Indian experimental Earth observation satellite), BIRD (German Earth observation satellite) and PROBA (experimental satellite from Belgium). This was India's and ISRO's second commercial spaceflight. PSLV-C3 was launched at 10:23 a.m. IST on 22 October 2001 from Satish Dhawan Space Centre (then called "Sriharikota Range"). [3] [4] [5] [6] [7] [8]
The mission involved placing Technology Experiment Satellite (TES) and Bispectral and Infrared Remote Detection (BIRD) in a 568 km circular orbit. It would then place the PRoject for On Board Autonomy (PROBA) satellite in an 568 km x 638 km elliptical orbit. This demonstrated ISRO capability to launch multiple satellites in multiple orbits. It also earned ISRO $1 million for each satellite. [1] [2] [9]
PSLV-C3 carried and deployed total three satellites. Technology Experiment Satellite (TES) was the main payload and BIRD and PROBA were two auxiliary payloads that were mounted on PSLV-C3. In the flight sequence, TES was injected first, followed by BIRD and then PROBA. [1] [2]
Country | Name | Nos | Mass | Type | Objective |
---|---|---|---|---|---|
India | TES | 1 | 1,108 kg | Satellite | Experimental Earth observation satellite |
Belgium | BIRD | 1 | 94 kg | Microsatellite | Remote sensing technology demonstration |
Germany | PROBA | 1 | 92 kg | Microsatellite | Earth observation technology demonstration |
PSLV-C3 was launched at 10:23 a.m. IST on 22 October 2001 from Satish Dhawan Space Centre (then called "Sriharikota Launching Range"). The mission was planned with pre-flight prediction of covering overall distance of 586.668 kilometres (365 mi). The total flight time was 1658 seconds as PROBA was to be launched into an elliptical orbit after TES and BIRD were launched into a circular orbit. [9] The orbit raise was done using the yaw RCS thrusters in off-modulated mode. [11]
Following was the planned flight profile. [1] [2] [3] [5] [6] [7] [8]
Stage | Time (seconds) | Altitude (kilometer) | Velocity (meter/sec) | Event | Remarks |
---|---|---|---|---|---|
First stage | T+0 | 0.02 | 452 | First stage ignition | Lift-off |
T+1.24 | Ignition of 4 ground-lit strap-on motors | ||||
T+25.04 | 2.515 | 551 | Ignition of 2 air-lit strap-on motors | ||
T+68.04 | 23.472 | 1,155 | Separation of 4 ground-lit strap-on motors | ||
T+90.04 | 40.061 | 1,644 | Separation of 2 air-lit strap-on motors | ||
T+112.73 | 67.601 | 2,028 | First stage separation | ||
Second stage | T+112.93 | 67.828 | 2,027 | Second stage ignition | |
T+156.73 | 115.604 | 2,284 | Heat shield separation | ||
T+278.81 | 236.272 | 4,099 | Second stage separation | ||
Third stage | T+280.01 | 237.433 | 4,097 | Third stage ignition | |
T+498.33 | 455.487 | 6,086 | Third stage separation | ||
Fourth stage | T+520.60 | 460.818 | 6,065 | Fourth stage ignition | |
T+914.92 | 571.247 | 7,575 | Fourth stage thrust cut-off | ||
T+971.92 | 572.080 | TES separation | |||
T+1,011.92 | 572.709 | BIRD separation | |||
T+1,091.92 | 574.064 | PROBA orbit raise start | |||
T+1,552.50 | 585.018 | 7,593 | PROBA orbit raise stop | ||
T+1,602.50 | 586.688 | 7,592 | PROBA orbit separation | Mission over | |
The fourth stage of the PSLV had undergone a break-up event on 19 December 2001, likely caused by an explosion. [12] After the explosion of PSLV-C3, ISRO carried out passivation of the upper stages of the PSLV, from the PSLV-C4 mission onwards. [13] As per ISRO, this event generated 386 debris objects, of which 76 are still in orbit, as on 2021. [14] [15]
The Polar Satellite Launch Vehicle (PSLV) is an expendable medium-lift launch vehicle designed and operated by the Indian Space Research Organisation (ISRO). It was developed to allow India to launch its Indian Remote Sensing (IRS) satellites into Sun-synchronous orbits, a service that was, until the advent of the PSLV in 1993, only commercially available from Russia. PSLV can also launch small size satellites into Geostationary Transfer Orbit (GTO).
Satish Dhawan Space Centre – SDSC, is the primary spaceport of the Indian Space Research Organisation (ISRO), located in Sriharikota, Andhra Pradesh.
Technology Experiment Satellite (TES) is an Indian remote sensing and photo-reconnaissance satellite.
PSLV-C34 was the 36th mission of the PSLV program and 14th mission of PSLV in XL configuration. The PSLV-C34 successfully carried and deployed 20 satellites in the Sun-synchronous orbit. With a launch mass of 320,000 kilograms (710,000 lb) and payload mass of 1,288 kilograms (2,840 lb), the C34 set a new record of deploying the maximum number of satellites by Indian Space Research Organisation in a single mission. The PSLV-C34 carried One Cartosat-2 satellite, SathyabamaSat, Swayam & 17 other satellites from United States, Canada, Germany & Indonesia.
PSLV-C35 was the successful mission of the Polar Satellite Launch Vehicle program which set eight satellites in space. It was launched on 26 September 2016 by Indian Space Research Organisation (ISRO) from the Satish Dhawan Space Centre at Sriharikota.
PSLV-C1 was the overall fourth mission of the Polar Satellite Launch Vehicle (PSLV) program by Indian Space Research Organisation (ISRO). The vehicle carried IRS-1D satellite which was deployed in the Sun-synchronous orbit (SSO). This was India's first launch vehicle built without Russian assistance and PSLV's first operational flight placed IRS-1D into a polar orbit. However, it could not place the satellite in the desired circular orbit but in an elliptical orbit due to a leak of helium gas from one of the components. The mission was termed partial failure since the satellite could not be placed at the desired altitude.
PSLV-C2 was the second operational launch and overall fifth mission of the Polar Satellite Launch Vehicle (PSLV) program. This launch was also the forty-third launch by Indian Space Research Organisation (ISRO) since its first mission on 1 January 1962. The vehicle carried three satellites which were deployed in the Sun-synchronous low Earth orbit. The vehicle carried India's first remote sensing satellite Oceansat-1 (IRS-P4) as the main payload. It also carried South Korean satellite KITSAT-3 and German satellite DLR-Tubsat as auxiliary payloads. PSLV-C2 was the first Indian Expendable launch vehicle to carry and deploy more than one satellite in a mission. This was also India's and ISRO's first commercial spaceflight where South Korea and Germany each paid US$1.0 million to ISRO for launching their satellites.
PSLV-C4 was the fourth operational launch and overall seventh mission of the PSLV program. This launch was also the forty-eight launch by Indian Space Research Organisation since its first mission on 1 January 1962. The vehicle carried and injected India's first dedicated Meteorological satellite, Kalpana-1 into the Geosynchronous transfer orbit. PSLV-C4 was launched at 15:53 hours IST on 12 September 2002 from Satish Dhawan Space Centre.
PSLV-C5 was the fifth operational launch and overall eighth mission of the Polar Satellite Launch Vehicle program. This launch was also the fifty-second launch by the Indian Space Research Organisation (IRSO) since its first mission on 1 January 1962. The vehicle carried and injected India's remote sensing satellite Resourcesat-1 into a Sun-synchronous orbit; this was the heaviest and most sophisticated satellite built by IRSO through 2003. PSLV-C5 was launched at 04:52 hours Coordinated Universal Time on 17 October 2003 from Satish Dhawan Space Centre.
PSLV-C6 was the sixth operational launch and overall ninth mission of the PSLV program. This launch was also the fifty-fourth launch by Indian Space Research Organisation since its first mission on 1 January 1962. The vehicle carried and injected India's two satellites; Cartosat-1 and HAMSAT into the Sun-synchronous orbit. PSLV-C6 was launched at 04:44 hours Coordinated Universal Time on 5 May 2005 from the second launch pad of the Satish Dhawan Space Centre.
PSLV-C37 was the 39th mission of the Indian Polar Satellite Launch Vehicle (PSLV) program and its 16th mission in the XL configuration undertaken by the Indian Space Research Organisation (ISRO). Launched on 15 February 2017 from the Satish Dhawan Space Centre at Sriharikota, Andhra Pradesh, the rocket successfully carried and deployed a record number of 104 satellites in Sun-synchronous orbits in a single mission, breaking the earlier record of launching 37 satellites by a Russian Dnepr rocket on 19 June 2014. This record was held until the launch of the Transporter-1 mission by SpaceX on 24 January 2021 which launched 143 satellites.
The Small Satellite Launch Vehicle (SSLV) is a small-lift launch vehicle developed by ISRO with payload capacity to deliver 500 kg (1,100 lb) to low Earth orbit or 300 kg (660 lb) to Sun-synchronous orbit for launching small satellites, with the capability to support multiple orbital drop-offs. SSLV is made keeping low cost, low turnaround time in mind with launch-on-demand flexibility under minimal infrastructure requirements.
The PSLV-C43 was the 45th mission of the Indian Polar Satellite Launch Vehicle (PSLV) program. It carried and deployed a total of 31 satellites, including the primary payload HySIS in Sun-synchronous orbits. It was launched on 29 November 2018 by the Indian Space Research Organisation (ISRO) from the first launch pad of the Satish Dhawan Space Centre at Sriharikota, Andhra Pradesh.
The PSLV-C44 was the 46th mission of the Indian Polar Satellite Launch Vehicle (PSLV) program. It was the first flight of PSLV-DL, having 2 strap-on boosters and placed a primary payload Microsat-R and a secondary payload of Kalamsat V2 in Sun-synchronous orbits.
The PSLV-C55 was the 57th mission of Indian Space Research Organisation's Polar Satellite Launch Vehicle (PSLV) and the 16th flight of the PSLV-CA variant.
PSLV-C46 was a mission of the Indian Polar Satellite Launch Vehicle (PSLV) rocket, launched on Thursday, May 22, 2019, at 05:30 Hrs (IST) by the Indian Space Research Organisation (ISRO) from the first launch pad of the Satish Dhawan Space Centre at Sriharikota, Andhra Pradesh. In this mission, the 'Core-Alone' configuration of PSLV was flown.
PSLV-C7 was a mission of the Indian Polar Satellite Launch Vehicle (PSLV) rocket, launched on January 10, 2007, by the Indian Space Research Organisation (ISRO) from the Satish Dhawan Space Centre at Sriharikota, Andhra Pradesh.
The PSLV C-58 was the 60th flight of the Indian Space Research Organisation's Polar Satellite launch Vehicle. It carried the XPoSAT mission along with rideshare payloads.
{{cite news}}
: CS1 maint: unfit URL (link)